Contents
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Models Project Brief Figures & Quantities Structural Overview Sequence of Work Cranage & Hoisting Concrete Placement Survey & Monitoring Spire Erection Photographs
Model
The Burj is a landmark high rise structure part of a very important development scheme in downtown Dubai
Model
Some artistical impressions
Model
Model
Model
Model
Project Brief
Pinnacle Spire
Communication (L160)
Office (L153)
876,000,000 USD EMAAR Properties Above 160 floors Above 800m Hotel, Residence, Office
Observatory (L123) Residence (L108)
Hotel (L39)
Project Brief
.Client Emaar Properties PJSC
.Consultants Project Manager Design Turner Construction Intl. Skidmore, Owings & Merill (SOM) Hyder Consulting DG Jones Intl.
.Construction Period
Total height of the tower : More than 800 M Gross area tower : 279,000 sq. M Gross area podium : 186,000 sq. M
Total concrete quantity tower : 145,000 cubic M Total concrete quantity podium : 115,000 cubic M Overall concrete quantity : 260,000 cubic M Overall rebar quantity : 34,000 tons
Structural Overview
Y-shaped floor plan is ideal for residential program Maximizes window perimeter to floor plate area Is inherently stable Buttressed core Three wings arranged around central core Each wing supports other two Setbacks occur at each wing in a spiraling pattern Reduces vortex shedding by changing building shape 2 4 times
Structural Overview
Analysis Model
Structural Overview
Hotel Residential Floor plan
Structural Overview
Tower Seismic Design
500 year Event Wind Typically Governs Seismic Only Governs near Top
Structural Overview
Predicted Wind Drift Location Elevation Drift (m) (mm) +604.9 1450 +569.7 1250 +442.1 +375.3 750 540
Top Residential
Structural Overview
Sequence of Work
Typical Work Sequence
wing-A
C-1
C-3
[Section A-A]
C-2
wing-C
wingB
3 to 5 levels below
2 levels below
2 levels below 6 to 8 levels below Wing Slab 3levels below Wing Corridor Slab Corner Slab Center Lobby Slab Nose Slab Wing Corewall Center Corewall Corner Slab
Sequence of Work
Work Sequence & Shoring Plan
Day 0 : Conc Pouring Day 1 : Slab formwork Day 2 : Slab formwork : Rebar Installation : MEP
N+1
N+0 Form N-1 Additional Raking Shore Form N-2 1/2 of Raking Shore 1/2 of Raking Shore 2/3 of Prop 2/3 of Prop N-5 1/3 of Prop 1/2 of Raking Shore 2/3 of Prop Form Form
N-3
N-4
. Hoist - 14 cages Phase 1 (Ground ~ L100) : H/C#1~#4 (8cages) Phase 2 (L100 ~ L142) Phase 3 (L142 ~ SL2) : H/C#5~#6 (4 cages) : H/C#7 (2 cages)
H/C#3~4 H/C#7 T/C#M2 T/C#M3
Jump Hoist : Jump#1, Jump#2 (2 cages) . Concrete Pump - 4 nos. Pump#1~#3 (Ground Level) : High Pressure Pump#4 (L124) for Secondary Pumping
H/C#5~6 H/C#1~2
. Concrete Placing Boom - 4 nos. CPB#1. for Center core : 32m Boom CPB#2~#4. for Wing core : 28m Boom
T/C#M1
T/C#M2 M380D
T/C#M3 M220D
Installation Height : 48m Top collar T/C#M1 : M440D Clamping Height : 15.5 ~ 17m Bottom collar
23
1st Station
W
22
21
SPIRE LEVEL 3 - MEZZA T/STEEL EL: +640.0
20
19
18
SPIRE LEVEL 2 - MEZZA T/STEEL EL: +627.2
17
16
SPIRE LEVEL 2 - MEZZA T/STEEL EL: +620.8
15
14
2nd
Station: L99
LEVEL 160 LEVEL 159 LEVEL 158 LEVEL 157
