Documente Academic
Documente Profesional
Documente Cultură
Subject Code : 06EEL78 No. of Practical Hrs/Week : 03 Total No. of Practical Hrs : 42 IA Marks : 25 Exam Hrs. : 03 Exam Marks : 50
2. Formation of Z-bus, using Z-bus build Algorithm without mutual coupling. 3. ABCD parameters: i) Formation for symmetric /T configuration. ii) Verification of AD-BC = 1. iii) Determination of co-efficient & regulation. 4. Determination of power angle diagrams for salient and non-salient pole synchronous m/cs, reluctance power, excitation emf & regulation. 5. To determine i) swing curve ii) critical clearing time for a single m/c connected to infinite bus through a pair of identical transmission lines, for a 3 fault on one of the lines for variation of inertia constant/line parameters/fault location/clearing time/prefault electrical output. 6. Formation of Jacobian for a system not exceeding 4 buses * (no PV buses) in polar co-ordinates. 7. Write a program to perform load flow analysis using Gauss-Siedel method(only PQ bus). 8. To determine fault currents and voltages in a single transmission line systems with stardelta transformers at a specified location for SLGF, DLGF. 9. Load flow analysis using Gauss Siedel method, NR method, Fast Decoupled flow method for both PQ and PV buses. 10. Optimal generator scheduling for thermal power plants. Note: 1, 2, 3, 4, 5, 6, 7, 8 Simulation experiments using MATLAB. 4, 6, 9, 10 Using Mi-Power package.
VII Semester
1. a) YBUS FORMATION FOR A GIVEN POWER SYSTEM i) Formation of YBus without mutual coupling by Inspection Method
Single Line Diagram of Transmission Network:
(1)
j 0.2
(2)
j 0.25
j 0.5
j 0.4
(4)
j 0.2
(3)
Shunt Admittance Element Data: Bus 4 Shunt Admittance j0.02
Half Line Charging Admittance Data: Bus Code 1-2 1-4 2-3 2-4 3-4 HLC Admittance j 0.03 j0.025 j0.02 j0.015 J0.01
Program for Ybus formation without mutual coupling by Inspection method: clc; clear; linedata = [1 2 0.2j 0.03i; 1 4 0.25j 0.025i; 2 3 0.4j 0.02i; 2 4 0.5j 0.015i; 3 4 0.2j 0.01i]; Sh=[4 0.02j]; fb=linedata(:,1); %From bus tb=linedata(:,2); %To bus z=linedata(:,3); %Series line impedance Bc=linedata(:,4); %Half line charging admittance nbus=max(max(fb),max(tb)); nbr=length(z); y=ones(nbr,1)./z; %branch admittance Ybus=zeros(nbus,nbus); % initialize Ybus to zero % formation of the off diagonal elements for k=1:nbr; Ybus(fb(k),tb(k))=Ybus(fb(k),tb(k))-y(k); Ybus(tb(k),fb(k))=Ybus(fb(k),tb(k));
Department of E & EE, SSIT, Tumkur 2
VII Semester
end % formation of the diagonal elements for n=1:nbus for k=1:nbr if fb(k)==n Ybus(n,n) = Ybus(n,n)+y(k) + Bc(k); elseif tb(k)==n Ybus(n,n) = Ybus(n,n)+y(k) + Bc(k); end end end %Addition of shunt admittance data [r,c]=size(Sh); for x=1:r for y=1:nbr p=fb(y); q=tb(y); if Sh(x,1)==p Ybus(p,p)=Ybus(p,p)+Sh(x,2); elseif Sh(x,1)==q Ybus(q,q)=Ybus(q,q)+Sh(x,2); end end end Ybus
OUTPUT: Ybus = 0 - 8.9450i 0 + 5.0000i 0 0 + 4.0000i 0 + 5.0000i 0 - 9.4350i 0 + 2.5000i 0 + 2.0000i 0 0 + 2.5000i 0 - 7.4700i 0 + 5.0000i 0 + 4.0000i 0 + 2.0000i 0 + 5.0000i 0 -10.8900i
VII Semester
(1)
(3)
(4)
(2)
Impedances and line charging admittances for the power system: Bus Code Impedance HLC Admittance 1-2 0.02 + j 0.06 0.0 + j 0.030 1-3 0.08 + j 0.24 0.0 + j 0.025 2-3 0.06 + j 0.18 0.0 + j 0.020 2-4 0.06 + j 0.18 0.0 + j 0.020 2-5 0.04 + j 0.12 0.0 + j 0.015 3-4 0.01 + j 0.03 0.0 + j 0.010 4-5 0.08 + j 0.24 0.0 + j 0.025
(5)
Program for Ybus formation without mutual coupling using Singular Transformation: clc; clear; Dm=input('Enter the Line data : '); fb=Dm(:,1); tb=Dm(:,2); z=Dm(:,3); hlc=Dm(:,4); nb=max(max(fb),max(tb)); e=length(z); %Formation of Bus Incidence matrix a=zeros(e,nb); for i=1:1:e p=fb(i); a(i,p)=1; q=tb(i); a(i,q)=-1; end a
Department of E & EE, SSIT, Tumkur 4
VII Semester
%Formation of the Primitive Admittance matrix Zpri=zeros(e,e); for j=1:1:e Zpri(j,j)=z(j); end Ypri=inv(Zpri); %Ybus formation Ybus=a'*Ypri*a; %Addition of Half Line Chaging Admittance for r=1:1:nb-1 for s=1:1:e if fb(s)==r|tb(s)==r Ybus(r,r)=Ybus(r,r)+hlc(s); end end end Ybus
INPUT Data:
Enter the Line data : [1 2 0.02+0.06i 0.03i;1 3 0.08+0.24i 0.025i;2 3 0.06+0.18i 0.02i; 2 4 0.06+0.18i 0.02i;2 5 0.04+0.12i 0.015i;3 4 0.01+0.03i 0.01i;4 5 0.08+0.24i 0.025i]
OUTPUT:
a= 1 -1 0 0 0 1 0 -1 0 0 0 1 -1 0 0 0 1 0 -1 0 0 1 0 0 -1 0 0 1 -1 0 0 0 0 1 -1
Ybus = 6.2500 -18.6950i -5.0000 +15.0000i -1.2500 + 3.7500i 0 0 -5.0000 +15.0000i 10.8333 -32.4150i -1.6667 + 5.0000i -1.6667 + 5.0000i -2.5000 + 7.5000i -1.2500 + 3.7500i -1.6667 + 5.0000i -10.0000 +30.0000i 0 0 0 0
-1.6667 + 5.0000i -2.5000 + 7.5000i 12.9167 -38.6950i -1.2500 + 3.7500i -1.2500 + 3.7500i 3.7500 -11.2500i
VII Semester
VII Semester
INPUT Data:
Enter the Line data : [1 2 0.6j 0;1 3 0.5j 0;3 4 0.5j 0;1 2 0.4j 0;2 4 0.2j 0] Enter the Mutual Coupling data : [1 2 0.1j;1 4 0.2j]
OUTPUT:
a= 1 -1 0 0 1 0 -1 0 0 0 1 -1 1 -1 0 0 0 1 0 -1 Ybus = 0 - 4.6875i 0 + 2.8125i 0 + 1.8750i 0 0 + 2.8125i 0 - 8.0208i 0 + 0.2083i 0 + 5.0000i 0 + 1.8750i 0 + 0.2083i 0 - 4.0833i 0 + 2.0000i 0 0 + 5.0000i 0 + 2.0000i 0 - 7.0000i
VII Semester
1. b) DETERMINATION OF BUS CURRENTS, BUS POWER & LINE FLOWS FOR A SPECIFIED SYSTEM VOLTAGE (BUS) PROFILE Case study:
G1 256.6 + j 110.2
(1)
1.05<0
0.02 + j 0.04
(2) 0.98183<-3.5
0.01 + j 0.03
0.0125 + j 0.025
(3) 1.00125<-2.8624
