Sunteți pe pagina 1din 7

VALORIZACION N O7 DE OBRA DE PARTIDAS CONTRACTUALES - MARAYBAMBA ABAJO

OBRA:

SISTEMA DE RIEGO MARAYBAMBA ABAJO

EJEC.:

CHACON CONTRATISTAS GENERALES

SUPERV.:

ING. PEDRO SOTOMAYOR IZAGUIRRE

FINANCIA:

FONDO MINERO ANTAMINA

N 07

MES DE VALORIZ. AL 31 DE AGOSTO DEL 2,009


MONTO DE OBRA

: S/. 730,134.53

REGION

: ANCASH

FECHA DE INICIO DE OBRA

: 13-Octubre-2,008

DEPARTAMENTO

: ANCASH

PLAZO DE EJECUCION

: 90 Das Calendarios

PROVINCIA

: SIHUAS

AMPLIACION DE PLAZO

: 00 Das calendarios

DISTRITO

: SIHUAS

FECHA DE TERMINO CONTRACTUAL

: 12-Enero-2,009

LOCALIDAD

: MARAYBAMBA ABAJO

A V A N C E S
PART.

PRESUPUESTO
Und.

Metrado

P. Unit.

ANTERIOR
Presup.

Metrado

S/.
01
01.01
01.02
01.03
01.04
02
02.01
02.01.01
02.02
02.02.01
02.02.02
02.03
02.03.01
02.03.02
02.03.03
02.03.04
02.03.05
03
03.01
03.01.01
03.02
03.02.01
03.03
03.03.01
03.03.02
03.03.03
03.04
03.04.01
03.05
03.05.01
03.06
03.06.01

OBRAS PRELIMINARES
CARTEL DE OBRA
MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA
DEMOLICION DE CONSTRUCCION EXISTENTE
INSTALACION DE CAMPAMENTO
CAPTACION DE QUEBRADA
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE ROCA DURA
ELIMINACION DE MATERIAL EXCEDENTE
OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADO
MAMPOSTERIA DE PIEDRA
CONCRETO fc 175 Kg /cm2 + 30% P.G.
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
DESARENADOR - CAMARA DE CARGA
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE ROCA DURA
OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
REVOQUES Y ENLUCIDO + IMPERMEABILIZANTE
TARRAJEO INTERIOR CON MORTERO
JUNTAS DE CONSTRUCCION
JUNTAS ASFALTICAS
COMPUERTA
COMPUERTA METALICA

ACTUAL

Valorizado

Metrado

S/.

ACUMULADO

Valorizado

Metrado

S/.

Valorizado

SALDO
%

Metrado

S/.

Valorizado

S/.

u
Glb
GLB
m2

1.00
1.00
1.00
30.00

857.11
8,987.32
909.54
75.20

13,009.95
857.11
8,987.32
909.54
2,255.98
3,175.55

1.00
1.00
1.00
30.00

13,009.95
857.11
8,987.32
909.54
2,255.98
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

1.00
1.00
1.00
30.00

13,009.95
857.11
8,987.32
909.54
2,255.98
0.00

100.00
100.00
100.00
100.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
3,175.55

0.00
0.00
0.00
0.00

m2

6.94

5.49

38.10

0.00

0.00

0.00

0.00

0.00

0.00

0.00

6.94

38.10

100.00

m3
m3

4.86
1.02

89.72
23.66

436.06
24.14

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

4.86
1.02

436.06
24.14

100.00
100.00

m2
m3
m3
m3
kg

13.80
4.00
1.23
1.43
105.81

33.13
141.43
324.88
388.74
6.60

457.17
565.71
399.61
555.90
698.86
2,214.25

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

13.80
4.00
1.23
1.43
105.81

457.17
565.71
399.61
555.90
698.86
2,214.25

100.00
100.00
100.00
100.00
100.00

m2

4.40

5.49

24.16

0.00

0.00

0.00

0.00

0.00

0.00

0.00

4.40

24.16

100.00

m3

1.05

89.72

94.21

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.05

94.21

100.00

m2
m3
kg

12.05
1.00
45.22

33.13
388.74
6.60

399.19
388.74
298.67

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

12.05
1.00
45.22

399.19
388.74
298.67

100.00
100.00
100.00

m2

4.85

45.28

219.59

0.00

0.00

0.00

0.00

0.00

0.00

0.00

4.85

219.59

100.00

1.20

11.21

13.45

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.20

13.45

100.00

1.00

776.24

776.24

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.00

776.24

100.00

A V A N C E S
PART.

