PROVIDING & CONSTRUCTING 230 THK. BRICK MASONRY IN CEMENT MORTOR 1:6 USING DEFECTLESS,SHARP EDGED TABLE MOULDED WELL BURNT, UNIFORM SIZE, APPROVED QUALITY BRICKS ADEQUATELY SOAKED IN WATER BEFORE USE FOR SUPER STRUCTURE,ETC., INCLUDING RACKING, SCAFFOLDING, CURING ETC., COMPLETE AS DIRECTED UP TO 3.00 MTR ABOVE GROUND LEVEL.
SL NO Unit = Cum Taking output = 1.00 Cum DESCRIPTION UNIT QUANTITY RATE Rs COST Rs
a)
b)
Material Brick Cement Sand Construction water Labour Mate Mason Unskilled
Total cost ( Material Cost + Labour Cost ) Add 10% profit including PPE cost, tools and tackles, Administrative charges and other incidental charges etc. Total cost for 5 Cum c+d Effectivbe cost / 1 Cum