PROYECTO:
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
MES 01
MES 02
MES 03
01.00.00
OBRAS PROVISIONALES
01.01.00
UND
1.00
350.00
350.00
350.00
01.02.00
ALMACEN DE OBRA
M2
1.00
180.00
180.00
180.00
02.00.00
TRABAJOS PRELIMINARES
02.01.00
TRAZO Y REPLANTEO
M2
789.75
6.35
5,014.91
5,014.91
02.02.00
M2
789.75
3.85
3,040.54
3,040.54
03.00.00
MOVIMIENTO DE TIERRAS
03.01.00
M3
1,184.63
2.57
3,044.50
3,044.50
03.02.00
M3
108.00
15.21
1,642.68
1,642.68
03.03.00
BASE DE 0.10 M.
M2
540.00
12.98
7,009.20
7,009.20
03.04.00
NIVELACION Y COMPACTACION
M2
1,080.00
3.38
3,650.40
3,650.40
03.05.00
M2
540.00
9.95
5,373.00
5,373.00
03.06.00
M3
2.41
21.55
51.94
51.94
03.07.00
M3
1,683.54
14.51
24,428.17
24,428.17
8,055.45
45,199.88
16,026.25
04.00.00
CONCRETO SIMPLE
04.01.00
M2
80.64
39.00
3,144.96
04.02.00
M3
56.43
227.32
12,827.67
04.05.00
6.08
8.82
53.63
05.00.00
CARPINTERIA METALICA
05.01.00
UND
2.00
1,750.00
3,500.00
3,500.00
05.02.00
PZA
2.00
43.50
87.00
87.00
06.00.00
PINTURA
06.01.00
GLB
06.02.00
01.00.00
TRABAJOS PRELIMINARES
01.01.00
M2
35.07
3.85
135.02
135.02
01.02.00
GLB
35.07
6.35
222.69
222.69
02.00.00
MOVIMIENTO DE TIERRAS
1,572.48
1,572.48
12,827.67
21.45
32.18
3,587.00
1,271.26
1.00
260.00
260.00
260.00
342.80
2.95
1,011.26
1,011.26
1,074.86
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
PRESUPUESTO DE CONSTRUCCION
EN LOSA
M3
18.80DEPORTIVA
18.24MULTIUSOS
342.91
MES 01
02.01.01
EXCAVACION DE ZANJAS
02.01.02
NIVELACION Y COMPACTACION
M2
10.17
18.24
185.50
185.50
02.01.03
ELIMINACION DE DESMONTE
M3
37.66
14.51
546.45
546.45
03.00.00
MES 02
MES 03
342.91
8,815.98
3,761.88
03.01.00
SOLADOS
03.01.01
03.02.00
CIMIENTOS CORRIDOS
03.02.01
03.03.00
SOBRECIMIENTOS
03.03.01
M3
3.35
105.22
352.49
352.49
03.03.02
M2
46.00
36.69
1,687.74
1,687.74
04.00.00
CONCRETO ARMADO
M3
188.00
20.01
M3
15.73
191.60
3,761.88
3,761.88
3,013.87
3,013.87
3,013.87
2,040.23
37,314.10
3,933.53
04.01.00
ZAPATAS
04.01.01
M3
9.40
287.51
2,702.59
2,702.59
04.01.02
KG
170.49
7.22
1,230.94
1,230.94
04.02.00
COLUMNAS
04.02.01
M2
63.00
28.19
1,775.97
1,243.18
532.79
04.02.02
KG
608.75
7.45
4,535.19
3,174.63
1,360.56
04.02.03
M3
4.00
263.29
1,053.16
737.21
315.95
04.03.00
VIGAS
04.03.01
M2
52.85
41.36
2,185.88
1,311.53
874.35
04.03.02
KG
357.16
7.45
2,660.84
1,596.51
1,064.34
04.03.03
M3
4.10
269.82
1,106.26
663.76
442.50
7,364.32
5,952.98
18,324.94
04.04.00
04.04.01
M2
9.20
39.00
358.80
269.10
89.70
04.04.02
KG
831.64
14.29
11,884.14
8,913.10
