To The Engineer Dear Sir Legally/Physically Impossible Work

Date..

Pursuant to Clause 13.1 of the Conditions we write to give notice that having examined your Drawings .. it is apparent that the work as designed cannot be constructed because it fails to .. /or is physically impossible to construct because.. Since this is a matter for which we are not liable under Clause 13.1 may we request an instruction to vary the works pursuant to Clause 51.1 Yours faithfully

Contractor Ltd