INSTRODUCTION
This work plan procedure covers only the field assembly and

installation of Condenser and LP Heater 1&2 , Omon Thermal Power Plant Unit No.2 PROJECT: OMON2 330MW THERMAL POWER PROJECT, Phuoc Thoi Commune, O Mon District, Can Tho City, CanTho Province, Vietnam OWNER: Can Tho Thermal Power Company Ltd CONTRACTOR: Daelim Industrial Co., Ltd.

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

DOCUMENT/DRAWING REFERENCES
3.3.16 Condenser Supply Division Instruction (MHI-Unit 1)

3.3.18 Install procedure for Condenser (MHI- Unit 1)


2.2.5.1. Attachment 1 Condenser Erection Tool &

Consumable List

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

GENERAL DESCRIPTION
The Condenser will be shipped to the site in the following
-

main modules: Packer plates and sliding plates - 0.4 tons (estimate) Temporaty structure - 8.1 tons (estimate) No. 1&2 LP Feed Water Heater - 56 tons (estimate) Two inlet waterboxes - 34.75 tons (estimate) Tow outlet waterboxes - 34.75 tons (estimate) Shell skirt with expansion joint in four modules - 50 tons (estimate) Shell block in four modules (no estimate)
SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

GENERAL DESCRIPTION
- Cooling Water Tubess (no estimate)
- Extraction pipes of the heater No. 1,2,3,4 (estimate for

each parts are not larger than 0.4 tons)

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


Item No Description Specification Quantity Prepared by Notes

A
1 2 3 4 5 6 7 8 9 10 11 12

Condenser Erection Tool


Tube roller (tube expansion) <Sugino machine limited>
Tube rolling controller (tube expansion) <Sugino machine limited> TR-506L TRC-1022 S22 5 Sets 5 Sets 5 Sets RC-28.58 EWF-15 1 Sets 5 Sets 1 Sets US-300 5 Sets 5 Sets 5 Sets 5 Sets 10 Sets 150T 1 pcs Daelim Daelim Daelim Daelim Daelim Daelim Daelim Daelim Daelim Daelim Daelim PTSC

Automatic voltage regulator (tube expansion) <Sugino machine limited>


Rolling tube cutter for tube cutting (tube cutting) <Sugino machine limited> Spring balancer (tube expansion & tube seal welding)

Thrust lever attachment (tube cutting) <Sugino machine limited>


Automatic seal welding machine <Mitsubishi electric corporation> Welding head for seal welding machine <Mitsubishi electric corporation> Remote control box for seal welding machine <Mitsubishi electric corporation> Seal welding machine accessory control cable, power cable <mitsubishi electric corporation> Seal welding machine accessory, gas hose, flowmeter <mitsubishi electric corporation> Crawler Crane

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


B
12 13 14

Condenser Erection Tool Consumable


Tube expander (inlet side) <Sugino machine limited> Tube expander (outlet) <Sugino machine limited> Extension universal joint (tube expander accessory) <Sugino machine limited> CB-244E5 x 30.5 R-0.5 CB-344E5 C4130 UE408 CB-244E5 x 30.5 R-0.5 CB-344E5 C4130 CB-244E5 x 30.5 R-0.5 CB-344E5 C4130 20 Sets 20 Sets 4 Sets Daelim Daelim Daelim

15

Mandrel (tube expander parts) <Sugino machine limited>

36 Sets 36 Sets

Daelim

16

Roller (tube expander parts) <Sugino machine limited>

36 Sets 36 Sets

Daelim

17 18 19 20 21

Screw for sidelock (tube expander parts) <Sugino machine limited>

13 Sets 4 Sets 70 Sets 70 Sets A: 70 Sets B: 70 Sets

Daelim Daelim Daelim Daelim Daelim

Mandrel coupling (tube roller accessory) <Sugino machine MC-64 limited>


Cutter wheel for rolling tube cutter <Sugino machine limited> Cutter pin for rolling tube cutter <Sugino machine limited> Pilot for rolling tube cutter T=0.5 <Sugino machine limited>

