Sunteți pe pagina 1din 10

Activity

ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
CONST OF 160 VILLAS FOR DUBAI SILICON OASIS
GENERAL
GEN40 Prep/Submittal/Approval of BOQ 60 90 01JUL13 10SEP13 01JUL13A 06AUG14 18
2SNG40 HandingOver of Cluster - Q& M 0 0 01JUL14 16AUG14 -36
MATERIALS
PROCURE & DELIVER
CIVIL MATERIALS
PMS690 ProcureEntrancePatioFlooring& Steps 60 92 02OCT13 17DEC13 09SEP13A 05AUG14 23
PMS640 ProcureSweet Soil 60 90 06OCT13 04DEC13 05OCT13A 02AUG14 30
PMS610 ProcureSanitaryWares 90 80 30SEP13 28DEC13 27OCT13A 14AUG14 18
PMS620 ProcureSanitaryFittings 90 80 02OCT13 30DEC13 27OCT13A 14AUG14 18
PMS220 ProcureExternal (Floor, Bull nosed& Skirting) 75 98 22SEP13 05DEC13 02NOV13A 29JUL14 34
PMS560 ProcureBathTubs 60 84 07OCT13 05DEC13 10NOV13A 06AUG14 26
PMS550 ProcureWater Meter cabinets 60 78 10OCT13 08DEC13 13NOV13A 09AUG14 23
PMS210 ProcureCeramic(Floor, Wall & Skirting) Tiles 75 95 06SEP13 19NOV13 28NOV13A 31JUL14 32
PMS490 ProcureVanityWork Top 75 82 29SEP13 12DEC13 28NOV13A 10AUG14 22
PMS240 ProcureStaircase/ThresholdMarble 75 90 22SEP13 05DEC13 30NOV13A 04AUG14 28
PMS600 ProcureSanitaryAccessories 90 80 17SEP13 15DEC13 30NOV13A 14AUG14 18
PMS480 ProcureKitchenWork Top 75 85 27SEP13 10DEC13 01DEC13A 07AUG14 25
PMS340 ProcureFalseCeilingMaterials 60 80 05NOV13 03JAN14 04DEC13A 08AUG14 24
PMS500 ProcurePergola 60 90 15NOV13 13JAN14 15DEC13A 02AUG14 30
PMS540 ProcureMainKitchenSinks 90 90 19SEP13 17DEC13 17DEC13A 05AUG14 27
PMS470 ProcureInt. Doors 60 85 26SEP13 24NOV13 22DEC13A 05AUG14 27
PMS660 ProcureCooker Hood 90 85 09OCT13 06JAN14 22DEC13A 10AUG14 22
PMS570 ProcureWardrobe& Vanity 60 90 21OCT13 19DEC13 01JAN14A 02AUG14 30
PMS580 ProcureKitchenCabinets 60 90 20OCT13 18DEC13 01JAN14A 02AUG14 30
PMS390 ProcureBalconyHandrails(Aluminium) 60 80 24OCT13 22DEC13 03JAN14A 08AUG14 24
PMS400 ProcureAluminumGate 60 80 07OCT13 05DEC13 03JAN14A 08AUG14 24
PMS410 ProcureAluminiumBoundaryWall Railing 60 80 07OCT13 05DEC13 03JAN14A 08AUG14 24
PMS290 ProcureIronmongery 60 80 09OCT13 07DEC13 04JAN14A 08AUG14 24
PMS380 ProcureStaircaseHandrails(Aluminium) 60 80 24OCT13 22DEC13 04JAN14A 08AUG14 24
PMS630 ProcureLight Fittings 90 85 29SEP13 27DEC13 09JAN14A 10AUG14 22
PMS430 ProcureMirrors 60 80 15NOV13 13JAN14 11JAN14A 08AUG14 24
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
PrimaveraSystems, Inc.
Start Date
PhaseI FinishDate(Cluster P - 14)
PhaseII FinishDate(Cluster Q&M - 40+38=78)
PhaseIII FinishDate(Cluster N&O- 28+40=68)
01J ul 13
21APR 14
16AUG14
23NOV14
Baseline
EarlyBar
Progress Bar
Critical Activity
1407 ARABTEC CONSTRUCTIONS LLC
CONSTRUCTION OF 160 VILLAS
DSOA VILLA COMPLEX - PHASE III
MPR - JULY 14
Forecast For The Next Month
Sheet 1 of 10

BaselineProgramme
Date Revision Checked Approved
18J UL13 REV 00
29AUG13 REV 01
Sheet 2of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
PMS520 ProcureAluminumDoors& Windows 98 85 11OCT13 08JAN14 11JAN14A 10AUG14 22
PMS720 ProcureMetal Framefor Vanity 45 95 12NOV13 05JAN14 11JAN14A 02AUG14 26
PMS510 ProcureShower Doors 60 85 21OCT13 19DEC13 20JAN14A 05AUG14 27
6PMS580 Procure Pump& GasEnclosure 45 85 18NOV13 01JAN14 22JAN14A 03AUG14 29
PMS730 ProcureCat Ladder 60 95 31OCT13 29DEC13 29JAN14A 30JUL14 33
PMS460 ProcureMainDoors 90 80 07OCT13 04JAN14 30JAN14A 14AUG14 18
PMS710 ProcureSunPipes 60 90 31OCT13 12JAN14 11FEB14A 06AUG14 22
PMS5805 ProcureSkylight 60 90 12NOV13 10JAN14 11MAR14A 02AUG14 30