PRESUPUESTO
Und.

04
04.01
04.01.01
04.01.02
04.02
04.02.01
04.02.02
04.02.03
04.02.04
04.02.05
04.02.06
04.03
04.03.01
04.03.02
05
05.01
05.01.01
05.02
05.02.01
05.03
05.03.01
05.03.03
05.04
05.04.01
05.05
05.05.01
05.06
05.06.01
05.06.02
06
06.01
06.01.01
06.02
06.02.01
06.02.02
06.03
06.03.01
06.03.02
06.03.03
06.03.04
06.04
06.04.01
06.05
06.05.01
06.06
06.06.01
06.06.02
07
07.01
07.01.01
07.02

LINEA DE CONDUCCION ENTUBADO


OBRAS PRELIMINARES
Km
LIMPIEZA DE TERRENO Y DESBROCE DE VEGETACION
Km
TRAZO, NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
m3
EXCAVACION DE ROCA DURA
m3
EXCAVACION EN MATERIAL CONGLOMERADO
m3
EXCAVACION EN MATERIAL SUELTO
m
REFINE Y PERFILADO DE ZANJAS PARA TUBERIA
m
CAMA DE APOYO CON MATERIAL SELECCIONADO
m3
RELLENO COMPACTADO CON MATERIAL PROPIO SELECCIONADO
INSTALACION DE TUBERIA
m
SUMINISTRO E INSTALACION DE TUBERIA PVC S-25 UF 4"
m
PRUEBA HIDRAULICA EN TUBERIA INSTALADA
CAJA DE LLAVE DE PASO (6 Und)
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION EN MATERIAL SUELTO
OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADO
CONCRETO f'c=175 kg/cm2
REVOQUES Y ENLUCIDO + IMPERMEABILIZANTE
TARRAJEO INTERIOR PISO
CERRAJERIA
TAPA METALICA
ACCESORIOS
VALVULA COMPUERTA DE BRONCE 2" + ACCESORIOS
VALVULA COMPUERTA DE BRONCE 1.5" + ACCESORIOS
CAMARA ROMPE PRESION
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION EN MATERIAL SUELTO
ELIMINACION DE MATERIAL EXCEDENTE
OBRAS DE CONCRETO
ENCOFRADO Y DESENCOFRADO
SOLADO DE PISO 1:4,E=4"
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
REVOQUES Y ENLUCIDO + IMPERMEABILIZANTE
TARRAJEO INTERIOR PISO
CERRAJERIA
TAPA METALICA
ACCESORIOS
VALVULA COMPUERTA DE BRONCE 2" + ACCESORIOS
VALVULA COMPUERTA DE BRONCE 1.5" + ACCESORIOS
REDES PRIMARIAS Y SECUNDARIAS
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS

Metrado

P. Unit.
S/.

ANTERIOR
Presup.

Metrado

97,768.66

ACTUAL

Valorizado
S/.

Metrado

71,542.68

ACUMULADO

Valorizado
S/.

Metrado

0.00

Valorizado
S/.

SALDO
%

Metrado

71,542.68

Valorizado
S/.

