Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 1 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SLNO LIST OF CONTENTS 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 PLANT DETAILS OBJECTIVE PROPOSAL SERVICES REQUIRED SAFETY PRECAUTIONS EMERGENCY PROCEDURE STATE OF THE PLANT METHOD COMPLETION CRITERIA APPENDICES a) LOG SHEET

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 2 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 1.0 PLANT DETAILS The Boiler Feed system consists of three Boiler Feed Pump sets for each unit of Simhadri STPP (2 Turbine Driven and 1 motor driven). Each pump set is of 50% capacity, which takes suction from the deaerator and discharge the Feed Water to series of HP heaters, economizer and finally to boiler drum. The important technical data of Boiler Feed booster pumps and Boiler Feed pumps are same as mentioned in testing schedule of MDBFP NO.PS-DC-186-500-118 1.1 Technical data of Turbine a. Maximum output b. Design rating (Economical rating) c. Speed d. Speed range e. Initial Steam Pressure f. Initial steam Temperature g. Exhaust pressure 1.2 Oil System a. Lube oil pump b. Emergency Oil pump c. Jacking Oil Pump d. Oil vapour extractor fans 2.0 OBJECTIVE To commission 2 Nos Turbine driven boiler feed pumps and associated auxiliaries and make them available for unit operation. 2 Nos 1 No. 1 No. 2 Nos 7575 KW 5732 KW 5275 RPM 1494-5750 RPM 6.33 ata. 289.6 0 C. 0.1064 ata.

STATUS

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 3 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 3.0 PROPOSAL Commissioning of each turbine driven Boiler Feed pump set proposed in the following steps. 3.1 Commissioning of oil system and turning gear operation of BFP Turbine. Commissioning of Governing System of BFP Turbine Steam rolling and actual over speeding of turbine (solo run of turbine) Commissioning of turbine driven Boiler Feed pump. SERVICES REQUIRED Availability of manpower with required tools for attending any leak, cleaning of filter and for adjustment of turbine governing system. Availability of operating personnal to carryout/ coordinate activities. Availability of lighting arrangements and communication facilities in operating Floors. Availability of instrument and service air. Availability of LT / HT Power Supply. Availability of auxiliary cooling water sypply. Availability of portable fire extinguishers around BFP area.

STATUS

3.2 3.3

3.4 4.0 4.1

4.2

4.3

4.4 4.5 4.6 4.7 Signatures

NTPC

BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 4 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 4.8 5.0 5.1 5.2 5.3 Availability of steam for turbine. SAFETY PRECAUTIONS Debris in and around BFP area shall be removed. First aid kit is available near the test area. Operation of local start / stop push button shall be ensured for perfect operation to facilitate for stopping of equipment in case of necessity. Approach / stair case / platform wherever required are made available. Portable fire fighting system made available at test area. Coupling gaurds are properly fixed. Safety appliances like helmet, hand gloves available for operating personnel. EMERGENCY PROCEDURES The test team should be aware of the procedure to be adopted in case of damage to machinery / injury of any personnel connected to the activity. The test team should be well aware of the procedures to be adopted in case of any abnormality in the activity.

STATUS

5.4

5.5 5.6 5.7

6.0 6.1

6.2

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 5 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 7.0 7.1 STATE OF THE PLANT Booster pump, Gearbox, Turbine, BFP and associated system are erected as per recommended drawing. Acid cleaning and oil flushing completed for lube oil and working oil, Jacking oil and governing oil piping as per test procedure No.PS-DC-186-500-104 and lines are normalized. Detergent flushing of feed water suction, discharge and recirculation piping are completed and all piping normalized. All piping supports are loaded to the rated value. Deaerator filled with fresh DM water with proper level indication and instrumentation completed. Flushing of following pipe lines completed. a) Cooling water lines of Booster pump and BFP (Seal Water cooler and seal body) b) Balancing leak off lines of main pump. c) Turbine exhaust hood spray line. 7.7 7.8 Turbovisory instrumentation completed. Erection of turbine complete and logsheets are filled, signed by concerned agencies. Insulation of turbine and steam lines complete. Steam blowing of live steam line complete and steam piping normalized.