PMS670 ProcureVillaNo. Plate 40 0 05NOV13 03JAN14 28JUL14 05SEP14 -4
MEP MATERIALS
HVAC MATERIALS
PMS1100 InsulatedFlexibleA/C Duct 50 90 15SEP13 03NOV13 28OCT13A 01AUG14 31
PMS1110 VolumeControl Dampers 50 90 15SEP13 03NOV13 29OCT13A 01AUG14 31
PMS1050 Pre-insulatedDuct 50 90 20SEP13 08NOV13 14NOV13A 01AUG14 31
PMS1070 VibrationIsolators 60 90 14OCT13 12DEC13 14NOV13A 02AUG14 30
PMS1080 Acoustical Duct Liner 40 90 20SEP13 29OCT13 14NOV13A 31JUL14 32
PMS1120 Exhaust Fans 60 85 15SEP13 13NOV13 14NOV13A 05AUG14 27
PMS1170 Hnagers& Supports 40 90 02OCT13 10NOV13 14NOV13A 31JUL14 32
PMS1010 Refrigerant Copper Pipes& Fittings 60 90 09SEP13 07NOV13 21NOV13A 02AUG14 30
PMS1060 FlexibleConnector 40 90 20SEP13 29OCT13 21NOV13A 31JUL14 32
PMS1090 Duct Support 40 90 20SEP13 29OCT13 21NOV13A 31JUL14 32
PMS1130 Grills& Diffusers 60 80 20SEP13 18NOV13 23NOV13A 08AUG14 24
PMS1020 Refrigerant PipeInsulation 50 90 20SEP13 08NOV13 30NOV13A 01AUG14 31
PMS1140 CanvasCoating& Adhesive 40 90 02OCT13 10NOV13 30NOV13A 31JUL14 32
PMS1160 FlexibleCouplings 40 90 02OCT13 10NOV13 30NOV13A 31JUL14 32
PMS1040 G.I Duct Sheet 50 90 20SEP13 08NOV13 01DEC13A 01AUG14 31
PMS1150 Sight Class 60 90 09SEP13 07NOV13 01DEC13A 02AUG14 30
PMS1000 DuctedSplit Units& Thermostats 90 90 16AUG13 13NOV13 10DEC13A 05AUG14 27
PLUMBING & DRAINAGE MATERIALS
PMS2090 Water Booster Pumps 60 85 08OCT13 06DEC13 21NOV13A 05AUG14 27
PMS2070 ElectricWater Heater 50 90 02OCT13 20NOV13 04JAN14A 01AUG14 31
PMS2110 FireExtinguishers& Blankets 60 80 08OCT13 06DEC13 15FEB14A 08AUG14 24
ELECTRICAL MATERIALS
PMS3020 Isolators, WP 50 90 02OCT13 20NOV13 10OCT13A 01AUG14 31
PMS3050 EarthingSystem 60 90 08OCT13 06DEC13 10OCT13A 02AUG14 30
PMS3000 LowVoltagePanels 90 90 03SEP13 01DEC13 23NOV13A 05AUG14 27
PMS3030 WiringAccessories 90 90 15SEP13 13DEC13 09DEC13A 05AUG14 27
PMS3060 FireAlarmSystem 60 90 08OCT13 06DEC13 05MAR14A 02AUG14 30
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 2of 10
Sheet 3of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
CONSTRUCTION OF 160 VILLAS
PHASE - II ( CLUSTER Q & M )
WALL & FLOOR TILES
WALL TILES (KITCHEN)
2KTWLTL06 KitchenWall Tiles- Group6 7 29 21JAN14 28JAN14 22APR14A 05AUG14 23
JOINERY WORKS
VANIY METAL FRAME
2VMTCR03 VanityMetal Frame- Group3 7 50 13FEB14 20FEB14 22MAY14A 04AUG14 24
2VMTCR04 VanityMetal Frame- Group4 7 50 22FEB14 01MAR14 23MAY14A 04AUG14 24
INTERNAL PAINTING WORKS
INTERNAL PAINTING PRIME & STUCCO COAT
2INTPTU10 Int. Paint Under Coat & First Coat - Group10 7 29 18MAR14 25MAR14 28APR14A 05AUG14 23
2INTPTU09 Int. Paint Under Coat & First Coat - Group9 7 86 10MAR14 17MAR14 26MAY14A 28JUL14 27
INTERNAL PAINTING FINAL TWO COATS
2INPTFN09 Int. Paint Final Coat - Group9 5 43 22MAY14 28MAY14 21JUL14A 03AUG14 25
SPRAY PLASTER WORKS
2SPRYPL10 SprayPlaster - Group10 7 29 18MAR14 25MAR14 28APR14A 05AUG14 23
2SPRYPL09 SprayPlaster - Group9 7 86 10MAR14 17MAR14 26MAY14A 28JUL14 27
BOUNDARY WALLS, GATES & MANHOLES
MANHOLES & DRAINAGE WORKS
2MNHLWK05 ManholeWorks- Group5 7 86 08JAN14 16JAN14 08MAR14A 28JUL14 27
2MNHLWK06 ManholeWorks- Group6 7 29 18JAN14 25JAN14 14APR14A 05AUG14 23
TESTING & COMMISSIONING
2TC20 Testing& Commissoning- Group6to11 25 95 27APR14 25MAY14 11JUN14A 28JUL14 27
SNAGGING & HAND OVER
SNAGGING-DESNAGGING
2SNG20 Snagging- Group6to11 25 48 25MAY14 23JUN14 30JUN14A 14AUG14 -36
2SNG30 HandingOver 1 0 24JUN14 01JUL14 16AUG14 16AUG14 -36