26,225.97

1.90
1.90

1,055.66
111.79

2,005.75
212.39

1.44
1.44

1,520.14
160.97

0.00
0.00

0.00
0.00

1.44
1.44

1,520.14
160.97

75.79
75.79

0.46
0.46

485.60
51.42

24.21
24.21

63.20
95.00
145.00
1,900.00
1,900.00
304.80

89.72
35.49
12.69
2.66
2.45
47.04

5,670.61
3,371.82
1,839.66
5,057.72
4,651.81
14,336.69

47.63
71.60
109.28
1,432.00
1,432.00
229.72

4,273.60
2,541.28
1,386.47
3,811.93
3,505.99
10,805.20

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

47.63
71.60
109.28
1,432.00
1,432.00
229.72

4,273.60
2,541.28
1,386.47
3,811.93
3,505.99
10,805.20

75.36
75.37
75.37
75.37
75.37
75.37

15.57
23.40
35.72
468.00
468.00
75.08

1,397.02
830.53
453.19
1,245.80
1,145.81
3,531.49

24.64
24.63
24.63
24.63
24.63
24.63

1,900.00
1,900.00

30.40
1.50

57,765.70
2,856.51
3,058.93

1,432.00
0.00

43,537.10
0.00
1,520.88

0.00
0.00

0.00
0.00
1,538.05

1,432.00
0.00

43,537.10
0.00
3,058.93

75.37
0.00

468.00
1,900.00

14,228.60
2,856.51
0.00

24.63
100.00

m2

0.64

5.49

3.51

0.64

3.51

0.00

0.00

0.64

3.51

100.00

0.00

0.00

0.00

m3

1.66

12.69

21.06

1.66

21.06

0.00

0.00

1.66

21.06

100.00

0.00

0.00

0.00

m2
m3

8.80
1.47

33.13
388.74

291.53
571.45

8.80
1.47

291.53
571.45

0.00
0.00

0.00
0.00

8.80
1.47

291.53
571.45

100.00
100.00

0.00
0.00

0.00
0.00

0.00
0.00

m2

5.60

31.26

175.07

5.60

175.07

0.00

0.00

5.60

175.07

100.00

0.00

0.00

0.00

4.00

114.57

458.26

4.00

458.26

0.00

0.00

4.00

458.26

100.00

0.00

0.00

0.00

u
u

4.00
4.00

216.81
167.70

867.23
670.82
3,641.08

0.00
0.00

0.00
0.00
0.00

4.00
4.00

867.23
670.82
3,641.08

4.00
4.00

867.23
670.82
3,641.08

100.00
100.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

m2

3.63

5.49

19.93

0.00

0.00

3.63

19.93

3.63

19.93

100.00

0.00

0.00

0.00

m3
m3

4.72
3.63

12.69
23.66

59.88
85.89

0.00
0.00

0.00
0.00

4.72
3.63

59.88
85.89

4.72
3.63

59.88
85.89

100.00
100.00

0.00
0.00

0.00
0.00

0.00
0.00

m2
m2
m3
kg

24.72
1.08
2.90
21.17

33.13
40.25
324.88
6.60

818.93
43.47
942.16
139.83

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

24.72
1.08
2.90
21.17

818.93
43.47
942.16
139.83

24.72
1.08
2.90
21.17

818.93
43.47
942.16
139.83

100.00
100.00
100.00
100.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

m2

1.08

31.26

33.76

0.00

0.00

1.08

33.76

1.08

33.76

100.00

0.00

0.00

0.00

3.00

114.57

343.70

0.00

0.00

3.00

343.70

3.00

343.70

100.00

0.00

0.00

0.00

u
u

3.00
3.00

216.81
167.70

650.42
503.11
132,575.91

0.00
0.00

0.00
0.00
112,010.48

3.00
3.00

650.42
503.11
20,565.42

3.00
3.00

650.42
503.11
132,575.91

100.00
100.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

KM

5.78

111.79

646.12

4.90

547.75

0.88

98.37

5.78

646.12

100.00

0.00

0.00

0.00

A V A N C E S
PART.

PRESUPUESTO
Und.

Metrado

P. Unit.

ANTERIOR
Presup.

Metrado

S/.
07.02.01
07.02.02
07.02.03
07.02.04
07.03
07.03.01
07.03.02
07.03.03
07.03.04
07.03.05
08
08.01
08.02.01
08.02
08.03.01
08.03.02
08.03.03
08.04
08.05.01
08.05
08.06.01
09
09.01
09.01.01
09.02
09.02.01
09.03
09.03.01
09.03.02
09.04
09.04.01
09.05
09.05.01
10
10.01
10.01.01
10.02
10.02.01
10.02.02
10.02.03
10.02.04
10.02.05
11
11.01
11.01.01
11.02
11.02.01
11.02.02
11.03
11.03.01
12

