Sunteți pe pagina 1din 35

RESUMEN DE VALORIZACION A JULIO DEL 2013

Obra
Ubicacin
Ejecuta
Financia
Fecha
Avance del Mes

N
3.00

:
:
:
:
:
:

SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA" DISTRITO DE HUACHOCOLPA - TAYACAJA - HUANCAVELICA
Supervisor
ARQ. HUGO ABEL VILLAVERDE RAFAEL
HUACHOCOLPA - TAYACAJA - HUANCAVELICA
:
Residente
ING. CLIFOR HECTOR GARCIA CORZO
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA
:
S/. 4,778,053.33
Monto del Proyecto
GOBIERNO REGIONAL HUANCAVELICA
:
S/. 4,648,419.93
Costo Total de Obra
JULIO DEL 2013
:
S/. 4,414,607.93
Costo Directo de Obra
11.22%
:
S/. 129,633.40
Monto de Supervisin
:

DESCRIPCION

PRESUPUESTA
DO S/.

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL

TOTAL DE COSTO DIRECTO

124,238.09
124,238.09

EJECUTADO ANTERIOR
S/.
13,435.15

13,435.15

MONTOS
EJECUTADO ACTUAL

10.81%

S/.
504.34

10.81%

504.34

EL AVANCE FISICO VALORIZADO ACUMULADO JULIO DEL 2013; ES DE SETECIENTOS SEIS MIL NOVECIENTOS OCHENTA Y OCHO CON 66/100 NUEVOS SOLES
EL MISMO QUE REPRESENTA UN AVANCE ACUMULADO DEL 11.22%

EJECUTADO ACUMULADO

0.41%

S/.
13,939.49

%
11.22%

0.41%

13,939.49

11.22%

VALORIZACION N 03 - MES DE JULIO


SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA

Nombre del Proyecto :


Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

01
01.01

ESTRUCTURAS
TRABAJOS PRELIMINARES

Costo
Parcial
(S/.)

Avance
Actual

Anterior
Metrado

Monto Valorizado
S/.

Metrado

13,435.15

504.34

13,939.49

11.22%

124,238.09

13,435.15

504.34

13,939.49

11.22%

57,147.96

13,435.15

504.34

13,939.49

24.39%

530.19

57.37
-

74.75%

01.01.01

LIMPIEZA DEL TERRENO MANUAL

M2

217.29

0.69

149.93

217.29

01.01.02

TRAZO Y REPLANTEO PRELIMINAR

M2

217.29

0.87

189.04

217.29

189.04

01.01.03

TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO

M2

217.29

0.88

191.22

MOVIMIENTO DE TIERRAS

Monto
Valorizado S/.

8,628.10

65.19

6,591.86
551.11

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

124,238.09

338.97
149.93

01.02

Metrado

Saldo

Acumulado

Monto Valorizado
S/.

110,298.60
110,298.60
-

43,208.47
133.85
-

217.29

396.34
149.93

100.00%

217.29

189.04

100.00%

57.37

65.19

57.37

30.00%

152.10

133.85

2,020.04
-

16.20
-

6,608.06
551.11

76.59%

01.02.01

EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO

M3

19.91

27.68

551.11

19.91

01.02.02

EXCAV. MANUAL DE ZANJAS HASTA 1.40 M

M3

146.76

27.68

4,062.32

146.76

146.76

01.02.03

EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA

M3

2.35

27.68

65.05

0.00%

01.02.04

EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS

M3

0.18

27.68

4.98

0.00%

0.18

4.98

01.02.05

RELLENO CON MATERIAL PROPIO

M3

92.95

8.30

771.49

0.00%

92.95

771.49

01.02.06

REFINE, NIVELACION Y COMPACTACION

M2

214.45

1.46

313.10

0.00%

214.45

313.10

01.02.07

RELLENO CON MATERIAL CLASIFICADO E=10 CM

M2

214.45

3.96

849.22

0.00%

214.45

849.22

01.02.08

ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.

M3

95.30

20.76

1,978.43

95.30

1,978.43

100.00%

01.02.09

ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km

M3

95.30

0.34

32.40

16.20

47.65

16.20

50.00%

47.65

16.20

430.77
-

91.72

1,287.43
856.66

100.00%

5,387.37
-

01.03

CONCRETO SIMPLE

95.30

4,062.32

1,978.43
-

6,674.80

47.65

856.66
856.66

19.91

4,062.32

100.00%
100.00%

2.35

65.05

19.29%

01.03.01

SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12

M2

91.72

9.34

856.66

01.03.02

CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G

M3

27.67

41.50

1,148.31

430.77

10.38

430.77

37.51%

17.29

717.54

01.03.03

SOBRECIMIENTO CONCRETO 1:8+25% PM

M3

3.91

69.17

270.45

0.00%

3.91

270.45

01.03.04

SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m

M2

52.18

18.17

948.11

0.00%

52.18

948.11

01.03.05

FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)

M2

160.65

9.57

1,537.42

0.00%

160.65

1,537.42

01.03.06

VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL

M2

53.80

17.39

935.58

0.00%

53.80

935.58

01.03.07

VEREDA ENCOFRADO Y DESENCOFRADO

M2

16.27

16.51

268.62

0.00%

16.27

268.62

01.03.08

SARDINELES CONCRETO FC=175 KG/CM2

M3

3.88

87.04

337.72

0.00%

3.88

337.72

01.03.09

SARDINELES ENCOFRADO Y DESENCOFRADO

M2

31.02

11.99

371.93

0.00%

31.02

01.04
01.04.01
01.04.01.01
01.04.01.02
01.04.02

CONCRETO ARMADO

39,953.45

ZAPATAS

2,619.51

ZAPATAS CONCRETO F'C=210 kg/cm2

M3

56.49

27.86

1,573.81

56.49

ZAPATAS ACERO F'Y=4200 KG/CM2

KG

1,323.67

0.79

1,045.70

1,323.67

COLUMNAS

8,126.42

01.04.02.01

COLUMNAS CONCRETO F'C=210 kg/cm2

M3

24.14

69.63

1,680.87

01.04.02.02

COLUMNAS ENCOFRADO Y DESENCOFRADO

M2

206.99

16.51

3,417.40

01.04.02.03

COLUMNAS ACERO F'C=4200 KG/CM2

KG

3,833.10

0.79

3,028.15

01.04.03

91.72

PLACAS DE CONCRETO

5,647.66

0.00

2,619.51
1,573.81

0.00
-

1,045.70
3,028.15
-

3,833.10

1,028.67

Valor. Mensual SP3

10.38

3,028.15
0.00

56.49
1,323.67

0.00
-

0.00

3,833.10

5,647.66

14.14%

2,619.51
1,573.81

100.00%
100.00%

1,045.70

100.00%

3,028.15
3,028.15
0.00

371.93
34,305.79
0.00
-

37.26%
0.00%

24.14

5,098.27
1,680.87

0.00%

206.99

3,417.40

100.00%

0.00%

1,028.67

Pgina 2

VALORIZACION N 03 - MES DE JULIO


SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA

Nombre del Proyecto :


Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

Costo
Parcial
(S/.)