PHASE - III ( CLUSTER N & O )
CRITICAL PROJECT REQUIREMENT
5CPR20 AffectionPlansbyDM/DSO 21 0 06AUG13 01SEP13 28JUL14 24AUG14 -28
5CPR40 Demarcation(BY SURVEY DEPARTMENT) 35 0 07SEP13 21OCT13 25AUG14 04OCT14 -28
WALL & FLOOR TILES
WALL TILES (BATHROOM)
3BTWLT08 BathroomWall Tiles- Group8 7 71 25MAY14 02JUN14 02JUN14A 02AUG14 -12
3BTWLT05 BathroomWall Tiles- Group5 7 57 30APR14 07MAY14 21JUL14A 03AUG14 25
3BTWLT03 BathroomWall Tiles- Group3 7 43 14APR14 21APR14 28JUL14A 04AUG14 24
3BTWLT04 BathroomWall Tiles- Group4 7 43 22APR14 29APR14 28JUL14A 04AUG14 24
3BTWLT01 BathroomWall Tiles- Group1 7 0 29MAR14 05APR14 28JUL14 07AUG14 -66
3BTWLT09 BathroomWall Tiles- Group9 7 0 03JUN14 10JUN14 03AUG14 10AUG14 -12
3BTWLT02 BathroomWall Tiles- Group2 7 0 06APR14 13APR14 09AUG14 16AUG14 14
3BTWLT10 BathroomWall Tiles- Group10 7 0 11JUN14 18JUN14 11AUG14 18AUG14 -12
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 3of 10
Sheet 4of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
WET AREA WATERPROOFING (KITCHEN & BATHROOM)
3WTAWP03 Wet AreaWaterproofing- Group3 7 71 20APR14 27APR14 18JUN14A 02AUG14 26
3WTAWP01 Wet AreaWaterproofing- Group1 7 57 03APR14 10APR14 28JUL14A 03AUG14 -69
3WTAWP02 Wet AreaWaterproofing- Group2 7 0 12APR14 19APR14 04AUG14 11AUG14 18
BATROOM FLOOR TILES
3BTFLT07 BathroomFloor Tiles- Group7 7 71 26MAY14 03JUN14 02JUN14A 02AUG14 26
3BTFLT08 BathroomFloor Tiles- Group8 7 71 04JUN14 11JUN14 02JUN14A 02AUG14 -12
3BTFLT03 BathroomFloor Tiles- Group3 7 29 23APR14 30APR14 14JUL14A 05AUG14 23
3BTFLT04 BathroomFloor Tiles- Group4 7 57 01MAY14 08MAY14 14JUL14A 03AUG14 18
3BTFLT06 BathroomFloor Tiles- Group6 7 43 18MAY14 25MAY14 21JUL14A 04AUG14 24
3BTFLT09 BathroomFloor Tiles- Group9 7 0 12JUN14 19JUN14 03AUG14 10AUG14 -12
3BTFLT01 BathroomFloor Tiles- Group1 7 0 07APR14 14APR14 04AUG14 11AUG14 -69
3BTFLT05 BathroomFloor Tiles- Group5 7 0 10MAY14 17MAY14 04AUG14 11AUG14 18
3BTFLT10 BathroomFloor Tiles- Group10 7 0 21JUN14 28JUN14 11AUG14 18AUG14 -12
3BTFLT02 BathroomFloor Tiles- Group2 7 0 15APR14 22APR14 12AUG14 19AUG14 11
MARBLE/GRANITE STEPS
3MRBLWK08 Marble/GraniteSteps- Group8 7 71 14JUN14 21JUN14 19MAY14A 02AUG14 -9
3MRBLWK01 Marble/GraniteSteps- Group1 7 71 16APR14 23APR14 14JUL14A 02AUG14 -58
3MRBLWK03 Marble/GraniteSteps- Group3 7 71 03MAY14 10MAY14 14JUL14A 02AUG14 26
3MRBLWK02 Marble/GraniteSteps- Group2 7 0 24APR14 01MAY14 03AUG14 10AUG14 19
3MRBLWK09 Marble/GraniteSteps- Group9 7 0 22JUN14 30JUN14 03AUG14 10AUG14 -9
3MRBLWK10 Marble/GraniteSteps- Group10 7 0 01JUL14 08JUL14 11AUG14 18AUG14 -9
EXTERNAL FLOOR TILES
3EXTFTL08 External Floor Tiles- Group8 7 71 14JUN14 21JUN14 20MAY14A 02AUG14 26
3EXTFTL03 External Floor Tiles- Group3 7 71 03MAY14 10MAY14 25JUN14A 02AUG14 26
3EXTFTL02 External Floor Tiles- Group2 7 43 24APR14 01MAY14 14JUL14A 04AUG14 24
3EXTFTL01 External Floor Tiles- Group1 7 0 16APR14 23APR14 28JUL14 07AUG14 -12
JOINERY WORKS
INTERNAL WOODEN DOOR FRAMES
3INTDRF07 Int. Door Frame- Group7 7 43 08JUN14 15JUN14 14JUL14A 04AUG14 24
3INTDRF08 Int. Door Frame- Group8 7 71 16JUN14 23JUN14 14JUL14A 02AUG14 -9
3INTDRF01 Int. Door Frame- Group1 7 0 19APR14 26APR14 28JUL14 07AUG14 -63
3INTDRF09 Int. Door Frame- Group9 7 0 24JUN14 02JUL14 03AUG14 10AUG14 -9
3INTDRF02 Int. Door Frame- Group2 7 0 27APR14 04MAY14 09AUG14 16AUG14 -14
3INTDRF10 Int. Door Frame- Group10 7 0 03JUL14 10JUL14 11AUG14 18AUG14 -9
