Fire Sprinkler System

Activity ID Activity Name Original Start Duration 33 27-Apr-13 07:00 AM A 33 27-Apr-13 07:00 AM A 33 27-Apr-13 07:00 AM A Finish 13-Jun-13 10:00 AM 13-Jun-13 10:00 AM 13-Jun-13 10:00 AM 07-May-13 02:00 PM A 07-May-13 02:00 PM A 05-Jun-13 09:00 AM 08-May-13 01:00 PM A 15-May-13 11:00 AM 20-May-13 03:00 PM 25-May-13 11:00 AM 28-May-13 08:00 AM 01-Jun-13 01:00 P M 05-Jun-13 09:00 AM 11-Jun-13 12:00 P M 06-Jun-13 04:00 P M 09-Jun-13 02:00 P M 10-Jun-13 01:00 P M 11-Jun-13 12:00 P M 13-Jun-13 10:00 AM 13-Jun-13 10:00 AM Budget At Completion QR7,296 QR7,296 QR7,296 QR0 QR0 QR6,240 QR576 QR960 QR1,440 QR768 QR768 QR960 QR768 QR864 QR288 QR288 QR144 QR144 QR192 QR192 Planned Value Cost QR576 QR576 QR576 QR0 QR0 QR576 QR576 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 Earned Value Cost QR595 QR595 QR595 QR0 QR0 QR595 QR576 QR19 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 QR0 Schedule % Complete 7.89% 7.89% 7.89% 0% 100% 9.23% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 2% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 100% 100% 2% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Activity % Complete Physical % Complete Sat Apr 27 Sun Mon Tue Wed Thr Fri Sat Sun

Classic WBS Layout


May 04 Mon Tue Wed Thr Fri Sat Sun Mon May 11 Tue Wed Thr Fri Sat Sun Mon May 18 Tue Wed Thr Fri Sat Sun Mon May 25 Tue Wed Thr Fri Sat Sun Mon Jun 01 Tue Wed Thr Fri Sat

10-May-13 04:07 PM
Jun 08 Sun Mon Tue Wed Thr Fri Jun 15 Sat Sun

Fire Sprinkler System


Construction
7th Floor

Dism antling Civil 7 27-Apr-13 07:00 AM A A1000 Dismantling of Ceiling / Services 11 27-Apr-13 07:00 AM A Roughing-In 22 06-May-13 07:00 AM A A1010 Dismantling of Existing Pipes / Hangers 3 06-May-13 07:00 AM A A1020 Installation of Headers / Hangers 5 09-May-13 07:00 AM A A1030 Installation of Main Branches A1040 Installation of Bedroom Branch A1050 Installation of Toilet Branch A1060 Installation of Foyer Branch Finishing A1080 Painting & Labeling A1090 Fixing Sprinkler Heads A1100 Rectification of Terminals A1110 Terminaton of Header on Riser Turn-Over A1120 Testing & Commissioning 5 15-May-13 11:00 AM 4 20-May-13 03:00 PM 4 23-May-13 12:00 PM 5 27-May-13 09:00 AM 4 05-Jun-13 09:00 AM 2 05-Jun-13 09:00 AM 2 08-Jun-13 07:00 AM 1 09-Jun-13 02:00 PM 1 10-Jun-13 01:00 PM 2 11-Jun-13 12:00 PM 2 11-Jun-13 12:00 PM

Dismantling of Ceiling / Services Dismantling of Existing Pipes / Hangers Installation of Headers / Hangers Installation of Main Branches Installation of Bedroom Branch Installation of Toilet Branch Installation of Foyer Branch Leak Test, Pressure Test & Flushing Painting & Labeling Fixing Sprinkler Heads Rectification of Terminals Terminaton of Header on Riser Testing & Commissioning

A1070 Leak Test, Pressure Test & Flushing 4 01-Jun-13 01:00 PM

Actual Work Remaining Work

Critical Remaining Work Milestone

Page 1 of 1

TASK filter: All Activities Primavera Systems, Inc.