Chapter 5 Scheduling the Project

This chapter covers the topic of scheduling, probably the most extensively covered subject dealing with project management. In addition to the usual PERT and CPM networks, Gantt charts, etc., the subject of project uncertainty and risk management is also discussed. The use of computer simulation and Crystal Ball to generate the approximate distribution of project completion times to help better understand the implications associated with schedule uncertainty is also discussed.

Cases and Readings


A case appropriate to the subject of this chapter is: Harvard: 9-613-021 Arrow Diagramming Exercise This 3-page case describes the marketing campaign for a newly developed industrial hardware item. Over two-dozen activities are noted and described. The case asks for the network diagram and critical path. A reading appropriate to the subject of this chapter is: L.P. Leach. Critical Chain Project Management Improves Project Performance (Project Management Journal, June 1999, p. 39-51). This article explains the procedures developed by E. Goldratt in his Critical Chain approach to project management. Includes a discussion of project and feeder buffers. Projects using the critical chain often report significantly improved schedule, cost, and scope performance.

Answers to Review Questions


1. How would a PM manager critical path tasks differently than noncritical tasks? By definition, critical tasks are those tasks that if delayed will delay the completion of the entire project. Therefore, these tasks should be managed more closely than non-critical tasks. In cases where the activity times are not known with certainty, the tasks assumed to be critical at the beginning of the project may turn out not to be so critical. Therefore, when tasks times are uncertain, all tasks that may reasonably delay project completion must be carefully managed. 2. How is slack determined? Slack for a particular task is calculated by: o Subtracting the earliest time the task can start from the latest time the task can start, o Subtracting the earliest time the task can finish from the latest time the task can finish. Both calculations result in the same slack and indicate a window in which the task can be started and finished without delaying the entire project. The slack for a particular path is calculated by subtracting the paths duration from the critical paths duration and provides an indication of how much the path can be delayed without delaying the completion of the project. 3. How do you determine the EST for an activity with two predecessors? How do you determine the LFT for an activity with two successors? The earliest start time for an activity with two predecessors is equal to the later earliest finish time of the two predecessors since both predecessors must be completed for the task to begin. The latest finish time for an activity with two successors is equal to the smaller latest start time of the two successors. If the larger were used, then the preceding task would be permitted to finish after the latest start time of the other successor.

4. Will all activities on a noncritical path have the same slack? Why or why not? No, all activities on the same non-critical path will not necessarily have the same slack. This is because a particular activity may be on multiple paths. When an activity is on more than one path, its slack is determined by the path with the least amount of slack. 5. For the following project, (a) List all predecessors of task 5. (b) List all predecessors of task 4. (c) List all predecessors of the network finish (F). Note: As pointed out in Section 3.3, p.75, only immediate predecessors should be listed. (a) Task 4 is the only immediate predecessor of task 5. (b) Tasks 2 and 3 are both immediate predecessors of task 4. (c) Task 5 is the immediate predecessor of the network finish (F). 6. What is a dummy activity? When two activities have the same beginning and ending nodes they do not have a unique identity in the project network. To solve this problem a new ending or starting node is created for one of the activities to provide them with a unique identity. Then a dummy activity or an activity with no duration is added to preserve the precedence relationship. 7. Consider Figure 5-14. Paths a-b-c and a-b-d converge at activity f, but we ignore this potential merge problem in the text. Why? Activities a and b are common to both paths and so do not need to be considered. They must take the same impact on both paths. Note: We did consider the partial paths d-g-h and c-f. 8. What is meant by project slack?

If the promised delivery date for a project is greater than the time required to complete the project, the project is said to have project slack. The amount of the project slack is equal to the delivery time minus the project completion time.

9. When using AON networks, how does one indicate an event such as a project milestone? A milestone could be added as a node to the AON network with zero duration. 10. A probabilistic network has a critical path of 21 days and a .95 probability of completing this path in 24 days. Therefore, the project has a .95 chance of being finished by the end of the 24 th day. True or False? Briefly explain your answer. False. Only the path claimed to be critical has a 95 percent chance of being completed within 24 days. However, there may be one or more other paths that also have a chance of taking longer than 24 days. If we are comfortable making the assumption that the paths are independent of one another, then the probability the project will be completed in 24 days or less can be calculated as the product of the probabilities that each path is finished on or before day 24. 11. Not uncommonly, the Gantt chart is deceptive in its apparent simplicity. Briefly explain. Because the Gantt chart is so easy to construct and read, people may use this tool with little project management training and no technical knowledge about the project. One danger is drawing conclusions and making decisions based on the relatively simple information displayed in the chart. 12. When activity times are known with certainty, the critical path is defined as the set of activities on a path from the projects start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? In cases where the activity times are not known with certainty, it is not possible to determine the actual duration of each path. Therefore, it is not possible to determine the critical path a priori.