3INTDRF03 Int. Door Frame- Group3 7 0 05MAY14 12MAY14 17AUG14 24AUG14 -14
3INTDRF04 Int. Door Frame- Group4 7 0 13MAY14 20MAY14 25AUG14 01SEP14 -14
INTERNAL WOODEN DOOR SHUTTERS & IRONMONGERY
3INTDRS01 Int. Door shutter & Ironmongery- Group1 7 0 27APR14 04MAY14 09AUG14 16AUG14 -63
3INTDRS02 Int. Door shutter & Ironmongery- Group2 7 0 05MAY14 12MAY14 17AUG14 24AUG14 -63
3INTDRS03 Int. Door shutter & Ironmongery- Group3 7 0 13MAY14 20MAY14 25AUG14 01SEP14 -63
EXTERNAL WOODEN DOOR FRAMES
3EXTDRF01 External Door Frame- Group1 7 0 13APR14 20APR14 28JUL14 07AUG14 -70
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 4of 10
Sheet 5of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
3EXTDRF02 External Door Frame- Group2 7 0 21APR14 28APR14 09AUG14 16AUG14 -70
3EXTDRF03 External Door Frame- Group3 7 0 29APR14 06MAY14 17AUG14 24AUG14 -70
3EXTDRF04 External Door Frame- Group4 7 0 07MAY14 14MAY14 25AUG14 01SEP14 -70
EXTERNAL WOODEN DOOR SHUTTERS & IRONMONGERY
3EXTDRS03 External Door shutter & Ironmongery- Group3 7 14 07MAY14 14MAY14 10JUL14A 06AUG14 -48
3EXTDRS04 External Door shutter & Ironmongery- Group4 7 0 15MAY14 22MAY14 07AUG14 14AUG14 -48
3EXTDRS01 External Door shutter & Ironmongery- Group1 7 0 21APR14 28APR14 09AUG14 16AUG14 7
3EXTDRS05 External Door shutter & Ironmongery- Group5 7 0 24MAY14 01JUN14 16AUG14 23AUG14 -48
3EXTDRS02 External Door shutter & Ironmongery- Group2 7 0 29APR14 06MAY14 17AUG14 24AUG14 7
3EXTDRS06 External Door shutter & Ironmongery- Group6 7 0 02JUN14 09JUN14 24AUG14 31AUG14 -48
WARDROBE CARCASS
3WRDCR08 WardrobeCarcass- Group8 7 71 18JUN14 25JUN14 26JUN14A 02AUG14 26
3WRDCR03 WardrobeCarcass- Group3 7 71 07MAY14 14MAY14 09JUL14A 02AUG14 26
3WRDCR04 WardrobeCarcass- Group4 7 71 15MAY14 22MAY14 12JUL14A 02AUG14 26
3WRDCR09 WardrobeCarcass- Group9 7 71 26JUN14 05JUL14 17JUL14A 02AUG14 -2
3WRDCR01 WardrobeCarcass- Group1 7 0 21APR14 28APR14 09AUG14 16AUG14 4
3WRDCR02 WardrobeCarcass- Group2 7 0 29APR14 06MAY14 17AUG14 24AUG14 7
WARDROBE SHUTTERS
3WRDSH07 WardrobeShutters- Group7 5 71 02AUG14 06AUG14 01JUL14A 28JUL14 27
3WRDSH03 WardrobeShutters- Group3 5 71 06JUL14 10JUL14 21JUL14A 28JUL14 27
3WRDSH04 WardrobeShutters- Group4 5 71 12JUL14 16JUL14 21JUL14A 28JUL14 27
3WRDSH08 WardrobeShutters- Group8 5 71 07AUG14 12AUG14 21JUL14A 28JUL14 27
3WRDSH09 WardrobeShutters- Group9 5 71 13AUG14 18AUG14 28JUL14A 28JUL14 15
KITCHEN CABINETS CARCASS
3KTCBCR08 KitchenCabinet Carcass- Group8 7 71 19JUN14 26JUN14 26JUN14A 02AUG14 26
3KTCBCR03 KitchenCabinet Carcass- Group3 7 71 08MAY14 15MAY14 09JUL14A 02AUG14 26
3KTCBCR04 KitchenCabinet Carcass- Group4 7 71 17MAY14 24MAY14 12JUL14A 02AUG14 26
3KTCBCR09 KitchenCabinet Carcass- Group9 7 71 28JUN14 06JUL14 17JUL14A 02AUG14 -2
3KTCBCR01 KitchenCabinet Carcass- Group1 7 0 22APR14 29APR14 09AUG14 16AUG14 -68
3KTCBCR02 KitchenCabinet Carcass- Group2 7 0 30APR14 07MAY14 17AUG14 24AUG14 7
KITCHEN WORK TOP
3KTWKTP07 KitchenWork Top- Group7 7 71 19JUN14 26JUN14 01JUL14A 02AUG14 26
3KTWKTP08 KitchenWork Top- Group8 7 86 28JUN14 06JUL14 02JUL14A 28JUL14 -1
3KTWKTP03 KitchenWork Top- Group3 7 71 17MAY14 24MAY14 21JUL14A 02AUG14 26
3KTWKTP04 KitchenWork Top- Group4 7 71 25MAY14 02JUN14 21JUL14A 02AUG14 26
3KTWKTP05 KitchenWork Top- Group5 7 43 03JUN14 10JUN14 28JUL14A 04AUG14 24
3KTWKTP06 KitchenWork Top- Group6 7 43 11JUN14 18JUN14 28JUL14A 04AUG14 24
3KTWKTP09 KitchenWork Top- Group9 7 0 07JUL14 14JUL14 02AUG14 09AUG14 -1
