MANPOWER SCHEDULE FOR STAIR CASE W.

O # = ___9141_________
OPERATIONS CUTTING & BENDING CUTTING & DRILLING CUTTING & NOTCHING PARTS DETAILS STEPS CHQ. PLATES= 32 LANDING CHQ. PLATES = 2 UPN 180 = 20 ANGLE 60 x 60 x 150 = 64 UPN 100 = 6 SHS 80 x 80 = 4 Cutting Pipe dia 42 = 58 Notching Straight = 12 Notching Angular = 46 STRINGERS 1 & 2 = 2 STRINGERS 3 & 4 = 2 FITUP COLLUMNS = 4 HANDRAIL BIG = 2 STEPS = 68 HANDRAIL SMALL = 2 STRINGERS = 8 WELDING GRINDING & CLEANING
SAND BLASTING

FABRICATOR 1

ASST. FABR 1 2 2

WELDER

HELPERS 1 1 2

REMARKS

1 1 1 2 1 2

2 2 1 2 1 2 3 3 2 2 4 1 4 2 1

HAND RAILS = 4 STEPS ALL ALL ALL = 68 COLLUMNS = 4

PAINTING

TOTAL REQUIRED = 46 TOTAL AVAILABLE = 28 TOTAL SHORT = 18

9 4 5

20 7 13

14 14 0

7 3 4 APPROVED BY:-

PREPARED BY:-