Avance
Actual

Anterior
Metrado

Monto Valorizado
S/.

Metrado

Acumulado

Monto
Valorizado S/.

Metrado

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

Saldo
Monto Valorizado
S/.

01.04.03.01

PLACA DE CONCRETO F'c=210 Kg/Cm2

M3

2.33

139.26

324.48

0.00%

2.33

324.48

01.04.03.02

PLACA ENCOFRADO Y DESENCOFRADO

M2

23.30

24.76

576.91

0.00%

23.30

576.91

01.04.03.03

PLACA ACERO F'c=4200 Kg/Cm2

KG

161.11

0.79

127.28

0.00%

161.11

0.00
-

0.00%

01.04.04

VIGAS

127.28

01.04.04.01

VIGAS CONCRETO F'C=210 kg/cm2

M3

44.10

77.48

3,416.87

0.00
-

0.00
-

0.00%

44.10

13,807.16
3,416.87

01.04.04.02

VIGAS ENCOFRADO Y DESENCOFRADO

M2

351.91

17.48

6,151.39

0.00%

351.91

6,151.39

01.04.04.03

VIGAS ACERO FY=4200 KG/CM2

KG

5,365.69

0.79

4,238.90

0.00%

5,365.69

0.00
-

0.00%

01.04.05

13,807.16

LOSAS ALIGERADAS

4,238.90

01.04.05.01

LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2

M3

30.95

59.94

1,855.14

0.00
-

0.00
-

0.00%

30.95

11,190.89
1,855.14

01.04.05.02

LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm

M2

208.72

7.20

1,502.78

0.00%

208.72

1,502.78

01.04.05.03

LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm

M2

156.10

7.20

1,123.92

0.00%

156.10

1,123.92

01.04.05.04

LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO

M2

364.82

14.68

5,355.56

0.00%

364.82

5,355.56

01.04.05.05

LOSA ALIGERADA ACERO FY=4200 KG/CM2

KG

1,713.28

0.79

1,353.49

0.00%

1,713.28

1,353.49

0.00
-

0.00%

01.04.06

11,190.89

LOSAS MACIZAS

01.04.06.01

LOSA MACIZA CONCRETO f'c=210 kg/cm2

M3

2.92

61.33

179.08

0.00
-

0.00
-

0.00%

2.92

685.94
179.08

01.04.06.02

LOSA MACIZA ENCOFRADO Y DESENCOFRADO

M2

14.61

14.86

217.10

0.00%

14.61

217.10

01.04.06.03

LOSA MACIZA ACERO FY=4200 KG/CM2

KG

366.79

0.79

289.76

0.00%

366.79

289.76

809.94

0.00
-

0.00
-

0.00%

0.00
-

01.04.07

ESCALERAS

01.04.07.01

ESCALERAS CONCRETO f'c=210 kg/cm2

01.04.07.02

ESCALERAS ENCOFRADO Y DESENCOFRADO

01.04.07.03

ESCALERA ACERO FY=4200 KG/CM2

01.04.08

M3

RAMPAS CONCRETO FC=210 KG/CM2

01.04.08.02

RAMPAS ENCOFRADO Y DESENCOFRADO

01.04.08.03

RAMPAS ACERO FY=4200 KG/CM2

56.72

47.64

M2

16.35

39.61

647.62

0.00%

16.35

647.62

KG

145.16

0.79

114.68

0.00%

145.16

114.68

968.66

0.84

0.00
-

0.00%

0.00
-

2.59

119.46

309.40

0.00
-

M2

19.80

28.30

560.34

KG

125.22

0.79

98.92

0.00
-

0.00
-

0.00%

0.00
-

0.00%

1.05

0.00%

23.65

669.30

0.00
-

0.00%

M3

DETALLES

716.26

01.04.09.01

DETALLES CONCRETO F'C= 175KG/CM2

M3

1.05

44.72

46.96

01.04.09.02

DETALLES ENCOFRADO Y DESENCOFRADO

M2

23.65

28.30

669.30

01.05

0.00%

809.94
47.64

0.84

RAMPAS

01.04.08.01

01.04.09

685.94

ESTRUCTURA DE MADERA Y COBERTURA

968.66
309.40

0.00%

19.80

560.34

0.00%

125.22

98.92
716.26
46.96

01.05.01

CORREAS DE MADERA 2" x 2"

ML

244.30

2.72

664.50

0.00
-

0.00
-

0.00%

244.30

1,361.42
664.50

01.05.02

COBERTURA TEJA ANDINA (0.72x1.14)

M2

232.50

2.81

653.33

0.00%

232.50

653.33

01.05.03

CUMBRERA TEJA ANDINA

ML

21.45

1.48

31.75

0.00%

21.45

31.75

01.05.04

LIMATESA TEJA ANDINA

ML

16.00

0.74

11.84

0.00%

16.00

56,359.67

0.00

0.00

0.00

0.00%

5,131.11

0.00
-

0.00
-

0.00
-

0.00%

02
02.01
02.01.01

1,361.42

2.59

0.00%

ARQUITECTURA
MUROS Y TABIQUES DE ALBAILERIA
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4

M2

305.06

16.82

5,131.11

Valor. Mensual SP3

0.00%

11.84
56,359.67
5,131.11
5,131.11

305.06

Pgina 3

VALORIZACION N 03 - MES DE JULIO


SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA

Nombre del Proyecto :


Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

02.02

REVOQUES ENLUCIDOS Y DERRAMES

Costo
Parcial
(S/.)

Anterior
Metrado

Metrado

Monto Valorizado
S/.

0.00
-

0.00%
0.00%

60.00

22,070.08
589.80

5,058.69

0.00%

411.61

5,058.69

2,672.83

0.00%

217.48

2,672.83

19.47

3,356.43

0.00%

172.39

3,356.43

359.42

21.41

7,695.18

0.00%

359.42

7,695.18

M2

17.31

18.32

317.12

0.00%

17.31

317.12

TARRAJEO C/IMPERMEABILIZANTE

M2

67.27

16.82

1,131.48

0.00%

67.27

1,131.48

DERRAMES E=15 cm (MORTERO 1:5)

ML

233.81

5.34

1,248.55

0.00%

233.81

1,248.55

5,377.45

0.00
-

0.00
-

0.00%

0.00
-

364.82

5,377.45
5,377.45

60.00

9.83

589.80

02.02.02

TARRAJEO EN INTERIORES (MORTERO 1:5)

M2

411.61

12.29

02.02.03

TARRAJEO EN EXTERIORES (MORTERO 1:5)

M2

217.48

12.29

02.02.04

TARRAJEO EN COLUMNAS (MORTERO 1:5)

M2

172.39

02.02.05

TARRAJEO EN VIGAS (MORTERO 1:5)

M2

02.02.06

TARRAJEO EN PLACAS (MORTERO 1:5)

02.02.07

02.04

Monto
Valorizado S/.