A path that is determined to be critical at the beginning of the project based on expected activity durations may turn out not to be critical when the project is half completed, perhaps as a result of the extra management attention this path received. Indeed, it is common for the status of various paths to alternate between being critical and not being critical as the project is completed.

Are there dangers associated with not modifying the definition? One danger is that what is thought to be the critical path at the beginning of the project consumes all of managements attention only to have other paths fall behind and actually end up delaying the project. The implication is that all paths that have the potential to delay the project should be appropriately managed.

Suggested Answers to Discussion Questions


13. How might you use the network approach to help prepare cost estimate? One way to use the network approach to prepare cost estimates would be to simply estimate the cost of each task in the diagram and then sum these costs up. The time estimates for the activities would likely be of significant help in estimating some of the costs (particularly when human labor is required), and developing a cash flow schedule. 14. When would it be accurate to determine the probability of project completion by multiplying the probabilities of all the paths through the network together? It would be accurate to multiply the probabilities together when the paths are independent of one another. When would it not be accurate? In reality, the paths are not likely to be truly independent because the paths have activities in common and common resources are shared across paths. This latter point is particularly noteworthy as the network diagram only shows technological precedence relationships and most often does not include information about how the resources will be allocated. In many textbooks it is common to argue that while true independence across the paths is rarely met, statistical independence is achieved for large network diagrams with only a few violations. Of course, the typical homework-type problems assigned are not large enough to justify the independence assumption and the calculations required for realisticallysized network diagrams would be far too tedious for most managers. That is why simulation is the recommended approach in this text. However, it

is important to note that understanding the statistical approach facilitates understanding the simulation approach.

15. Reconcile Question 14. If this approach is not accurate, would the probability of completion considering the critical path alone be more accurate? No, the probability would not be more accurate if only the critical path were considered unless this one path was much longer than all the other paths. In this case the other paths would have virtually no chance of delaying the entire project. When activity times are uncertain, properly calculating the probability that the project is completed by a certain date requires considering the probability that all paths are completed by the specified date. How might you estimate the correct probability without resorting to simulation? If the assumption of path independence is reasonable then the product of the probability of each path completing by the specified time can be calculated. Otherwise, simulation must be used. 16. Why do you think most PMs use MSPs Gantt chart format (see Figure 5-24) more commonly than the network format? It is much more intuitive, easier to read, and may contain much more information relevant to the project. 17. Which of the linkages in precedence diagramming do you think is most commonly used? Why? As noted in the chapter, the finish-to-start is the most commonly used linkage because typically certain activities must be completed before other activities can start. The start-to-start and finish-to-finish linkages are occasionally applicable. In these cases certain activities must either be started or finished at the same time. The start-to-finish linkage is probably used the least frequently.

18. In the calculation of variance for optimistic and pessimistic activity duration estimates made at the 95 or 90 percent level, the denominator of the fraction that approximated the standard deviation of the time distribution changes from the traditional (b - a)/6 to (b - a)/3.3 for 95 percent and to (b - a)/2.6 for 90%. Where did the 3.3 and the 2.6 come from? The 3.3 corresponding to 95 percent is based on a z-value of 1.645 which has 5 percent of the area in the upper tail. Doubling this yields the 3.3 given in the text. Note that the 3.3 is appropriately used when management specifies an optimistic time estimate that has a 95 percent chance of being achieved and a pessimistic time estimate that has only a 5 percent chance of being exceeded. The 2.6 corresponding to 90 percent is based on a z-value of 1.28 which has 10 percent of the area in the upper tail. Doubling 1.28 yields the 2.6 given in the book. Again, the 2.6 is appropriately used when management specifies an optimistic time estimate that has a 90 percent chance of being achieved and a pessimistic time estimate that has only a 10 percent chance of being exceeded. 19. Given all the estimating done to determine the duration of project activities, what does it mean to say that only after the fact do we know which path was actually the critical path? When activity times are uncertain, we can only estimate how long they will actually take. This means that we can only estimate the duration of the paths also. Since these are only estimates, we will not know for certain which path actually took the longest to complete until the project is complete. 20. It was noted that the PM must manage the project team as well as the project. Explain why. There are actually two sets of trade-offs project managers must make. Most commonly, we talk about making trade-offs between cost, schedule, and performance. However, there is often another set of trade-offs the project manager must deal with. Project managers must often make trade-offs between achieving the project goals and the project team viability. Managing this second set of

trade-offs is what is meant by managing the project team while the first set of goals refers to managing the project.

21. Why do you think scheduling has been the major focus of effort throughout the history of project management rather than performance or budgeting? Performance the performance of a project is measured by three criteria: is it on time? Is it on budget? And does it meet the agreed-upon specifications? These are outcomes which depend, to a large extent, on the effectiveness of the planning process which, in turn, depends on the quality of the scheduling? Budgeting as pointed out at the beginning of the chapter, one cannot prepare a budget without knowing the specifics of each task and the time period(s) during which the task must be undertaken. The effectiveness of the budgeting process therefore depends on the accuracy of the scheduling. Thus, both performance and budgeting rely on the scheduling and the more effective that is, the more likely the later stages (i.e., performance and budgeting) will be.