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


22

Pilot for rolling tube cutter T=0.7 <Sugino machine limited>


Frame for rolling tube cutter <Sugino machine limited> C pin for rolling tube cutter <Sugino machine limited> Stop ring for rolling tube cutter <Sugino machine limited> Cutter shaft for rolling tube <Sugino machine limited> Hexagonal socket button head screw <Sugino machine limited> Set screw Type -1, Type -2 <Sugino machine limited> Facing Tool <Sugino machine limited> Cutter <Sugino machine limited> Pilot <Sugino machine limited> Ball retainer (parts for facing tool) <Sugino machine limited> Cap nut (facing tool parts) <Sugino machine limited> Knock out tool <Sugino machine limited> Seal welding machine accessory: gas lens, fuse, battery, collet chack, nozzle for gas lens, torch cap, electrode, etc FF-8T

A: 6 Sets B: 6 Sets
3 Sets 6 Sets 6 Sets 1 Sets 6 Sets Type-1:6 Sets Type-2: 6 Sets 8 Sets 40 Sets T=0.5: 35 Sets T= 0.7: 3 Sets 5 Sets 10 Sets 5 Sets 1 Sets

Daelim

23 24 25 26 27 28 29 30 31 32 33 34 35

Daelim Daelim Daelim Daelim Daelim Dealim Dealim Dealim Dealim Dealim Dealim Dealim Dealim

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


C Condenser Erection Jig
T=0.5:150 Sets T= 0.7:50 Sets Tube guide for tube insertion T= 0.5mm T= 0.7mm

36

Plastic

Dealim

37

Center guide for seal welding machine T=0.5mm T=0.7mm

T=0.5: 30 Sets T= 0.7:30 Sets Cr-Cu Dealim

38

Cooling tube gap revision punch for seal welding Piano wire centering jig for tube support plate centering

S45C or S35C

2 Sets

Dealim

39

SUS304

8 Sets

Dealim

40

Piano wire centering check jig for tube support plate centering
Lifting beam for shell block Lifting beam for tube box Lifting beam for shell skirt

SUS304

4 Sets

Dealim

41 42 43

1 Set 1 Set 1 Set

Dealim Dealim Dealim

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


D
44 45 46 47 48 49 50

Erection Tool
Tir tank for shell kirt & shell block handling Hydrolic jack for shell bock lift down Winch for shell skirt & shell block handling Chain block for shell skirt suspend Chain block for lifting Eye bolt for tube plate lifting Hexagonal wrench for tube expander 25T 100T 20T 25T 15T M48 8 Sets 4 Sets 1 Sets 6 Sets 6 Sets 4 Sets 5 Sets PTSC PTSC PTSC PTSC PTSC PTSC Dealim

E
51 52 53

Erection Measuring Tool


Micro meter for tube expansion ratio check Vernier calipers for tube expansion ratio check Inside micrometer for tube expansion ratio check MDQ-30 CD-15CX 1 Set 1 Set PTSC PTSC PTSC

Borematic SBM-25C 1 Set

54

Inside micrometer for setting ring for tube expansion ratio check

Borematic Series 117-139

1 Set

PTSC

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


F
55 56

Erection Consumable
Piano wire 0.5mmx100m Liquid gasket for tube plate sealing
Three bond 1215 250 g Tube Three bond 5211E 250 g Tube BO Mejicon #10S 250 g Tube SUS304 16L

2 Sets 60 Sets

PTSC Dealim

57

Silicone sealant for water box sealing

20 Sets

Dealim

58 59 60 61 62 63 64

Epoxy coating for bolt nut coating Wire brush for tube plate polishing Alcohol for tube plate cleaning Expander oil for steel <Sugino machine limited> Expander cream <Sugino machine limited> Rubber Liner for tir tank

20 Sets 50 Sets 2 Sets

Dealim PTSC PTSC Dealim Dealim

8 Sets 100 Sets

Dealim PTSC Refer to 3.3.16-Condenser supply division instruction shown that the packer plates and sliding plates shall be provided by condenser s supplier. With size of 120x180x t20 x 100pcs , with estimation of weight is about 339.23 kg. Refer to 3.3.16-Condenser supply division instruction shown that the temporary structure/working stage shall be provided by condenser s supplier. The estimation of weight is about 8.1 tons.