Saldo

M2

02.03.01

Metrado

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

0.00
-

TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)

02.03

Monto Valorizado
S/.

Acumulado

0.00
-

22,070.08

02.02.01

02.02.08

Avance
Actual

CIELORRASOS
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA

M2

364.82

14.74

PISOS Y PAVIMENTOS

5,377.45

0.00%

CONTRAPISO DE 48 mm, MEZCLA 1:5

M2

230.20

9.08

2,090.22

0.00
-

0.00
-

0.00
-

0.00%

02.04.01

0.00%

230.20

8,722.43
2,090.22

02.04.02

PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM

M2

229.20

14.74

3,378.41

0.00%

229.20

3,378.41

02.04.03

PISO DE CEMENTO PULIDO BRUADO

M2

172.25

18.89

3,253.80

0.00%

172.25

3,253.80

2,117.40

0.00
-

0.00%

0.00
-

0.00%

60.00

2,117.40
737.40
831.66

02.05

8,722.43

ZOCALOS Y CONTRAZOCALOS

02.05.01

ZOCALO DE CERAMICO 20 x 30 CM

M2

60.00

12.29

737.40

0.00
-

02.05.02

CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm

ML

93.55

8.89

831.66

0.00%

93.55

02.05.03

CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM

ML

74.10

7.40

548.34

0.00%

74.10

548.34

0.00
-

0.00
-

0.00%
43.10

1,480.80
1,149.05

02.06

REVESTIMIENTOS DE GRADAS Y ESCALERAS

02.06.01

REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO

ML

43.10

26.66

1,149.05

0.00
-

02.06.02

REVESTIMIENTO DE DESCANSOS DE CEMENTO

M2

1.35

14.74

19.90

0.00%

1.35

19.90

02.06.03

REVESTIMIENTO DE RAMPAS DE CEMENTO

M2

19.80

15.75

311.85

0.00%

19.80

311.85

231.58
7.98

29.02

0.00
-

0.00
-

0.00
-

0.00%

M2

7.98

231.58
231.58

0.00%

1,526.86
-

02.07
02.07.01
02.08

1,480.80

CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA (INC. PUERTA/M2)
CARPINTERIA METALICA Y HERRERIA

231.58
1,526.86

0.00
-

0.00
-

0.00
-

#DIV/0!

62.42

0.00

0.00

#DIV/0!

26.76

99.04

629.89

0.00%

6.36

629.89

0.00%

42.35

896.97

0.00
-

0.00%

0.00
-

0.00%

32.00

203.38
33.92

0.00%

3.00

63.54

VENTANA DE ALUMINIO C/TUBO 3 1/4" x 1 1/2" INC. NAVES, BRAZO, BURDETE Y CIERRE

M2

62.42

02.08.02

MAMPARA C/ESTRUCTURA DE ALUMINIO 3 1/4"x2"

M2

26.76

02.08.03

PUERTA METALICA (INC. PUERTA/M2)

M2

6.36

BARANDA EN ESCALERA C/TUBO 2" Y 1"

ML

42.35

21.18

896.97
203.38

02.09

0.00%

0.00

02.08.01

02.08.04

0.00%

0.00

CERRAJERIA

02.09.01

BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4"

UN

32.00

1.06

33.92

0.00
-

02.09.02

CERRADURA PARCHE 2 GOLPES

UN

3.00

21.18

63.54

Valor. Mensual SP3

Pgina 4

VALORIZACION N 03 - MES DE JULIO


SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA

Nombre del Proyecto :


Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

02.09.03
02.10

CERRADURA DE PERILLA LIVIANA

UN

4.00

26.48

VIDRIOS, CRISTALES Y SIMILARES

Costo
Parcial
(S/.)

Anterior
Metrado

105.92
2,331.07

02.10.01

VIDRIO TEMPLADO DE 6MM

M2

63.32

30.40

1,924.93

02.10.02

VIDRIO TEMPLADO DE 10MM

M2

26.72

15.20

406.14

02.11

PINTURA

Avance
Actual
Metrado

Monto
Valorizado S/.

Metrado

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

0.00%

0.00
-

0.00
-

0.00%

0.00
-

0.00
-

0.00
-

0.00%

Saldo
Monto Valorizado
S/.

4.00

105.92

0.00%

63.32

2,331.07
1,924.93

0.00%

26.72

406.14
6,619.17
1,546.84

02.11.01

PINTURA EN CIELORASOS AL LATEX

M2

364.82

4.24

1,546.84

0.00
-

0.00%

364.82

02.11.02

PINTURA EN COLUMNAS AL LATEX

M2

172.39

3.53

608.54

0.00%

172.39

608.54

02.11.03

PINTURA EN VIGAS AL LATEX

M2

359.42

3.53

1,268.75

0.00%

359.42

1,268.75

02.11.04

PINTURA EN MUROS INTERIORES AL LATEX

M2

411.61

3.53

1,452.98

0.00%

411.61

1,452.98

02.11.05

PINTURA EN MUROS EXTERIORES AL LATEX

M2

217.48

3.53

767.70

0.00%

217.48

767.70

02.11.06

PINTURA LATEX EN DERRAMES DE A=15CM.

ML

233.81

2.36

551.79

0.00%

233.81

551.79

02.11.07

PINTURA EN CONTRAZOCALO C/ESMALTE H=0.20 M

ML

93.55

0.74

69.23

0.00%

93.55

69.23

02.11.08

PINTURA EN CARPINTERIA DE MADERA CON BARNIZ

M2

15.96

4.91

78.36

0.00%

15.96

78.36

02.11.09

PINTURA EN CARPINTERIA METALICA C/ESMALTE

M2

12.73

5.90

75.11

0.00%

12.73

75.11

02.11.10

PINTURA EN BARANDAS C/ESMALTE

ML

135.05

1.48

199.87

0.00%

135.05

199.87

548.34
ML

6.00

1.32

7.92

0.00
-

0.00
-

0.00
-

0.00%

JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.

02.12.02

SEALIZACION

UN

1.00

0.00

0.00

#DIV/0!

1.00

02.12.03

TURBA Y PREPARACION DE SUSTRATO AGRICOLA

M3

14.22

18.89

268.62

0.00%

14.22

268.62

FLORES

UN

60.00

4.53

60.00

02.12
02.12.01

02.12.04
03
03.01

6,619.17

Monto Valorizado
S/.

Acumulado

VARIOS, LIMPIEZA Y JARDINERIA

INSTALACIONES SANITARIAS
APARATOS Y ACCESORIOS SANITARIOS

03.01.01

INODORO TOP PICCE C/FLUXOMETRO

03.01.02
03.01.03

3,520.70

0.00

0.00

560.69

0.00
-

0.00
-

271.80

0.00%

0.00

0.00%

0.00
-

0.00%

UN

2.00

49.15

98.30

LAVATORIO DE LOZA BLANCA 20"X16"

UN

3.00

62.99

188.97

URINARIOS DE LOZA DE PICO BLANCO

PZA

1.00

0.00

0.00

03.01.04

LAVADERO DE ACERO INOXIDABLE, 01 P0ZA C/ESCURRIDERO+ACCES.