3KTWKTP01 KitchenWork Top- Group1 7 0 30APR14 07MAY14 17AUG14 24AUG14 -25
3KTWKTP02 KitchenWork Top- Group2 7 0 08MAY14 15MAY14 25AUG14 01SEP14 0
KITCHEN CABINETS SHUTTERS
3KTCBSH07 KitchenCabinet Shutters- Group7 5 71 27JUL14 04AUG14 21JUL14A 28JUL14 27
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 5of 10
Sheet 6of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
3KTCBSH08 KitchenCabinet Shutters- Group8 5 71 05AUG14 10AUG14 21JUL14A 28JUL14 27
3KTCBSH09 KitchenCabinet Shutters- Group9 5 71 11AUG14 16AUG14 28JUL14A 28JUL14 13
VANITIES CRACASS
3VNTCR01 VanityCarcass- Group1 7 0 28APR14 05MAY14 12AUG14 19AUG14 -69
3VNTCR02 VanityCarcass- Group2 7 0 06MAY14 13MAY14 20AUG14 27AUG14 -69
3VNTCR03 VanityCarcass- Group3 7 0 14MAY14 21MAY14 28AUG14 04SEP14 -69
VANIY METAL FRAME
3VMTCR01 VanityMetal Frame- Group1 7 86 28APR14 05MAY14 02JUN14A 28JUL14 -14
3VMTCR02 VanityMetal Frame- Group2 7 29 06MAY14 13MAY14 02JUN14A 05AUG14 23
3VMTCR03 VanityMetal Frame- Group3 7 29 14MAY14 21MAY14 02JUN14A 05AUG14 23
3VMTCR04 VanityMetal Frame- Group4 7 71 22MAY14 31MAY14 02JUN14A 02AUG14 26
VANITY WOTK TOP
3VNTWTP07 VanityWork Top- Group7 7 71 23JUN14 01JUL14 14JUL14A 02AUG14 26
3VNTWTP08 VanityWork Top- Group8 7 71 02JUL14 09JUL14 14JUL14A 02AUG14 -2
3VNTWTP09 VanityWork Top- Group9 7 0 10JUL14 17JUL14 03AUG14 10AUG14 -2
3VNTWTP01 VanityWork Top- Group1 7 0 04MAY14 11MAY14 16AUG14 23AUG14 -27
3VNTWTP02 Vanitywork Top- Group2 7 0 12MAY14 19MAY14 24AUG14 31AUG14 -27
MISCELLANEOUS
KITCHEN EXHAUST HOOD
3KTEXHD01 KitchenExhaust Hood- Group1 7 0 30APR14 07MAY14 09AUG14 16AUG14 -68
3KTEXHD02 KitchenExhaust Hood- Group2 7 0 08MAY14 15MAY14 17AUG14 24AUG14 -68
3KTEXHD03 KitchenExhaust Hood- Group3 7 0 17MAY14 24MAY14 25AUG14 01SEP14 -68
MIRROR FIXING
3MIRR01 Mirrors- Group1 7 0 10MAY14 17MAY14 09AUG14 16AUG14 -68
3MIRR02 Mirrors- Group2 7 0 18MAY14 25MAY14 17AUG14 24AUG14 -68
3MIRR03 Mirrors- Group3 7 0 26MAY14 03JUN14 25AUG14 01SEP14 -68
CAT LADDER
3CTLDR01 FixingCat Ladder- Group1 7 57 08APR14 15APR14 28JUL14A 03AUG14 18
3CTLDR02 FixingCat Ladder- Group2 7 0 16APR14 23APR14 04AUG14 11AUG14 18
SKY LIGHT & SUN PIPE
3SKYLT01 SkyLight - Group1 7 0 27APR14 04MAY14 28JUL14 07AUG14 0
3SKYLT07 SkyLight - Group7 7 0 16JUN14 23JUN14 28JUL14 07AUG14 -34
3SKYLT02 SkyLight - Group2 7 0 05MAY14 12MAY14 09AUG14 16AUG14 0
3SKYLT08 SkyLight - Group8 7 0 24JUN14 02JUL14 09AUG14 16AUG14 -34
3SKYLT03 SkyLight - Group3 7 0 13MAY14 20MAY14 17AUG14 24AUG14 0
3SKYLT09 SkyLight - Group9 7 0 03JUL14 10JUL14 17AUG14 24AUG14 -34
3SKYLT04 SkyLight - Group4 7 0 21MAY14 29MAY14 25AUG14 01SEP14 0
3SKYLT10 SkyLight - Group10 7 0 12JUL14 19JUL14 25AUG14 01SEP14 -34
ALUMINIUM DOORS & WINDOWS
ALUMINIUM DOORS
3UPVDR02 AluminiumDoors- Group2 7 43 26APR14 03MAY14 10JUN14A 04AUG14 24
3UPVDR03 AluminiumDoors- Group3 7 71 04MAY14 11MAY14 21JUL14A 02AUG14 26
3UPVDR10 AluminiumDoors- Group10 7 60 02JUL14 09JUL14 28JUL14A 03AUG14 25
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 6of 10
Sheet 7of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
ALUMINIUM WINDOW FRAMES
3UPVWN02 AluminiumWindowFrames- Group2 7 43 26APR14 03MAY14 10JUN14A 04AUG14 24
3UPVWN03 AluminiumWindowFrames- Group3 7 71 04MAY14 11MAY14 21JUL14A 02AUG14 26
3UPVWN10 AluminiumWindowFrames- Group10 7 60 02JUL14 09JUL14 28JUL14A 03AUG14 25
GLASS FOR WINDOWS
3GLSWND02 Glassfor Windows- Group2 7 43 04MAY14 11MAY14 10JUN14A 04AUG14 24