2,971.03
M3
24.05
252.89
6,082.00
4,561.50
1,520.50
04.04.03
04.05.00
GRADAS
04.04.01
M2
7.80
35.16
274.25
205.69
68.56
04.04.02
KG
94.23
6.93
653.01
489.76
163.25
1,738.33
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
PRESUPUESTO DE CONSTRUCCION
EN LOSA
DEPORTIVA
M3
2.29
354.18MULTIUSOS
811.07
MES 01
MES 02
MES 03
04.04.03
05.00.00
05.01.00
M2
167.33
70.58
11,810.15
11,810.15
05.02.00
M2
11.07
57.36
634.98
634.98
06.00.00
06.01.00
M2
97.26
34.26
3,332.13
3,332.13
06.02.00
TARRAJEO EN INTERIORES
M2
190.33
34.99
6,659.65
6,659.65
06.03.00
TARRAJEO EN EXTERIORES
M2
94.31
32.33
3,049.04
3,049.04
06.04.00
M2
28.14
14.81
416.75
250.05
06.05.00
92.90
14.81
1,375.85
06.06.00
M2
96.30
27.72
07.00.00
CONTRAZOCALOS Y ZOCALOS
07.01.00
ZOCALO DE CERAMICA
M2
97.26
35.30
07.02.00
CONTRAZOCALO SANITARIO
M2
40.70
19.36
08.00.00
PISOS Y PAVIMENTOS
08.03.00
M2
96.30
60.18
08.01.00
M3
19.67
104.44
08.02.00
M2
76.28
42.24
09.00.00
CARPINTERIA DE MADERA
09.01.00
09.02.00
ESTRUCTURA DE MADERA
09.02.01
TIJERALES Y RETICULADOS
09.01.01.01
M.
22.75
77.22
1,756.76
1,756.76
09.01.01.02
M.
44.70
14.26
637.42
637.42
09.01.01.03
M2.
34.00
19.26
654.84
654.84
09.01.01.04
M.
14.90
16.54
246.45
246.45
10.00.00
CARPINTERIA METALICA
10.01.00
M2
10.02.00
UND.
11.00.00
PINTURA
608.30
202.77
12,445.13
17,502.86
2,669.44
166.70
1,375.85
1,601.66
1,067.77
3,433.28
2,403.29
1,029.98
787.95
551.57
236.39
5,795.33
2,897.67
2,897.67
2,054.33
2,054.33
3,222.07
3,222.07
4,221.23
11,071.74
4,375.46
UND.
6.00
180.00
1,080.00
1,080.00
3,295.46
2,318.60
15.27
60.00
916.20
916.20
8.00
175.30
1,402.40
1,402.40
8,998.49
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
MES 01
MES 02
MES 03
11.01.00
PRESUPUESTO
EN LOSA
PINTURA LATEX LAVABLE EN MURO INTERIORES
02 MANOS DE CONSTRUCCION
M2
283.23DEPORTIVA
17.46MULTIUSOS
4,945.20
3,956.16
989.04
11.02.00
M2
94.31
17.46
1,646.65
1,317.32
329.33
11.03.00
M2
28.14
17.46
491.32
491.32
11.04.00
M2
96.30
17.46
1,681.40
1,681.40
11.05.00
PINTURA DE CONTRAZOCALOS
M2
23.70
9.87
233.92
12.00.00
INSTALACIONES ELECTRICAS
12.01.00
12.01.01
UND.
23.00
12.56
288.88
12.01.02
SALIDA DE INTERRUPTORES
UND.
11.00
9.09
99.99
99.99
12.01.03
UND.
20.00
8.79
175.80
175.80
12.01.04
UND.
14.00
7.40
103.60
103.60
12.01.05
47.00
8.24
387.28
387.28
12.01.06
67.00
8.24
552.08
552.08
12.01.07
17.00
8.24
140.08
140.08
12.02.00
TABLEROS Y CUCHILLAS
12.02.01
TABLERO ELECTRICO
UND.
1.00
237.07
237.07
237.07
12.02.02
TABLERO DE DISTRIBUCION
UND.