138.6 + j 45.2 Program: clc; clear; linedata = [1 2 0.02 0.04 0 1 3 0.01 0.03 0 2 3 0.0125 0.025 0]; fr=linedata(:,1); to=linedata(:,2); R=linedata(:,3); X=linedata(:,4); B_half=linedata(:,5); nb=max(max(fr),max(to)); nbr=length(R); bus_data = [1 1.05 0 2 0.98183 -3.5 3 1.00125 -2.8624]; bus_no=bus_data(:,1); volt_mag=bus_data(:,2); angle_d=bus_data(:,3); Z = R + j*X; %branch impedance y= ones(nbr,1)./Z; %branch admittance Vbus=(volt_mag.*cos(angle_d*pi/180))+ (j*volt_mag.*sin(angle_d*pi/180)); %line current for k=1:nbr Ifr(k)=(Vbus(fr(k))-Vbus(to(k)))*y(k) + (Vbus(fr(k))*j*B_half(k)); Ito(k)=(Vbus(to(k))-Vbus(fr(k)))*y(k) + (Vbus(to(k))*j*B_half(k)); end %line flows
Department of E & EE, SSIT, Tumkur 8
VII Semester
% S=P+jQ for k=1:nbr Sfr(k)=Vbus(fr(k))*Ifr(k)'; Sto(k)=Vbus(to(k))*Ito(k)'; end %line losses for k=1:nbr SL(k)=Sfr(k)+Sto(k); end %bus power Sbus=zeros(nb,1); for n=1:nb for k=1:nbr if fr(k)==n Sbus(n)=Sbus(n)+Sfr(k); elseif to(k)==n Sbus(n)=Sbus(n)+Sto(k); end end end %Bus current %P+jQ=V*I' Ibus=(Sbus./Vbus)'; fprintf(' OUTPUT DATA \n'); fprintf('------------------------------\n'); fprintf(' Line Currents\n'); fprintf('------------------------------\n'); for k=1:nbr fprintf(' I%d%d= %4.3f (+) %4.3f \n',fr(k),to(k),real(Ifr(k)),imag(Ifr(k))); fprintf(' I%d%d= %4.3f (+) %4.3f \n', to(k),fr(k),real(Ito(k)),imag(Ito(k))); end fprintf('------------------------------\n'); fprintf(' Line Flows\n') fprintf('------------------------------\n'); for k=1:nbr fprintf(' S%d%d= %4.3f (+) %4.3f \n',fr(k),to(k),real(Sfr(k)),imag(Sfr(k))); fprintf(' S%d%d= %4.3f (+) %4.3f \n', to(k),fr(k),real(Sto(k)),imag(Sto(k))); end fprintf('------------------------------\n'); fprintf(' Line Losses\n') fprintf('------------------------------\n'); for k=1:nbr fprintf(' SL%d%d= %4.3f (+) %4.3f \n',fr(k),to(k),real(SL(k)),imag(SL(k))); end fprintf('------------------------------\n'); fprintf(' Bus Power\n') fprintf('------------------------------\n'); for k=1:nb fprintf(' P%d= %4.3f (+) %4.3f \n',k,real(Sbus(k)),imag(Sbus(k))); end fprintf(' Bus Current\n') fprintf('------------------------------\n');
Department of E & EE, SSIT, Tumkur 9
VII Semester
for k=1:nb fprintf(' I%d= %4.3f (+) %4.3f \n',k,real(Ibus(k)),imag(Ibus(k))); end fprintf('------------------------------\n'); OUTPUT: OUTPUT DATA -----------------------------Line Currents -----------------------------I12= 1.899 (+) -0.801 I21= -1.899 (+) 0.801 I13= 2.000 (+) -1.000 I31= -2.000 (+) 1.000 I23= -0.638 (+) 0.481 I32= 0.638 (+) -0.481 -----------------------------Line Flows -----------------------------S12= 1.994 (+) 0.841 S21= -1.909 (+) -0.671 S13= 2.100 (+) 1.050 S31= -2.050 (+) -0.900 S23= -0.654 (+) -0.433 S32= 0.662 (+) 0.449 -----------------------------Line Losses -----------------------------SL12= 0.085 (+) 0.170 SL13= 0.050 (+) 0.150 SL23= 0.008 (+) 0.016 -----------------------------Bus Power -----------------------------P1= 4.094 (+) 1.891 P2= -2.563 (+) -1.104 P3= -1.388 (+) -0.451 Bus Current -----------------------------I1= 3.899 (+) -1.801 I2= -2.537 (+) 1.282 I3= -1.362 (+) 0.519 ------------------------------
VII Semester
VII Semester
continue end %Type-3 Modification %A new element is added between an old bus and reference bus if newbus<=currentbusno & ref==0 disp('Adding Z ='); disp(value); disp('between buses:'); disp(from); disp(to); disp('This impedance is added between an existing bus and reference(Type3)'); zbus=zbus-1/(zbus(newbus,newbus)+value)*zbus(:,newbus)*zbus(newbus,:) continue end %Type-4 Modification %A new element is added between two old buses(bus-2 to 3) if newbus<=currentbusno & ref~=0 disp('Adding Z ='); disp(value); disp('between buses:'); disp(from); disp(to); disp('This impedance is added between two existing buses(Type4)'); zbus=zbus-1/(value+zbus(from,from)+zbus(to,to)-2*zbus(from,to))*((zbus(:,from)zbus(:,to))*((zbus(from,:)-zbus(to,:)))) continue end end
OUTPUT: Zbus Building Algorithm Adding Z = 0.2500 between buses: 1 0 This impedance is added between a new bus and reference(Type1) zbus = 0.2500 Adding Z = 0.1000
Department of E & EE, SSIT, Tumkur 12
VII Semester
between buses: 2 1 This impedance is added between a new bus and an existing bus(Type2) zbus = 0.2500 0.2500 0.2500 0.3500 Adding Z = 0.1000 between buses: 3 1 This impedance is added between a new bus and an existing bus(Type2) zbus = 0.2500 0.2500 0.2500 0.2500 0.3500 0.2500 0.2500 0.2500 0.3500 Adding Z = 0.2500 between buses: 2 0 This impedance is added between an existing bus and reference(Type3) zbus = 0.1458 0.1042 0.1458 0.1042 0.1458 0.1042 0.1458 0.1042 0.2458 Adding Z = 0.1000 between buses: 2 3 This impedance is added between two existing buses(Type4)
Department of E & EE, SSIT, Tumkur 13
VII Semester
zbus = 0.1397 0.1103 0.1250 0.1103 0.1397 0.1250 0.1250 0.1250 0.1750
VII Semester
3. ABCD PARAMETERS
i) Formation of Symmetric T/PI Configuration ii) Verification of AD-BC =1 iii) Determination of Efficiency & Regulation Program : z=0.2+0.408i; y=0+3.14e-6i; k1=input('\n enter 1-for short line 2- for medium line 3- for long line'); switch k1, case 1, length=40; Z=z*length;Y=y*length; A=1;B=Z;C=0;D=1; case 2, length=140; Z=z*length;Y=y*length; A=1+Y*Z/2; B=Z; C=Y*(1+Y*Z/4); D=A; case 3, length=300; zc=sqrt(z/y); gam=sqrt(z*y)*length; A=cosh(gam); D=A; B=zc*sinh(gam); C=1/zc*sinh(gam); fprintf('\n the equivalent pi circuit constants:'); zeq=z*length*sinh(gam)/gam; yeq=y*length/2*tanh(gam/2)/(gam/2); fprintf('\n Zeq = %15.4f%+15.4fi',real(zeq),imag(zeq)); fprintf('\n yeq/2 = %15.4f%+15.4fi',real(yeq),imag(yeq)); otherwise disp('wrong choice of transmission line'); end fprintf('\n A,B,C and D constants:\n'); fprintf('---------------------------------------'); fprintf('\n A = %15.4f%+15.4fi',real(A),imag(A)); fprintf('\n B = %15.4f%+15.4fi',real(B),imag(B)); fprintf('\n C = %15.4f%+15.4fi',real(C),imag(C)); fprintf('\n D = %15.4f%+15.4fi',real(D),imag(D)); fprintf('\n The product AD-BC = %f',A*D-B*C); k2=input('\n enter 1- to read Vr, Ir and compute Vs, Is\n 2- to read Vs, Is and compute Vr, Ir'); switch k2, case 1, vr=132+0.0i; ir=174.96-131.22i; vr=vr*1e3/sqrt(3);