3GLSWND03 Glassfor Windows- Group3 7 71 12MAY14 19MAY14 21JUL14A 02AUG14 26
3GLSWND10 Glassfor Windows- Group10 7 60 10JUL14 17JUL14 28JUL14A 03AUG14 -9
FALSE CEILING WORKS
SUSPENSION SYSTEM
3FLCESS10 FalseCeilingSuspension- Group10 7 20 05JUL14 12JUL14 20JUL14A 06AUG14 -15
3FLCESS03 FalseCeilingSuspension- Group3 7 14 06MAY14 13MAY14 28JUL14A 06AUG14 22
3FLCESS04 FalseCeilingSuspension- Group4 7 43 14MAY14 21MAY14 28JUL14A 04AUG14 24
3FLCESS01 FalseCeilingSuspension- Group1 7 0 20APR14 27APR14 17AUG14 24AUG14 -31
3FLCESS02 FalseCeilingSuspension- Group2 7 0 28APR14 05MAY14 25AUG14 01SEP14 0
GYPSUM BOARD
3GYPBRD07 GypsumBoard- Group7 7 43 12JUN14 19JUN14 21JUL14A 04AUG14 24
3GYPBRD08 GypsumBoard- Group8 7 43 21JUN14 28JUN14 21JUL14A 04AUG14 -26
3GYPBRD09 GypsumBoard- Group9 7 0 30JUN14 07JUL14 05AUG14 12AUG14 -26
3GYPBRD10 GypsumBoard- Group10 7 0 08JUL14 15JUL14 13AUG14 20AUG14 -26
3GYPBRD01 GypsumBoard- Group1 7 0 23APR14 30APR14 20AUG14 27AUG14 -31
3GYPBRD02 GypsumBoard- Group2 7 0 01MAY14 08MAY14 28AUG14 04SEP14 -31
FALSE CEILING TILES
3FLCETL06 FalseCeilingTiles- Group6 5 57 23JUL14 28JUL14 28JUL14A 02AUG14 -1
3FLCETL07 FalseCeilingTiles- Group7 5 0 02AUG14 06AUG14 03AUG14 07AUG14 -1
3FLCETL08 FalseCeilingTiles- Group8 5 0 07AUG14 12AUG14 09AUG14 13AUG14 -1
3FLCETL09 FalseCeilingTiles- Group9 5 0 13AUG14 18AUG14 14AUG14 19AUG14 -1
HANDRAILS
BALCONY HANDRAILS
3BLHNRL06 BalconyHandrails- Group6 7 57 03JUN14 10JUN14 21JUL14A 03AUG14 25
3BLHNRL07 BalconyHandrails- Group7 7 71 11JUN14 18JUN14 21JUL14A 02AUG14 26
3BLHNRL08 BalconyHandrails- Group8 7 71 19JUN14 26JUN14 21JUL14A 02AUG14 -2
3BLHNRL09 BalconyHandrails- Group9 7 0 28JUN14 06JUL14 03AUG14 10AUG14 -2
3BLHNRL01 BalconyHandrails- Group1 7 0 22APR14 29APR14 06AUG14 13AUG14 -12
3BLHNRL10 BalconyHandrails- Group10 7 0 07JUL14 14JUL14 11AUG14 18AUG14 -2
3BLHNRL02 BalconyHandrails- Group2 7 0 30APR14 07MAY14 14AUG14 21AUG14 -12
3BLHNRL03 BalconyHandrails- Group3 7 0 08MAY14 15MAY14 23AUG14 30AUG14 -12
STAIRCASE HANDRAILS
3STRHNR01 StaircaseHandrails- Group1 7 0 24APR14 01MAY14 03AUG14 10AUG14 -58
3STRHNR02 StaircaseHandrails- Group2 7 0 03MAY14 10MAY14 11AUG14 18AUG14 -58
3STRHNR03 StaircaseHandrails- Group3 7 0 11MAY14 18MAY14 19AUG14 26AUG14 -58
3STRHNR04 StaircaseHandrails- Group4 7 0 19MAY14 26MAY14 27AUG14 03SEP14 -58
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 7of 10
Sheet 8of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
INTERNAL PAINTING WORKS
INTERNAL PAINTING FINAL TWO COATS
3INPTFN09 Int. Paint Final Coat - Group9 5 0 07AUG14 12AUG14 28JUL14 05AUG14 6
3INPTFN10 Int. Paint Final Coat - Group10 5 0 13AUG14 18AUG14 06AUG14 11AUG14 6
EXTERNAL WORKS
PERGOLAS
3PERGL07 ShadedStructure: Pergola- Group7 7 71 07JUL14 14JUL14 22JUN14A 02AUG14 26
3PERGL08 ShadedStructure: Pergola- Group8 7 71 15JUL14 22JUL14 22JUN14A 02AUG14 -2
3PERGL09 ShadedStructure: Pergola- Group9 7 0 23JUL14 03AUG14 03AUG14 10AUG14 -2
3PERGL01 ShadedStructure: Pergola- Group1 7 0 17MAY14 24MAY14 09AUG14 16AUG14 -21
3PERGL02 ShadedStructure: Pergola- Group2 7 0 25MAY14 02JUN14 17AUG14 24AUG14 -21
3PERGL03 ShadedStructure: Pergola- Group3 7 0 03JUN14 10JUN14 25AUG14 01SEP14 -21
GAS ENCLOSURES
3PMGSEN01 Pump& GasEnclosures- Group1 7 0 17MAY14 24MAY14 09AUG14 16AUG14 -65
3PMGSEN02 Pump& GasEnclosures- Group2 7 0 25MAY14 02JUN14 17AUG14 24AUG14 -65
3PMGSEN03 Pump& GasEnclosures- Group3 7 0 03JUN14 10JUN14 25AUG14 01SEP14 -65
