Sno 1 2 3 4 5 6 7 8 9 10 11 12 13

Item Glycol Flash Tank Surge Tank Glycol Reboiler Inlet Gas Scrubber Glycol Contactor Outlet Scrubber RichTEG Filter Activated Carbon Filter STAHL Column Reflux Condenser and STILL column Gas/Lean Glycol Heat Exchanger HP Lean/Rich Glycol Exchanger LP Lean/Rich Glycol Exchanger

Tagno 402-V-0814,402-V-0824 402-v-0815, 402-V-0825 402-E-0814,402-E-0824 402-V-0811,0821 402-C-0811/0821 402-V-0813/0823 402-S-8012,0822 402-S-0813 A/B, 402-S-0823 A/B 402-C-0813,0823 402-E-0812/0822& 402-C-0812/0822 402-E-0811/0821 402-E-0813/0823 402-E-0815/0825

Quantity 2 2 2 2 2 2 4 4 2 2 2

Vendor PSA Nitrogen Limited Faridabad PSA Nitrogen Limited Faridabad PSA Nitrogen Limited Faridabad INDICON PROJECTS & EQUIPMENT LTD FARIDABAD INDICON PROJECTS & EQUIPMENT LTD FARIDABAD INDICON PROJECTS & EQUIPMENT LTD FARIDABAD INDICON PROJECTS & EQUIPMENT LTD DELHI INDICON PROJECTS & EQUIPMENT LTD DELHI INDICON PROJECTS & EQUIPMENT LTD DELHI INDICON PROJECTS & EQUIPMENT LTD DELHI INDICON PROJECTS & EQUIPMENT LTD DELHI ????????????????????????????????? ?????????????????????????????????

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Inlet Scrubber Description Schedule Given New Schedule Plate/Pipe Identification 10/5/2012 Dish 25/5/2012 Shell Cutting 15/5/2012 Shell Roll 25/5/2012 Long Seam Setup 30/5/2012 Welding 20/6/2012 C-Seam Setup 25/6/2012 C-Seam Welding 5/7/2012 First Dish End Setup/Body Flange 5/7/2012 Welding 10/7/2012 Nozzle Cutting 15/7/2012 Nozzle Setup+Welding 25/7/2012 Internal Fitment 30/7/2012 Closing Dish End Setup & Welding of body Flange 5/8/2012 Skirt/Saddle/Leg Support Fitment 10/8/2012 Heat Treatment N/A Vessel Hydro Testing 15/8/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Glycol Contactor Description Schedule Given Plate/Pipe Identification 15/5/2012 Dish 5/6/2012 Shell Cutting 20/5/2012 Shell Roll 30/5/2012 Long Seam Setup 15/6/2012 Welding 5/7/2012 C-Seam Setup 15/7/2012 C-Seam Welding 30/7/2012 First Dish End Setup/Body Flange 30/7/2012 Welding 5/8/2012 Nozzle Cutting 10/8/2012 Nozzle Setup+Welding 25/8/2012 Internal Fitment 30/8/2012 Closing Dish End Setup & Welding of body Flange 5/9/2012 Skirt/Saddle/Leg Support Fitment 10/9/2012 Heat Treatment N/A Vessel Hydro Testing 15/9/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Outlet Scrubber Description Schedule Given New Schedule Plate/Pipe Identification 10/5/2012 Dish 25/5/2012 Shell Cutting 15/5/2012 Shell Roll 25/5/2012 Long Seam Setup 30/5/2012 Welding 15/6/2012 C-Seam Setup 20/6/2012 C-Seam Welding 30/6/2012 First Dish End Setup/Body Flange 30/6/2012 Welding 5/7/2012 Nozzle Cutting 10/7/2012 Nozzle Setup+Welding 20/7/2012 Internal Fitment N/A Closing Dish End Setup & Welding of body Flange 25/7/2012 Skirt/Saddle/Leg Support Fitment 30/7/2012 Heat Treatment 5/8/2012 Vessel Hydro Testing 10/8/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Manufacturing Schedule for ARPL GDU-Glycol Flash Tank Description Given Schedule New Schedule Plate Material Marking 15/5/2012 Flange Plate Manufacturing 22/5/2012 Pipe Marking 22/5/2012 Dish(Vendor) 22/5/2012 Shell Cutting 17/5/2012 Shell Roll 19/5/2012 Long Seam Setup 21/5/2012 Welding 22/5/2012 Back Chip 23/5/2012 C-Seam Setup(Shell) 24/5/2012 Welding From Dish 26/5/2012 C-Seam Welding 29/5/2012 First Dish End setup 30/5/2012 Welding 1/6/2012 Back Chip+welding 2/6/2012 Partition plate & Welding 11/6/2012 Nozzle Cutting 12/6/2012 Nozzle Setup+Welding 18/6/2012 Shell Closing & Dish Welding 19/6/2012 Saddle & Welding 26/6/2012 Radiography 4/7/2012 Internal Assembly 12/7/2012 Vessel Hydrotesting 13/7/2012