13
LEVEL 162 / SPIRE LEV T/SLAB EL: +608.0
12
11
LEVEL 161 T/SLAB EL: +601.9
10
LEVEL 156 LEVEL 155 LEVEL 154 LEVEL 153 LEVEL 152 LEVEL 151 LEVEL 150 LEVEL 149 LEVEL 148 LEVEL 147
LEVEL 145
LEVEL 135
LEVEL 130
LEVEL 125
LEVEL 120
LEVEL 115
LEVEL 110
2nd
Station
LEVEL 105
S6 S5 S4 S3 S2 S1
4500
4500
4500
4500
4500
Step 1 : Main T/C Dismantling 1) Main T/C Descending to L161 2) Main T/C Dismantled to L99 by Favco 242R 3) Dismantled Components moved to Ground by Ogawa OT4520
10
LEVEL 160
8
LEVEL 159
7 6
LEVEL 156 LEVEL 155 LEVEL 154 LEVEL 153 LEVEL 152 LEVEL 151 LEVEL 150 LEVEL 149 LEVEL 148 LEVEL 147
LEVEL 145
LEVEL 135
10
LEVEL 130
LEVEL 160
8
LEVEL 159
7
LEVEL 125
LEVEL 158
LEVEL 120
Main T/C
LEVEL 157
LEVEL 115
LEVEL 156
LEVEL 155
LEVEL 110
LEVEL 154
LEVEL 105
S6
S5
S4
S3
S2
S1
4500
4500
4500
4500
4500
1st Station
Step 2 : Favco 242R Dismantling 1) Favco SDD 3/10 Installed on L161 2) Favco 242R Dismantled to L99 by Favco SDD3/10 3) Dismantled Components moved to Ground
LEVEL 160
LEVEL 159
LEVEL 156 LEVEL 155 LEVEL 154 LEVEL 153 LEVEL 152 LEVEL 151 LEVEL 150 LEVEL 149 LEVEL 148 LEVEL 147
by Ogawa OT4520.
LEVEL 145
SPIRE LEVEL 2 - MEZ T/STEEL EL: +627.2
LEVEL 135
LEVEL 130
LEVEL 125
Favco SDD3/10
LEVEL 120
LEVEL 115
LEVEL 110
2nd
Station
LEVEL 105
S6 S5 S4 S3 S2 S1
4500
4500
4500
4500
4500
Step 3 : Ogawa OT4520 Dismantling 1) Favco SDD 3/10 Re-installed on L99 2) Ogawa OT4520 Dismantled to Ground by Favco SDD3/10
LEVEL 160
LEVEL 159
LEVEL 156
LEVEL 155 LEVEL 154 LEVEL 153 LEVEL 152 LEVEL 151 LEVEL 150 LEVEL 149 LEVEL 148 LEVEL 147
LEVEL 145
LEVEL 135
Ogawa OT4520
VEL 105
LEVEL 130
S6
S5
S4
S3
S2
S1
4500
4500
4500
4500
4500
LEVEL 125
LEVEL 120
L99
LEVEL 115
LEVEL 110
2nd Station
Favco SDD3/10
S5 S4 S3 S2 S1
LEVEL 105
S6
4500
4500
4500
4500
4500
Concrete Placement
Concrete Placement Method
Level Ground ~ L145 L146 ~ L160M L160M ~ Spire1 . Concrete Pump Level Pressure 185 / 320 bar 220 / 260 bar Output 71 / 36 m3/hr 110 m3/hr Engine 470 kw 200 kw Remarks 2 nos. of Main 1 no. of Stand by Secondary Pumping
CPB#4
Remarks Target Height (RC Structure) Secondary Pump on L124 (East wing 442m) From Ground Level
Pumping Area (Ground Level) Pipe Lines
Pump#1~#3 Pump#4
. Concrete Placing Boom - 32m boom for Center Core - 3nos. of 28m boom for Wing Core . Pipe Lines
CPB#1
CPB#3
CPB#2
Concrete Placement
Pipe Line Schedule
Line#1. (L160) for Center Core Pinnacle Top of Finial : Spire
Line#3. (L124) for East Wing Line#4. (L112) for West Wing
Concrete Placement
Re-pumping
Spire1 (682m)
Line#1 (~L154)
S1
4500
W1 E1
S2
00 45
45 00
E2
00 45
45 00
CPB#2
CPB#1
Survey & Monitoring Low Level Tower Control Classical Control Method
XYZ
XYZ
XYZ
XYZ
XYZ
ANTENNA
REFERENCE STATION
Level 92
: Middle Floor Level between Outrigger Floors : Level 5, 16, 19, 26, 39, 43, 58, 72, 76, 92, 108, 112, 138, 146 (14 Floors)
Level 58
. Wind Speed/Direction, Temperature, Humidity - Location ; Level 5, 43, 76, 112, 146 (Tower Outside)
Spire Erection
Spire Erection
Spire Erection Method
Completion of Lifting
Spire Erection
Thank you !
Photographs
22/01/2005
Photographs
Photographs
Photographs
Photographs
Thank you !