Department of E & EE, SSIT, Tumkur 15
VII Semester
vs=(A*vr+B*ir)/1e3; is=C*vr+D*ir; fprintf('\n Sending end voltage/ph=%f%+fi KV', real(vs),imag(vs)); fprintf('\n Sending end current/ph=%f%+fi Amp', real(is),imag(is)); vs=vs*1e3; case 2, vs=132+0.0i; is=174.96-131.22i; vs=vs*1e3/sqrt(3.0); vr=(D*vs-B*is)/1e3; ir=-C*vs+D*is; fprintf('\n Receiving end voltage/ph=%f%+fi KV', real(vr),imag(vr)); fprintf('\n Receiving end current/ph=%f%+fi Amp', real(ir),imag(ir)); vr=vr*1e3; otherwise disp('wrong choice'); end rec_pow=3*real(vr*conj(ir))/1e6; send_pow=3*real(vs*conj(is))/1e6; eff=rec_pow/send_pow*100; reg=(abs(vs)/abs(A)-abs(vr))/abs(vr)*100; fprintf('\n Recieving end power=%.2fKVA',rec_pow); fprintf('\n sending end power=%.2fKVA',send_pow); fprintf('\n efficiency=%.2f%%',eff); fprintf('\n voltage regulation=%.2f%%',reg); Note: For Equivalent T circuit constants fprintf('\n the equivalent T circuit constants:'); yeq=y*length*sinh(gam)/gam; zeq=z*length/2*tanh(gam/2)/(gam/2); fprintf('\n Zeq/2 = %10.4f%+10.4fi',real(zeq),imag(zeq)); fprintf('\n yeq = %10.4f%+10.4fi',real(yeq),imag(yeq)); OUTPUT : Equivalent PI enter 1-for short line 2- for medium line 3- for long line3 the equivalent pi circuit constants: Zeq = 57.7123 +120.6169i yeq/2 = 0.0000 +0.0005i A,B,C and D constants: --------------------------------------A= 0.9428 +0.0277i B= 57.7123 +120.6169i C= -0.0000 +0.0009i D= 0.9428 +0.0277i The product AD-BC = 1.000000 enter 1- to read Vr, Ir and compute Vs, Is 2- to read Vs, Is and compute Vr, Ir1 Sending end voltage/ph=97.773395+15.642655i KV
Department of E & EE, SSIT, Tumkur 16
VII Semester
Sending end current/ph=167.915908-48.443896i Amp Recieving end power=40.00KVA sending end power=46.98KVA efficiency=85.15% voltage regulation=37.75%>> Equivalent T enter 1-for short line 2- for medium line 3- for long line3 the equivalent T circuit constants: Zeq/2 = 30.5858 +61.6486i yeq = -0.0000 +0.0009i A,B,C and D constants: --------------------------------------A= 0.9428 +0.0277i B= 57.7123 +120.6169i C= -0.0000 +0.0009i D= 0.9428 +0.0277i The product AD-BC = 1.000000 enter 1- to read Vr, Ir and compute Vs, Is 2- to read Vs, Is and compute Vr, Ir2 Receiving end voltage/ph=45.924027-11.417589i KV Receiving end current/ph=169.252896-189.276902i Amp Recieving end power=29.80KVA sending end power=40.00KVA efficiency=74.50% voltage regulation=70.75%>>
17
VII Semester
VII Semester
Power_non=abs(Ef)*Vtph*sin(delta_rad)/Xd; Net_Power=3*Power_non/1000000; plot(delta,Net_Power); xlabel('\Delta(deg)-------->'); ylabel('Three Phase Power(MW)-------->'); title('Plot:Power Angle Curve for Non-Salient Synchronous M/c'); legend('Non-Salient Power'); end grid; Input Data: from the keyboard: (Salient Pole) P = 48 Power in MW Pf = 0.8 Power Factor V = 34.64 Line to Line Voltage in kV Xd = 13.5 Xd in ohm Xq = 9.33 Xq in ohm Output: Excitation EMF = 30000 Volts/ phase Regulation = 50.0024 %
Input Data: from the keyboard: (Non-Salient Pole) P = 48 Power in MW Pf = 0.8 Power Factor V = 34.64 Line to Line Voltage in kV Xd = 10Xd in ohm Xq = 10Xq in ohm Output: Excitation EMF = 27203 Volts/ phase Regulation = 36.01 %
19
VII Semester
VII Semester
if(t>tc), Pa = Pm-Ppost*sin(delta*pi/180); end ddelta = ddelta+(tstep*tstep*Pa/M); delta = (delta+ddelta); t = t+tstep; time(i) = t; ang(i) = delta; i = i+1; end plot(time,ang,'bo-');grid; title(['One-machine system swing curve by Point by Point method. Fault cleared at ', num2str(tc),'s']); xlabel('t, sec'), ylabel('Delta, degree'); deltamax = pi-asin(Pm/Ppost); dmax = deltamax; d0 = asin(Pm/Ppre); dc = acos((Pm*(dmax-d0)+Ppost*cos(dmax)-Pfault*cos(d0))/(Ppost-Pfault)); fprintf('\nCritical clearing angle = %6.2f degrees ',dc*180/pi); it = 1; while(time(it)<1.0) if (ang(it)> = (dc*180/pi)) break; end it = it+1; end fprintf('\n Critical clearing time = %4.2f seconds \n', time(it)); Input: Sustained fault: Generator Inertia constant H in MJ/MVA = 5.2 Pre fault reactance Xpre in p.u. = 0.7 Reactance during fault Xfault in p.u. = 1.9 Post fault reactance Xpost in p.u. = 0.9 Sending end voltage E in p.u. = 1.2 Receiving end voltage V in p.u. = 1.0 Base MVA = 20 Generator output power in MW = 16 Initial displacement angle in degree = 27.82 Fault clearing time in sec = 1.5 Final time for swing equation in sec = 1.5 ** For Fault cleared in 2.5 cycles & Fault cleared in 6.5 cycles, Fault clearing time is 0.05 seconds & 0.125 seconds respectively.
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
Output:
21
VII Semester
Sustained fault: Critical clearing angle = 91.24 degrees Critical clearing time = 0.45 seconds
Fault cleared in 2.5 cycles (0.05secs): Critical clearing angle = 91.24 degrees Critical clearing time = 1.00 seconds
Fault cleared in 6.5 cycles (0.125secs): Critical clearing angle = 91.24 degrees
Department of E & EE, SSIT, Tumkur 22
VII Semester
6. FORMATION OF JACOBIAN FOR A SYSTEM NOT EXCEEDING 4 BUSES (NO PV BUSES) IN POLAR CO-ORDINATES USING
Department of E & EE, SSIT, Tumkur 23
VII Semester
SOFTWARE PACKAGE
A Three-Bus system is given below. The system parameters are given in the Table A and the load and generation data in Table B. Line impedances are in per unit on a 100 MVA Base. Line charging susceptances are neglected. Taking bus 1 as slack bus, obtain the Jacobian matrix.
