ActivityID ActivityName Start Finish Activity%

Complete
PWB-3 PRIVATE WING BUILDING PWB-3 PRIVATE WING BUILDING
13-Apr-14A 15-Feb-15
PWB-3.1 CLARIFICATION PWB-3.1 CLARIFICATION
10-May-14A 10-May-14A
A1000 Clarification/Contract sign 10-May-14A 100%
PWB-3.2 CONCEPT DESIGN PWB-3.2 CONCEPT DESIGN
10-May-14A 10-May-14A
A1010 Concept Design 10-May-14A 100%
A1020 Review&Approval 10-May-14A 100%
PWB-3.3 MOCK UP PWB-3.3 MOCK UP
10-May-14A 05-J un-14
PWB-3.3.1 Submittal PWB-3.3.1 Submittal 10-May-14A 29-May-14
A1030 Mockup&Material Sample 10-May-14A 100%
A1040 Mockup&Material Sample (Resubmittal) 10-May-14 29-May-14 0%
PWB-3.3.2 Approval PWB-3.3.2 Approval 10-May-14A 05-J un-14
A1050 Mockup&Material Sample 10-May-14A 100%
A1060 Mockup&Material Sample (Resubmittal) 31-May-14 05-J un-14 0%
PWB-3.4 FACADE DESIGN PWB-3.4 FACADE DESIGN
10-May-14 01-J un-14
PWB-3.4.1 Shop Drawing & Structural Calculation PWB-3.4.1 Shop Drawing & Structural Calculation 10-May-14 01-J un-14
PWB-3.4.1.1 Curt ain wall Drawings PWB-3.4.1.1 Curt ain wall Drawings 10-May-14 20-May-14
A1070 Complete Detail Drawing 10-May-14 13-May-14 0%
A1080 Review&Approval 14-May-14 20-May-14 0%
PWB-3.4.1.2 Canopy Drawings PWB-3.4.1.2 Canopy Drawings 21-May-14 01-J un-14
A1090 Complete detail drawing 21-May-14 25-May-14 0%
A1100 Review&Aapproval 26-May-14 01-J un-14 0%
PWB-3.5 MATERIAL PROCUREMENT PWB-3.5 MATERIAL PROCUREMENT
05-May-14A 21-Dec-14
PWB-3.5.1 Material Order PWB-3.5.1 Material Order 05-May-14A 26-Nov-14
A1110 Aluminium&Steel 05-May-14A 16-Nov-14 0%
A1120 Glass 11-May-14* 26-Nov-14 0%
A1130 Accessories &AppendixMaterial 10-May-14 25-Nov-14 0%
PWB-3.5.2 Procurement of Materials PWB-3.5.2 Procurement of Materials 08-May-14A 21-Dec-14
A1140 Aluminium&Steel 08-May-14A 01-Dec-14 0%
A1150 Glass 14-May-14 21-Dec-14 0%
A1160 Accessories &AppendixMaterial 15-May-14 21-Dec-14 0%
PWB-3.6 SOUTH ELEVATION PWB-3.6 SOUTH ELEVATION
13-Apr-14A 31-Aug-14
PWB-3.6.1 Fabrication Order PWB-3.6.1 Fabrication Order 13-Apr-14A 17-J ul-14
PWB-3.6.1.1 Curt ainwall PWB-3.6.1.1 Curt ainwall 13-Apr-14A 29-J un-14
A1170 Brackets ( all elevation) 13-Apr-14A 16-Apr-14A 100%
A1180 AluminiumProfile (Level 2to Level 6) 07-J un-14 17-J un-14 0%
A1190 AluminiumProfile (Level 1) 18-J un-14 29-J un-14 0%
PWB-3.6.1.2 Canopy PWB-3.6.1.2 Canopy 30-J un-14 17-J ul-14
A1200 Structural supportingSteel 30-J un-14 08-J ul-14 0%
A1210 ACP Cladding 09-J ul-14 17-J ul-14 0%
PWB-3.6.6 Production PWB-3.6.6 Production 17-Apr-14A 10-Aug-14
PWB-3.6.6.1 Curt ainwall PWB-3.6.6.1 Curt ainwall 17-Apr-14A 03-Aug-14
A1220 Brackets ( all elevation) 17-Apr-14A 29-May-14 18.18%
A1230 AluminiumProfile (Level 2to Level 6) 18-J un-14 20-J ul-14 0%
A1240 AluminiumProfile (Level 1) 21-J ul-14 03-Aug-14 0%
PWB-3.6.6.2 Canopy PWB-3.6.6.2 Canopy 09-J ul-14 10-Aug-14
A1250 Structural supportingSteel 09-J ul-14 27-J ul-14 0%
A1260 ACP Cladding 19-J ul-14 10-Aug-14 0%
PWB-3.6.5 Delivery PWB-3.6.5 Delivery 23-Apr-14A 18-Aug-14
PWB-3.6.5.1 Curt ainwall PWB-3.6.5.1 Curt ainwall 23-Apr-14A 18-Aug-14
Mar Apr May J un J ul Aug Sep Oct Nov Dec J an Feb Mar Apr May J un J ul
2014 2015
15-Feb-15, PWB-3 PRIVATE WING BUILDING
10-May-14A, PWB-3.1 CLARIFICATION
Clarification/Contract sign
10-May-14A, PWB-3.2 CONCEPT DESIGN
Concept Design
Review&Approval
05-J un-14, PWB-3.3 MOCK UP
29-May-14, PWB-3.3.1 Submittal
Mockup&Material Sample
Mockup&Material Sample (Resubmittal)
05-J un-14, PWB-3.3.2 Approval
Mockup&Material Sample
Mockup&Material Sample (Resubmittal)
01-J un-14, PWB-3.4 FACADE DESIGN
01-J un-14, PWB-3.4.1 ShopDrawing&Structural Calculation
20-May-14, PWB-3.4.1.1 Curtainwall Drawings
Complete Detail Drawing
Review&Approval
01-J un-14, PWB-3.4.1.2 CanopyDrawings
Complete detail drawing
Review&Aapproval
21-Dec-14, PWB-3.5 MATERIAL PROCUREMENT
26-Nov-14, PWB-3.5.1 Material Order
Aluminium&Steel
Glass
Accessories &AppendixMaterial
21-Dec-14, PWB-3.5.2 Procurement of Materials
Aluminium&Steel
Glass
Accessories &AppendixMaterial
31-Aug-14, PWB-3.6 SOUTH ELEVATION
17-J ul-14, PWB-3.6.1 FabricationOrder
29-J un-14, PWB-3.6.1.1 Curtainwall
Brackets ( all elevation)
AluminiumProfile (Level 2to Level 6)
AluminiumProfile (Level 1)
17-J ul-14, PWB-3.6.1.2 Canopy
Structural supportingSteel
ACP Cladding
10-Aug-14, PWB-3.6.6 Production
03-Aug-14, PWB-3.6.6.1 Curtainwall
Brackets ( all elevation)
AluminiumProfile (Level 2to Level 6)
AluminiumProfile (Level 1)
10-Aug-14, PWB-3.6.6.2 Canopy
Structural supportingSteel
ACP Cladding
18-Aug-14, PWB-3.6.5 Delivery
18-Aug-14, PWB-3.6.5.1 Curtainwall
PRIVATE WING BUILDING
RECOVERY SCHEDULE 18-May-1411:39
Actual Work
RemainingWork
Critical RemainingWork
Milestone
Summary
Page1of 4 Date Revision Checked Approved