SWEET SOIL
3SWTSOL01 Sweet Soil - Group1 7 0 08MAY14 15MAY14 28JUL14 07AUG14 -65
3SWTSOL02 Sweet Soil - Group2 7 0 17MAY14 24MAY14 09AUG14 16AUG14 -65
3SWTSOL03 Sweet Soil - Group3 7 0 25MAY14 02JUN14 17AUG14 24AUG14 -65
3SWTSOL04 Sweet Soil - Group4 7 0 03JUN14 10JUN14 25AUG14 01SEP14 -65
BOUNDARY WALLS, GATES & MANHOLES
BOUNDARY WALL RAILING & GATES
3BNDRRL01 BoundaryWall Railing- Group1 7 0 09APR14 16APR14 28JUL14 07AUG14 -42
3BNDRRL02 BoundaryWall Railing- Group2 7 0 17APR14 24APR14 09AUG14 16AUG14 -42
3BNDRRL03 BoundaryWall Railing- Group3 7 0 26APR14 03MAY14 17AUG14 24AUG14 -42
3BNDRRL04 BoundaryWall Railing- Group4 7 0 04MAY14 11MAY14 25AUG14 01SEP14 -42
MEP SECOND FIX
INSTALLATION OF FCU'S
3FCUINS09 Inst.of FCU's- Group9 7 57 01JUN14 08JUN14 29JUN14A 03AUG14 18
3FCUINS01 Inst.of FCU's- Group1 7 0 26MAR14 02APR14 28JUL14 07AUG14 -30
3FCUINS10 Inst.of FCU's- Group10 7 0 09JUN14 16JUN14 04AUG14 11AUG14 18
3FCUINS02 Inst.of FCU's- Group2 7 0 03APR14 10APR14 09AUG14 16AUG14 -14
3FCUINS03 Inst.of FCU's- Group3 7 0 12APR14 19APR14 17AUG14 24AUG14 -14
3FCUINS04 Inst.of FCU's- Group4 7 0 20APR14 27APR14 25AUG14 01SEP14 -14
INSTALLATION OF AC DUCT
3ACDCT03 Inst.of AC Duct - Group3 7 71 17APR14 24APR14 02JUL14A 02AUG14 26
3ACDCT02 Inst.of AC Duct - Group2 7 29 09APR14 16APR14 23JUL14A 05AUG14 23
3ACDCT10 Inst.of AC Duct - Group10 7 20 15JUN14 22JUN14 28JUL14A 06AUG14 -28
3ACDCT01 Inst.of AC Duct - Group1 7 0 01APR14 08APR14 06AUG14 13AUG14 -30
INSTALLATION OF REFRIGRANT PIPES
3RFRPIP05 Refrigrant Pipes- Group5 7 86 06MAY14 13MAY14 25JUN14A 28JUL14 20
3RFRPIP03 Refrigrant Pipes- Group3 7 71 20APR14 27APR14 02JUL14A 02AUG14 26
3RFRPIP02 Refrigrant Pipes- Group2 7 29 12APR14 19APR14 23JUL14A 05AUG14 23
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 8of 10
Sheet 9of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
3RFRPIP10 Refrigrant Pipes- Group10 7 20 17JUN14 24JUN14 23JUL14A 06AUG14 16
3RFRPIP06 Refrigrant Pipes- Group6 7 0 14MAY14 21MAY14 02AUG14 09AUG14 20
3RFRPIP01 Refrigrant Pipes- Group1 7 0 03APR14 10APR14 09AUG14 16AUG14 -27
INSTALLATION OF WATER HEATERS
3WTRHTR01 Inst.of Water Heaters- Group1 7 0 06APR14 13APR14 09AUG14 16AUG14 -61
3WTRHTR02 Inst.of Water Heaters- Group2 7 0 14APR14 21APR14 17AUG14 24AUG14 -61
3WTRHTR03 Inst.of Water Heaters- Group3 7 0 22APR14 29APR14 25AUG14 01SEP14 -61
INSTALLATION OF CU'S
3CUINST01 Inst.of CU's- Group1 7 0 26APR14 03MAY14 28JUL14 07AUG14 -66
3CUINST02 Inst.of CU's- Group2 7 0 04MAY14 11MAY14 09AUG14 16AUG14 -66
3CUINST03 Inst.of CU's- Group3 7 0 12MAY14 19MAY14 17AUG14 24AUG14 -66
3CUINST04 Inst.of CU's- Group4 7 0 20MAY14 28MAY14 25AUG14 01SEP14 -66
MEP FINAL FIX
INSTALLATION OF EXHAUST FANS
3EXHFN03 Inst.of Exhaust Fan- Group3 7 71 23APR14 30APR14 02JUL14A 02AUG14 26
3EXHFN05 Inst.of Exhaust Fan- Group5 7 29 10MAY14 17MAY14 04JUL14A 05AUG14 23
3EXHFN02 Inst.of Exhaust Fan- Group2 7 29 15APR14 22APR14 23JUL14A 05AUG14 23
3EXHFN09 Inst.of Exhaust Fan- Group9 7 0 12JUN14 19JUN14 28JUL14 07AUG14 -30
3EXHFN10 Inst.of Exhaust Fan- Group10 7 0 21JUN14 28JUN14 09AUG14 16AUG14 -30
3EXHFN01 Inst.of Exhaust Fan- Group1 7 0 07APR14 14APR14 12AUG14 19AUG14 -14
INSTALLATION OF AC GRILLS & DIFFUSSERS
3ACGRDF01 Inst.of AC Grills& Diffusers- Group1 7 0 17APR14 24APR14 09AUG14 16AUG14 -30
3ACGRDF02 Inst.of AC Grills& Diffusers- Group2 7 0 26APR14 03MAY14 11AUG14 18AUG14 -30