Bus 2 (PQ)
Bus 3 (PQ)
Table A Bus Code (i-k) 1-2 1-3 2-3 Impedance (p.u) Zik 0.08+j0.24 0.02+j0.06 0.06+j0.18 Table B Bus No 1 2 3 Bus Voltage 1.05 + j0.0 ---------Generation MW Mvar -----0 0 0 0 Load MW 0 50 60 Mvar 0 20 25 Line charging Admittance (p.u) Yi 0 0 0
Procedure to enter the data for performing studies using Mi Power Mi Power - Database Configuration Open Power System Network Editor. Select menu option DatabaseConfigure. Configure Database dialog is popped up. Click Browse button.
24
VII Semester
Open dialog box is popped up as shown below, where you are going to browse the desired directory and specify the name of the database to be associated with the single line diagram. Click Open button after entering the desired database name. Configure Database dialog will appear with path chosen.
Select the folder and give database name in File name window with .Mdb extension. And now click on Open.
Click OK Click on OK button in the Configure database dialog, the following dialog appears.
25
VII Semester
Uncheck the Power System Libraries and Standard Relay Libraries. For this example these standard libraries are not needed, because all the data is given on p u for power system libraries (like transformer, line\cable, generator), and relay libraries are required only for relay coordination studies. If Libraries are selected, standard libraries will be loaded along with the database. Click Electrical Information tab. Since the impedances are given on 100 MVA base, check the pu status. Enter the Base MVA and Base frequency as shown below. Click Breaker Ratings tab. If the data is furnished, modify the breaker ratings for required voltage levels. Otherwise accept the default values. Click OK button to create the database to return to Network Editor. Bus Base Voltage Configuration In the network editor, configure the base voltages for the single line diagram. Select menu option Configure Base voltage. Dialog shown below appears. If necessary change the Base-voltages, color, Bus width and click OK.
Procedure to Draw First Element - Bus Click on Bus icon provided on power system tool bar. Draw a bus and a dialog appears prompting to give the Bus ID and Bus Name. Click OK. Database manager with corresponding Bus Data form will appear. Modify the Area number, Zone number and Contingency Weightage data if it is other than the default values. If this data is not furnished, keep the default values. Usually the minimum and maximum voltage ratings are 5% of the rated voltage. If these ratings are other than this, modify these fields. Otherwise keep the default values. Bus description field can be effectively used if the bus name is more than 8 characters. If bus name is more than 8 characters, then a short name is given in the bus name field and the bus description field can be used to abbreviate the bus name. For example let us say the bus name is Northeast, then bus name can be given as NE and the bus description field can be North East.
26
VII Semester
After entering data click save, which invokes Network Editor. Follow the same procedure for remaining buses. Following table gives the data for other buses. Bus Number 1 2 3 Bus Name Bus 1 Bus 2 Bus 3 Nominal Voltage (KV) 11 11 11
Note: Since the voltages are in pu, any kV can be assumed. So the base voltage is chosen as 11kV. Procedure to Draw Transmission Line Click on Transmission Line icon provided on power system tool bar. To draw the line click in between two buses and to connect to the from bus, double click LMB (Left Mouse Button) on the From Bus and join it to another bus by double clicking the mouse button on the To Bus Element ID dialog will appear.
Enter Element ID number and click OK. Database manager with corresponding Line\Cable Data form will be open. Enter the details of that line as shown below. Enter Structure Ref No. as 1 and click on Transmission Line Library >> button. Line & Cable Library form will appear. Enter transmission line library data in the form as shown. Transmission Line Element Data Line No 1 2 3 From Bus 1 1 2 To Bus 2 3 3 Structure Ref No 1 2 3
VII Semester
Structure Ref No 1 2 3
Procedure to Draw Generator Click on Generator icon provided on power system tool bar. Draw the generator by clicking LMB (Left Mouse Button) on the Bus1. Element ID dialog will appear. Enter ID number and Click OK. Database with corresponding Generator Data form will appear. Enter details as given below.
28
VII Semester
29
VII Semester
Procedure to Enter Load Data Click on Load icon provided on power system tool bar. Connect load 1 at Bus 2 by clicking the LMB (Left Mouse Button) on Bus 2. Element ID dialog will appear. Give ID no. as 1 and say OK. Load Data form will appear. Enter load details as shown below. Then click Save button, which invokes Network Editor.
When Study info button is clicked, following dialog will open. Select Newton Raphson
Department of E & EE, SSIT, Tumkur 30
VII Semester
method and enter P-Tolerance and Q-tolerance as 0.001. Select print option as Detailed results with Data. Click OK.
2. Click OK Click on Execute to run the power flow. When Report button is clicked, following dialog box will open. Select Standard and then click OK.
Report:
Department of E & EE, SSIT, Tumkur
1. Select standard
31
VII Semester
2. Click OK
32
VII Semester
33
VII Semester
34
VII Semester
35
VII Semester
36
VII Semester
37
VII Semester
Line impedance and line charging data: Line (bus to bus) 1-2 1-5 2-3 2-5 3-4 3-5 4-5 Ybus matrix of the system: 1 2 3 4 5 1 2.6923 - j 13.4115 - 1.9231 + j 9.6154 0 0 - 0.7692 + j 3.8462 2 - 1.9231 + j 9.6154 3.6538 - j 18.1942 - 0.9615 + j 4.8077 0 - 0.7692 + j 3.8462 3 0 - 0.9615 + j 4.8077 2.2115 - j 11.0027 - 0.7692 + j 3.8462 - 0.4808 + j 2.4038 4 0 0 - 0.7692 + j 3.8462 1.1538 - j 5.6742 - 0.3846 + j 1.9231 5 - 0.7692 + j 3.8462 - 0.7692 + j 3.8462 - 0.4808 + j 2.4038 - 0.3846 + j 1.9231 2.4038 - j 11.8942 Impedance 0.02 + j 0.10 0.05 + j 0.25 0.04 + j 0.20 0.05 + j 0.25 0.05 + j 0.25 0.08 + j 0.40 0.10 + j 0.50 Line charging (Y /2) j 0.030 j 0.020 j 0.025 j 0.020 j 0.020 j 0.010 j 0.075