Solutions to Problems
22. The expected duration and variance of path a-b-c-f are 44.5 (10 4/6 + 12 1/6 + 12 2/6 + 9 2/6) and 6.47 (1.78 + .25 + 4.00 + .44) respectively. The probability that this path will take longer than 50 weeks and therefore interfere with the project completion can be calculated as follows:
z= 50 44.5 = 2.17 6.47

From Appendix A, the area in the upper tail for a z-value of 2.17 can be easily calculated as 1.5%. This means there is a 98.5% chance that this path will not interfere with the project being completed in 50 weeks. The probability that both paths finish by time 50 (assuming the paths are reasonably independent of one another) is .985 .86 = 84.71%.

23. Occasionally, students make the assumption that by 95% we mean that there is a 95% probability that the task will be completed within the range defined by the optimistic and pessimistic range. In these cases, (b-a) should be divided by 3.92, rather than 3.3. The spreadsheet below provides the solutions for the 99+ percent probability estimates, as well as the 95% estimates using both the 3.92 and 3.3. Students may find the use of 3.92 more intuitive. Using this factor, the probability that path a-b-d-g-h finishes on or before time 50 is 76.5%.
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Activity a b c d e f g h a-b-d-g-h Std Dev Prob B Opt. a 8 11 7 6 10 6 5 4 C Norm. m 10 12 12 6 14 10 10 8 D Pess. b 16 14 19 6 20 10 17 11 E TE 10.67 12.17 12.33 6.00 14.33 9.33 10.33 7.83 47.00 F Var. ((b-a)/6)2 1.78 0.25 4.00 0.00 2.78 0.44 4.00 1.36 7.39 2.72 86.5% G H Var. Var. ((b-a)/3.92)2 ((b-a)/3.3)2 4.16 5.88 0.59 0.83 9.37 13.22 0.00 0.00 6.51 9.18 1.04 1.47 9.37 13.22 3.19 4.50 17.31 4.16 76.5% 24.43 4.94 72.8%

Key Formulas Cell E12 =E3+E4+E6+E9+E10 {copy to cells F12:H12} Cell F13 =SQRT(F12) {copy to cells G13:H13} Cell F 14 =NORMDIST(50,47,F13,TRUE) {copy to cells G14:H14}

If students follow the text and make the assumption that there is a 5% chance of completing the tasks faster than the optimistic time estimates and there is a 5% chance that completing the tasks takes longer than the pessimistic time estimates, then the probability of path a-b-d-g-h finishing on or before time 50 is 72.8%

24. If students assume that by 90% we mean that there is a 90% probability that the task will be completed with the range defined by the optimistic and pessimistic range then (b - a) should be divided by 3.29, rather than 2.6. The spreadsheet below provides the solutions for the 99+ percent probability estimates, as well as the 90% estimates using both the 3.29 and 2.6. Students may find the use of 3.29 more intuitive. Using this factor, the probability that path a-b-d-g-h finishes on or before time 50 is 72.7%. If students follow the text and make the assumption that there is a 10% chance of completing the tasks faster than the optimistic time estimates and there is a 10% chance that completing the tasks takes longer than the pessimistic time estimates, then the probability of path ab-d-g-h finishing on or before time 50 is 68.4%
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Activity a b c d e f g h a-b-d-g-h Std Dev Prob B Opt. a 8 11 7 6 10 6 5 4 C Norm. m 10 12 12 6 14 10 10 8 D Pess. b 16 14 19 6 20 10 17 11 E TE 10.67 12.17 12.33 6.00 14.33 9.33 10.33 7.83 47.00 F Var. ((b-a)/6)2 1.78 0.25 4.00 0.00 2.78 0.44 4.00 1.36 7.39 2.72 86.5% G H Var. Var. ((b-a)/3.29)2 ((b-a)/2.6)2 5.91 9.47 0.83 1.33 13.30 21.30 0.00 0.00 9.24 14.79 1.48 2.37 13.30 21.30 4.53 7.25 24.57 4.96 72.7% 39.35 6.27 68.4%

Key Formulas Cell E12 =E3+E4+E6+E9+E10 {copy to cells F12:H12} Cell F13 =SQRT(F12) {copy to cells G13:H13} Cell F 14 =NORMDIST(50,47,F13,TRUE) {copy to cells G14:H14}

25 a. Network diagram.