EXCAVACION ZANJA 0.60 *0.40m


REFINE Y PERFILADO DE ZANJAS PARA TUBERIA
CAMA DE APOYO CON MATERIAL SELECCIONADO
RELLENO Y COMPACTACION DE ZANJA
TUBERIA Y ACCESORIOS
TUBERIA PVC - SAP 3" C- 10
TUBERIA PVC - SAP 2" C- 10
TUBERIA PVC - SAP 1" C- 10
PRUEBA HIDRAULICA EN TUBERIAS
ACCESORIOS PVC - SAP
ARCOS DE RIEGO (8 Und)
MOVIMIENTO DE TIERRAS
EXCAVACION EN MATERIAL SUELTO
OBRAS DE CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
CONCRETO f'c=175 kg/cm2
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60
VALVULAS Y ACCESORIOS
VALVULAS 1.5" + ACCESORIOS
COMPUERTA
TAPA METALICA 0.90* 0.065m. 3/16"
HIDRANTES (38 Und)
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MOVIMIENTO DE TIERRAS
EXCAVACION DE MATERIAL SUELTA
OBRAS DE CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
CONCRETO f'c=175 kg/cm2
TAPA METALICA
TAPA METALICA 0.40* 0.30m 1/8"
VALVULAS Y ACCESORIOS
ACCESORIOS DE HIDRANTES
RAMALES DE ASPERSORES
OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO
MANGUERAS Y ASPERSORES
MANGUERA DE PE 32mm
ASPERSORES DE q =0.66 m3/hr+accesorios
ASPERSORES De q=0.41 m3/hr+accesorios
ACCESORIOS DE CONECCION HIDRANTES Y RAMALES
ELEVADOR c/ TRIPODE PARA ASPERSORES
VALVULA DE PURGA CON DADOS DE CONCRETO (13 UND)
MOVIMIENTO DE TIERRAS
EXCAVACION EN MATERIAL SUELTO
OBRAS DE CONCRETO SIMPLE
ENCOFRADO Y DESENCOFRADO
CONCRETO f'c=175 kg/cm2

ACTUAL

Valorizado

Metrado

S/.

ACUMULADO

Valorizado

Metrado

S/.

Valorizado

SALDO
%

Metrado

S/.

Valorizado

S/.

m
m
m
m

5,780.00
5,780.00
5,780.00
5,780.00

5.92
2.66
2.45
4.41

34,191.40
15,386.13
14,151.29
25,472.32

4,896.40
4,896.40
4,896.40
4,896.40

28,964.49
13,034.02
11,987.95
21,578.32

883.60
883.60
883.60
883.60

5,226.91
2,352.11
2,163.34
3,894.00

5,780.00
5,780.00
5,780.00
5,780.00

34,191.40
15,386.13
14,151.29
25,472.32

100.00
100.00
100.00
100.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

m
m
m
m
u

440.00
1,040.00
4,300.00
5,780.00
59.00

20.61
9.42
3.19
1.09
65.48

9,068.19
9,793.61
13,726.64
6,277.05
3,863.16
24,435.06

440.00
802.40
3,654.00
4,896.40
35.00

9,068.19
7,556.14
11,664.45
5,317.46
2,291.71
4,227.07

0.00
237.60
646.00
883.60
24.00

0.00
2,237.46
2,062.19
959.58
1,571.46
20,207.99

440.00
1,040.00
4,300.00
5,780.00
59.00

9,068.19
9,793.61
13,726.64
6,277.05
3,863.16
24,435.06

100.00
100.00
100.00
100.00
100.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