Program: %Power flow solution by Gauss-Seidel method clc clear all d2r=pi/180;w=100*pi; % The Y_bus matrix is ybus=[2.6923-13.4115j -1.9231+9.6154j 0 0 -0.7692+3.8462j; -1.9231+9.6154j 3.6538-18.1942j -0.9615+4.8077j 0 -0.7692+3.8462j; 0 -0.9615+4.8077j 2.2115-11.0027j -0.7692+3.8462j -0.4808+2.4038j; 0 0 -0.7692+3.8462j 1.1538-5.6742j -0.3846+1.9231j; -0.7692+3.8462j -0.7692+3.8462j -0.4808+2.4038j -0.3846+1.9231j 2.4038-11.8942j]; g = real(ybus);
Department of E & EE, SSIT, Tumkur 38
VII Semester
b = imag(ybus); % The given parameters and initial conditions are p = [0;-0.96;-0.35;-0.16;0.24]; q = [0;-0.62;-0.14;-0.08;-0.35]; mv = [1.05;1;1;1;1.02]; th = [0;0;0;0;0]; v = [mv(1);mv(2);mv(3);mv(4);mv(5)]; acc = input('Enter the acceleration constant: '); del = 1; indx =0; nb = length(p); % The Gauss-Seidel iterations starts here while del>1e-6 % P-Q buses for i = 2:4 tmp1= (p(i)-j*q(i))/conj(v(i)); tmp2 = 0; for k =1:5 if (i = = k) tmp2 = tmp2+0; else tmp2 = tmp2+ybus(i,k)*v(k); end end vt = (tmp1-tmp2)/ybus(i,i); v(i) = v(i)+acc*(vt-v(i)); end % P-V bus q5 = 0; for i =1:5 q5 = q5+ybus(5,i)*v(i); end q5 = -imag(conj(v(5))*q5); tmp1 = (p(5)-j*q5)/conj(v(5)); tmp2 = 0; for k =1:4 tmp2 = tmp2+ybus(5,k)*v(k); end vt = (tmp1-tmp2)/ybus(5,5); v(5) = abs(v(5))*vt/abs(vt); % Calculate P and Q for i =1:5 sm = 0; for k =1:5 sm = sm+ybus(i,k)*v(k); end s(i) = conj(v(i))*sm; end % The mismatch delp = p-real(s)';
Department of E & EE, SSIT, Tumkur 39
VII Semester
delq = q+imag(s)'; delpq = [delp(2:5);delq(2:4)]; del = max(abs(delpq)); indx = indx+1; V = abs(v)'; V_angle = angle(v)'/d2r; Real_pow = (real(s)+[0 0 0 0 0.24])*100; Reactive_pow = (-imag(s)+[0 0 0 0 0.11])*100; fprintf('\nGS LOAD FLOW ITERATION NO. %d',indx); fprintf('\nVOLTAGES ARE:'); for k =1:nb fprintf('\nV(%d) = %.4f<%.2f',k,V(k),V_angle(k)); end fprintf('\n\nTHE REAL POWERS IN EACH BUS IN MW ARE:'); for k =1:nb fprintf('\nP(%d) = %.4f',k,Real_pow(k)); end fprintf('\n\nTHE REACTIVE POWERS IN EACH BUS IN MVar ARE:'); for k =1:nb fprintf('\nQ(%d) = %.4f',k,Reactive_pow(k)); end fprintf('\n'); if indx = = 4 break end end OUTPUT: Enter the acceleration constant: 1.02 GS LOAD FLOW ITERATION NO. 1 VOLTAGES ARE: V(1) = 1.0500<0.00 V(2) = 0.9926<-2.65 V(3) = 0.9881<-2.91 V(4) = 0.9967<-3.61 V(5) = 1.0200<-0.94 THE REAL POWERS IN EACH BUS IN MW ARE: P(1) = 67.3133 P(2) = -68.1565 P(3) = -8.3389 P(4) = -13.9469 P(5) = 48.6426 THE REACTIVE POWERS IN EACH BUS IN MVar ARE: Q(1) = 55.0891 Q(2) = -58.1404 Q(3) = -17.0080
Department of E & EE, SSIT, Tumkur 40
VII Semester
Q(4) = -7.6435 Q(5) = 5.5171 GS LOAD FLOW ITERATION NO. 2 VOLTAGES ARE: V(1) = 1.0500<0.00 V(2) = 0.9875<-3.50 V(3) = 0.9842<-4.72 V(4) = 0.9928<-5.05 V(5) = 1.0200<-1.82 THE REAL POWERS IN EACH BUS IN MW ARE: P(1) = 89.4186 P(2) = -75.8852 P(3) = -22.5474 P(4) = -13.4738 P(5) = 48.6714 THE REACTIVE POWERS IN EACH BUS IN MVar ARE: Q(1) = 56.9216 Q(2) = -62.7689 Q(3) = -14.2286 Q(4) = -8.3363 Q(5) = 9.7661 GS LOAD FLOW ITERATION NO. 3 VOLTAGES ARE: V(1) = 1.0500<0.00 V(2) = 0.9858<-4.14 V(3) = 0.9816<-5.67 V(4) = 0.9907<-5.96 V(5) = 1.0200<-2.38 THE REAL POWERS IN EACH BUS IN MW ARE: P(1) = 104.9689 P(2) = -85.2345 P(3) = -27.0838 P(4) = -14.4166 P(5) = 48.4644 THE REACTIVE POWERS IN EACH BUS IN MVar ARE: Q(1) = 56.5431 Q(2) = -61.8314 Q(3) = -14.4077 Q(4) = -8.2172 Q(5) = 11.9342
Department of E & EE, SSIT, Tumkur 41
VII Semester
GS LOAD FLOW ITERATION NO. 4 VOLTAGES ARE: V(1) = 1.0500<0.00 V(2) = 0.9846<-4.49 V(3) = 0.9800<-6.25 V(4) = 0.9895<-6.52 V(5) = 1.0200<-2.70 THE REAL POWERS IN EACH BUS IN MW ARE: P(1) = 113.4867 P(2) = -89.4466 P(3) = -30.2157 P(4) = -15.0810 P(5) = 48.2889 THE REACTIVE POWERS IN EACH BUS IN MVar ARE: Q(1) = 56.7268 Q(2) = -61.9553 Q(3) = -14.2487 Q(4) = -8.1218 Q(5) = 13.3465
42
VII Semester
Figure shows a single line diagram of a 6-bus system with two identical generating units, five lines and two transformers. Per-unit transmission line series impedances and shunt susceptances are given on 100 MVA base, generator's transient impedance and transformer leakage reactances are given in the accompanying table. If a 3-phase to ground fault occurs at bus 5, find the fault MVA. The data is given below. Bus-code p-q 3-4 3-5 3-6 5-6 4-6 Impedance Zpq 0.00+j0.15 0.00+j0.10 0.00+j0.20 0.00+j0.15 0.00+j0.10 Line Charging Ypq/2 0 0 0 0 0
Generator details: G1= G2 = 100MVA, 11KV with Xd =10% Transformer details: T1= T2 = 11/110KV , 100MVA, leakage reactance = X = 5%
**
VII Semester
SOLUTION: In transmission line data, elements 3 4 & 5 6 have common parameters. Elements 3 - 5 & 4 6 have common parameters. Therefore 3 libraries are required for transmission line. As generators G1 and G2 have same parameters, only one generator library is required. The same applies for transformers also. Procedure to enter the data for performing studies using Mi Power Mi Power - Database Configuration Open Power System Network Editor. Select menu option DatabaseConfigure. Configure Database dialog is popped up. Click Browse button.
Open dialog box is popped up as shown below, where you are going to browse the desired directory and specify the name of the database to be associated with the single line diagram. Click Open button after entering the desired database name. Configure Database dialog will appear with path chosen.
Select the folder and give database name in File name window with .Mdb extension. And now click on Open.
Click OK
44
VII Semester
Click on OK button in the Configure database dialog, the following dialog appears.
Uncheck the Power System Libraries and Standard Relay Libraries. For this example these standard libraries are not needed, because all the data is given on p u for power system libraries (like transformer, line\cable, generator), and relay libraries are required only for relay coordination studies. If Libraries are selected, standard libraries will be loaded along with the database. Click Electrical Information tab. Since the impedances are given on 100 MVA base, check the pu status. Enter the Base MVA and Base frequency as shown below. Click Breaker Ratings tab. If the data is furnished, modify the breaker ratings for required voltage levels. Otherwise accept the default values. Click OK button to create the database to return to Network Editor. Bus Base Voltage Configuration In the network editor, configure the base voltages for the single line diagram. Select menu option Configure Base voltage. Dialog shown below appears. If necessary change the Base-voltages, color, Bus width and click OK.