F C D

b. Each activitys EST, EFT, LST, and LFT. See following spreadsheet: Activity A B C D E F G H I EST 0 4 4 8 10 10 8 15 19 EFT 4 10 8 10 14 15 11 19 21 LST 0 4 4 8 15 10 12 15 19 LFT 4 10 8 10 19 15 15 19 21 Slack 0 0 0 0 5 0 4 0 0

c. Alternative paths and the critical path: Path a-b-e-i a-b-f-h-i a-c-d-f-h-i a-c-g-h-i Duration 16 21 21 17 Critical? No Yes Yes No

There are, therefore, two critical paths. d. Each activitys slack. See spreadsheet above (section b). e. The length of time to complete the project. The project will take 21 (units of time) to complete (i.e., the length of time of the critical paths). 26. Note to instructor: In order to familiarize student with MSPs Help facilities, we have not given precise instructions in the text for changing MSPs project calendars, and for using MSP to find slack. If you wish to make these available, they follow: The MSP calendar must be reset to a 7-day work week from its usual default of a 5-day work week. To reset the MSP calendar, click Tools, and then click Change working time. On the calendar you will note that Saturdays and Sundays for June and July are shaded, i.e., nonworking time. Click on each of these days and then click on Working time. Alternatively, you may highlight the entire months of June and July and then click on Working time. To show slack or float in MSP, click on View, then on More views, on Detail Gantt, and Apply. Activity slack will be shown on the Gantt chart. Then click on View, Table, and then Schedule. Drag the divider bar to the right, and you will find Total slack and Free slack listed in the MSP table. (For these instructions to take effect, project activity data must have been entered into MSP.)

d a b c
4 2 5

i h f
6

k l j
8 9

e
3

One way the critical path can be determined is by identifying all paths and calculate their duration. As shown below, this project has six paths and path b-e-h-j-l is the critical path with a duration of 40. Path a-d-i-k a-d-h-j-k b-e-i-k b-e-h-j-l b-f-j-l c-g-j-l Duration 29 35 35 35 35 35 Critical? No No No Yes No No

The slack for each task is calculated as follows:


Activity a b c d e f g h I j k l ES 0 0 0 5 7 7 4 16 16 22 24 31 EF 5 7 4 11 16 13 8 22 24 31 34 40 LS 5 0 14 10 7 16 18 16 22 22 30 31 LF 10 7 18 16 16 22 22 22 30 31 40 40 Slack 5 0 14 5 0 9 14 0 6 0 6 0

27.

a.

The spreadsheet below can be used to calculate the expected time and variance for each activity.
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Activity a b c d e f g B Opt. a 2 3 4 4 4 3 3 C Norm. m 4 5 5 6 5 4 5 D Pess. b 6 9 7 10 7 8 8 E TE 4.00 5.33 5.17 6.33 5.17 4.50 5.17 F Var. ((b-a)/6)2 0.44 1.00 0.25 1.00 0.25 0.69 0.69 G H Var. Var. ((b-a)/3.92)2 ((b-a)/3.3)2 1.04 1.47 2.34 3.31 0.59 0.83 2.34 3.31 0.59 0.83 1.63 2.30 1.63 2.30

Paths a-d-f a-c-e-g b-e-g Prob Path Fin by 23 a-d-f a-c-e-g b-e-g Prob Project Fin by 23 Key Formulas: Cell B13 Cell B14 Cell B15 Cell C18 Cell C22

Expected Variance Variance Variance Duration Column F Column G Column H 14.83 2.14 5.01 7.07 19.50 1.64 3.84 5.42 15.67 1.94 4.56 6.43

100.0% 99.7% 100.0% 99.7%

100.0% 96.3% 100.0% 96.3%

99.9% 93.4% 99.8% 93.1%

=E3+E6+E8 {copy to cells C13:E13} =E3+E5+E7+E9 {copy to cels C14:E14} =E4+E7+E9 {copy to cells C15:E15} =NORMDIST(23,$B13,SQRT(C13),TRUE) {copy to cells D18:E18 and C19:E20} =PRODUCT(C18:C20) {copy to cells D22:E22}

b. The precedence diagram using an AOA (Activity on Arrow) network is as follows:

d a b c e

f g

The critical path is a-c-e-g since it has the longest expected duration of 19.5 weeks. Note: although this path has the longest expected duration, given the uncertainty associated with the activity times, it may not be the path with the longest actual duration. c. d. e. Referring to column H in the spreadsheet above, the probability of completing path a-c-eg in 23 weeks or less is 93.4%. Both of the other two paths have virtually a 100% chance of being completed by week 23. As shown in the spreadsheet, there is a 93.1% probability of completing the entire project by week 23.

28. a. The spreadsheet below was used to calculate the expected time and variance for each activity.