UN

2.00

62.99

125.98

03.01.05

LLAVE CROMADO 1/2" PARA LAVATORIO

UN

3.00

13.24

39.72

03.01.06

LLAVE TIPO CUELLO DE CISNE CROMADO DE 1/2"

UN

2.00

47.24

94.48

03.01.07

LLAVE CROMADO PARA URINARIO

UN

1.00

13.24

13.24

03.02

SISTEMA DE DESAGUE

1,658.82

0.00%

548.34
7.92

6.00

271.80
3,520.70
560.69
98.30

0.00%

2.00

0.00%

3.00

#DIV/0!

1.00

0.00%

2.00

125.98

0.00%

3.00

39.72

0.00%

2.00

94.48

0.00%

1.00

0.00
-

0.00
-

0.00%

188.97

13.24

03.02.01

SALIDA DE DESAGUE PVC D=4"

PTO

2.00

47.24

94.48

0.00
-

0.00%

2.00

1,658.82
94.48

03.02.02

SALIDA DE DESAGUE PVC D=2"

PTO

6.00

47.24

283.44

0.00%

6.00

283.44

03.02.03

SALIDA DE VENTILACION PVC D=2"

PTO

2.00

47.24

94.48

0.00%

2.00

94.48

03.02.04

REGISTROS DE BRONCE 4"

UN

3.00

24.57

73.71

0.00%

3.00

73.71

03.02.05

SUMIDEROS DE 2"

UN

5.00

24.57

122.85

0.00%

5.00

122.85

Valor. Mensual SP3

Pgina 5

VALORIZACION N 03 - MES DE JULIO


SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA

Nombre del Proyecto :


Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

Costo
Parcial
(S/.)

Avance
Actual

Anterior
Metrado

Monto Valorizado
S/.

Metrado

Acumulado

Monto
Valorizado S/.

Metrado

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

Saldo
Monto Valorizado
S/.

03.02.06

TUBERIA DE PVC SAL 4"

ML

14.21

13.60

193.26

0.00%

14.21

193.26

03.02.07

TUBERIA DE PVC SAL 2"

ML

23.90

13.60

325.04

0.00%

23.90

325.04

03.02.08

YEE PVC SAL 4"

PZA

1.00

13.24

13.24

0.00%

1.00

13.24

03.02.09

YEE PVC SAL 2"

PZA

5.00

13.24

66.20

0.00%

5.00

66.20

03.02.10

YEE PVC SAL 4" x 2"

PZA

2.00

13.24

26.48

0.00%

2.00

26.48

03.02.11

TEE PVC SAL 2"

PZA

5.00

13.24

66.20

0.00%

5.00

66.20

03.02.12

CODO PVC SAL 2"X45

PZA

2.00

13.24

26.48

0.00%

2.00

26.48

03.02.13

CODO PVC SAL 4" x 45

UN

2.00

13.24

26.48

0.00%

2.00

26.48

03.02.14

REDUCCION PVC SAL 4" A 2"

PZA

4.00

13.24

52.96

0.00%

4.00

52.96

03.02.15

CAJA DE REGISTRO DE 12" X 24"

UN

1.00

193.52

193.52

0.00%

1.00

193.52

671.64
8.00

36.86

294.88

0.00
-

0.00
-

0.00
-

0.00%

PTO

0.00%

8.00

671.64
294.88

03.03

SISTEMA DE AGUA FRIA

03.03.01

SALIDA DE AGUA FRIA DE 1/2"

03.03.02

TUBERIA PVC CLASE 10 DE 1/2"

ML

17.80

6.30

112.14

0.00%

17.80

112.14

03.03.03

CODO PVC SAP 1/2" x 90

UN

11.00

13.24

145.64

0.00%

11.00

145.64

03.03.04

TEE PVC SAP 1/2"

UN

4.00

13.24

52.96

0.00%

4.00

52.96

03.03.05

VALVULAS DE COMPUERTA DE BRONCE DE 1/2"

UN

2.00

33.01

66.02

0.00%

2.00

66.02

0.00
-

0.00%

0.00
-

0.00%

41.40

629.55
391.23

0.00%

18.00

0.00

0.00%

03.04

SISTEMA DE AGUA DE LLUVIA

03.04.01

TUBERIA PVC SAL 4" D/PLUVIAL

ML

41.40

9.45

391.23

0.00
-

03.04.02

CODO PVC SAL 4" x 90

UN

18.00

13.24

238.32

7,209.76

0.00

0.00

2,240.53

04
04.01

629.55

INSTALACIONES ELECTRICAS
INSTALACIONES ELECTRICAS Y MECANICAS
26.16

889.44

0.00
-

0.00
-

0.00
-

0.00%

34.00

PTO

3.00

41.04

123.12

PTO

18.00

26.71

480.78

SALIDA PARA INTERRUPTOR SIMPLE

PTO

9.00

6.62

59.58

04.01.05

SALIDA PARA INTERRUPTOR DOBLE

PTO

3.00

6.62

19.86

04.01.06

SALIDA P/TOMACORRIENTE DOBLE, CON LINEA TIERRA

PTO

21.00

26.71

560.91

SALIDA P/TOMACORRIENTE DOBLE, C/ LINEA TIERRA P/AGUA

PTO

4.00

26.71

04.01.01

SALIDA PARA CENTRO DE LUZ

PTO

04.01.02

SALIDA DE PARED (BRAQUETES) CON PVC

04.01.03

SALIDA P/TOMACORRIENTE SIMPLE PARA LUZ DE EMERGENCIA

04.01.04

04.01.07
04.02
04.02.01
04.03
04.03.01
04.03.02
04.04
04.04.01

CANALIZACIONES, CONDUCTOS O TUBERIAS


TUBO 20MM D' PVC SEL

106.84
1,284.12

ML

626.40

2.05

CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS

1,284.12
2,211.19

CABLE NH - 80 2 x 4 + 1x4 MM2

ML

338.40

3.53

1,194.55

CABLE NH - 80 2 x 2.5 MM2

ML

288.00

3.53

1,016.64

ARTEFACTOS ELECTRICOS
ARTEFACTO FLUORESCENTE 2/36W +CAJA C/REJILLA

910.44
UN

24.00

23.62

566.88

Valor. Mensual SP3

238.32
7,209.76

34.00

2,240.53
889.44

0.00%

3.00

123.12

0.00%

18.00

480.78

0.00%

9.00

59.58

0.00%

3.00

19.86

0.00%

21.00

560.91

0.00%

4.00

0.00%

0.00%

0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.00%

0.00
-

0.00
-

0.00
-

106.84

626.40

1,284.12
1,284.12

0.00%

338.40

2,211.19
1,194.55

0.00%

288.00

1,016.64

0.00
-

0.00%

0.00%

0.00%

910.44
566.88

24.00

Pgina 6

VALORIZACION N 03 - MES DE JULIO


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

SUSTITUCION Y MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO "SANTA ROSA"-DISTRITO DE HUACHOCOLPA, HUANCAVELICA-TAYACAJA


CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL
MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Y ALMACEN GENERAL

240 DIAS

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Fecha de Inicio :

01/ MAYO / 2,013

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Fecha de termino :

26 / DICIEMBRE / 2,013

Supervisor

Arq. Hugo Abel Villaverde Rafael

Lugar :

HUACHOCOLPA

Fecha de la valorizacin

01 / AGOSTO / 2,013

Ejecuta :

Costo

tem

Partidas

Und. Metrado Unitario


(S/.)