45
VII Semester
Procedure to Draw First Element - Bus Click on Bus icon provided on power system tool bar. Draw a bus and a dialog appears prompting to give the Bus ID and Bus Name. Click OK. Database manager with corresponding Bus Data form will appear. Modify the Area number, Zone number and Contingency Weightage data if it is other than the default values. If this data is not furnished, keep the default values. Usually the minimum and maximum voltage ratings are 5% of the rated voltage. If these ratings are other than this, modify these fields. Otherwise keep the default values. Bus description field can be effectively used if the bus name is more than 8 characters. If bus name is more than 8 characters, then a short name is given in the bus name field and the bus description field can be used to abbreviate the bus name. For example let us say the bus name is Northeast, then bus name can be given as NE and the bus description field can be North East. After entering data click save, which invokes Network Editor. Follow the same procedure for remaining buses. Following table gives the data for other buses. Bus Number Bus Name Nominal voltage Area number Zone number Contingency Weightage Bus data 1 2 Bus1 Bus2 11 11 1 1 1 1 1 1 3 Bus3 110 1 1 1 4 Bus4 110 1 1 1 5 Bus5 110 1 1 1 6 Bus6 110 1 1 1
Procedure to Draw Transmission Line Click on Transmission Line icon provided on power system tool bar. To draw the line click in between two buses and to connect to the from bus, double click LMB (Left Mouse Button) on the From Bus and join it to another bus by double clicking the mouse button on the To Bus .Element ID dialog will appear.
Enter Element ID number and click OK. Database manager with corresponding Line\Cable Data form will be open. Enter the details of that line as shown below. Enter Structure Ref No. as 1 and click on Transmission Line Library >> button. Line & Cable Library form will appear. Enter transmission line library data in the form as shown for Line3-4. After entering data, Save and Close. Line\Cable Data form will appear. Click Save, which invokes network editor. Data for remaining elements given in the following table. Follow the same procedure for rest of the elements.
46
VII Semester
Line Number Line Name De-Rated MVA No. Of Circuits From Bus No. To Bus No. Line Length From Breaker Rating To Breaker Rating Structure Ref No.
Transmission Line Element Data 1 2 3 Line3-4 Line3-5 Line3-6 100 100 100 1 1 1 3 3 3 4 5 6 1 1 1 5000 5000 5000 5000 5000 5000 1 2 3
Transmission Line Library Data Structure Ref. No. 1 2 Structure Ref. Name Line3-4 & 5-6 Line3-5 & 4-6 Positive Sequence Resistance 0 0 Positive Sequence Reactance 0.15 0.1 Positive Sequence Susceptance 0 0 Thermal Rating 100 100 Procedure to Draw Transformer
Click on Two Winding Transformer icon provided on power system tool bar. To draw the transformer click in between two buses and to connect to the from bus, double click LMB (Left Mouse Button) on the From Bus and join it to another bus by double clicking the mouse button on the To Bus Element ID dialog will appear. Click OK.
47
VII Semester
Transformer Element Data form will be open. Enter the Manufacturer Ref. Number as 30. Enter transformer data in the form as shown below. Click on Transformer Library >>button. Transformer library form will be open. Enter the data as shown below. Save and close library screen.
Transformer element data form will appear. Click Save button, which invokes network editor. In the similar way enter other transformer details.
48
VII Semester
2nd Transformer details Transformer Number 2 Transformer Name 2T2 From Bus Number 6 To Bus Number 2 Control Bus Number 2 Number of Units in Parallel 1 Manufacturer ref. Number 30 De Rated MVA 100 From Breaker Rating 5000 To Breaker Rating 350 Nominal Tap Position 5 Procedure to Draw Generator Click on Generator icon provided on power system tool bar. Draw the generator by clicking LMB (Left Mouse Button) on the Bus1. Element ID dialog will appear. Click OK.
Generator Data form will be opened. Enter the Manufacturer Ref. Number as 20. Enter Generator data in the form as shown below.
Click on Generator Library >> button. Enter generator library details as shown below. Save and Close the library screen. Generator data screen will be reopened. Click Save button, which invokes Network Editor. Connect another generator to Bus 2. Enter its details as given in the following table.
Department of E & EE, SSIT, Tumkur 49
VII Semester
2nd Generator details Name Bus Number Manufacturer Ref. Number Number of Generators in Parallel Capability Curve Number De-Rated MVA Specified Voltage Scheduled Power Reactive Power Minimum Reactive Power Maximum Breaker Rating Type of Modeling GEN-2 2 20 1 0 100 11 20 0 60 350 Infinite
Note: To neglect the transformer resistance, in the multiplication factor table give the X to R Ratio as 9999. TO solve short circuit studies choose menu option Solve Short Circuit Analysis or click on SCS button on the toolbar on the right side of the screen. Short circuit analysis screen appears.
2 Click here to open short circuit studies screen
Study Information.
50
Click OK
Afterwards click Execute. Short circuit study will be executed. Click on Report to view the report file.
51
VII Semester
Exercise: Simulate single line to ground fault, line to line fault for the above case. Exercise problems: 1. Using the available software package determine (a) fault current (b) post fault voltages at all buses (c) fault MVA , when a line to ground fault with / with out Zf = ___ occurring at _____ bus for a given test system.( Assume pre fault voltages at all buses to be 1 pu) compare the results with the symmetrical fault. 2. Using the available software package determine (a) fault current (b) post fault voltages at all buses (c) fault MVA , when a line to line & ground fault with / with out Zf = ___ occurring at _____ bus for a given test system.( Assume pre fault voltages at all buses to be 1 pu) compare the results with the symmetrical fault. Refer below question for Q.(1) & Q(2) Reactance of all transformers and transmission lines Zero sequence reactance of transmission line Negative sequence reactance of generator Zero sequence reactance of generator = 0.1 pu = 0.25 pu = Subtransient reactace = 0.1 pu
G1 X= 0.3
G2 X= 0.2
G3 X= 0.1 3. For the given circuit, find the fault currents, voltages for the following type of faults at Bus3. 1. Single Line to Ground Fault 2. Line to Line Fault 3. Double line to Ground Fault For the transmission line assume X 1=X 1, X 0=2.5 XL
52
VII Semester
Bus 1
Bus 2
Bus 3
G Xd= 0.3
Y
XL= 0.4
Xt = 0.1
4. For the given circuit, find the fault currents, voltages for the following type of faults at Specified location. 1. Single Line to Ground Fault 2. Double line to Ground Fault 3. Line to Line Fault Bus 1 Bus 2 Bus 3 Bus 4 G1 100MVA 13.8 kV X= 0.15 X2 = 0.17 X0= 0.05
Y
X1= X2= 20 X0= 60
53
VII Semester
9. LOAD FLOW STUDIES FOR A GIVEN POWER SYSTEM USING SOFTWARE PACKAGE
Figure below shows a single line diagram of a 5bus system with 2 generating units, 7 lines. Per unit transmission line series impedances and shunt susceptances are given on 100MVA Base, real power generation, real & reactive power loads in MW and MVAR are given in the accompanying table with bus1 as slack, obtain a load flow solution with Y-bus using GaussSiedel method and Newton Raphson method. Take acceleration factors as 1.4 and tolerances of 0.0001 and 0.0001 per unit for the real and imaginary components of voltage and 0.01 per unit tolerance for the change in the real and reactive bus powers.
(1)
(3)
(4)
(2)
G
(5)
IMPEDANCES AND LINE CHARGING ADMITTANCES FOR THE SYSTEM Table: 1.1 Impedance Line Charging R+jX B/2 0.02+j0.06 j 0.030 0.08+j0.24 j 0.025 0.06+j0.18 j 0.020 0.06+j0.18 j 0.020 0.04+j0.12 j 0.015 0.01+j0.03 j 0.010 0.08+j0.24 j 0.025
Bus cone From-To 1-2 1-3 2-3 2-4 2-5 3-4 4-5
54
VII Semester
GENERATION, LOADS AND BUS VOLTAGES FOR THE SYSTEM Bus No 1 2 3 4 5 Bus Voltage 1.06+j0.0 1.00+j0.0 1.00+j0.0 1.00+j0.0 1.00+j0.0 Table: 1.2 Generation Generation MW MVAR 0 0 40 30 0 0 0 0 0 0 Load MW 0 20 45 40 60 Load MVAR 0 10 15 5 10
Procedure to enter the data for performing studies using MiPower MiPower - Database Configuration Open Power System Network Editor. Select menu option Database Configure. Configure Database dialog is popped up as shown below. Click Browse button.