3ACGRDF03 Inst.of AC Grills& Diffusers- Group3 7 0 04MAY14 11MAY14 13AUG14 20AUG14 -30
3ACGRDF04 Inst.of AC Grills& Diffusers- Group4 7 0 12MAY14 19MAY14 16AUG14 23AUG14 -30
3ACGRDF05 Inst.of AC Grills& Diffusers- Group5 7 0 20MAY14 28MAY14 18AUG14 25AUG14 -30
3ACGRDF06 Inst.of AC Grills& Diffusers- Group6 7 0 29MAY14 05JUN14 20AUG14 27AUG14 -30
3ACGRDF07 Inst.of AC Grills& Diffusers- Group7 7 0 07JUN14 14JUN14 23AUG14 30AUG14 -30
3ACGRDF08 Inst.of AC Grills& Diffusers- Group8 7 0 15JUN14 22JUN14 25AUG14 01SEP14 -30
3ACGRDF09 Inst.of AC Grills& Diffusers- Group9 7 0 23JUN14 01JUL14 27AUG14 03SEP14 -30
INSTALLATION OF WATER PUMPS
3WTRPMP07 Inst.of Water Pumps- Group7 7 43 22JUN14 30JUN14 23JUL14A 04AUG14 24
3WTRPMP08 Inst.of Water Pumps- Group8 7 71 01JUL14 08JUL14 23JUL14A 02AUG14 -16
3WTRPMP01 Inst.of Water Pumps- Group1 7 0 03MAY14 10MAY14 28JUL14 07AUG14 -14
3WTRPMP09 Inst.of Water Pumps- Group9 7 0 09JUL14 16JUL14 03AUG14 10AUG14 -16
3WTRPMP02 Inst.of Water Pumps- Group2 7 0 11MAY14 18MAY14 09AUG14 16AUG14 -14
3WTRPMP10 Inst.of Water Pumps- Group10 7 0 17JUL14 24JUL14 11AUG14 18AUG14 -16
3WTRPMP03 Inst.of Water Pumps- Group3 7 0 19MAY14 26MAY14 17AUG14 24AUG14 -14
3WTRPMP04 Inst.of Water Pumps- Group4 7 0 28MAY14 04JUN14 25AUG14 01SEP14 -14
ELECTRICAL ACCESSORIES
3ELCAC01 Electrical Accessories- Group1 7 0 01MAY14 08MAY14 28JUL14 07AUG14 -71
3ELCAC02 Electrical Accessories- Group2 7 0 10MAY14 17MAY14 09AUG14 16AUG14 -71
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 9of 10
Sheet 10of 10
Activity
ID
Activity
Description
MAIN GEN AREA TYPE TASK Cal
ID
Orig
Dur
%
Comp
Baseline
Early Start
Baseline
Early Finish
Early
Start
Early
Finish
Total
Float
3ELCAC03 Electrical Accessories- Group3 7 0 18MAY14 25MAY14 17AUG14 24AUG14 -71
3ELCAC04 Electrical Accessories- Group4 7 0 26MAY14 03JUN14 25AUG14 01SEP14 -71
LIGHT FITTINGS & THERMOSTATS
3LITEFT01 Inst.of Light Fittings- Group1 7 71 01MAY14 08MAY14 30JUN14A 02AUG14 -71
3LITEFT02 Inst.of Light Fittings- Group2 7 57 10MAY14 17MAY14 30JUN14A 03AUG14 -60
3LITEFT03 Inst.of Light Fittings- Group3 7 0 18MAY14 25MAY14 04AUG14 11AUG14 -60
3LITEFT04 Inst.of Light Fittings- Group4 7 0 26MAY14 03JUN14 12AUG14 19AUG14 -60
3LITEFT05 Inst.of Light Fittings- Group5 7 0 04JUN14 11JUN14 20AUG14 27AUG14 -60
3LITEFT06 Inst.of Light Fittings- Group6 7 0 12JUN14 19JUN14 28AUG14 04SEP14 -60
SWITCH GEAR CIRCUIT BREAKERS
3SWCRBR03 Switchgear Circuit Breakers- Group3 7 71 08MAY14 15MAY14 28JUN14A 02AUG14 26
3SWCRBR04 Switchgear Circuit Breakers- Group4 7 43 17MAY14 24MAY14 28JUN14A 04AUG14 24
3SWCRBR01 Switchgear Circuit Breakers- Group1 7 57 22APR14 29APR14 14JUL14A 03AUG14 25
3SWCRBR02 Switchgear Circuit Breakers- Group2 7 43 30APR14 07MAY14 14JUL14A 04AUG14 24
3SWCRBR09 Switchgear Circuit Breakers- Group9 7 86 28JUN14 06JUL14 16JUL14A 28JUL14 -9
3SWCRBR10 Switchgear Circuit Breakers- Group10 7 0 07JUL14 14JUL14 02AUG14 09AUG14 -9
INSTALLATION OF SANITARY WARES & FITTINGS
3SNTFWR01 Inst. of SanitaryFittings& Wares- Group1 7 0 01MAY14 08MAY14 28JUL14 07AUG14 -70
3SNTFWR02 Inst. of SanitaryFittings& Wares- Group2 7 0 10MAY14 17MAY14 09AUG14 16AUG14 -70
3SNTFWR03 Inst. of SanitaryFittings& Wares- Group3 7 0 18MAY14 25MAY14 17AUG14 24AUG14 -70
3SNTFWR04 Inst. of SanitaryFittings& Wares- Group4 7 0 26MAY14 03JUN14 25AUG14 01SEP14 -70
2013 2014 2015
JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
Sheet 10of 10