Costo
Parcial
(S/.)

Avance
Actual

Anterior
Metrado

Monto Valorizado
S/.

Metrado

Acumulado

Monto
Valorizado S/.

Metrado

Porcentaje
(%)
Monto Valorizado
Metrado
S/.

Saldo
Monto Valorizado
S/.

04.04.02

ARTEFACTO FLUORESCENTE 4 x 18 W C/EQ

UN

6.00

23.62

141.72

0.00%

6.00

141.72

04.04.03

ARTEFACTO BRAQUET GLOBO

UN

3.00

33.64

100.92

0.00%

3.00

100.92

04.04.04

ARTEFACTO SPOT-LIGHT C/DOBLE LAMPARA AHORRADOR

UN

3.00

33.64

100.92

0.00%

3.00

100.92

0.00
-

0.00
-

0.00%

21.18

0.00
-

0.00%

1.00

21.18

0.00%

1.00

21.18

0.00
-

0.00
-

0.00%

0.00
-

2.00

521.12
521.12

04.05

TABLEROS DE DISTRIBUCION

42.36

04.05.01

TABLERO GENERAL 4

UN

1.00

21.18

04.05.02

TABLERO DISTRIBUCION 41

UN

1.00

21.18

04.06
04.06.01

EQUIPOS ELECTRICOS Y MECANICOS

521.12

POZO A TIERRA C/C CU 16MM2 CC

UN

COSTO DIRECTO TOTAL

2.00

260.56

S/.

521.12

124,238.09

S/.

13,435.15
10.81%
Avance Anterior

Valor. Mensual SP3

S/.

504.34
0.41%
Avance Actual

S/.

13,939.49

0.00%

11.22%

S/.

42.36
21.18

110,298.60

11.22%
Avance acumulado

88.78%
Por ejecutar

Pgina 7

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL

Ejecuta :

MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

91,933.43
ESTRUCTURAS
01
TRABAJOS PRELIMINARES
01.01
LIMPIEZA DEL TERRENO MANUAL
01.01.01
TRAZO Y REPLANTEO PRELIMINAR
01.01.02
TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO
01.01.03
MOVIMIENTO DE TIERRAS
01.02
EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO
01.02.01
EXCAV. MANUAL DE ZANJAS HASTA 1.40 M
01.02.02
EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA
01.02.03
EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS
01.02.04
RELLENO CON MATERIAL PROPIO
01.02.05
REFINE, NIVELACION Y COMPACTACION
01.02.06
RELLENO CON MATERIAL CLASIFICADO E=10 CM
01.02.07
ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.
01.02.08
ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km
01.02.09
CONCRETO SIMPLE
01.03
SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12
01.03.01
CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G
01.03.02
SOBRECIMIENTO CONCRETO 1:8+25% PM
01.03.03
SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m
01.03.04
FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)
01.03.05
VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL
01.03.06
VEREDA ENCOFRADO Y DESENCOFRADO
01.03.07
SARDINELES CONCRETO FC=175 KG/CM2
01.03.08
SARDINELES ENCOFRADO Y DESENCOFRADO
01.03.09
CONCRETO ARMADO
01.04
ZAPATAS
01.04.01
ZAPATAS CONCRETO F'C=210 kg/cm2
01.04.01.01
ZAPATAS ACERO F'Y=4200 KG/CM2
01.04.01.02
COLUMNAS
01.04.02
COLUMNAS CONCRETO F'C=210 kg/cm2
01.04.02.01
COLUMNAS ENCOFRADO Y DESENCOFRADO
01.04.02.02
COLUMNAS ACERO F'C=4200 KG/CM2
01.04.02.03
PLACAS DE CONCRETO
01.04.03
PLACA DE CONCRETO F'c=210 Kg/Cm2
01.04.03.01
PLACA ENCOFRADO Y DESENCOFRADO
01.04.03.02
PLACA ACERO F'c=4200 Kg/Cm2
01.04.03.03
VIGAS
01.04.04
VIGAS CONCRETO F'C=210 kg/cm2
01.04.04.01
VIGAS ENCOFRADO Y DESENCOFRADO
01.04.04.02
VIGAS ACERO FY=4200 KG/CM2
01.04.04.03
LOSAS ALIGERADAS
01.04.05
LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2
01.04.05.01
LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm
01.04.05.02
LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm
01.04.05.03
LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO
01.04.05.04
LOSA ALIGERADA ACERO FY=4200 KG/CM2
01.04.05.05
LOSAS MACIZAS
01.04.06
LOSA MACIZA CONCRETO f'c=210 kg/cm2
01.04.06.01
LOSA MACIZA ENCOFRADO Y DESENCOFRADO
01.04.06.02
LOSA MACIZA ACERO FY=4200 KG/CM2
01.04.06.03
ESCALERAS
01.04.07
ESCALERAS CONCRETO f'c=210 kg/cm2
01.04.07.01
ESCALERAS ENCOFRADO Y DESENCOFRADO
01.04.07.02
ESCALERA ACERO FY=4200 KG/CM2
01.04.07.03
RAMPAS
01.04.08
RAMPAS CONCRETO FC=210 KG/CM2
01.04.08.01
RAMPAS ENCOFRADO Y DESENCOFRADO
01.04.08.02
RAMPAS ACERO FY=4200 KG/CM2
01.04.08.03
DETALLES
01.04.09

Mano de obra 100 %

M2
M2
M2

217.29
217.29
217.29

M3
M3
M3
M3
M3
M2
M2
M3
M3

19.91
146.76
2.35
0.18
92.95
214.45
214.45
95.30
95.30

M2
M3
M3
M2
M2
M2
M2
M3
M2

91.72
27.67
3.91
52.18
160.65
53.80
16.27
3.88
31.02

M3
KG

56.49
1,323.67

M3
M2
KG

24.14
206.99
3,833.10

69.63
16.51

M3
M2
KG

2.33
23.30
161.11

139.26
24.76
0.79

M3
M2
KG

44.10
351.91
5,365.69

77.48
17.48
0.79

M3
M2
M2
M2
KG

30.95
208.72
156.10
364.82
1,713.28

59.94
7.20
7.20
14.68
0.79

M3
M2
KG

2.92
14.61
366.79

61.33
14.86
0.79

M3
M2
KG

0.84
16.35
145.16

56.72
39.61
0.79

M3
M2
KG

2.59
19.80
125.22

119.46
28.30
0.79

27.68
27.68

69.17
18.17
9.57
17.39
16.51
87.04
11.99

91,933.43
40,407.07
0.00
0.00
0.00
0.00
70.03
0.00
0.00
65.05
4.98
0.00
0.00
0.00
0.00
0.00
4,669.83
0.00
0.00
270.45
948.11
1,537.42
935.58
268.62
337.72
371.93
34,305.79
0.00
0.00
0.00
5,098.27
1,680.87
3,417.40
0.00
1,028.67
324.48
576.91
127.28
13,807.16
3,416.87
6,151.39
4,238.90
11,190.89
1,855.14
1,502.78
1,123.92
5,355.56
1,353.49
685.94
179.08
217.10
289.76
809.94
47.64
647.62
114.68
968.66
309.40
560.34
98.92
716.26