A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 Activity a b c d e f g h i j k

B Opt. a 5 4 7 6 4 12 8 7 10 6 7

C Norm. m 6 4 9 6 5 16 12 9 14 12 9

D Pess. b 9 6 15 6 7 17 20 16 18 20 14

E TE 6.33 4.33 9.67 6.00 5.17 15.50 12.67 9.83 14.00 12.33 9.50 Expected Duration 26.33 23.50 32.17 34.67 29.00

F Var. ((b-a)/6)2 0.44 0.11 1.78 0.00 0.25 0.69 4.00 2.25 1.78 5.44 1.36

G H Var. Var. ((b-a)/3.29)2 ((b-a)/2.6)2 1.48 2.37 0.37 0.59 5.91 9.47 0.00 0.00 0.83 1.33 2.31 3.70 13.30 21.30 7.48 11.98 5.91 9.47 18.11 28.99 4.53 7.25

Paths a-d-i b-e-i b-f-j c-g-j c-h-k Prob of Fin Path c-g-j < 38

Variance 2.22 2.14 6.25 11.22 5.39

Variance 7.39 7.11 20.79 37.32 17.92

Variance 11.83 11.39 33.28 59.76 28.70

=NORMDIST(38,$E20,SQRT(F20),TRUE) copy to cells G25:H25 84.0% 70.7% 66.7%

90% Chance =NORMINV(0.9,$E20,SQRT(F20)) copy to cells G29:H29 of Fin path c-g-j

39.0

42.5

44.6

b. The network d a b c e f g h c. As shown in the spreadsheet above, this project has five paths. Path c-g-j has the longest expected duration of 34.67 days although this path may turn out not to be the critical path given the uncertainty associated with the activity times. i j k

d. As calculated in the above spreadsheet, the probability that path c-g-j will be completed in 38 days or less is 66.7%. e. Assuming the paths are independent, for a 38 day delivery, paths a-d-i and b-e-i have virtually no chance of delaying the project and therefore can be ignored. The probabilities for paths b-f-i and c-h-k are .843 and .954 respectively. Given the probability that the nominal critical path is .667, the chance that all three paths will be completed in 38 days is the product of their individual probabilities or 53.5%. f. Column F in the spreadsheet above corresponds to the 99+ percent level. According to the calculations shown, there is an 84% chance that path cg-j will be completed in 38 days or less. The difference in probabilities is caused by the fact that the estimation of a and b at the 99+ percent level produces a distribution of activity times (and thus of path lengths) that is much smaller than the range produced by estimations at the 90 percent level. The greater uncertainty reduces that chance that any path will be completed in a specific time. g. As shown in the spreadsheet, if the estimates were made at the 99+ percent level, the project would have a 90 percent chance of being completed by day 39. On the other hand, if the estimates were made at the 90 percent level, the project would have a 90 percent chance of being completed within 44.6 days. 29. The spreadsheet below as developed to simulate this project using Crystal Ball. Cells A12:G12 are Assumption Cells for the activity times based on a normal distribution with the means in cells E2:E8 and standard deviations in cells G2:G8. Cells L12:O12 were defined as Forecast Cells.
A B Opt 1 Activity 2 A 2 3 B 3 4 C 4 5 D 4 6 E 4 7 F 3 8 G 3 9 10 Activity Activity A B 11 12 4.00 5.34 C Most Likely 4 5 5 6 5 4 5 Activity C 5.17 D Pess 6 9 7 10 7 8 8 Activity D 6.33 E F G Expected Variance Std Dev 4.00 1.47 1.21 5.33 3.31 1.82 5.17 0.83 0.91 6.33 3.31 1.82 5.17 0.83 0.91 4.50 2.30 1.52 5.17 2.30 1.52 Activity E 5.17 Activity F 4.51 H I J K L M N O

Activity Path Path Path Finish A-D-F A-C-E-G B-E-G Finished G A-D-F A-C-E-G B-E-G Time Critical? Critical? Critical? 23 Weeks? 5.17 14.84 19.51 15.68 19.51 0 1 0 1

a. Based on 1000 replications of the simulation model, path a-d-f had the longest duration in 7% of the replications. Similarly, paths a-c-e-g and b-

e-g had the longest durations in 89% and 4% of the simulation replications, respectively. This demonstrates the difficulty in determining which path will be the critical path when activity times are uncertain. b. The probability of the project being completed in 23 weeks or less was 93%. c. The 93% calculated here is extremely close to the 93.1% calculated in Problem 26.

