Drawing Ref No:

Location: Area:
Package: SubSubSystem:
Sub System: System:
Description: TagNo:
21-Feb-2013 Date: Murphy Sarawak Oil Ltd. Client:
Function Test Report
M01B Tank
SOUTH ACIS
Type:
SerialNo: Model: Manufacturer:
Final Box Up certificate signed (certificate No:) *W* 17
Check that tank has been leak tested & documented. *W* 16
Torque manway flanges and confirm that torquing/tightening certification is completed.
*W*
15
After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gaskets
and bolting. *W*
14
Confirm earth bonding completed. 13
If specified on project drawings, confirm that vacuum breaker,Flame Arrester is installed
and its certification is valid
12
Remove all non soluble preservation, and ensure that soluble preservation coatings are
applied, (if specified in project Preservation Procedure).
11
Vent and drain valves fitted properly 10
Vessel internally clean and no internal degradation has occurred since the A checks
were carried out *W* - attach photo
09
Vessel externally clean and free from obstruction. 08
All checks sheets for associated equipment such as pumps that require internal access to
the tank have been completed. e.g. inspection of pump inlet strainers.
07
All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has been
completed.
06
All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present and
in good order.
05
All flange management tags are still intact on all vessel flanges (if specified) 04
All flange bolts have been torqued/tensioned/tightened. 03
All pipes ,valves, equipments,bridles & instrumentations which interface with the tank
have been installed.
02
Construction check list completed and no subsequent damage has occurred. 01
Output /Remarks PL OK NA Description Item
Note:
*W* MOC rep. Witness points
___________________________________________________________________________________________________________________
Remarks:
Date of Signing:
Print Name:
Signature:
Company:
Accepted By Verified By Performed By