2.00
107.07
214.14
214.14
12.03.00
ARTEFACTOS
12.03.01
UND
24.00
60.00
1,440.00
1,440.00
12.03.02
INTERRUPTOR
UND
12.00
12.20
146.40
146.40
12.03.03
TOMACORRIENTE
UND
20.00
2.60
52.00
52.00
12.03.04
UND
4.00
320.83
1,283.32
1,283.32
13.00.00
INSTALACIONES SANITARIAS
6,150.41
13.01.00
2,663.00
13.01.01
UND
8.00
210.00
1,680.00
1,680.00
13.01.02
UND
6.00
38.00
228.00
228.00
13.01.02
LAVADERO DE METAL
UND
1.00
65.00
65.00
65.00
13.01.02
DUCHAS CROMADAS
UND
6.00
60.00
360.00
360.00
13.01.03
UND
3.00
110.00
330.00
330.00
13.02.00
INSTALACIONES Y O TUBERIAS
233.92
5,120.64
1,747.71
288.88
451.21
2,921.72
2,796.05
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
PRESUPUESTO DE CONSTRUCCION
EN LOSA
PTO
12.00DEPORTIVA
45.19MULTIUSOS
542.28
MES 01
MES 02
MES 03
13.02.01
13.02.02
PTO
28.00
12.33
345.24
13.02.05
PTO
2.00
12.33
24.66
13.02.06
22.00
45.10
992.20
992.20
13.02.07
48.00
12.24
587.52
587.52
13.02.03
1.00
31.45
31.45
13.02.04
PZA
14.00
5.00
70.00
70.00
13.02.08
PZA
2.00
8.50
17.00
17.00
13.02.09
PZA
4.00
19.50
78.00
78.00
13.02.10
UND
3.00
20.90
62.70
62.70
13.02.11
UND
1.00
45.00
45.00
45.00
13.03.00
13.03.01
PTO
23.00
8.22
189.06
13.03.02
27.10
3.31
89.70
89.70
13.03.03
31.60
4.29
135.56
135.56
13.03.04
27.30
6.06
165.44
165.44
13.03.05
PZA
4.00
27.90
111.60
111.60
01.00.00
TRABAJOS PRELIMINARES
01.01.00
02.00.00
MOVIMIENTO DE TIERRAS
03.06.00
M3
25.40
21.55
547.37
547.37
03.07.00
M3
33.02
14.51
479.12
479.12
542.28
345.24
24.66
31.45
691.36
189.06
62.36
6.35
395.99
395.99
1,026.49
8,028.51
03.00.00
CONCRETO SIMPLE
03.01.00
M3
107.94
36.69
3,960.32
3,960.32
03.02.00
M3
21.50
107.00
2,300.50
2,300.50
03.03.00
M3
16.80
105.22
1,767.70
1,767.70
04.00.00
MUROS Y TABIQUES
04.01.00
05.00.00
CARPINTERIA METALICA
1,904.25
M2
26.98
70.58
1,904.25
24,899.42
571.27
1,332.97
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
MES 01
MES 02
PRESUPUESTO DE CONSTRUCCION
EN LOSA
M2
337.25DEPORTIVA
73.55MULTIUSOS
24,804.74
05.03.00
MALLA OLIMPICA
05.04.00
06.00.00
PINTURA
06.01.00
UND
2.00
47.34
MES 03
24,804.74
94.68
94.68
260.00
GLB
1.00
260.00
260.00
260.00
01.00.00
TRABAJOS PRELIMINARES
01.01.00
02.00.00
MOVIMIENTO DE TIERRAS
02.01.00
M3
77.76
2.57
199.84
199.84
02.05.00
M2
98.62
12.46
1,228.81
1,228.81
02.06.00
M3
8.83
11.74
103.66
103.66
02.07.00
M3
112.57
14.51
1,633.39
1,633.39
03.00.00
CONCRETO SIMPLE
03.01.00
M2
84.32
45.35
3,823.91
1,911.96
03.03.00
M3
7.68
23.58
181.09
181.09
03.05.00
44.61
146.96
6,555.89
2,622.35
04.00.00
CARPINTERIA METALICA
04.06.00
GBL
1.00
750.00
750.00
750.00
04.06.00
BARANDAS
ML
10.50
18.03
189.32
189.32
05.00.00
PINTURA
05.01.00
M2
51.84
6.35
329.18
329.18
3,165.70
10,560.89
1,911.96
3,933.53
939.32
260.00
GLB
1.00
260.00
260.00
260.00
PRESUPUESTO DE FLETES
9,435.81
01.00.00
FLETE Y OTROS
01.01.00
FLETE TERRESTRE
GLB
1.00
8,765.81
8,765.81
4,382.91
3,068.03
01.02.00
UND
4.00
35.00
140.00
70.00
70.00
01.03.00
DENSIDAD DE CAMPO
UND
2.00
80.00
160.00
160.00
01.04.00
PROCTOR
UND
2.00
60.00
120.00
60.00
60.00
01.05.00
UND
1.00
250.00
250.00
125.00
125.00
255,642.61
119,524.67
82,256.73
COSTO DIRECTO
1,314.87
53,861.21
"INSTALACION DE LOSA DE RECREACION MULTIUSO EN EL BARRIO ACOBAMBA, DISTRITO DE HUANDO HUANCAVELICA - HUANCAVELICA"
REGION :
PROVINCIA:
HUANCAVELICA
PARTIDA
ACTIVIDADES
DISTRITO:
HUANCAVELICA
GASTOS GENERALES 7%
UTILIDAD 8%
SUB TOTAL
IGV 18%
VALOR REFERENCIAL
SUPERVISION DE OBRA
TOTAL GENERAL
HUANDO
FECHA:
UNID
METR.