30. Since the times for activities are now known for activities a - d, updating the simulation model simply requires replacing the Assumption Cells in cells A12:D12 with the known times. After making these changes, the revised probability of the project being completed by week 23 increases to 98%. With the updated information, path b-e-g has the longest expected completion time of 19.34 weeks. However, the expected completion time for the other two paths decreases and these paths have virtually no chance of taking longer than 23 weeks to complete. Furthermore, while task b is now known to take its maximum duration, even if tasks e and g take as long as possible, the path would only take 24 weeks to complete. Therefore, delaying the project beyond 23 weeks requires that both tasks e and g go about as poorly as possible, which is not very likely. 31. The spreadsheet below was developed to simulate this project using Crystal Ball. Cells B3:L3 (excluding cell E3) are Assumption Cells for the activity times based on the triangular distribution and the optimistic, most likely, and pessimistic times given in the problem. Cells B8:F8 and B10:B12 were defined as Forecast Cells.
A 1 2 3 4 5 6 7 8 9 10 11 12 B Activity A 6.67 Path ADI 26.67 0 0 0 1 C Activity B 4.67 Path BEI 24.00 0 D Activity C 10.72 Path BFJ 32.33 0 E Activity D 6.00 Path CGJ 36.72 1 F Activity E 5.33 Path CHK 31.39 0 G Activity F 15.00 Project Duration 36.72 H Activity G 13.33 I Activity H 10.67 J Activity I 14.00 K Activity J 12.67 L Activity K 10.00

Duration

Duration Critical? P( < 32) P( < 34) P( < 38)

a. Probability of each path becoming the critical path. Path a-d-i b-e-i b-f-j c-g-j c-h-k Probability of Being Critical Path 1% 0% 6% 83% 10%

b. Based on 1,000 replications of the model there is an 8%, 20%, and 60% chance that the project can be completed in 32, 34, and 38 weeks, respectively. c. In part e of problem 27, it was determined that there was a 53.5% chance of completing the project in 38 weeks. In the current simulation, the probability was calculated to be 60% which is in the same ballpark. This difference may in part be due to the use of the triangular distribution.

Suggested Solution to Discussion Problem


32. Note: If students use MSP to generate the AON network, and if they use a Start node to begin the project, the Start node will be numbered 1. This will increase by one all the task numbers used in the problem statement. This is a common source of confusion in reality as well as in the classroom. There appear to be three activities that have no logical predecessors: o Organize the sales office. o Order stock from the manufacturer, and o Design the package. Organize the office has three logical successors: select distributors, hire sales personnel, and select advertising agency. Given these relationships, the other predecessor-successor relationships are obvious. Besides the need to manage the critical path carefully, there are only two managerial problems or opportunities readily apparent. If resources could be made available to speed up organization of the sales office, project slack would result. Second, selecting distributors is the only activity with low slack, 2 weeks. It bears watching. Students may advise shifting resources from ordering stock from the manufacturer, but once the purchase order has been made out and sent, the 13 week duration is mostly waiting for delivery and there are no resource commitments involved.

Start
B

H L E G F I K J

Finis h

1 2 3 4 5 6 7 8 9 10 11 12 13 14

A Task A B C D E F G H I J K L M

B Description
Design package Order stock from manf. Org. sales office Set up packing facility Select distributors Hire sales personnel Select adv. agency Package initial stocks Sell to distributors Train sales personnel Plan adv. campaign Ship stock to distributors Conduct adv. campaign

C ES 0 0 0 2 6 6 6 13 17 10 8 23 12

D EF 2 13 6 12 15 10 8 19 23 17 12 29 22

E LS 5 4 0 7 8 6 13 17 17 10 15 23 19

F LF 7 17 6 17 17 10 15 23 23 17 19 29 29

G Slack 5 4 0 5 2 0 7 4 0 0 7 0 7

Incident for Discussion Suggested Answer


Springville Fire Department: The scheduling techniques mentioned are not mutually exclusive, they are complementary and could be used together: o PERT/CPM serves well for planning and control. o A Gantt chart would provide the ease of use, showing durations, monitoring and on-going analysis. It might also be noted that CPM has traditionally been favored by the construction industry. Question: If you were the project manager, which method would you use, and why? If only one technique must be used, the modified PERT/CPM method, plotted on a time scale, would probably be the best choice. Attack of the Killer Worm Question: How would you recommend they reach a consensus on the action plan for the project? Andy and Lee need to set up a win-win negotiation of the steps in the action plan. Andy needs to: o Acknowledge that by his using a bottom-up approach to his budget for this project the staff actually doing the work may have overestimated the time it takes to ensure that the work gets done and/or may have wanted to increase their overtime pay. o Needs to educate Lee on the impact of the project on the organization. o Explain how his staff are closer to the users and can estimate how the PC or system downtime will affect their customers work processes. Lee needs to realize that: o Andy and his team have a much better idea of how long it will take to check the machines and make any necessary repairs.

Together they can work to make sure that each others point of view is taken into consideration for the steps of the project.

Suggested Case Analyses and Solutions


St. Dismas Assisted Living Facility Project Action Plan -- 3 Teaching Purpose: This installment of the St. Dismas case provides students with an opportunity to further develop their skills in creating and using Gantt charts. Question 1: Draw a Gantt chart for the construction phase of the project. What is the completion date if construction starts in March? What is the completion date of the project if construction is started in November? The following is the Gantt chart using MSP with a March 1, 2000 start date. This was entered using the standard calendar defaults used by MSP of a Monday through Friday 8 am to 5 pm workday with an hour off for lunch. The project completion date is 7/30/01. Note: Start and finish milestones were added to the action plan for ease in identifying the projects start and finish dates.