Sno

Manufacturing Schedule for ARPL GUD-Glycol Exchangers(HPLP_LeanRich Description Schedule Given New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Manufacturing Schedule for ARPL GDU-Glycol Surge Tank Description Given Schedule New Schedule Plate Material Marking 15/5/2012 Flange Plate Manufacturing 22/5/2012 Pipe Marking 22/5/2012 Dish(Vendor) 22/5/2012 Shell Cutting 17/5/2012 Shell Roll 19/5/2012 Long Seam Setup 21/5/2012 Welding 22/5/2012 Back Chip 23/5/2012 C-Seam Setup(Shell) 24/5/2012 Welding From Dish 26/5/2012 C-Seam Welding 29/5/2012 First Dish End setup 30/5/2012 Welding 1/6/2012 Back Chip+welding 2/6/2012 Partition plate & Welding 11/6/2012 Nozzle Cutting 12/6/2012 Nozzle Setup+Welding 18/6/2012 Shell Closing & Dish Welding 19/6/2012 Saddle & Welding 26/6/2012 Radiography 4/7/2012 Internal Assembly 12/7/2012 Vessel Hydrotesting 13/7/2012

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Rich TEG,ACF Description Schedule Given Plate/Pipe Identification 10/5/2012 Dish 20/5/2012 Shell Cutting pipe Shell Roll N/A Long Seam Setup N/A Welding N/A C-Seam Setup N/A C-Seam Welding N/A First Dish End Setup/Body Flange 30/5/2012 Welding 10/6/2012 Nozzle Cutting 20/6/2012 Nozzle Setup+Welding 30/6/2012 Internal Fitment 5/7/2012 Closing Dish End Setup & Welding of body Flange 10/7/2012 Skirt/Saddle/Leg Support Fitment 20/7/2012 Heat Treatment N/A Vessel Hydro Testing 30/7/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

New Schedule

Status 10/5/2012 20/5/2012 15/5/2012 20/5/2012 25/5/2012 30/5/2012 N/A N/A N/A N/A 10/6/2012 20/6/2012 30/6/2012 5/7/2012 10/7/2012 N/A 15/7/2012

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Manufacturing Schedule for ARPL GDU-Glycol Reboiler Description Given Schedule New Schedule Plate Material Marking 15/5/2012 Flange Plate Manufacturing 22/5/2012 Pipe Marking 22/5/2012 Dish(Vendor) 22/5/2012 Shell Cutting 17/5/2012 Shell Roll 19/5/2012 Long Seam Setup 21/5/2012 Welding 22/5/2012 Back Chip 23/5/2012 C-Seam Setup(Shell) 24/5/2012 Welding From Dish 26/5/2012 C-Seam Welding 29/5/2012 First Dish End setup 30/5/2012 Welding 1/6/2012 Back Chip+welding 2/6/2012 Partition plate & Welding 11/6/2012 Nozzle Cutting 12/6/2012 Nozzle Setup+Welding 18/6/2012 Shell Closing & Dish Welding 19/6/2012 Saddle & Welding 26/6/2012 Radiography 4/7/2012 Internal Assembly 12/7/2012 Vessel Hydrotesting 13/7/2012