TOTAL S/.
MES 01
MES 02
MES 03
8,366.73
5,757.97
20,451.41
9,561.97
6,580.54
4,308.90
293,989.00
137,453.37
94,595.24
61,940.39
PORCENTAJE DE AVANCE
3,770.28
52,918.02
24,741.61
17,027.14
11,149.27
346,907.02
162,194.98
111,622.38
73,089.66
18,000.00
6,000.00
6,000.00
6,000.00
364,907.02
168,194.98
117,622.38
79,089.66
100.00%
46.09%
32.23%
21.67%
1351568.97
787528.59
75914.36
123168.12
134156
156000
70890
187695.4
2886921.44
01.00.00
TRABAJOS PRELIMINARES
01.01.00
LIMPIEZA DE TERRENO
M2 MANUAL
77.40
0.36
27.86
01.02.00
TRAZO Y REPLANTEO
M2
77.40
0.61
47.21
02.00.00
MOVIMIENTO DE TIERRAS
02.01.00
EXCAVACIONES
02.01.01
EXCAVACION DE ZANJAS
M3 PARA ZAPATAS
19.22
29.69
570.64
02.01.02
EXCAVACION DE ZANJAS
M3 PARA CIMIENTOS
9.36
25.45
238.21
02.01.03
9.61
6.00
57.66
02.02.00
ELIMINACION MATERIAL
M3 EXCEDENTE
23.71
4.13
97.92
02.03.00
NIVELACION, RELLENO
M2 Y COMPACTADO CON MATERIAL
67.34DE PRESTAMO 5.26
354.21
03.00.00
CONCRETO SIMPLE
03.01.00
CIMIENTOS CORRIDOS
03.01.01
03.02.00
03.03.00
SOBRECIMIENTOS
03.03.01
SOBRECIMIENTO CONCRETO
M3
1:8+25% P.M.
03.03.02
04.00.00
CONCRETO ARMADO
04.01.00
ZAPATAS DE CONCRETO
04.01.01
CONCRETO EN ZAPATAS
M3 F'C= 210 KG/CM2
04.01.02
04.02.00
COLUMNAS DE CONCRETO
04.02.01
CONCRETO EN COLUMNAS
M3
F'C=210 KG/CM2
04.02.02
04.02.03
ACERO GRADO 60 EN
KGCOLUMNAS
04.03.00
VIGAS
04.03.01
CONCRETO EN VIGAS
M3 F'C=210 KG/CM2
04.03.02
04.03.03
ACERO GRADO 60 EN
KGVIGAS
04.04.00
04.04.01
CONCRETO EN LOSA
M3LAVADERO DE COCINA F'C=2100.14
KG/CM2
04.04.02
ENCOFRADO Y DESENCOFRADO
M2
NORMAL EN LOSA DE
1.86
LAVADERO DE COCINA
40.12
04.04.03
ACERO GRADO 60 EN
KGLOSA DE LAVADERO DE COCINA
34.13
04.05.00
04.05.01
CONCRETO EN LOSAS
M3 ALIGERADAS F'C=210 KG/CM211.11
04.05.02
ENCOFRADO Y DESENCOFRADO
M2
NORMAL EN LOSAS
111.07
ALIGERADAS
04.05.03
ACERO GRADO 60 EN
KGLOSAS ALIGERADAS
170.86
1,667.59
14.98
239.98
3.18
171.95
546.80
ENCOFRADO Y DESENCOFRADO
M2
DE SOBRECIMIENTOS
35.54
21.54
765.53
8.01
381.80
3,058.22
ACERO ESTRUCTURAL
KG TRABAJADO PARA ZAPATAS245.59
4.62
1,134.63
6.62
444.02
2,939.41
ENCOFRADO Y DESENCOFRADO
M2
NORMAL EN COLUMNAS
75.90
46.49
3,528.59
809.14
4.76
3,851.51
11.32
444.02
5,026.31
ENCOFRADO Y DESENCOFRADO
M2
NORMAL EN VIGAS143.75
37.48
5,387.75
4.73
7,171.86
444.02
62.16
1,516.25
74.62
4.45
151.88
452.46
5,026.83
22.76
2,527.95
4.33
5,551.88
04.05.04
LADRILLO HUECO DE
UND
ARCILLA 15X30X30 CM PARA TECHO
999.54 ALIGERADO 2.73
2,728.74
04.06.00
CONTROL DE CALIDAD
04.06.01
PRUEBA DE CALIDAD
UND
DEL CONCRETO (PRUEBA A LA COMPRESION)
6.00
05.00.00
ESTRUCTURA Y COBERTURA
1,282.19
12.60
75.60
05.01.00
05.02.00
111.07
44.79
4,974.83
19.35
35.99
696.41
06.00.00
06.01.00
06.02.00
63.25
3,379.45
98.44
07.00.00
4,158.11
07.01.00
TARRAJEO EN EXTERIORES
M2
E INTERIORES DE MUROS
191.34
CON CEMENTO-ARENA
27.51
5,263.76
07.02.00
TARRAJEO DE SUPERFICIE
M2
DE COLUMNAS
07.03.00
TARRAJEO EN SUPERFICIE
M2
DE VIGAS
07.04.00
75.90
29.66
2,251.19
143.75
29.58
4,252.13
TARRAJEO DE EN CIELO
M2 RASO
91.85
29.66
2,724.27
07.05.00
TARRAJEO EN REMATES
M
Y DERRAMES
76.25
22.22
1,694.28
07.06.00
TARRAJEO PRIMARIO
M2RAYADO CON CEMENTO-ARENA1.86
14.30
26.60
07.07.00
83.00
1.48
122.84
08.00.00
PISOS Y PAVIMENTOS
08.01.00
64.44
19.10
1,230.80
08.02.00
CONTRAPISO DE 48M2
MM.
64.44
23.14
1,491.14
08.03.00
PISO DE CERAMICOM2
DE COLOR CLARO 0.30 X 0.30
64.44
44.82
2,888.20
09.00.00
CONTRAZOCALOS Y ZOCALOS
09.01.00
CONTRAZOCALO SANITARIO
M
DE GRANITO PULIDO H= 9.95
5 cm
12.45
123.88
09.02.00
90.52
14.84
1,343.32
09.03.00
ZOCALO DE CERAMICO
M2
9.86
40.46
398.94
09.04.00
CERAMICO DE 30X30
M2EN DETALLES DE BAOS
1.86
44.82
83.37
10.00.00
CARPINTERIA DE MADERA
10.01.00
PUERTA APANELADADE
M2 MARCO DE MADERA Y PLANCHA
18.36 METALICA (VER
307.51
DETALLE NE PLANO)
5,645.88
11.00.00
CARPINTERIA METALICA
11.01.00
VENTANA DE ALUMINIO
M2 S/DISEO
12.00.00
CERRAJERIA
12.01.00
BISAGRA ALUMINIZADA
PZA CAPUCHINA DE 3" X 3"
12.02.00
12.03.00
MANIJA DE BRONCEUND
13.00.00
13.01.00
VIDRIOS 6 mm (TRIPLES)
P2 INCLUYE INSTALACION
14.00.00
PINTURA
18.76
153.14
2,872.91
21.00
13.16
276.36
7.00
69.86
489.02
7.00
8.88
62.16
208.42
5.12
1,067.11
14.01.00
1,993.76
14.02.00
14.03.00
14.04.00
14.05.00
15.00.00
INSTALACIONES SANITARIAS
15.01.00
15.01.01
LAVADERO DE COCINA
PZA DE ACERO INOXIDABLE
15.02.00
SISTEMA DE DESAGUE
15.02.01
15.02.02
75.90
9.95
755.21
143.75
7.35
1,056.56
91.85
10.42
957.08
76.25
3.88
295.85
1.00
194.54
194.54
SALIDA DE DESAGUE
PTO
EN PVC 2'
3.00
23.24
69.72
SALIDA DE DESAGUE
PTO
EN PVC 4'
2.00
28.62
57.24
15.02.03
4.90
8.68
42.53
15.02.04
RED DE DISTRIBUCION
M TUBERIA PVC DE 4"
2.48
27.70
68.70
15.02.05
REGISTRO DE BRONCE
UND2", PROVISION Y COLOCACION2.00
8.15
16.30
15.02.06
REGISTROS DE BRONCE
UND DE 4"
1.00
18.17
18.17
15.02.07
2.00
6.14
12.28
15.02.08
1.00
9.45
9.45
15.02.09
1.00
4.12
4.12
15.02.10
4.00
5.16
20.64
15.02.11
2.00
5.17
10.34
15.02.12
1.00
8.81
8.81
15.02.13
1.00
6.30
6.30
15.02.14
UND
2.00
4.31
8.62
15.02.15
UND
1.00
5.14
5.14
15.03.00
15.03.01
23.41
46.82
15.03.02
4.23
25.38
15.03.03
VALVULA COMPUERTA
UNDDE BRONCE DE UNION ROSCADA
2.00DE 1/2"
45.72
91.44
15.03.04
1.00
4.53
4.53
15.03.05
4.00
10.44
41.76
15.03.06
2.00
10.44
20.88
15.03.07
GRIFO CROMADO DE
UND
1/2" PESADO
2.00
28.52
57.04
16.00.00
INSTALACIONES ELECTRICAS
16.01.00
CONDUCTORES ELECTRICOS
16.01.01
CONDUCTOR DE 2 M
X 2.5 mm2 LSOH
80.49
3.45
277.69
16.01.02
51.09
6.38
325.95
16.02.00
TUBERIAS Y ACCESORIOS
16.02.01
131.58
3.51
461.85
16.02.02
86.00
1.22
104.92
16.03.00
16.03.01
TOMACORRIENTE CON
UNDTOMA A TIERRA
13.00
15.88
206.44
16.03.02
INTERRUPTOR SIMPLE
UND
5.00
21.14
105.70
16.03.03
INTERRUPTOR DOBLE
UND
3.00
18.40
55.20
16.03.04
CENTRO DE LUZ
25.00
36.18
904.50
16.04.00
ARTEFACTOS DE ILUMINACION
16.04.01
FLUORESCENTE RECTO
UND ISPE 1 X 32 W INCLUYENDO13.00
EQUIPO Y PANTALL71.15
924.95
16.04.02
1,792.44
16.05.00
16.05.01
TABLERO DE DISTRIBUCION
UND
16.06.00
16.06.01
CAJA RECTANGULAR
UND
100x55x40mm
16.07.00
UND
6.00
1.00
384.02
384.02
2.00
15.90
31.80
16.07.01
CONDUCTOR UTP DE
M 8 HILOS PARA RED INTERNET 2.00
1.32
2.64
16.07.02
2.00
4.06
8.12
16.07.03
TOMA DE RED
1.00
17.47
17.47
16.08.00
16.08.01
2.00
1.88
3.76
16.08.02
CAJA DE INTERCONECCION
UND
VOZ Y DATA
1.00
15.90
15.90
16.09.00
16.09.01
22.00
1.97
43.34
16.09.02
22.00
4.06
89.32
16.09.03
SALIDA DE DETECTOR
PTODE HUMO -CONTRA INCENDIO 7.00
57.39
401.73
16.10.00
16.10.01
LUZ DE EMERGENCIA
UND
85.55
855.50
UND
10.00