Subject

: PERT / CPM Schedule & S- CURVE

DATE
ITEM

MONTH
WEEK
START

100

DRAWING PREP.
ENGINEERING DESIGN

PERMITS & OTHERS

90
PERT/CPM

PROCUREMENT, HAULING AND DELIVERY OF MATERIALS


130 DAYS
CONSTRUCTION OF FENCE
52 DAYS
SITE GRADING WORKS / CONSTRUCTION OF TRUCK MARSHALING AREA
38 DAYS

40 DAYS

ROOAD PAVING WORKS

LANDSCAPING WORKS

15

52 DAYS

40 DAYS

80

STORM & WASTE WATER DRAINAGE SYSTEM


52 DAYS

CONSTRUCTION OF PARKING AREA


30 DAYS

MAIN PRODUCTION CENTER


TEMPORARY FACILITIES

CHB LAYING 150MM THK & 100MM THK. AND PLASTERING WORKS

FABRICATION OF REBARS & FORMWORKS

CONCRETING

CONCRETING

OF FOOTING

OF PEDESTAL

28 DAYS

18 DAYS

MOVE - IN

10 DAYS

DEMOLITION / REMOVAL WORKS

20 DAYS

DOORS & WINDOWS W/ ACCESSORIES

ROOF & SIDING FRAMING WORKS


11 DAYS

EXCAVATION & DISPOSAL


4
10 DAYS

INSTALLATION OF FTG.

ERECTION OF STR'L STEEL

METAL

& COLUMN REBARS

COLUMN, BEAMS & GIRDERS


5 DAYS
10
12 DAYS

DECKING

GRAVEL BEDDING

8 DAYS

8 DAYS

8
3 DAYS

SURVEY WORKS

9
5 DAYS

11

5 DAYS

CONC. OF

METAL ROOFING &


SIDING WORKS

13

6 DAYS

14 DAYS

16

8 DAYS

TOILET & SHOWER


FIXTURES

17

14 DAYS

6 DAYS

BACKFILLING, ENGINEERED FILL

18

14 DAYS

19 DAYS

AND COMPACTION WORKS

16 DAYS

DEMOBILIZATION

19

20 DAYS

10 DAYS

20

CONSTRUCTION OF

PAINTING WORKS

CONSTRUCTION OF GUARD HOUSES

28 DAYS
FABRICATION OF STRUCTURAL STEEL

70

20 DAYS
CONSTRUCTION OF SMOKER'S LOUNGE

CERAMIC FLOOR & WALL TILES


CONSTRUCTION OF SEPTIC TANK

8 DAYS

CONSTRUCTION OF PAINT STORAGE BLDG.

DRY WALL PARTITIONS

STR'L COL. CONC. ENCASEMENT

SOIL POISONING

20 DAYS

20 DAYS

ACOUSTIC CEILING BOARD

2ND FLR. SLAB

12

CONSTRUCTION OF TRUCKERS SHED & C.R.

20 DAYS

CONCRETING OF SLAB ON FILL

14

20 DAYS

CONCRETING OF EQUIP. FOUNDATION SUPPORTS

60

CONSTRUCTION OF PARKING AREA

17 DAYS

20 DAYS
SANITARY / PLUMBING WORKS
39 DAYS
ELECTRICAL WORKS
39 DAYS

STR'L COL. CONC. ENCASEMENT

POWER CENTER and UTILITIES BUILDING


GRAVEL BEDDING

ELECTRICAL WORKS AND SANITARY PLUMBING WORKS

CANTEEN, MEDICAL & DENTAL CLINIC


CONCRETING

ROOF & SIDING

OF FOOTING

FRAMINGWORKS

DOORS AND WINDOWS


W/ ACCESSORIES

GRAVEL BEDDING

CONCRETING

ROOF & SIDING

OF FOOTING

FRAMINGWORKS

CONCRETING OF PEDESTAL
EXCAVATION

INSTALLATION OF FTG.

&DISPOSAL

7 DAYS

5 DAYS

7 DAYS

5
3 DAYS

FABRICATION OF REBARS &


FORMWORKS

3 DAYS

ACOUSTIC CEILING BOARD

10 DAYS

13 DAYS

15 DAYS

AND COMPT'N

13 DAYS

INSTALLATION OF FTG.