Open dialog box is popped up as shown below, where you are going to browse the desired directory and specify the name of the database to be associated with the single line diagram. Click Open button after entering the hired database name. Configure Database dialog will appear with path chosen.
55
VII Semester
Note: Do not work in the MiPower directory. Click OK button on the Configure database dialog. The dialog shown below appears.
Uncheck the Power System Libraries and Standard Relay Libraries. For this example these standard libraries are not needed, because all the data is given on pu for power system libraries (like transformer, line\cable, generator), and relay libraries are required only for relay coordinate studies. If Libraries are selected, standard libraries will be loaded along with the database. Click Electrical Information tab. Since the impedances are given on 100 MVA base, check the pu status. Enter the Base and Base frequency as shown below. Click on Breaker Ratings button to give breaker ratings. Click OK to create the database to return to Network Editor.
Bus Base Voltage Configuration In the network editor, configure the base voltages for the single line diagram. Select menu option ConfigureBase voltage. The dialog shown below appears. If necessary change the Base-voltages, color, Bus width and click OK.
56
VII Semester
Procedure to Draw First Element - Bus Click on Bus icon provided on power system tool bar. Draw a bus and a dialog appears prompting to give the Bus ID and Bus Name. Click OK. Database manager with corresponding Bus Data form will appear. Modify the Area number, Zone number and Contingency Weightage data if it is other than the default values. If this data is not furnished, keep the default values. Usually the minimum and maximum voltage ratings are 5% of the rated voltage. If these ratings are other than this, modify these fields. Otherwise keep the default values. Bus description field can be effectively used if the bus name is more than 8 characters. If bus name is more than 8 characters, then a short name is given in the bus name field and the bus description field can be used to abbreviate the bus name. For example let us say the bus name is Northeast, then bus name can be given as NE and the bus description field can be North East.
57
VII Semester
58
VII Semester
59
VII Semester
60
VII Semester
61
VII Semester
62
VII Semester
63
VII Semester
64
VII Semester
Signature of the Staff Incharge Exercise Problems: 1. Using the available software package conduct load flow analysis for the given power system using Gauss-Siedel / Newton-Raphson / Fast decoupled load flow method. Determine (a) Voltage at all buses (b) Line flows (c) Line losses and (d) Slack bus power. Also draw the necessary flow chart ( general flow chart) 2. Using the available software package conduct load flow analysis for the given power system using Gauss-Siedel / Newton-Raphson / Fast decoupled load flow method. Determine (a) Voltage at all buses (b) Line flows (c) Line losses and (d) Slack bus power. Also draw the necessary flow chart ( general flow chart), Compare the results with the results obtained when (i) a line is removed (ii) a load is removed. Refer below question for Q.(1) & Q(2) Consider the 3 bus system of figure each of the line has a series impedence of (0.02 + j0.08) p.u. & a total shunt admittance of j 0.02 p.u. The specified quantities at the buses are tabulated below on 100 MVA base.
65
VII Semester
Bus No. 1 2 3
Voltage Specification V1 = (1.04 + j 0) (Slack Bus) Unspesified (PQ Bus) V3 = 1.04 (PV Bus)
Controllable reactive power source is available at bus 3 with the constraint 0 QG3 1.5 p.u. Find the load flow solution using N R method. Use a tolerance of 0.01 for power mismatch. G1 G2
(1)
(2)
(3)
G3 3. Figure shows the one line diagram of a simple three bus system with generation at bus 1, the voltage at bus 1 is V1 = 1.0<00 pu. The scheduled loads on buses 2 and 3 are marked on diagram. Line impedances are marked in pu on a 100MVA base. For the purpose of hand calculations line resistances and line charging susceptances are neglected. Using Gauss-Seidel method and initial estimates of V2 = 1.0<00 pu & V3 = 1.0<00 pu. Conduct load flow analysis. G
j0.03333
Bus 2 (400+j320) MW
j0.0125
66
VII Semester
10. OPTIMAL GENERATOR SCHEDULING FOR THERMAL POWER PLANTS USING SOFTWARE PACKAGE
67
VII Semester
68
VII Semester
69
VII Semester
70
VII Semester
71
VII Semester
Exercise Problems: 1. Data given: Total No. of Generators Total Demand :2 : 100MW
GENERATOR RATINGS: GENERATOR 1: Pscheduled = 70 MW ; Pmin= 0.0MW; Pmax= 100MW C0 = 50 ; C1 = 16 ; C2 = 0.015 Cg1 = 50 + 16 P1 + 0.015 P12 Rs / hr GENERATOR 2: Pscheduled = 70 MW; Pmin= 0.0MW; Pmax= 100MW C0 = 30 ; C1 = 12 ; C2 = 0.025 Cg1 = 30 + 12 P1 + 0.025 P12 Rs / hr Loss ( or B) Co- efficients : B11 = 0.005; B12 = B21 = 0.0012;
Department of E & EE, SSIT, Tumkur
B22 = 0.002
72
VII Semester
2. Given the cost equation and loss Co-efficient of different units in a plant determine economic generation using the available software package for a total load demand of _____ MW ( typically 150 MW for 2 units and 250 MW for 3 Units) neglecting transmission losses. 3. Given the cost equation and loss Co-efficient of different units in a plant determine penalty factor, economic generation and total transmission loss using the available software package for a total load demand of _____ MW ( typically 150 MW for 2 units and 250 MW for 3 Units) . Refer below questions for Q(2) & Q(3) A) Unit No. 1 2 3 Cost of Fuel input in Rs./ hr. C1 = 800 + 20 P1 + 0.05 P12 0 P1 100 2 C2 = 1000 + 15 P2 + 0.06 P2 0 P2 100 2 C3 = 900 + 18 P3 + 0.07 P3 0 P3 100
Loss ( or B) Co- efficients : B11 = 0.0005 B12 = 0.00005 B13 = 0.0002 B22 = 0.0004 B23 = 0.00018 B33 = 0.0005 B21 = B12 B) Unit No. Cost of Fuel input in Rs./ hr. 1 C1 = 50 + 16 P1 + 0.015 P12 0 P1 100 2 2 C2 = 30 + 12 P2 + 0.025 P2 0 P2 100 Loss ( or B) Co- efficients : B11 = 0.005 B12 = B21 = -0.0012 B22 = 0.002 B32 = B23 B13 = B31
73
VII Semester
VIVA QUESTIONS
FORMATION OF Z BUS & Y BUS: 1. 2. 3. 4. 5. What is meant by graph and sub graph? Define tree and co-tree of a network? What is meant by cut set and basic cut set? What is ment by bus incidence matrix (A)? Write the performance equation of an element both in impedance form and in admittance form.