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Chemical Injection Tank Description Schedule Given Plate/Pipe Identification 15/7/2012 Dish N/A Shell Cutting 20/7/2012 Shell Roll N/A Long Seam Setup N/A Welding 30/7/2012 C-Seam Setup N/A C-Seam Welding N/A First Dish End Setup/Body Flange N/A Welding N/A Nozzle Cutting 5/8/2012 Nozzle Setup+Welding 15/8/2012 Internal Fitment N/A Closing Dish End Setup & Welding of body Flange N/A Skirt/Saddle/Leg Support Fitment 20/8/2012 Heat Treatment N/A Vessel Hydro Testing 30/8/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-STILL COLUMN Description Schedule Given Plate/Pipe Identification 15/7/2012 Dish N/A Shell Cutting 20/7/2012 Shell Roll N/A Long Seam Setup N/A Welding N/A C-Seam Setup N/A C-Seam Welding N/A First Dish End Setup/Body Flange 30/7/2012 Welding 5/8/2012 Nozzle Cutting 5/8/2012 Nozzle Setup+Welding 10/8/2012 Internal Fitment N/A Closing Dish End Setup & Welding of body Flange N/A Skirt/Saddle/Leg Support Fitment N/A Heat Treatment N/A Vessel Hydro Testing 30/8/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-STAHL COLUMN Description Schedule Given Plate/Pipe Identification 10/5/2012 Dish 20/5/2012 Shell Cutting pipe Shell Roll N/A Long Seam Setup N/A Welding N/A C-Seam Setup N/A C-Seam Welding N/A First Dish End Setup/Body Flange 30/5/2012 Welding 10/6/2012 Nozzle Cutting 20/6/2012 Nozzle Setup+Welding 30/6/2012 Internal Fitment 5/7/2012 Closing Dish End Setup & Welding of body Flange 10/7/2012 Skirt/Saddle/Leg Support Fitment 20/7/2012 Heat Treatment N/A Vessel Hydro Testing 30/7/2012 Tube Sheet/Baffle Drilling Bundle Readiness Channel Shell Readiness Nozzle Cutting/Welding Saddel Support Fitment Bundle Insertion PWHT Hydro Test of Exchanger Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

N New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Gas Glycol Hxer Description Schedule Given Plate/Pipe Identification 30/5/2012 Dish 10/6/2012 Shell Cutting 5/6/2012 Shell Roll 15/6/2012 Long Seam Setup 20/6/2012 Welding 30/6/2012 C-Seam Setup C-Seam Welding First Dish End Setup/Body Flange Welding Nozzle Cutting Nozzle Setup+Welding Internal Fitment Closing Dish End Setup & Welding of body Flange Skirt/Saddle/Leg Support Fitment Heat Treatment Vessel Hydro Testing Tube Sheet/Baffle Drilling 15/7/2012 Bundle Readiness 30/7/2012 Channel Shell Readiness 30/7/2012 Nozzle Cutting/Welding 10/8/2012 Saddel Support Fitment 15/8/2012 Bundle Insertion 20/8/2012 PWHT N/A Hydro Test of Exchanger 30/8/2012 Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

New Schedule

Sno 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Manufacturing Schedule for ARPL GUD-Reflux Condenser Description Schedule Given Plate/Pipe Identification 30/5/2012 Dish N/A Shell Cutting N/A Shell Roll N/A Long Seam Setup N/A Welding N/A C-Seam Setup C-Seam Welding First Dish End Setup/Body Flange Welding Nozzle Cutting Nozzle Setup+Welding Internal Fitment Closing Dish End Setup & Welding of body Flange Skirt/Saddle/Leg Support Fitment Heat Treatment Vessel Hydro Testing Tube Sheet/Baffle Drilling 15/7/2012 Bundle Readiness 30/7/2012 Channel Shell Readiness 30/7/2012 Nozzle Cutting/Welding 10/8/2012 Saddel Support Fitment N/A Bundle Insertion 20/8/2012 PWHT N/A Hydro Test of Exchanger 30/8/2012 Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

Status

1 2 3 4 5 6

Base Frame/Structure Mounting of Vessels on Base Frame Piping Spool Fabrication & assembly check Dismantling and Piping Spool Hydro Painting Despatch

Dehydration Skid 10/9/2012 20/9/2012 10/10/2012 20/10/2012 27/10/2012 30/10/2012

Regeneration Skid 30/8/2012 10/9/2012 10/10/2012 20/10/2012 27/10/2012 30/10/2012