STATUS

7.2

7.3

7.4 7.5

7.6

7.9 7.10

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 6 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 7.11 Erection of gland steam supply piping complete. Supports, steam blowing and insulation complete. Turbine drain piping and all steam piping drain lines are complete. For initial rolling orifice plates in drains are removed to avoid chocking. Turbine exhaust piping complete with supports upto condensor. Bursting diaphragm is erected and healty. Gland leak off piping erection complete to condensor (including supports and insulation) All motorized valves related to turbine including live steam isolation valves, turbine drain valves are commissioned. Gland steam pressure controller commissioned available for operation. Governing valves erected and protection devices like overspeed trip device, hand trip device are mounted properly. Feed water suction strainer erected in position in clean condition with DP indicator commissioned. All erection log sheets are followed up / signed by concernced agencies with respect to clearances and alignment data. Instrument and service air line for the Feed pump system erected and the air is made available for operation. All local and remote instrumentation for the system is complete. Insulation of the following completed.

STATUS

7.12

7.13 7.14 7.15

7.16

7.17

7.18

7.19

7.20

7.21

7.22 7.23 Signatures

NTPC

BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 7 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO STATUS a) Recirculation line of main pump. b) Suction and discharge line of booster pump and main pump. c) Main pump and booster pump body. 7.24 Commissioning of valves related to the feed pump system are completed. (Suction isolating valve, discharge isolating valve, recirculation valve and motor cooling water isolating valve) Interlock and protection system simulation checking completed. METHOD Commissioning of Oil System and Turning Gear Operation of BFP Turbine Ensure oil flushing of lub oil system completed and pipings are normalized. Ensure that the turbine is disconnected from gear box and main pump. Ensure completion of lube oil inlet lines with throttles / orifices pressure gauges and return lines with view glass and temperature gauges Check healthiness of bearing metal temperature detectors of turbine, main pump and booster pump. Ensure proper mounting of speed probes and turbovisory probes. Ensure the completion of Jacking Oil of lines with throttle valve, NRV and isolating valve. Ensure healthy filter elements in MOP, AOP, EOP suction lines, MOP, AOP and EOP discharge lines and JOP suction line.

7.25 8.0 8.1

8.1.1

8.1.2

8.1.3

8.1.4

8.1.5 8.1.6

8.1.7

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 8 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.1.8 8.1.9 8.1.10 Ensure oil is filled in MOT through centrifuge to adequate level. Keep open the vents of lube oil coolers and filters. Keep the changeover valve of lube oil cooler and filter in such a way that only one cooler ad filter will be in service. Ensure drains of lube oil coolers, filters are closed. Start one of the oil vapour fans with its suction valve open condition. Start one of the lube oil pumps ensuring flow through recircution. Adjust lube oil header pressure control valve to maintain lube oil pressure of 2.5 kg/cm2 after control station. Adjust lube oil discharge pressure to 10.0kg/cm2 by setting recirculation control valve. By operating isolating valve of recirculation control valve, check the safety valve popping and adjust if required. Check the lube oil flow to the bearing of turbine, main pump and booster pump. Monitor lube oil duplex filter DP. Stop the pump and start other lube oil pump and check its discharge safety valve popping and adjust if required. Stop running pump and start DC EOP. Ensure adequate lube oil pressure and flow. Keep DC EOP running for 4 hours to check the healthiness.

STATUS

8.1.11 8.1.12

8.1.13 8.1.14

8.1.15

8.1.16

8.1.17

8.1.18 8.1.19

8.1.20 8.1.21

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 9 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.1.22 8.1.23 8.1.24 8.1.25 8.1.26 Stop DC EOP and keep lube oil pump in service Charge the suction line of JOP from lube oil header. Start JOP and adjust the safety relief valve to 110 kg/cm2. Adjust pressure regulating valve to 100 kg/cm2 Adjust the throttle valves in Jacking oil supply to front and rear journal bearings such that the rotor lifts around 0.05 to 0.1 mm. Stop JOP and start again. Check and record the Jacking oil pressures and rotor lifts in the turbine front and rear journal bearings. Check and ensure the freeness of rotor for rotation by engaging hand barring lever and then stop JOP. Ensure auto operation of AOP I, AOP II and DC EOP through corresponding pressure switches operation. Keep AOP I in service, AOP II and EOP on auto. Ensure oil temperature more than 400C Charge cooling water to cooler and ensure oil temperature control valve auto operation. Start JOP and open turning gear valve. Once the rotor picks up speed, turning gear valve may be closed for checking the rotor for possible rubbing at end gland seals, heat shields, oil gaurds etc., while coasting down. If the rotor is found smooth till it comes to standstill, turning gear valve may be opened full.

