Budget Estimate

1 unit CSU
for unloading of Clinker

CFC Chinfon Cement Corporation


Clinker Grinding Plant, middle of Vietnam

BudgetEstimate_CSU_Clk_080213US_080217JLee.doc

Pg 1 of 3

1.

2.

3.

Main Technical Data


Materials:
Capacity:
Ship Size:

Clinker
800 tph (max 1,000 tph)
30,000 DWT

Estimated Weight of Machine


Mechanical, Electrical and Steel Structure
Counterweight (concrete)
Total weight of machine

310 tons
220 tons
530 tons

Estimated Price
S/N

Description

Supply of machine - Mechanical,


Electrical, Steel structure including
engineering and packing
Ballast (Counterweight)
Erection
Commissioning
CIF Vietnam

2
3
4
5

Est Weight
tons

Est Price
Euro (FOB)

310

3,410,000.00

220
530

110,000.00
742,000.00
220,000.00
155,000.00

Total Estimate

4.

Remarks

4.1

Rails are not included.

4.2

Erection Time estimated as 25 weeks (5 working days per week)

4.3

Commissioning Time:
No Load test - estimated as 3 weeks (without material)
Load test - estimated as 2 weeks (with material)
Total estimated as 5 weeks

4,637,000.00

In case of any interruption (no ships, etc), the time will be extended. The 5 weeks are the minimum
time that is needed.

BudgetEstimate_CSU_Clk_080213US_080217JLee.doc

Pg 2 of 3

4.4

All estimates are given based on price level of European costs. It can be reduced by using local
steel structure fabricated in Vietnam and erection costs of local Vietnamese companies. We do not
have these local costs at the moment.

5.

Example of FAM CSU


Enclosed is a PPT brochure of our FAM CSU already in operation at Rotterdam. The above
estimate is with a discharge directly to one quay conveyor only. The additional discharge option by
stacker boom as shown in this reference CSU is not included.

BudgetEstimate_CSU_Clk_080213US_080217JLee.doc

Pg 3 of 3