COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

PRECOMMISSIONING CHECK LIST AND TEST REPORT - HT MOTOR


1. LOCATION 2. DESIGNATION : :

3. NAME PLATE DETAILS : MAKE POWER VOLTAGE : : :

FULL LOAD CURRENT : SERIAL NO. MODEL NO. FREQUENCY COS EFFICIENCY IP SPEED CONNECTION INSULATION CLASS FRAME SIZE ROTOR TYPE AMB.TEMP. NO. OF START DUTY BEARING DE/NDE : : : : : : : : : : : : : :

4. MOTOR SPACE HEATER : POWER RATING : VOLTAGE RATING RESISTANCE VALUE : : OHMS (Applied Voltage : V)

INSULATION RESISTANCE .

SEPCO-III

Adani Project

Adani Commissioning Page 1 of 6

COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

CURRENT MEASURED HEATER OPERATION

: : : : : : : : : : : : : :

5. SWITCHBOARD NAME & FEEDER NO. FOR HT MOTOR 6. BREAKER TYPE 7. BREAKER STARTER TYPE 8. MOTOR POWER CABLE SIZE 9. MOTOR CONTROL CABLE SIZE 10. MOTOR ANTI CONDENSATION HEATER CABLE SIZE 11.EARTHING CABLE / STRIP SIZE 12.MOTOR TERMINALS TIGHTNESS 13.OUTDOOR MOTOR CANOPY 14. LOCAL CONTROL STATION INSTALLATION 15. FIELD AMMETER AS PER THE CT SPECIFICATION 16. PANEL AMMETER AS PER THE CT SPECIFICATION

17. LOCAL CONTROL STATION EARTHING INSTALLATION : 18. ELECTRICAL CLEARANCE TO THE BODY :

19. HT MOTOR RTD VALUE ( FOR Winding / Bearing) : ( RTD VALUE AT AMBIENT TEMPERATURE ) BEARING TEMPERATURE GAUGE READING AT AMBIENT TEMPERATURE 1) DRIVING END : 2) NON DRIVING END : TERMINAL RESISTANCE TERMINAL WINDING BEARING NO. VALUE NO. Rph DRIVING END

RESISTANCE VALUE

SEPCO-III

Adani Project

Adani Commissioning Page 2 of 6

COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

Yph

NON DRIVING END

Bph

20. INSULATION RESISTANCE VALUE OF MOTOR :

Megger Make : Megger Sl.no : Voltage Rating of Megger :S.NO 1. 2. REFERENCE U1 V1 + W1 + EARTH V1 U1 + W1 + EARTH

5 kV
R15 R60 R600 POLARISATION INDEX = R600 / R15

SEPCO-III

Adani Project

Adani Commissioning Page 3 of 6

COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

3.

W1 U1 + V1 + EARTH

21. ROTOR INSULATION RESISTANCE TEST :

Megger Make :. Megger Sl.no : Voltage Rating of Megger ..V.


S.NO 1. REFERENCE IR VALUE

22. WINDING RESISTANCE TEST : ( microohms / milliohms / ohms ) U1 U2 V1 V2 W1 W2

23. POLARITY TEST : S.NO 1. DESCRIPTION U1 U2 V1 V2 W1 W2

24. HIGH VOLTAGE TEST : THIS TEST WILL BE CONDUCTED, ONLY IF RECOMMENDED BY MANUFACTURER / VENDOR. VOLTAGE APPLIED : 10kV (AC ). TIME DURATION : 60 SECONDS. S.NO 1. 2. 3. REFERENCE U1 EARTH V1 EARTH W1 EARTH EARTHED V1 + W1 EARTH W1 + U1 EARTH U1 + V1 EARTH LEAKAGE CURRENT (milliamps) REMARK

SEPCO-III

Adani Project

Adani Commissioning Page 4 of 6

COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

25. CHECK LIST S.NO 1.

Check List
Check that motor base frame ( solo plate ) is properly grouted / bolted to the foundation. Check that motor is firmly bolted to the base frame. Check that motor is free to rotate by hand , without any abnormal sound. Check the condition of grease in motor bearings. Check continuity of earthing up to earth riser / grid. Check Continuity / IR value proper termination at both ends for following points. Power cable (Including Phase Indication) Space heater cable. Local start/stop station cable. Check that Motor / Drive is clearly labelled. Check for cleanliness of Motor & its terminal box. Check Local start / stop station functionally upto HT Feeder. Check that Motors and push button stations in hazardous are designed for the same. Check that Cable glands are properly installed and terminals covers are properly closed. Direction of motor from driving end. Check speed switch(if provided) upto HT Feeder. Check Space Heater operation from HT feeder.

Status o.k / not o.k

Remarks

2.

3.

4. 5. 6. 6.1 6.2 6.3 7. 8. 9. 10. 11. 12. 13. 14.

SEPCO-III

Adani Project

Adani Commissioning Page 5 of 6

COMMISSIONING PROCEDURE COMMNG / ELEC / 043

PROJECT : 5 x 660MW Mundra Power Project.

26. CHECK STABILITY OF MOTOR DIFFERENTIAL PROTECTION: Current Measured in Motor Differential Relay. (i) When Current is injected B/W Uphase & Vphase.Bypassing the Uphase & Vphase winding by putting the loop across the winding. Description Phase Side Neutral Side I d Differential Current I r Restraint Current Uph Vph Wph 3Io

-----

(ii) When Current is injected B/W V phase & W phase. Bypassing the V phase & W phase winding by putting the loop across the winding. Description Phase Side Neutral Side I d Differential Current I r Restraint Current Uph Vph Wph 3Io

-----

SEPCO-III

Adani Project