1 unit CSU
for unloading of Clinker
BudgetEstimate_CSU_Clk_080213US_080217JLee.doc
Pg 1 of 3
1.
2.
3.
Clinker
800 tph (max 1,000 tph)
30,000 DWT
310 tons
220 tons
530 tons
Estimated Price
S/N
Description
2
3
4
5
Est Weight
tons
Est Price
Euro (FOB)
310
3,410,000.00
220
530
110,000.00
742,000.00
220,000.00
155,000.00
Total Estimate
4.
Remarks
4.1
4.2
4.3
Commissioning Time:
No Load test - estimated as 3 weeks (without material)
Load test - estimated as 2 weeks (with material)
Total estimated as 5 weeks
4,637,000.00
In case of any interruption (no ships, etc), the time will be extended. The 5 weeks are the minimum
time that is needed.
BudgetEstimate_CSU_Clk_080213US_080217JLee.doc
Pg 2 of 3
4.4
All estimates are given based on price level of European costs. It can be reduced by using local
steel structure fabricated in Vietnam and erection costs of local Vietnamese companies. We do not
have these local costs at the moment.
5.
BudgetEstimate_CSU_Clk_080213US_080217JLee.doc
Pg 3 of 3