Pgina 8

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL

Ejecuta :

MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

DETALLES CONCRETO F'C= 175KG/CM2


01.04.09.01
DETALLES ENCOFRADO Y DESENCOFRADO
01.04.09.02
ESTRUCTURA DE MADERA Y COBERTURA
01.05
CORREAS DE MADERA 2" x 2"
01.05.01
COBERTURA TEJA ANDINA (0.72x1.14)
01.05.02
CUMBRERA TEJA ANDINA
01.05.03
LIMATESA TEJA ANDINA
01.05.04
ARQUITECTURA
02
MUROS Y TABIQUES DE ALBAILERIA
02.01
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4
02.01.01
REVOQUES ENLUCIDOS Y DERRAMES
02.02
TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)
02.02.01
TARRAJEO EN INTERIORES (MORTERO 1:5)
02.02.02
TARRAJEO EN EXTERIORES (MORTERO 1:5)
02.02.03
TARRAJEO EN COLUMNAS (MORTERO 1:5)
02.02.04
TARRAJEO EN VIGAS (MORTERO 1:5)
02.02.05
TARRAJEO EN PLACAS (MORTERO 1:5)
02.02.06
TARRAJEO C/IMPERMEABILIZANTE
02.02.07
DERRAMES E=15 cm (MORTERO 1:5)
02.02.08
CIELORRASOS
02.03
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
02.03.01
PISOS Y PAVIMENTOS
02.04
CONTRAPISO DE 48 mm, MEZCLA 1:5
02.04.01
PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM
02.04.02
PISO DE CEMENTO PULIDO BRUADO
02.04.03
ZOCALOS Y CONTRAZOCALOS
02.05
ZOCALO DE CERAMICO 20 x 30 CM
02.05.01
CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm
02.05.02
CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM
02.05.03
REVESTIMIENTOS DE GRADAS Y ESCALERAS
02.06
REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO
02.06.01
REVESTIMIENTO DE DESCANSOS DE CEMENTO
02.06.02
REVESTIMIENTO DE RAMPAS DE CEMENTO
02.06.03
CARPINTERIA DE MADERA
02.07
PUERTA APANELADA DE MADERA (INC. PUERTA/M2)
02.07.01
CARPINTERIA METALICA Y HERRERIA
02.08
VENTANA DE ALUMINIO C/TUBO 3 1/4" x 1 1/2" INC. NAVES, BRAZO, BURDETE Y CIERRE
02.08.01
MAMPARA C/ESTRUCTURA DE ALUMINIO 3 1/4"x2"
02.08.02
PUERTA METALICA (INC. PUERTA/M2)
02.08.03
BARANDA EN ESCALERA C/TUBO 2" Y 1"
02.08.04
CERRAJERIA
02.09
BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4"
02.09.01
CERRADURA PARCHE 2 GOLPES
02.09.02
CERRADURA DE PERILLA LIVIANA
02.09.03
VIDRIOS, CRISTALES Y SIMILARES
02.10
VIDRIO TEMPLADO DE 6MM
02.10.01
VIDRIO TEMPLADO DE 10MM
02.10.02
PINTURA
02.11
PINTURA EN CIELORASOS AL LATEX
02.11.01
PINTURA EN COLUMNAS AL LATEX
02.11.02
PINTURA EN VIGAS AL LATEX
02.11.03
PINTURA EN MUROS INTERIORES AL LATEX
02.11.04
PINTURA EN MUROS EXTERIORES AL LATEX
02.11.05
PINTURA LATEX EN DERRAMES DE A=15CM.
02.11.06
PINTURA EN CONTRAZOCALO C/ESMALTE H=0.20 M
02.11.07
PINTURA EN CARPINTERIA DE MADERA CON BARNIZ
02.11.08
PINTURA EN CARPINTERIA METALICA C/ESMALTE
02.11.09
PINTURA EN BARANDAS C/ESMALTE
02.11.10
VARIOS, LIMPIEZA Y JARDINERIA
02.12
JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.
02.12.01
SEALIZACION
02.12.02
TURBA Y PREPARACION DE SUSTRATO AGRICOLA
02.12.03

Mano de obra 100 %

Metrado

Costo
Unitario
(S/.)

M3
M2

1.05
23.65

44.72
28.30

ML
M2
ML
ML

244.30
232.50
21.45
16.00

2.72
2.81
1.48
0.74

M2

305.06

16.82

M2
M2
M2
M2
M2
M2
M2
ML

60.00
411.61
217.48
172.39
359.42
17.31
67.27
233.81

9.83
12.29
12.29
19.47
21.41
18.32
16.82
5.34

M2

364.82

14.74

M2
M2
M2

230.20
229.20
172.25

9.08
14.74
18.89

M2
ML
ML

60.00
93.55
74.10

12.29
8.89
7.40

ML
M2
M2

43.10
1.35
19.80

26.66
14.74
15.75

M2

7.98

M2
M2
M2
ML

62.42
26.76
6.36
42.35

UN
UN
UN

32.00
3.00
4.00

M2
M2

63.32
26.72

M2
M2
M2
M2
M2
ML
ML
M2
M2
ML

364.82
172.39
359.42
411.61
217.48
233.81
93.55
15.96
12.73
135.05

4.24
3.53
3.53
3.53
3.53
2.36
0.74
4.91
5.90
1.48

ML
UN
M3

6.00
1.00
14.22

1.32

Costo
Parcial
(S/.)

46.96
669.30
1,361.42
664.50
653.33
31.75
11.84
51,526.36
5,131.11
5,131.11
22,070.08
589.80
5,058.69
2,672.83
3,356.43
7,695.18
317.12
1,131.48
1,248.55
5,377.45
5,377.45
8,722.43
2,090.22
3,378.41
3,253.80
2,117.40
737.40
831.66
548.34
1,480.80
1,149.05
19.90
311.85
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
6,619.17
1,546.84
608.54
1,268.75
1,452.98
767.70
551.79
69.23
78.36
75.11
199.87
7.92
7.92
0.00
0.00

Pgina 9

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL

Ejecuta :

MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

02.12.04
03
03.01
03.01.01
03.01.02
03.01.03
03.01.04
03.01.05
03.01.06
03.01.07
03.02
03.02.01
03.02.02
03.02.03
03.02.04
03.02.05
03.02.06
03.02.07
03.02.08
03.02.09
03.02.10
03.02.11
03.02.12
03.02.13
03.02.14
03.02.15
03.03
03.03.01
03.03.02
03.03.03
03.03.04
03.03.05
03.04
03.04.01
03.04.02
04
04.01
04.01.01
04.01.02
04.01.03
04.01.04
04.01.05
04.01.06
04.01.07
04.02
04.02.01
04.03
04.03.01
04.03.02
04.04
04.04.01
04.04.02
04.04.03
04.04.04
04.05
04.05.01
04.05.02
04.06
04.06.01

Partidas

Und.