m3

14.85

12.69

188.41

5.80

73.59

9.05

114.82

14.85

188.41

100.00

0.00

0.00

0.00

m2
m3
KG

176.50
0.53
316.13

33.13
324.88
6.60

5,847.13
172.19
2,088.00

16.60
0.53
71.10

549.93
172.19
469.61

159.90
0.00
245.03

5,297.20
0.00
1,618.39

176.50
0.53
316.13

5,847.13
172.19
2,088.00

100.00
100.00
100.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

25.00

275.35

6,883.87

0.00

0.00

25.00

6,883.87

25.00

6,883.87

100.00

0.00

0.00

0.00

25.00

370.22

9,255.46
35,619.33

8.00

2,961.75
15,408.72

17.00

6,293.71
20,210.57

25.00

9,255.46
35,619.33

100.00

0.00

0.00
0.00

0.00

m2

17.70

5.49

97.19

9.50

52.16

8.20

45.02

17.70

97.19

100.00

0.00

0.00

0.00

m3

10.62

12.69

134.74

4.75

60.26

5.87

74.47

10.62

134.74

100.00

0.00

0.00

0.00

m2
m3

265.50
19.12

33.13
324.88

8,795.54
6,211.75

22.80
4.56

755.32
1,481.46

242.70
14.56

8,040.21
4,730.29

265.50
19.12

8,795.54
6,211.75

100.00
100.00

0.00
0.00

0.00
0.00

0.00
0.00

59.00

250.22

14,762.89

38.00

9,508.30

21.00

5,254.59

59.00

14,762.89

100.00

0.00

0.00

0.00

59.00

95.21

5,617.22
53,806.69

37.30

3,551.22
30,851.55

21.70

2,065.99
22,955.14

59.00

5,617.22
53,806.69

100.00

0.00

0.00
0.00

0.00

KM

3.39

739.12

2,505.62

2.34

1,729.54

1.05

776.08

3.39

2,505.62

100.00

0.00

0.00

0.00

ml
ud
ud
ud
ud

3,393.00
190.00
55.00
59.00
245.00

6.17
83.04
73.04
23.17
37.53

20,943.12
15,778.12
4,017.35
1,366.96
9,195.52
1,605.93

2,350.00
114.00
0.00
37.60
114.00

14,505.26 1,043.00
9,466.87
76.00
0.00
55.00
871.15
21.40
4,278.73
131.00
0.00

6,437.86
6,311.25
4,017.35
495.81
4,916.79
1,605.93

3,393.00
190.00
55.00
59.00
245.00

20,943.12
15,778.12
4,017.35
1,366.96
9,195.52
1,605.93

100.00
100.00
100.00
100.00
100.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

m3

3.38

12.69

42.88

0.00

0.00

3.38

42.88

3.38

42.88

100.00

0.00

0.00

0.00

m2
m3

0.97
3.00

33.13
324.88

32.13
974.65

0.00
0.00

0.00
0.00

0.97
3.00

32.13
974.65

0.97
3.00

32.13
974.65

100.00
100.00

0.00
0.00

0.00
0.00

0.00
0.00

27.00

20.60

556.27

0.00

0.00

27.00

556.27

27.00

556.27

100.00

0.00

0.00

0.00

ACCESORIOS
ACCESORIOS
RESERVORIO DE MAMPOSTERIA DE PIEDRA

205,569.04

186,674.47

18,894.58

205,569.04

0.00

A V A N C E S
PART.

PRESUPUESTO
Und.

Metrado

P. Unit.

ANTERIOR
Presup.

Metrado

S/.
12.01
12.01.01
12.02

Metrado

S/.

ACUMULADO

Valorizado

Metrado

S/.

Valorizado

SALDO
%

Metrado

S/.

Valorizado

S/.

