To The Engineer Dear Sir Notice to treat Suspended Work as Omitted from Contract

Date..

We refer to our letter dated . Seeking your agreement to proceed with the contract works/part of the work and note that the periods of 28 days have now elapsed since our request to proceed. We write therefore to give notice pursuant to Clause 40.3 that we elect to treat the suspension as an event of default by the Employer and terminate our employment under the Contract in accordance with the provisions of Clause 69.1 of the Conditions/an omission of the suspended part of the Contract under Clause 51 Yours faithfully

Contractor Ltd