FLORES
INSTALACIONES SANITARIAS
APARATOS Y ACCESORIOS SANITARIOS
INODORO TOP PICCE C/FLUXOMETRO
LAVATORIO DE LOZA BLANCA 20"X16"
URINARIOS DE LOZA DE PICO BLANCO
LAVADERO DE ACERO INOXIDABLE, 01 P0ZA C/ESCURRIDERO+ACCES.
LLAVE CROMADO 1/2" PARA LAVATORIO
LLAVE TIPO CUELLO DE CISNE CROMADO DE 1/2"
LLAVE CROMADO PARA URINARIO
SISTEMA DE DESAGUE
SALIDA DE DESAGUE PVC D=4"
SALIDA DE DESAGUE PVC D=2"
SALIDA DE VENTILACION PVC D=2"
REGISTROS DE BRONCE 4"
SUMIDEROS DE 2"
TUBERIA DE PVC SAL 4"
TUBERIA DE PVC SAL 2"
YEE PVC SAL 4"
YEE PVC SAL 2"
YEE PVC SAL 4" x 2"
TEE PVC SAL 2"
CODO PVC SAL 2"X45
CODO PVC SAL 4" x 45
REDUCCION PVC SAL 4" A 2"
CAJA DE REGISTRO DE 12" X 24"
SISTEMA DE AGUA FRIA
SALIDA DE AGUA FRIA DE 1/2"
TUBERIA PVC CLASE 10 DE 1/2"
CODO PVC SAP 1/2" x 90
TEE PVC SAP 1/2"
VALVULAS DE COMPUERTA DE BRONCE DE 1/2"
SISTEMA DE AGUA DE LLUVIA
TUBERIA PVC SAL 4" D/PLUVIAL
CODO PVC SAL 4" x 90
INSTALACIONES ELECTRICAS
INSTALACIONES ELECTRICAS Y MECANICAS
SALIDA PARA CENTRO DE LUZ
SALIDA DE PARED (BRAQUETES) CON PVC
SALIDA P/TOMACORRIENTE SIMPLE PARA LUZ DE EMERGENCIA
SALIDA PARA INTERRUPTOR SIMPLE
SALIDA PARA INTERRUPTOR DOBLE
SALIDA P/TOMACORRIENTE DOBLE, CON LINEA TIERRA
SALIDA P/TOMACORRIENTE DOBLE, C/ LINEA TIERRA P/AGUA
CANALIZACIONES, CONDUCTOS O TUBERIAS
TUBO 20MM D' PVC SEL
CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS
CABLE NH - 80 2 x 4 + 1x4 MM2
CABLE NH - 80 2 x 2.5 MM2
ARTEFACTOS ELECTRICOS
ARTEFACTO FLUORESCENTE 2/36W +CAJA C/REJILLA
ARTEFACTO FLUORESCENTE 4 x 18 W C/EQ
ARTEFACTO BRAQUET GLOBO
ARTEFACTO SPOT-LIGHT C/DOBLE LAMPARA AHORRADOR
TABLEROS DE DISTRIBUCION
TABLERO GENERAL 4
TABLERO DISTRIBUCION 41
EQUIPOS ELECTRICOS Y MECANICOS
POZO A TIERRA C/C CU 16MM2 CC
COSTO DIRECTO TOTAL

Mano de obra 100 %

Metrado

UN

60.00

UN
UN
PZA
UN
UN
UN
UN

2.00
3.00
1.00
2.00
3.00
2.00
1.00

PTO
PTO
PTO
UN
UN
ML
ML
PZA
PZA
PZA
PZA
PZA
UN
PZA
UN

2.00
6.00
2.00
3.00
5.00
14.21
23.90
1.00
5.00
2.00
5.00
2.00
2.00
4.00
1.00

PTO
ML
UN
UN
UN

8.00
17.80
11.00
4.00
2.00

ML
UN

41.40
18.00

PTO
PTO
PTO
PTO
PTO
PTO
PTO

34.00
3.00
18.00
9.00
3.00
21.00
4.00

ML

626.40

ML
ML

338.40
288.00

UN
UN
UN
UN

24.00
6.00
3.00
3.00

UN
UN

1.00
1.00

UN

2.00

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
S/.

91,933.43

Pgina 10

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL

Ejecuta :

MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Mano de obra 100 %

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

Pgina 11

Mano de obra 100 %

Pgina 12

Mano de obra 100 %

Pgina 13

Mano de obra 100 %

Pgina 14

Mano de obra 100 %

Pgina 15

COSTO REAL DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

65,691.98
ESTRUCTURAS
01
TRABAJOS PRELIMINARES
01.01
LIMPIEZA DEL TERRENO MANUAL
01.01.01
TRAZO Y REPLANTEO PRELIMINAR
01.01.02
TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO
01.01.03
MOVIMIENTO DE TIERRAS
01.02
EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO
01.02.01
EXCAV. MANUAL DE ZANJAS HASTA 1.40 M
01.02.02
EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA
01.02.03
EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS
01.02.04
RELLENO CON MATERIAL PROPIO
01.02.05
REFINE, NIVELACION Y COMPACTACION
01.02.06
RELLENO CON MATERIAL CLASIFICADO E=10 CM
01.02.07
ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.
01.02.08
ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km
01.02.09
CONCRETO SIMPLE
01.03
SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12
01.03.01
CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G
01.03.02
SOBRECIMIENTO CONCRETO 1:8+25% PM
01.03.03
SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m
01.03.04
FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)
01.03.05
VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL
01.03.06
VEREDA ENCOFRADO Y DESENCOFRADO
01.03.07
SARDINELES CONCRETO FC=175 KG/CM2
01.03.08
SARDINELES ENCOFRADO Y DESENCOFRADO
01.03.09
CONCRETO ARMADO
01.04
ZAPATAS
01.04.01
ZAPATAS CONCRETO F'C=210 kg/cm2
01.04.01.01
ZAPATAS ACERO F'Y=4200 KG/CM2
01.04.01.02
COLUMNAS
01.04.02
COLUMNAS CONCRETO F'C=210 kg/cm2
01.04.02.01
COLUMNAS ENCOFRADO Y DESENCOFRADO
01.04.02.02
COLUMNAS ACERO F'C=4200 KG/CM2
01.04.02.03
PLACAS DE CONCRETO
01.04.03
PLACA DE CONCRETO F'c=210 Kg/Cm2
01.04.03.01
PLACA ENCOFRADO Y DESENCOFRADO
01.04.03.02
PLACA ACERO F'c=4200 Kg/Cm2
01.04.03.03
VIGAS
01.04.04
VIGAS CONCRETO F'C=210 kg/cm2
01.04.04.01
VIGAS ENCOFRADO Y DESENCOFRADO
01.04.04.02
VIGAS ACERO FY=4200 KG/CM2
01.04.04.03
LOSAS ALIGERADAS
01.04.05
LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2
01.04.05.01
LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm
01.04.05.02
LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm
01.04.05.03
LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO
01.04.05.04
LOSA ALIGERADA ACERO FY=4200 KG/CM2
01.04.05.05
LOSAS MACIZAS
01.04.06
LOSA MACIZA CONCRETO f'c=210 kg/cm2
01.04.06.01
LOSA MACIZA ENCOFRADO Y DESENCOFRADO
01.04.06.02
LOSA MACIZA ACERO FY=4200 KG/CM2
01.04.06.03
ESCALERAS
01.04.07
ESCALERAS CONCRETO f'c=210 kg/cm2
01.04.07.01
ESCALERAS ENCOFRADO Y DESENCOFRADO
01.04.07.02
ESCALERA ACERO FY=4200 KG/CM2
01.04.07.03
RAMPAS
01.04.08
RAMPAS CONCRETO FC=210 KG/CM2
01.04.08.01
RAMPAS ENCOFRADO Y DESENCOFRADO
01.04.08.02
RAMPAS ACERO FY=4200 KG/CM2
01.04.08.03
DETALLES
01.04.09