205,569.04

OBRAS PRELIMINARES
TRAZO NIVELACION Y REPLANTEO

ACTUAL

Valorizado

m2

648.00

5.49

3,557.99

648.00

3,557.99

0.00

0.00

648.00

3,557.99

100.00

0.00

0.00

0.00

MOVIMIENTO DE TIERRAS

12.02.01

EXCAVACION DE VASO EN SUELO COMPACTADO

m3

1,717.20

12.69

21,786.67

1,717.20

21,786.67

0.00

0.00

1,717.20

21,786.67

100.00

0.00

0.00

0.00

12.02.02

EXCAVACION PARA ZAPATAS EN TERRENO NORMAL

m3

117.38

35.49

4,166.14

117.38

4,166.14

0.00

0.00

117.38

4,166.14

100.00

0.00

0.00

0.00

12.02.03

RELLENO COMPACTADO A MANO

m3

106.40

47.04

5,004.67

106.40

5,004.67

0.00

0.00

106.40

5,004.67

100.00

0.00

0.00

0.00

12.02.04

NIVELACION Y APISONADO DE PISO e=0.20m

m2

600.00

6.66

3,997.19

600.00

3,997.19

0.00

0.00

600.00

3,997.19

100.00

0.00

0.00

0.00

12.02.05

ELIMINACION DE MATERIAL EXCEDENTE D=30M

m3

1,555.20

23.66

36,798.94

1,555.20

36,798.94

0.00

0.00

1,555.20

36,798.94

100.00

0.00

0.00

0.00

12.03

MURO DEL RESERVORIO


m3

314.40

188.22

59,177.88

314.40

59,177.88

0.00

0.00

314.40

59,177.88

100.00

0.00

0.00

0.00

12.03.02

ENCOFRADO Y DESENCOFRADO

m2

266.88

33.13

8,841.25

0.00

0.00

266.88

8,841.25

266.88

8,841.25

100.00

0.00

0.00

0.00

12.03.03

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60

kg

1,095.80

6.60

7,237.62

944.34

6,237.25

151.46

1,000.37

1,095.80

7,237.62

100.00

0.00

0.00

0.00

12.03.04

ESCALERA DE GATO METALICA

1.00

744.60

744.60

1.00

744.60

0.00

0.00

1.00

744.60

100.00

0.00

0.00

0.00

m2

240.00

28.22

6,772.37

240.00

6,772.37

0.00

0.00

240.00

6,772.37

100.00

0.00

0.00

0.00

12.03.01

12.03.05
12.04

MURO DE MANPOSTERIA

REVESTIMIENTO, ENLUCIDOS IMPERMEABILIZADO e=3cm


PISO DEL RESERVORIO

12.04.01

PISO DE MANPOSTERIA DE PIEDRA

m3

150.11

6.60

990.73

150.11

990.73

0.00

0.00

150.11

990.73

100.00

0.00

0.00

0.00

12.04.02

ENCOFRADO Y DESENCOFRADO

m2

25.00

33.13

828.21

25.00

828.21

0.00

0.00

25.00

828.21

100.00

0.00

0.00

0.00

12.04.03

ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60

kg

2,679.04

6.60

17,694.72

1,851.42

12,228.40

827.62

5,466.33

2,679.04

17,694.72

100.00

0.00

0.00

0.00

12.04.04

REVESTIMIENTO, ENLUCIDOS IMPERMEABILIZADO e=3cm

m2

600.00

28.22

16,930.92

600.00

16,930.92

0.00

0.00

600.00

16,930.92

100.00

0.00

0.00

0.00

12.04.05

JUNTAS ASFALTICAS

380.00

11.21

4,258.37

380.00

4,258.37

0.00

0.00

380.00

4,258.37

100.00

0.00

0.00

0.00

12.05

VERTEDERO DE DEMASIAS

12.05.01

ENCOFRADO Y DESENCOFRADO

m2

2.44

33.13

80.83

0.00

0.00

2.44

80.83

2.44

80.83

100.00

0.00

0.00

0.00

12.05.02

CONCRETO f'c=175 kg/cm2

m3

0.16

324.88

51.98

0.00

0.00

0.16

51.98

0.16

51.98

100.00

0.00

0.00

0.00

12.06

CAJA ALIMENTADORA

12.06.01

CONCRETO fc 175 Kg /cm2

m3

0.14

324.88

45.48

0.00

0.00

0.14

45.48

0.14

45.48

100.00

0.00

0.00

0.00

12.06.02

ENCOFRADO Y DESENCOFRADO

m2

2.44

33.13

80.83

0.00

0.00

2.44

80.83

2.44

80.83

100.00

0.00

0.00

0.00

12.06.03

REVESTIMIENTO, ENLUCIDOS IMPERMEABILIZADO

m2

1.14

28.22

32.17

0.00

0.00

1.14

32.17

1.14

32.17

100.00

0.00

0.00

0.00

12.06.04

TAPA METALICA

und

1.00

114.57

114.57

0.00

0.00

1.00

114.57

1.00

114.57

100.00

0.00

0.00

0.00

12.07

VALVULA DE ESCARGA

12.07.01

EXCAVACION MATERIAL SUELTO

m3

0.48

12.69

6.09

0.00

0.00

0.48

6.09

0.48

6.09

100.00

0.00

0.00

0.00

12.07.02

ENCOFRADO Y DESENCOFRADO

m2

2.12

33.13

70.23

0.00

0.00

2.12

70.23

2.12

70.23

100.00

0.00

0.00

0.00

12.07.03

CONCRETO fc 175 Kg /cm2

m3

0.23

324.88

74.72

0.00

0.00

0.23

74.72

0.23

74.72

100.00

0.00

0.00

0.00

12.07.04

Tuberia pvc sap 4"

0.87

31.05

27.01

0.00

0.00

0.87

27.01

0.87

27.01

100.00

0.00

0.00

0.00

12.07.05

Sum. y Inst. de valvula Compuerta de Bronce de 2" + Acc

Und.

1.00

216.81

216.81

0.00

0.00

1.00

216.81

1.00

216.81

100.00

0.00

0.00

0.00

12.07.06

Acero fy = 4200 kg/cm2

kg

15.64

6.60

103.30

0.00

0.00

15.64

103.30

15.64

103.30

100.00

0.00

0.00

0.00

12.07.07

Tapa metalica

und

1.00

370.22

370.22

0.00

0.00

1.00

370.22

1.00

370.22

100.00

0.00

0.00

0.00

12.08

POZA DE DISIPACION

12.08.01

Excavacion de material suelto

m3

1.00

12.69

12.69

0.00

0.00

1.00

12.69

1.00

12.69

100.00

0.00

0.00

0.00

12.08.02

Encofrado y desencofrado

m2

5.78

33.13

191.48

0.00

0.00

5.78

191.48

5.78

191.48

100.00

0.00

0.00

0.00

12.08.03

concreto f'c=175kg/cm2

m3

0.81

324.88

263.15

0.00

0.00

0.81

263.15

0.81

263.15

100.00

0.00

0.00

0.00

12.09

CERCO PERIMETRICO

12.09.01

CERCO PERIMETRICO DE ALAMBRE

160.00

21.32

3,410.76

120.00

2,558.07

40.00

852.69

160.00

3,410.76

100.00

0.00

0.00

0.00

12.09.02

PORTON DE INGRESO

und

1.00

636.07

636.07

1.00

636.07

0.00

0.00

1.00

636.07

100.00

0.00

0.00

0.00

12.09.03
13.00

EXCAVACION DE ZANJA DE DERIVACION


CAJA DE INSPECCION (7 UND)