The following is the Gantt chart using MSP with a November 9, 1999 start date. This start date was chosen because one of the constraints placed on the project was that it does not begin until after the elections in November. Elections are usually held the first Tuesday in the month of November. The case stated that one to two months was estimated as needing to be added to the project schedule to allow for bad weather conditions during the outside construction phases of the project (30 - 60 working days). Days of work need to be added to the duration of each of the steps where work takes place outside if it will happen during the winter months.

Note: The authors chose to add 30 days to each of the steps affected, step # 4 and #5. Step #6 is also work done outside, but with the changes made to #4 and #5, step #6 will not start until the month of April. Students may also change the calendars to let the workers off for the holidays of 1999 in addition to those allowed for in 2000. The new ending date is May 18, 2001. The project will take a total of 30 additional days to complete. By adding 30 days of working time to each of the steps possibly affected by the weather, we only ended up adding 30 days total to the project.

This is a good discussion point of how the tasks affected by the increased durations were not both on the critical path - only Step #4 extended the length of the project. However, the students must keep in mind resource availability and the increased cost of the project extension.

Question 2: Why is it not possible to meet the scheduling constraints set by the Board? What is your recommendation to handle the scheduling problem? The case outlined two specific constraints that the Board placed on the project: o o The project should not start until after the elections in November, and The building must be ready for occupancy by July of the following year since the board wanted to target occupancy for the summer months.

The constraint of the building opening by July of the year following construction beginning cannot be met. No matter when the project begins it takes longer than one year to complete. If the project begins immediately after the November 1999 elections it will be completed by May 18, 2001, if the project begins in March of 2000 (as recommended by the construction manager) it will be completed by July 30, 2001. The constraint of construction beginning after the November elections can be met without any affect on the project. Meeting the July complete occupancy constraint is possible only if the project is started in the winter months, this would add cost and time to the project. It would also

make the first units available in April, which is before the targeted summer occupancy. Recall that the case stated that research showed that most people shopped for assisted living facilities during the summer months. A summer occupancy could be met by starting the project March 1, 2000, without additional time or cost added to the original estimated project action plan. 45 units would be available for occupancy as early as June 25, 2001 (see step #9 of Gantt chart with 3/1/00 start date).

Question 3: When will the project be completed based on your recommendation? If students chose to start the project on: o o March 1, 2000 the entire project will be completed by July 31, 2001. February 1, 2000 without any schedule changes due to weather conditions, the project would be completed by June 29, 2001.

By using MSP to change the projects start date, students can easily choose various new start dates and see the associated project end date. Question 4: Draw a Gantt Chart of the Marketing Plan and Implementation Phase of the Project. Determine the start date of the Marketing Plan phase of the project in order to meet your recommended facility ready for occupancy date? Note: We assumed a March 1, 2000 start date for the project. Below is the Gantt chart for the steps in the Marketing Plan and Implementation phase of the St. Dismas Assisted Living Project. The action steps were taken directly from the Marketing plan developed and implemented section of the broad marketing plan that was presented in the case. To determine the projects start date, you must first determine the start date of the final step in the project action plan, Implementation of the Marketing Plan. This must be started 5 months prior to the building being ready for occupancy so that marketing has time to find residents to move in when the facility is available. The marketing plan must be implemented based on the date that the first 45 units are ready for residents. This date is June 25, 2001. In order to determine the start date of the Implementation task, Step #7, one can schedule this project backwards, we know the completion date, we do not know when to start. Once we enter the projects completion date, MSP will determine when each step of the project should take place. First enter all of the tasks names, precedences, and their durations, as shown below:

Next, we must enter this projects overall finish date, using the project information dialog box, found in the Project menu on the tool bar. Enter an end date of 6/25/01, and select Schedule from the project finish date. MSP will automatically determine each steps start and end date to meet the constraint you set. See below:

Question 5: What is the next step the team members must take in order to complete their action plans? Each member of the project steering team needs to prepare final action plans, including dates and resources. The team must also determine the predecessors from outside their specific plan that link to their plans; for example if a step cannot be completed on the marketing phase of the project until Legal has completed a step in their project plan, this must be noted on the action plan. This will enable a complete overall integrated project action plan to be tied to the project budget, monitored and controlled. Nutristar Teaching Purpose: The purpose of this case is to reinforce students skills in analyzing projects with probabilistic time estimates. The case also provides students with an opportunity to use spreadsheets to simulate the completion of the project and use the results of the simulation to perform standard probability calculations.