Welding shrinkage lug for shell skirt & shell block T= 20 welding Packer plate for shell skirt & block handling/water T= 20 filling beam

65

20 Sets

PTSC

66

Working stage for tube insertion

1 Set

PTSC

67 68

Dust protection stage for shell inside Welding rod for tube seal welding repair

Wooden/tin plate Wel Tig Ti-316L

1 Set 5 kg

PTSC Dealim

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION TOOL & CONSUMABLE LIST


69 70 Suport Beam for assembly of condenser H300x300x10x 2000 8 pcs 2 pcs PTSC PTSC With estimation of weight is about 1.6 tons With estimation of weight is about 9.6 tons Temporary Beam on the T/G foundation opening H300x300x10x to suspend temporary the shell skirt with expansion 12000 joint

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

TRANSPORTATION, UNLOADING & PRESERVATION AT SITE


In principle, Trailers, Dollies, or other types shall be

used for field transportation. The Condenser will be directed transported from Fabrication shop to the plant site (to the staging area) based on the erection sequence.

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


1. PREPARATION WORK

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


2. CENTER LINE AND DIMENSION CHECK OF FOUNDATION

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


3. SETTING OF PACKER PLATES, SLIDING PLATES AND GROUTING WORK

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


4. SETTING OF TEMPORARY STRUCTRURE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


Detail Temporary Structure Drawing

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


Detail Temporary Structure Drawing

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


5. CARRY-IN AND TEMPORARY STORING OF LP-1/2 HEATERS BY CRAWLER CRANE 150T AND TIR ROLLER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR LP 1/2 HEATERS

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR LP 1/2 HEATERS

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


6. CARRY-IN AND TEMPORARY STORING OF WATER BOX (REVERSING SIDE) BY OVERHEAD CRANE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


7. CARRY-IN AND TEMPORARY STORING OF EXPANSION JOINT BY OVERHEAD CRANE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


8. CARRY-IN SHELL SKIRT OF CONDENSER BY OVERHEAD CRANE AND TIR ROLLER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR CONDENSER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR CONDENSER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


9. ASSEMBLY OF CONDENSER SHELL SKIRT
-

Fit-up shell skirt

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


-

Welding of shell skirt

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE

Take down expansion on shell skirt Lift up of shell skirt for temporary storage

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


10. CARRY IN OF CONDENSER SHELL BLOCK BY OVERHEAD CRANE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR CONDENSER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


11. ASSEMBLY CONDENSER SHELL BLOCK - Fit-up shell blocks

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


- Setting of shell skirt with expansion to sheel block

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


- Welding of shell blocks /shell blocks and shell skirt

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


12. SETTING OF DUST PROTECTION COVER

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


13. CENTERING OF TUBE PLATE AND TUBE SUPPORT PLATE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


14. SETTING WATERBOX (REVERSE SIDE)

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


15. INSERTION OF COOLING WATER TUBES

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


16. SETTING OF WATER BOX (IN/OUTLET SIDE)

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


17. EXPANDING &CUTTING OF COOLING TUBE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


18. SEAL WELDING OF COOLING TUBE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


19. INSPECTION AFTER SEAL WELDING

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


20. SETTINH OF LP 1/2 HEATERS

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


INSTALLATION PLAN FOR LP 1/2 HEATERS

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


21. LP 1/2 HEATERS ALIGNMENT AND FIT-UP EXTRACTION

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


22. SETTING OF INNER PIPING

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


23. FITTING OF AIR EXTRACTIOB PIPE (INSIDE OF WATER BOX)

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


24. WELDING BETWEEN SHELL SKIRT AND EXPANSION JOINT

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


25. WELDING BETWEEN EXPANSION JOINT AND LP TURBINE LOWER CASING

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


26. WATER FILLING TEST (SHELL SIDE)

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

ERECTION SEQUENCE AND PROCEDURE


27. PAINTING - The condenser painting shall be carried out in accordance with the painting specification for Condenser

SOLUTION FOR OIL & GAS INDUSTRY

O Mon Thermal Power Plant Unit No.2

THANK YOUR FOR YOUR ATTENTION