b)
Calculul termenului minim de realizare al fiecrei faze.
t1m=0 zile
t2m= t1m+dA=0+4=4 zile
t3m= t2m+dE=4+5=9 zile
t4m= t2m+dD=4+5=9 zile
t5m= t2m+dB=4+2=6 zile
t6m=t2m+dC=4+2=6 zile
t7m=max{(t4m+dJ);(t5m+dF);(t5m+dG)}=max{(9+4);(6+2);(6+2)}=13 zile
t8m= t5m+ dG=6+2=8 zile
t9m=max{( t5m+dG);( t5m+dI);( t6m+dH)}=max{(6+2);(6+3);(6+3)}=9 zile
t10m=max{( t7m+dK);( t8m+dL);( t9m+dM)}=max{(13+3);(8+5);(9+5)}=16 zile
Calculul termenului maxim de realizare al fiecrei faze
t10M=16 zile
t9M= t10M-dM=16-5=11 zile
t8M= min{(t10M-dL);(t7M-0);(t9M-0)}=min{(16-5);(13-0);(11-0)}=11 zile
t7M= t10M-dK=16-3=13 zile
t6M= t9M-dH=11-3=8 zile
t5M=min{( t7M-dF);(t8M-dG);(t9M-dI)}=min{(13-2);(11-2);(11-3)}=8 zile
t4M= t7M-dJ=13-4=9 zile
t3M= t10M-0=16-0=16 zile
t2M=min{( t3M-dE);( t4M-dD);( t5M-dB);( t6M-dC)}=min{(11-5);(9-5);(8-2);(8-2)}=4 zile
t1M= t2M-dA=4-4=0 zile
Calculul rezervelor totale de timp pentru fiecare activitate
RtA= t2M- t1m-dA=4-0-4=0 zile
RtB= t5M- t2m-dB=8-4-2=2 zile
RtC= t6M- t2m-dC=8-4-2=2 zile
RtD= t4M- t2m-dD=9-4-5=0 zile
RtE= t3M- t2m-dE=16-4-5=7 zile
RtF= t7M- t5m-dF=13-6-2=5 zile
RtG= t8M- t5m-dG=11-6-2=3 zile
RtH= t9M- t6m-dH=11-6-3=2 zile
RtI= t9M- t5m-dI=11-6-3=2 zile
RtJ= t7M- t4m-dJ=13-9-4=0 zile
RtK= t10M- t7m-dK=16-13-3=0 zile
RtL= t10M- t8m-dL=16-8-5=3 zile
RtM= t10M- t9m-dM=16-9-5=2 zile
Rezult:
- activitile critice: A; D; J; K
- lungimea drumului critic : dA+dD + dJ +dK = 4 +5+4+3=16 zile
- proiectul nu poate fi terminat mai devreme de 16 de zile
F
3
2
5
G
2
C
4
D
7
H
6
I
3
05.09
Axa timpului
A
B
C
D
E
F
G
H
I
B
A
A
A, C
E, F
D
H, G
zile
3
4
2
5
6
3
4
8
2
a)S se construiasc graficul Gantt tiind c termenul cel mai devreme prevzut pentru
nceputul proiectului este 25 septembrie 2012.
b)S se elaboreze programul de realizare al proiectului.
Rezolvare:
a.Construirea graficului reea