Question 1: Draw a network diagram for this project. Identify all the paths through the network diagram. The following abbreviations will be used for the activities.
Activity Description Concept Development Plan Development
Define project scope

Abbreviatio n A B C D E F G H I J K L M

Develop broad schedule Detailed cost estimates Develop staffing plan Design and Construction Detailed engineering Facility construction Mobilization of construction Employees Procurement of equipment Start-up and Turnover Pre-startup inspection Recruiting and training Solving start-up problems Centerlining

Using these abbreviations and the information provided in the case, the following AOA network diagram can be constructed.

B A C D E

F G H I J K L M

There are 32 paths through the network as follows A, A, A, A, A, A, A, A, A, A, A, A, A, A, A, B, B, B, B, B, B, B, B, C, C, C, C, C, C, C, F, G, J, K, M F, G, J, L, M F, I, J, K, M F, I, J, L, M H, G, J, K, M H, G, J, L, M H, I, J, K, M H, I, J, L, M F, G, J, L, M F, I, J, K, M F, I, J, L, M H, G, J, K, M H, G, J, L, M H, I, J, K, M H, I, J, L, M A, A, A, A, A, A, A, A, A, A, A, A, A, A, A, A, D, D, D, D, D, D, D, D, E, E, E, E, E, E, E, E, F, G, J, K, M F, G, J, L, M F, I, J, K, M F, I, J, L, M H, G, J, K, M H, G, J, L, M H, I, J, K, M H, I, J, L, M F, G, J, K, M F, G, J, L, M F, I, J, K, M F, I, J, L, M H, G, J, K, M H, G, J, L, M H, I, J, K, M H, I, J, L, M

A, C, F, G, J, K, M

Question 2: Simulate the completion of this project 100 times assuming that activity times follow a normal distribution. Estimate the mean and standard deviation of the project completion time. Prior to simulating the project, the mean and standard deviation for each activity must be calculated. The spreadsheet shown below was developed to calculate these parameters.
B Optimistic Activity Time A 3 B 1 C 0.25 D 0.2 E 0.2 F 2 G 8 H 0.5 I 1 J 0.25 K 0.25 L 0 M 0 A C Most Likley 12 2 0.5 0.3 0.3 3 12 2 3 0.5 0.5 1 1 D E F G Pessimistic Expected Standard Time Time Variance Deviation 24 12.500 12.250 3.500 12 3.500 3.361 1.833 1 0.542 0.016 0.125 0.5 0.317 0.003 0.050 0.6 0.333 0.004 0.067 6 3.333 0.444 0.667 24 13.333 7.111 2.667 4 2.083 0.340 0.583 12 4.167 3.361 1.833 1 0.542 0.016 0.125 1 0.542 0.016 0.125 2 1.000 0.111 0.333 4 1.333 0.444 0.667

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Key Formulas: Cell E3: =(B3+(C3*4)+D3)/6 {copy to cells E4:E15} Cell F3: =((D3-B3)/6)^2 {copy to cells F4:F15} Cell G3 =SQRT(F3) {copy to cells G4:G15}

Next, the actual spreadsheet to simulate the completion of the project can be developed. As demonstrated in the textbook, one approach is to dedicate a column to each activity and then generate random activity times. Thus, in the spreadsheet developed for this case, columns A - M were dedicated to activities A - M, respectively. Then random numbers were generated for the activities using Crystal Ball and defining cells A3:M3 as Assumption Cells. A portion of the simulation model is shown below.
1 2 3 A B C D E F G H I J K L M N O P Act Act Act Act Act Act Act Act Act Act Act Act Act Path Path Path A B C D E F G H I J K L M ABFGJKM ABFGJLM ABFIJKM 12.50 3.62 0.54 0.32 0.33 3.33 13.33 2.08 4.22 0.54 0.54 1.00 1.37 35.24 35.70 26.13

After generating the random numbers in the Assumption Cells, one column is dedicated to each path and formulas are entered to calculate the path completion time based on the random activity times generated. Entering the formulas is very straightforward since the letters used to label the activities correspond directly to the column labels. To illustrate, the formula for path A - B - F- G - J - K - M in row three is: =A3+B3+F3+G3+J3+K3+M3. To determine the time to complete the project, a final column was entered that calculates the maximum path completion time across all paths in the spreadsheet. Then, summary statistics for this column were calculated. One simulation of 1,000 replications of the project yielded an average project completion time of 35.85 months with a standard deviation of 4.69 months. The maximum completion time was 50.83 months and the minimum completion time was 19.52 months. Question 3: Develop a histogram to summarize the results of your simulation. This histogram created by Crystal Ball is shown below.

Question 4: Calculate the probability that the project can be completed within 30 months. What is the probability that the project will take longer than 40 months? What is the probability that the project will take between 30 and 40 months? The probability of completing the project in 30 months or less is 10.2%:

The probability of the project taking more than 40 weeks is 19.0%:

The probability of the project taking 30 to 40 months is 70.8%: