Matter of email

23.07.2008
Ma'am / Sir,
In further continuation to my messages dated 15.07.2008 ,16.07.2008 .19.07.2008
and 22.07.2008 transmitted by e-mail you are requested to please monitor that the
mud cleaning is satisfactority done which is still found accumalated on the base of
raft of TG Unit No.5 proposed to cast .The mud is dry hence it can comfactably be
removed .
This observation has also been made by GM [Quality] APL , Ahmedabad Office during
his visit to site on 22.07.2008 and 23.07.2008.
Thanks.
With regards.
K.P.Chakerwarti,
Deputy General Manager,
Field Quality Assurance,
5 x 660 MW TPP,
Adani Power Limited