DETERMINATION OF ABCD CONSTANTS: 1. Define Regulation and efficiency of transmission line. 2. Write the expression for Vs and Is in terms of Vr, Ir and ABCD constants. SWING EQUATION: 1. Write the swing equation for a synchronous m/c connected to an infinite bus and explain the terms. 2. What is swing curve and what are its uses? 3. What are the assumptions made in the solution of swing equation? LOAD FLOW STUDIES: 1. 2. 3. 4. 5. 6. What is load flow analysis? How the bases are classified in load flow studies? What is the data required to carry out load flow analysis? What is the significance of slack bus? What are the methods of load flow analysis? Write down the equation for the calculation of voltage at any bus in Gauss & Gauss sidle iterative method. 7. What are acceleration factors? What for they are used? 8. What are the advantages of NR method over Gauss seidel method of load flow analysis? 9. What is meant by Fast decoupled load flow analysis? FAULT STUDIES: 1. What are the various types of faults that occur normally on power system? 2. What are the parameters considered for a fault study? 3. How the sequence networks are connected for (i) L-L-G fault (ii) LL fault (iii) L-G fault. 4. Write down the fault current equation for (i) single line to ground fault (ii) double line to ground fault (iii) LL fault 5. What are the limitations of ungrounded system? 6. Write zero sequence equivalent for (i) Y-Y (ii) Y- (iii) (iv)Y-Y
74
VII Semester
ECONOMIC OPERATION OF POWER SYSTEM: 1. 2. 3. 4. What do you mean by Economic operation of a power system? Name the performance characteristic curves of a turbo generator boiler unit. What are heat rate, incremental fuel rate and incremental fuel cost of a unit? Write down the co-ordination equation for economic operation of generators in a thermal plant when (i) transmission losses are neglected (ii) transmission losses are considered. 5. What is penalty factor? Write down the total transmission loss formula in terms of B Co-efficient.
QUESTION BANK
3. Using singular transformation analysis, determine the bus admittance matrix of given test system. 4. Using singular transformation analysis, determine Ybus for a given test system with mutual coupling of j0.01 pu between the line numbers _____ & ______ Neglect line charging. 5. Using singular transformation analysis, determine the bus admittance matrix of given test system & hence find Zbus. 6. Using singular transformation analysis, determine Ybus for a given test system with mutual coupling of j0.01 pu between the line numbers _____ & ______ & hence find Zbus _______ . Neglect line charging. Refer below figure for Q.(1) Q.(4)
1
(0.0125 + j0.025)
(0.02 + j0.04)
2
(0.0125 + j0.025)
(0.01 + j0.03)
7. Given any two of the I/O parameters given either (Vs, Is) or (Vr ,Ir) of a two port short transmission line network ( 0-80km or 0-50 miles), determine the following . Regulation . Efficiency ( The line impedance and admittance values are to be specified) 8. Given any two of the I/O parameters given either (Vs, Is) or (Vr ,Ir) of a two port short transmission line network ( >80km 24 km or > 50 miles to 150 miles), determine the following . Regulation . Efficiency ( The line impedance and admittance values are to be specified)
75
VII Semester
9.
Given any two of the I/O parameters given either (Vs, Is) or (Vr ,Ir) of a two port short transmission line network ( >240km or >150 miles), determine the following . Regulation . Efficiency ( The line impedance and admittance values are to be specified)
10. Given any two of the I/O parameters of a two port short transmission line system and for a given set of line parameters ( Z & Y) and length _______km( >240km or >150 miles),determine the following (i) ABCD constants and hence the generalized equivalent circuit (ii) Regulation, (iii) Efficiency 11. Determine the generalized circuit constants for a transmission line with the following Data: (a) Line length: _________________ km (b) Line impedance : _____________ /km (c) Total shunt admittance : ___________________ mho / km 12. The system having a single machine connected to an infinite bus has the following data. Pi =0.9 M= 0.016 ( 2.8 10 -4 S / electrical Degree) E1 = 1.1 Transfer reactance before fault Xo = 0.45 pu E2 = 1.0 Transfer reactance during fault X1 = 1.25 pu Plot the swing curve ( either using graph sheet or any grapher software) for sustained fault step by step method up to 1 second. 13. The system having a single machine connected to an infinite bus has the following data.Write and execute a program to plot the swing curve when the fault is cleared in 0.125 seconds. Pi =0.9 M= 0.016 ( 2.8 10 -4 S / electrical Degree) E1 = 1.1 Transfer reactance before fault Xo = 0.45 pu E2 = 1.0 Transfer reactance during fault X1 = 1.25 pu Transfer reactance after clearing the fault X2 = 0.55 pu Plot the swing curve ( either using graph sheet or any grapher software) for a fault cleared in _______ ( Typically 0.3 & 0.42 second) or ______ cycle using step by step method . 14. Using the available software package conduct load flow analysis for the given power system using Gauss-Siedel / Newton-Raphson / Fast decoupled load flow method. Determine (a) Voltage at all buses (b) Line flows (c) Line losses and (d) Slack bus power. Also draw the necessary flow chart ( general flow chart) 15. Using the available software package conduct load flow analysis for the given power system using Gauss-Siedel / Newton-Raphson / Fast decoupled load flow method. Determine (a) Voltage at all buses (b) Line flows (c) Line losses and
Department of E & EE, SSIT, Tumkur 76
VII Semester
(d) Slack bus power. Also draw the necessary flow chart ( general flow chart), Compare the results with the results obtained when (i) a line is removed (ii) a load is removed. Refer below question for Q.(12) & Q(13) Consider the 3 bus system of figure each of the line has a series impedence of (0.02 + j0.08) p.u. & a total shunt admittance of j 0.02 p.u. The specified quantities at the buses are tabulated below on 100 MVA base. Bus No. 1 2 3 Real Load Demand PD 2.0 0.0 0.5 Reactive Load Demand QD 1.0 0.0 0.6 Real Power Generation PG Unspesified 0.5 0.0 Reactive Power Generation QG Unspesified 1.0 QG3 = ? Voltage Specification V1 = (1.04 + j 0) (Slack Bus) Unspesified (PQ Bus) V3 = 1.04 (PV Bus)
Controllable reactive power source is available at bus 3 with the constraint 0 QG3 1.5 p.u. Find the load flow solution using N R method. Use a tolerance of 0.01 for power mismatch. G1 G2
(1)
(2)
(3)
G3 14. Given the cost equation and loss Co-efficient of different units in a plant determine economic generation using the available software package for a total load demand of _____ MW ( typically 150 MW for 2 units and 250 MW for 3 Units) neglecting transmission losses. 15. Given the cost equation and loss Co-efficient of different units in a plant determine penalty factor, economic generation and total transmission loss using the available software package for a total load demand of _____ MW ( typically 150 MW for 2 units and 250 MW for 3 Units) . Refer below questions for Q.(14) & Q(15) A) Unit No. 1 2 3 Cost of Fuel input in Rs./ hr. C1 = 800 + 20 P1 + 0.05 P12 0 P1 100 2 C2 = 1000 + 15 P2 + 0.06 P2 0 P2 100 C3 = 900 + 18 P3 + 0.07 P32 0 P3 100
77
VII Semester
B11 = 0.0005 B12 = 0.00005 B13 = 0.0002 B22 = 0.0004 B23 = 0.00018 B33 = 0.0005 B21 = B12 B32 = B23 B13 = B31
B) Unit No. Cost of Fuel input in Rs./ hr. 1 C1 = 50 + 16 P1 + 0.015 P12 0 P1 100 2 C2 = 30 + 12 P2 + 0.025 P22 0 P2 100 Loss ( or B) Co- efficients : B11 = 0.005 B12 = B21 = -0.0012 B22 = 0.002
16. Using the available software package determine (a) fault current (b) post fault voltages at all buses (c) fault MVA , when a line to ground fault with / with out Zf = ___ occurring at _____ bus for a given test system.( Assume pre fault voltages at all buses to be 1 pu) compare the results with the symmetrical fault. 17. Using the available software package determine (a) fault current (b) post fault voltages at all buses (c) fault MVA , when a line to line & ground fault with / with out Zf = ___ occurring at _____ bus for a given test system.( Assume pre fault voltages at all buses to be 1 pu) compare the results with the symmetrical fault. Refer below question for Q.(16) & Q(17) Reactance of all transformers and transmission lines Zero sequence reactance of transmission line Negative sequence reactance of generator Zero sequence reactance of generator = 0.1 pu = 0.25 pu = Subtransient reactace = 0.1 pu
G1 X= 0.3
G2 X= 0.2
G3 X= 0.1
78