m3

27.96

35.49

992.38

0.00

0.00

27.96

992.38

27.96

992.38

100.00

0.00

0.00

0.00

13.01

TRAZO NIVELACION Y REPLANTEO

m2

18.56

5.49

101.91

4.48

24.60

14.08

77.31

18.56

101.91

100.00

0.00

0.00

0.00

13.02

EXCAVACION MATERIAL SUELTO

m3

13.92

12.69

176.61

3.14

39.84

10.78

136.77

13.92

176.61

100.00

0.00

0.00

0.00

13.03

CONCRETO fc 175 Kg /cm2

m3

105.56

324.88

34,294.58

3.35

1,088.36

102.21

33,206.22

105.56

34,294.58

100.00

0.00

0.00

0.00

35,995.85

2,015.42

33,980.43

35,995.85

0.00

A V A N C E S
PART.

PRESUPUESTO
Und.

Metrado

P. Unit.
S/.

ANTERIOR
Presup.

Metrado

ACTUAL

Valorizado
S/.

Metrado

ACUMULADO

Valorizado
S/.

Metrado

Valorizado
S/.

SALDO
%

Metrado

Valorizado
S/.

13.04

ENCOFRADO Y DESENCOFRADO

m2

5.52

33.13

182.87

5.52

182.87

0.00

0.00

5.52

182.87

100.00

0.00

0.00

0.00

13.05

ACERO fy=4200 kg/cm2

kg

45.24

6.60

298.80

45.24

298.80

0.00

0.00

45.24

298.80

100.00

0.00

0.00

0.00

13.06

REVESTIMIENTO, ENLUCIDOS IMPERMEABILIZADO

m2

33.35

28.22

941.08

13.50

380.95

19.85

560.13

33.35

941.08

100.00

0.00

0.00

0.00

612,476.23

437,261.22

71.39

143,599.19

23.45

580,860.45

94.84

31,615.77

5.16

68,660.20

49,018.14

COSTO DIRECTO
GASTOS GENERALES 11.21%
UTILIDAD(8%)

16,097.85

65,115.99

3,544.21

48,998.10

34,980.90

11,487.94

46,468.84

2,529.26

SUB-TOTAL

730,134.53

521,260.26

171,184.98

692,445.28

37,689.24

IGV (19 %)

138,725.56

99,039.45

32,525.15

131,564.60

7,160.96

TOTAL PRESUPUESTO

868,860.09

620,299.71

203,710.13

824,009.88

44,850.20

RESUMEN VALORIZACION N O7 DE OBRA DE PARTIDAS CONTRACTUALES - MARAYBAMBA ABAJO


OBRA:

SISTEMA DE RIEGO MARAYBAMBA ABAJO

EJEC.:

CHACON CONTRATISTAS GENERALES

SUPERV.:

ING. PEDRO SOTOMAYOR IZAGUIRRE

FINANCIA:

FONDO MINERO ANTAMINA

N 07

MES DE VALORIZ. AL 31 DE AGOSTO DEL 2,009


MONTO DE OBRA

: S/. 730,134.53

REGION

: ANCASH

FECHA DE INICIO DE OBRA

: 13-Octubre-2,008

DEPARTAMENTO

: ANCASH

PLAZO DE EJECUCION

: 90 Das Calendarios

PROVINCIA

: SIHUAS

AMPLIACION DE PLAZO

: 00 Das calendarios

DISTRITO

: SIHUAS

FECHA DE TERMINO CONTRACTUAL

: 12-Enero-2,009

LOCALIDAD

: MARAYBAMBA ABAJO

A V A N C E S
PART.

PRESUPUESTO
Und.

Metrado

P. Unit.

ANTERIOR
Presup.

S/.

Metrado

ACTUAL

Valorizado

Metrado

ACUMULADO

Valorizado

S/.

S/.

Metrado

Valorizado

SALDO
%

S/.

