Weighting
60
40
Range
(Minor time impact 40-60, Medium time impact 20-40, Major time impact 0-20)
(Major cost impact 0-15, Medium cost impact 15-25, Low cost impact 25-40)
Score
Commentary
Option 1
15
Potential delay in receiving proposal from Contractor will result in delay to the works and likely delay to the
project completion date.
Option 2
60
Design and engineering works can immediately commence for critical areas.
Option 3
40
Slight delayed implementation is likely to increase the requirement for dismantling installed services to
provide access in congested areas.
Score
Commentary
Option 1
20
Due to the uncertain nature and quantity of the work, the Contractor would likely price in the risk.
Option 2
10
Option 3
35
Cost certainty for design and installation and competitive pricing due to known quantities.
Result
Option
Score
Rank
Option 1
35
Rank 3
Option 2
70
Rank 2
Option 3
75
Rank 1