STATUS

8.1.27

8.1.28

8.1.29 8.1.30 8.1.31

8.1.32 8.1.33

8.1.34

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 10 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.1.35 Ensure turning gear speed of around 200 RPM and smooth running. Observe and record bearing metal temperatures, vibrations, eccentricity etc., Run for 8 hours. stop turning gear and observe coasting down. Commissioning of Governing System of BFP Turbine Check that the connection from governing rack to governing elements and at the governing rack are as per governing scheme. Ensure main and auxiliary control valves lift reference indicator is fixed and set to zero position. Check the damping valve in HP and LP secondary oil lines are kept open by few turns. Check the filter elements at the control rack of the duplex filter are clean and healthy. Ensure emergency stop valve open / close limit switches mounted. Switch off the supply to the following solenoids. a) Trip solenoid valves, b) Remote reset of trip lever solenoid valve. c) Power supply off to the I/H convertors. 8.2.7 Ensure lube oil pump in service and charge governing oil to the governing system.

STATUS

8.1.36

8.1.37 8.2.0 8.2.1

8.2.2

8.2.3

8.2.4

8.2.5

8.2.6

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 11 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.2.8 Ensure all pressure switches and pressure gauges in governing rack are charged and their drain valves are closed. Reset the turbine locally and ensure following: a) Trip oil pressure more than 5.0 kg/cm2. b) Stop and control valves in closed condition. c) HP and LP secondary oil pressures less than 1.0 kg/cm2 8.2.10 Ensure oil temperature of 45-50 deg C during governing system adjustment. Opening / closing of emergency stop valve. Ensure power supply for solenoids 2220 and 2221. (It will be normally in deenergised condition) Ensure no steam available ahead of ESV and live steam isolating valve in closed condition. Give open command to ESV and observe the following sequential operation of solenoid valves 2220 and 2221. a) Both solenoids energises. Oil pressure above piston more than 5 kg/cm2 and below disc 0 kg/cm2 b) Solenoids 2220 deenergises oil pressure above piston more than 5 kg/cm2 and below disc more than 5 kg/cm2 . c) Solenoid 2221 also deenergises. Oil from above piston starts draining gradually through orifice and ESV opens. d) When ESV full open oil pressure below disc is more than 5 kg/cm2 and above piston 0 kg/cm2 . Adjust open limit switch and check feed back available in control room. 8.2.11.4 By tripping turbine trip lever, ensure tripping/closing of ESV. Check close feed back available in control room.

STATUS

8.2.9

8.2.11 8.2.11.1

8.2.11.2

8.2.11.3

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 12 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.2.12 Reset the turbine from remote by energising solenoid 1050. Ensure the same solenoid gets automatically deenergised when trip oil pressure raises more than 4.5 kg/cm2 through pressure switch. Switch on power supply to HP and LP I/H convertors. Give 4 mA current to HP I/H convertor with external source or through governor panel. Ensure HP sec. Oil pressure of 1.5 kg/cm2. If not set the pressure to 1.5 kg/cm2 by adjusting potentiometer XO in I/H convertor. Check that the control valve servomotor pilot is rotating freely and having a slight up and down movements. Check the main control valve servomotor is just opened, by 0.2 mm. The start of opening can be measured by fixing dial guage on servomotor. If the start of opening is not correct adjust the adjustment screw of the pilot slide to achieve the start of opeing. Raise the current to I/H conventor to 20 mA. Observe HP sec oil pressure increases to 4.5 kg/cm2 . If not adjust the potentiometer X1 of I/H convertor to achieve the pressure. Check the main control valve servomotor lift is maximum. If the lift is not correct adjust feed back angle to obtain the full lift. Check and adjust auxiliary control valve servomotor similarly as done for main control valve through steps 8.2.14 to 8.2.20. Record control valve characteristics (from 4 mA to 20 mA to I/H convertor)

