APLICACION PRACTICA DE LA METODOLOGIA DEL VALOR GANADO AL PROYECTO

N ACTIVIDAD
1 OBRAS GENERALES

MONTO
215,502.19

0
-

Valorizacion a precios aprobados (VPA)


Costos reales de lo efectuado (CRE)

2 PAVIMENTO FLEXIBLE

1,407,770.23

788,832.37

80,010.66

214,030.66

1,081,643.78

Avance planeado (APL)

1
32,103.50
32,103.50
22,546.33
-

2
74,678.01
74,678.01
57,543.23
-

3
19,015.72
19,015.72
13,456.32
-

20,038.74
18,765.76
12,345.43
-

98,921.98
96,764.98
81,231.43
8,001.06
7,576.87
4,324.54
21,403.06
18,645.34
10,532.00
216,328.76
105,435.76
98,765.54
419,332.87
11.07
15.30
579,639.49
303,100.96
8.00
12.20
462,134.42
252,396.74
379,634.15

295,494.20
295,494.20
263,345.43
32,004.27
29,765.87
19,761.32
85,612.26
83,645.23
65,674.54
324,493.13
320,222.54
300,345.76
756,619.58
19.98
35.28
1,336,259.07
748,143.56
19.75
31.95
1,210,277.98
662,583.37
1,042,217.52

Valorizacion a precios aprobados (VPA)


Costos reales de lo efectuado (CRE)

3 VEREDAS
Valorizacion a precios aprobados (VPA)
Costos reales de lo efectuado (CRE)

4 RAMPAS
Valorizacion a precios aprobados (VPA)
Costos reales de lo efectuado (CRE)

5 SARDINELES SUMERGIDOS

Valorizacion a precios aprobados (VPA)


Costos reales de lo efectuado (CRE)

6 MUROS DE SOSTENIMIENTO
Valorizacion a precios aprobados (VPA)
Costos reales de lo efectuado (CRE)
Costo presupuestado trabajo planeado (BCWS)

Avance planeado %
Avance planeado acumulado %
Avance planeado acumulado (APA)
Costo presupuestado trabajo realizado (BCWP)

Avance real (ARE)

Avance real %
Avance real acumulado %
Avance real acumulado (ARA)
Costo real del trabajo realizado (ACWP)

Resultados costo real (RCR)


Resultados costo acumulado (RCA)

108,164.38
108,164.20
92,345.65
160,306.62
4.23
4.23
160,306.62
159,033.46
4.20
4.20
159,033.46
127,237.41
127,237.41

4
2,508.52
2,508.52
1,754.54
193,697.91
193,697.91
156,783.32
295,494.21
294,754.54
258,654.54
32,004.27
30,765.87
15,341.43
85,612.27
80,643.23
65,294.54
324,493.13
322,765.65
303,245.43
933,810.31
24.65
59.93
2,270,069.38
925,135.72
24.42
56.38
2,135,413.70
801,073.80
1,843,291.32

5
7,485.57
7,485.57
4,535.45
1,023,343.16
1,023,343.16
989,654.98
78,883.24
70,764.65
54,765.87
8,001.06
7,900.98
3,456.54
21,403.07
18,987.12
10,112.43
108,164.38
103,654.98
85,435.54
1,247,280.48
32.93
92.86
3,517,349.86
1,232,136.46
32.53
88.91
3,367,550.16
1,147,960.81
2,991,252.13

6
79,710.87
79,710.87
65,675.43
190,729.16
190,729.17
154,789.65
12,288.24
5,654.78
4,001.06
2,654.43
12,109.74
4,567.43
121,400.65
100,324.32
270,440.03
7.14
100.00
3,787,789.89
420,239.73
11.09
100.00
3,787,789.89
333,666.04
3,324,918.17

215,502.19
215,502.19
165,511.30
1,407,770.23
1,407,770.24
1,301,227.95
788,832.37
788,832.37
675,997.48
80,010.66
80,010.65
45,538.26
214,030.66
214,030.66
156,180.94
1,081,643.78
1,081,643.78
980,462.24
3,787,789.89
100.00

3,787,789.89
100.00

3,324,918.17

DATOS PARA ANALISIS DE RESULTADOS


Plazo contractual
Variable

Significado

4 meses
Descripcion/formula

Avance planeado
Avance planeado acumulado
Avance real

BCWP
ACWP

20.96
71.78
15,535

68,600

28,300

86,450

36,200

-26.02
-12,030.00
-26.02

-27.92
12,765.00
-27.92

-14.92

82.17

50.81
50.81

20.96
71.78

64.04
64.04

26.81
90.85

EAC = BAC/CPI

170,127.55

172,685.51

EDP = Plazo/IDT

4.7

2.2

CPI = BCWP/ACWP

0.79

0.78

SPI = BCWP/BCWS

0.85

1.82

Costo
presupuestado
del Dato resultante del planeamiento
trabajo planeado
Costo
presupuestado
del Dato resultante del trabajo ejecutado
trabajo realizado
Costo real del trabajo realizado Dato resultante del costo real, segn

CV
SV
%CV

Variacin de costo

los recursos realmente empleados


CV = BCWP-ACWP

Variacin de tiempo

SV = BCWP-BCWS

Variacin de costo porcentual

CV (%) = (CV/BCWP) x 100

%SV

Variacin de tiempo porcentual SV (%) = (SV/BCWS) x 100

%PC
%PCA

Porcentaje de completado

%PG
%PGA
EAC
EDP
CPI
SPI

PC (%) = (BCWP/BAC) x100

Porcentaje de completado
acumulado
PG (%) = (ACWP/BAC) x100
Porcentaje de gastado
Porcentaje
de
gastado
acumulado
Costo estimado del proyecto al
termino
Plazo estimado para el termino
del proyecto
ndice de desempeo de
costos
ndice de desempeo de
tiempo

Monto contractual $US


2
11.51
71.23

50.81
50.81
80,630

Avance real acumulado

BCWS

1
59.73
59.73

GRAFICO CPI VS SPI

1.82

1.5
3

SPI

0.5
0.85
1

0.5

NALISIS DE RESULTADOS
Monto contractual $US
3
14.64
85.87

135,000.00
4
14.13
100

6
100

Total
100.01

18.96
90.74
19,760

18.37
109.11
19,075

5.78
114.89

25,600

24,800

7,800

155,100.00

28,150

28,000

4,600

183,400.00

-9.96
5,840.00
-9.96

-12.9
5,725.00
-12.9

41.03
7,800.00
41.03

29.55

30.01

18.96
90.74

18.37
109.11

5.78
114.89

20.85
111.7

20.74
132.44

3.41
135.85

148,447.27

152,419.35

79,615.38

3.09

3.08

0.91

0.89

1.3

1.3

GRAFICO CPI VS SPI


2

1.82

1.5

1.3
1.3

114.88
135,000.00

1.7

-26.02
-14.92
-26.02

(61.79)

135.85
170,127.55

1.3
1.3

1
0.85

0.5

0
CPI

1.5