& DISPOSAL

10

7 DAYS

ERECT'N OF STR'L STEEL

& COLUMN REBARS

11

5 DAYS

12

7 DAYS

DOWNSPOUTS & CATCH BASINS

EQUIP. FND'N SUPPORTS

ENGINEERED FILL

FABRICATION OF STRUCTURAL STEEL

EXCAVATION

& SIDING WORKS

CONC. OF GRADE SLAB &


BACKFILLING

7 DAYS

12 DAYS

METAL ROOFING

COLUMN & ROOF BEAMS


5 DAYS
6
7
8
8 DAYS

SOIL POISONING

DOORS AND WINDOWS


W/ ACCESSORIES

CONCRETING OF PEDESTAL

ERECT'N OF STR'L STEEL

& COLUMN REBARS


2

50

STR'L COL. CONC. ENCASEMENT

ELECTRICAL WORKS AND SANITARY PLUMBING WORKS

13

14

3 DAYS

13 DAYS

FABRICATION OF REBARS &

PAINTING WORKS

FORMWORKS

28 DAYS

12 DAYS

3 DAYS

SOIL POISONING

& SIDING WORKS

FABRICATION OF STRUCTURAL STEEL

19

INSTALL TOILET FIXTURES


7 DAYS

PAINTING WORKS

AND COMPT'N

13 DAYS

13 DAYS

14 DAYS

ENGINEERED FILL

40

ACOUSTIC CEILING BOARD

18

9 DAYS

CONC. OF GRADE SLAB &


BACKFILLING

7 DAYS

12 DAYS

METAL ROOFING

COLUMN & ROOF BEAMS


5 DAYS
15
16
17
8 DAYS

18 DAYS

8 DAYS

CONSTRUCTION OF SEPTIC TANK

30

12 DAYS
CHB LAYING 150MM THK & 100MM THK. AND PLASTERING WORKS

CHB LAYING 150MM THK & 100MM THK. AND PLASTERING WORKS

21 DAYS

28 DAYS

16

17

STR'L COL. CONC. ENCASEMENT

STR'L COL. CONC. ENCASEMENT

ELECTRICAL WORKS AND SANITARY PLUMBING WORKS

LOCKER, WASHROOMS, SECURITY OFFICE


GRAVEL BEDDING

CONCRETING

ROOF & SIDING

OF FOOTING

FRAMINGWORKS

CONCRETING OF PEDESTAL
EXCAVATION

INSTALLATION OF FTG.

&DISPOSAL

7 DAYS

5 DAYS

7 DAYS

42
3 DAYS

FABRICATION OF REBARS &


FORMWORKS
12 DAYS

SOIL POISONING
7 DAYS
FABRICATION OF STRUCTURAL STEEL

W/ ACCESSORIES

BACKFILLING

ACOUSTIC CEILING BOARD

AND COMPT'N

FRAMINGWORKS

13 DAYS

INSTALLATION OF FTG.

& DISPOSAL

10

7 DAYS

15 DAYS

13 DAYS
INSTALL DOWNSPOUTS

15 DAYS

13 DAYS
PAINTING WORKS

11 5 DAYS

12

7 DAYS

13
3 DAYS

FABRICATION OF REBARS &


FORMWORKS
12 DAYS

ERECT'N OF STR'L STEEL

& COLUMN REBARS

TOILET & SHOWER FIXTURES

SEPTIC TANK

13 DAYS

ROOF & SIDING

OF FOOTING

20

DOORS AND WINDOWS


W/ ACCESSORIES

CONCRETING OF PEDESTAL
EXCAVATION

& SIDING WORKS


10 DAYS

CONCRETING

13 DAYS

CONC. OF GRADE SLAB

ENGINEERED FILL

GRAVEL BEDDING

METAL ROOFING

COLUMN & ROOF BEAMS


5 DAYS
7
8
6
8 DAYS
3 DAYS

DOORS AND WINDOWS

10 DAYS

ERECT'N OF STR'L STEEL

& COLUMN REBARS

ELECTRICAL WORKS AND SANITARY PLUMBING WORKS

MULTI PURPOSE BUILDING

23 DAYS

14

3 DAYS

SOIL POISONING
7 DAYS
FABRICATION OF STRUCTURAL STEEL
13 DAYS

METAL ROOFING

COLUMN & ROOF BEAMS


5 DAYS
15
16
17
8 DAYS

& SIDING WORKS


9 DAYS

CONC. OF GRADE SLAB &


BACKFILLING
ENGINEERED FILL
AND COMPT'N

ACOUSTIC CEILING BOARD

18

13 DAYS

14 DAYS

7 DAYS

CONST. SEPTIC TANK

10

INSTALL DOWNSPOUT

14 DAYS

8 DAYS

19

INSTALL TOILET FIXTURES

13 DAYS
PAINTING WORKS

28 DAYS

18 DAYS

CHB LAYING 150MM THK & 100MM THK. AND PLASTERING WORKS

CHB LAYING 150MM THK & 100MM THK. AND PLASTERING WORKS

21 DAYS

28 DAYS

0
Projected Monthly Accomp (PESO)
(% )
Cummulative Monthly Accomp (PESO)
(%)
Submitted By:

12.50

20.00

27.50

27.50

12.50

12.50

32.50

60.00

87.50

100.00