STATUS

8.2.13 8.2.14

8.2.15

8.2.16

8.2.17

8.2.18

8.2.19

8.2.20

8.2.21

8.2.22

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 13 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 1. Current mA Vs HP sec oil pressure Vs main control valve lift. 2. Current to LP I/H convertor mA Vs LP sec-oil pressure Vs Auxiliary control valve lift. 8.2.23 Compare the characteristics and ensure these are in line with governing adjustment diagram/ shop floor test protocol. Operate the tester for ESV and ensure partial closing of ESV and put back the tester in normal position, ESV opens back to full open position. Energise the remote trip solenoid 2222 A/ 2222B and ensure the following. a) b) c) d) ESV closed. Main control valve is closed Auxiliary control valve is closed. Trip oil pressure is zero.

STATUS

8.2.24

8.2.25

8.3

Steam rolling and actual overspeeding of Turbine (solo run of turbine) Ensure that Gear box and main pump are disconnected from the turbine. Ensure healthiness of turbovisory system. Ensure proper clearance at the holding down bolts of turbine casing and front bearing pedestal. Ensure tightness of flanges in the turbine casing and exhaust line.

8.3.1

8.3.2 8.3.3

8.3.4

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 14 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.3.5 Check that all the temporary supports are removed from turbine casing, steam lines, oil lines etc., Ensure that the TD BFP foundation is separated from the main turbine foundation all around and the support spring assembly of TD BFP is properly placed. Start oil system. Keep the turbine on hydraulic barring. Record the measurements of oil system and turbovisory. Instal dial gauges for checking even expansion of the casing and pedestal. Warm up gland sealing steam supply header measurement of sealing steam supply temperature. ensure

STATUS

8.3.6

8.3.7

8.3.8

8.3.9

8.3.10 8.3.11

Keep open casing drain and balance piston loop drain valves. Observe vacuum created in turbine casing and exhaust line. Check for tightness of exhaust line and casing joints. Keep the gland steam controller on auto and observe that it maintains properly. Gradually open the exhaust butterfly valve in steps, keeping a watch on the vacuum in the condensor. Check the protections of the turbine. A typical list of turbine protections are given below: a) b) c) d) Lube oil pressure very low. Condensor vacuum very low. Turbine exhaust temperature very high. Control oil pressure very low.

8.3.12

8.3.13

8.3.14

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 15 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO e) f) g) h) i) j) Trip oil pressure very low Bearing temperatures very high Vibrations very high. Turbine speed very high. Turbine axial shift very high Any other protection as applicable and provided in the system.

STATUS

8.3.15

Keep open all drain valves in extraction 4 to TDBFP, CRH to TDBFP and auxiliary steam to TDBFP lines. Ensure governing oil system charged and ESV in close Condition. Warm up the steam inlet line to turbine (Steam supply can be taken from any one of the available sources) Ensure steam inlet pressure, measurements are healthy. temperature and flow

8.3.16

8.3.17

8.3.18

8.3.19 8.3.20 8.3.21

Reset the turbine and observe the trip oil pressure is available. Ensure steam purity as recommended in O & M manual. Ensure isolating valve in the steam supply source to turbine is opened full and all the drain lines are hot. Ensure steam parameters are achieved. The desirable start up parameter is approximately 4.0 kg/cm2 and 1800 C. Open emergency stop valve. Raise the speed of the turbine gradually to 1500 RPM, keeping a close watch on bearing metal temperature, shaft vibrations, casing expansions and for any rubbing noise. Check whether JOP is switching off and turning gear valve closes at speed of 500 RPM.

8.3.22

8.3.23 8.3.24

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 16 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.2.25 Soak the turbine at 1500 rpm for about 30 minutes observe the parameters are stablised. Raise the speed of the turbine gradually to rated speed as per start up curve, given in O & M manual. Monitor the behaviour of control valve during warming up speed and at rated speed for any hunting. At rated speed soak the machine for 15 minutes, observe for all parameters. Adjust lube oil flow to bearings if required. Carry out oil injection test of overspeed governor for few times to check repeatability of the action. Keep exhaust hood spray system on auto. Ensure its operation. Carryout actual overspeeding test of the turbine if the parameters such as vibration within limits and the casing expansion is more than 2 mm. If actual overspeed trip does not occur at required value, hand trip the turbine and adjustment to be done at emergency governor. Keep the hot turbine on hydraulic barring, ensuring gradual cooling down. Commissioning of Turbine Driven Boiler Feed Pump. Ensure alignment readings are logged and cleared for coupling.