Metrado

Valorizado

01
02
03
04
05
06
07
08
09
10
11

OBRAS PRELIMINARES
CAPTACION DE QUEBRADA
DESARENADOR - CAMARA DE CARGA
LINEA DE CONDUCCION ENTUBADO
CAJA DE LLAVE DE PASO (6 Und)
CAMARA ROMPE PRESION
REDES PRIMARIAS Y SECUNDARIAS
ARCOS DE RIEGO (8 Und)
HIDRANTES (38 Und)
RAMALES DE ASPERSORES
VALVULA DE PURGA CON DADOS DE CONCRETO (13 UND)

13,009.95
3,175.55
2,214.25
97,768.66
3,058.93
3,641.08
132,575.91
24,435.06
35,619.33
53,806.69
1,605.93

13,009.95
0.00
0.00
71,542.68
1,520.88
0.00
112,010.48
4,227.07
15,408.72
30,851.55
0.00

0.00
0.00
0.00
0.00
1,538.05
3,641.08
20,565.42
20,207.99
20,210.57
22,955.14
1,605.93

13,009.95
0.00
0.00
71,542.68
3,058.93
3,641.08
132,575.91
24,435.06
35,619.33
53,806.69
1,605.93

0.00
3,175.55
2,214.25
26,225.97
0.00
0.00
0.00
0.00
0.00
0.00
0.00

12
13.00

RESERVORIO DE MAMPOSTERIA DE PIEDRA


CAJA DE INSPECCION (7 UND)

205,569.04

186,674.47

18,894.58

205,569.04

0.00

35,995.85

2,015.42

33,980.43

35,995.85

COSTO DIRECTO

612,476.23

437,261.22

68,660.20

49,018.14

GASTOS GENERALES 11.21%


UTILIDAD(8%)

71.39

143,599.19
16,097.85

23.45

580,860.45
65,115.99

S/.

0.00
94.84

31,615.77
3,544.21

48,998.10

34,980.90

11,487.94

46,468.84

2,529.26

SUB-TOTAL

730,134.53

521,260.26

171,184.98

692,445.28

37,689.24

IGV (19 %)

138,725.56

99,039.45

32,525.15

131,564.60

7,160.96

TOTAL PRESUPUESTO

868,860.09

620,299.71

203,710.13

824,009.88

44,850.20

5.16

LIQUIDACIN VALORIZACIN N 007


OBRA

UBICACIN

"CONSTRUCCION DEL SISTEMA DE RIEGO MARAYBAMBA ABAJO"

:
DISTRITO

SIHUAS

PROVINCIA

SIHUAS

DEPARTAMENTO :

PRESUPUESTO BASE :
MONTO CONTRATADO:
CONTRATISTA
:
FECHA PRESUPUESTO BASE :
ADELANTO EN EFECTIVO
:

TEM
1.00

ANCASH

S/.
S/.

SIN I.G.V

904,071.61
868,860.09

S/. 759,724.04
S/. 730,134.53

CHACON CONTRATISTAS GENERAL S.A.

S/. 0.00

DESCRIPCIN

ACUMULADO
ANTERIOR

MOVIMIENTO
ACTUAL

ACUMULADO
ACTUAL

171,184.98

609,961.63

VALORIZACIN DE OBRA

1.01 VALORIZACIN MENSUAL N 07

521,260.29

1.02 VALORIZACION DEL DEDUCTIVO N 02

(171,184.98)

1.03 VALORIZACION DEL ADICIONAL N 02

88,701.34

2.00

REINTEGROS

2.01 REINTEGROS (R)


3.00

VALORIZACIN BRUTA (VB=V+R)

4.00

AMORTIZACIONES :

0.00
521,260.29

a) ADELANTO EN EFECTIVO (D)

0.00

0.000
88,701.34

0.000

0.00
609,961.63

0.00

5.00

VAPORIZACIN NETA (VN=VB-D)

521,260.29

88,701.34

609,961.63

6.00

MONTO A PAGAR AL CONTRATISTA (VN-Fg)

521,260.29

88,701.34

609,961.63

7.00

I.G.V. (19 %) = VN x 0.19

99,039.46

16,853.25

115,892.71

MONTOS A CANCELAR AL CONTRATISTA


SUB TOTAL
I.G.V. (19 % )

S/.
S/.

88,701.34
16,853.25

TOTAL A FACTURAR POR EL CONTRATISTA

S/.

105,554.59

8.00

SALDO

RETENCIN DEL FONDO DE GARANTA Fg=0.05 x VB

26,063.01

4,435.07

30,498.08

120,172.90