STATUS

8.2.26

8.2.27

8.2.28

8.2.29

8.2.30 8.2.31

8.2.32

8.2.33

8.4 8.4.1

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 17 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.4.2 Couple turbine with BFP and Gearbox. Couple gearbox with booster pump. Crack open feed water suction isolating valve and vent out air in all the vents. Flush and shut the booster pump casing drain and BFP drain and interconnecting pipe drain. Check all the instrument tapping point isolating valves are open and that all drain and equalizing valves are shut. Gradually open suction isolating valve keeping watch on the trend of differential temperature of top and bottom of the main pump casing. Check mechanical seal water control isolating valves are open for Booster pump and BFP. Check magnetic separator isolating valves for BFP seal water are open. Ensure cooling water flow through all coolers. a) b) c) d) Booster pump seal water cooler. BFP seal water cooler. Lube oil cooler Jacket cooling of mechanical seals of Booster pump and BFP.

STATUS

8.4.3

8.4.4

8.4.5

8.4.6

8.4.7

8.4.8

8.4.9

8.4.10

Ensure isolating valves in recirculation line and leak off line are open. Ensure all alarm points and measuring points available in DCS/local.

8.4.11

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 18 of 21

Plant area: TURBING TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.4.12 Ensure all flanged joints are tightened properly with proper gaskets. Ensure proper clearance at the holding down bolts of the booster pump and main pump. Check the booster pump and main pump. Ensure oil system in service. Start jacking oil pump. Engage the main pump with turbine. Check the freeness of Turbine rotor along with booster pump and main pump by hand barring. Disengage the main pump and keep the turbine on hydraulic barring and prepare the turbine for steam rolling. When the turbine is ready for steam rolling, stop the turbine and engage the main pump with turbine. Keep the turbine along with main pump and booster pump on hydraulic barring. Raise the speed of the TDBFP to rated speed as per start up curve. Keep the pump on recirculation flow of approximately 250 T/hr for 8 hours to observe and record performance. Check lube oil flow through return oil sight glasses. Check for any undue noise, vibration in bearings, seals and pumps,

STATUS

8.4.13

8.4.14 8.4.15 8.4.16 8.4.17

8.4.18

8.4.19

8.4.20

8.4.21

8.4.22

8.4.23 8.4.24

Signatures NTPC BHEL

Station: NTPC- Simhadri

BHEL Ref No.PS-DC-186-500-119 NTPC Ref no SIM/1/TS/2/119

Sheet 19 of 21

Plant area: TURBINE TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP SL.NO 8.4.25 Check the speed control and pressure variations during operation of BFP for drum level control. During trial operation feed water suction strainers of Booster pump and BFP should be closely monitored. Stop TDBFP after trial run, put turbine on hydraulic barring The second set of TD BFP is to be commissioned in the same procedure as above. COMPLETION CRITERIA Commissioning of Turbine driven Boiler Feed pump set completed by carrying out the proposals given in section 3.0.

STATUS

8.4.26

8.4.27 8.4.28

9.0 9.1

Signatures NTPC BHEL

TESTING SCHEDULE FOR COMMISSIONING OF TURBINE DRIVEN BOILER FEED PUMP

SHEET 10.0 LOG SHEET 1 DATE : PROJECT UNIT EQUIPMENT ACTIVITY : : : BFP TURBINE :

20 OF 21

Time Hrs

Speed

Lub oil Hdr. Pressure

Oil pressure to Bearings Front Front Journal Thrust

Rear Journal

Bearing temperatures Front Front Journal Thrust

Rear Journal

Oil temperature Bef. cooler After cooler

Signatures NTPC BHEL

SHEET 21 OF 21 LOG SHEET 2 DATE : PROJECT UNIT EQUIPMENT ACTIVITY


Time Hrs Speed

: : : BFP TURBINE :
Live steam pressure Live steam Temp. Vibrations Front Rear
Casing expansion

Axial shift

HP sec Oil pr.

LP sec oil pr

HP valve lift

LP valve lift

Turbine exhaust pr.

Turbine exhaust temp.

Gland steam pr.

Gland steam temp.

Signatures NTPC BHEL