Mano de obra 77 %

M2
M2
M2

217.29
217.29
217.29

M3
M3
M3
M3
M3
M2
M2
M3
M3

19.91
146.76
2.35
0.18
92.95
214.45
214.45
95.30
95.30

M2
M3
M3
M2
M2
M2
M2
M3
M2

91.72
27.67
3.91
52.18
160.65
53.80
16.27
3.88
31.02

M3
KG

56.49
1,323.67

M3
M2
KG

24.14
206.99
3,833.10

53.62
12.71

M3
M2
KG

2.33
23.30
161.11

107.23
19.07
0.61

M3
M2
KG

44.10
351.91
5,365.69

59.66
13.46
0.61

M3
M2
M2
M2
KG

30.95
208.72
156.10
364.82
1,713.28

46.15
5.54
5.54
11.30
0.61

M3
M2
KG

2.92
14.61
366.79

47.22
11.44
0.61

M3
M2
KG

0.84
16.35
145.16

43.67
30.50
0.61

M3
M2
KG

2.59
19.80
125.22

91.98
21.79
0.61

21.31
21.31

53.26
13.99
7.37
13.39
12.71
67.02
9.23

65,691.98
31,113.46
0.00
0.00
0.00
0.00
53.93
0.00
0.00
50.09
3.84
0.00
0.00
0.00
0.00
0.00
3,595.78
0.00
0.00
208.25
730.05
1,183.81
720.40
206.84
260.04
286.39
26,415.47
0.00
0.00
0.00
3,925.67
1,294.27
2,631.40
0.00
792.07
249.85
444.22
98.00
10,631.51
2,630.99
4,736.57
3,263.95
8,616.99
1,428.46
1,157.14
865.42
4,123.78
1,042.19
528.18
137.89
167.17
223.12
623.66
36.69
498.67
88.30
745.87
238.24
431.46
76.17
551.52

Pgina 16

COSTO REAL DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

DETALLES CONCRETO F'C= 175KG/CM2


01.04.09.01
DETALLES ENCOFRADO Y DESENCOFRADO
01.04.09.02
ESTRUCTURA DE MADERA Y COBERTURA
01.05
CORREAS DE MADERA 2" x 2"
01.05.01
COBERTURA TEJA ANDINA (0.72x1.14)
01.05.02
CUMBRERA TEJA ANDINA
01.05.03
LIMATESA TEJA ANDINA
01.05.04
ARQUITECTURA
02
MUROS Y TABIQUES DE ALBAILERIA
02.01
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4
02.01.01
REVOQUES ENLUCIDOS Y DERRAMES
02.02
TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)
02.02.01
TARRAJEO EN INTERIORES (MORTERO 1:5)
02.02.02
TARRAJEO EN EXTERIORES (MORTERO 1:5)
02.02.03
TARRAJEO EN COLUMNAS (MORTERO 1:5)
02.02.04
TARRAJEO EN VIGAS (MORTERO 1:5)
02.02.05
TARRAJEO EN PLACAS (MORTERO 1:5)
02.02.06
TARRAJEO C/IMPERMEABILIZANTE
02.02.07
DERRAMES E=15 cm (MORTERO 1:5)
02.02.08
CIELORRASOS
02.03
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
02.03.01
PISOS Y PAVIMENTOS
02.04
CONTRAPISO DE 48 mm, MEZCLA 1:5
02.04.01
PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM
02.04.02
PISO DE CEMENTO PULIDO BRUADO
02.04.03
ZOCALOS Y CONTRAZOCALOS
02.05
ZOCALO DE CERAMICO 20 x 30 CM
02.05.01
CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm
02.05.02
CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM
02.05.03
REVESTIMIENTOS DE GRADAS Y ESCALERAS
02.06
REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO
02.06.01
REVESTIMIENTO DE DESCANSOS DE CEMENTO
02.06.02
REVESTIMIENTO DE RAMPAS DE CEMENTO
02.06.03
VARIOS, LIMPIEZA Y JARDINERIA
02.12
JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.
02.12.01
SEALIZACION
02.12.02
TURBA Y PREPARACION DE SUSTRATO AGRICOLA
02.12.03
FLORES
02.12.04
COSTO DIRECTO TOTAL

Mano de obra 77 %

Metrado

Costo
Unitario
(S/.)

M3
M2

1.05
23.65

34.43
21.79

ML
M2
ML
ML

244.30
232.50
21.45
16.00

2.09
2.16
1.14
0.57

M2

305.06

12.95

M2
M2
M2
M2
M2
M2
M2
ML

60.00
411.61
217.48
172.39
359.42
17.31
67.27
233.81

7.57
9.46
9.46
14.99
16.49
14.11
12.95
4.11

M2

364.82

11.35

M2
M2
M2

230.20
229.20
172.25

6.99
11.35
14.55

M2
ML
ML

60.00
93.55
74.10

9.46
6.85
5.70

ML
M2
M2

43.10
1.35
19.80

20.53
11.35
12.13

ML
UN
M3
UN

6.00
1.00
14.22
60.00

1.02

S/.

Costo
Parcial
(S/.)

36.16
515.36
1,048.28
511.66
503.06
24.44
9.12
34,578.52
3,950.95
3,950.95
16,993.96
454.15
3,895.19
2,058.08
2,584.45
5,925.29
244.18
871.24
961.38
4,140.63
4,140.63
6,716.27
1,609.47
2,601.37
2,505.43
1,630.40
567.80
640.38
422.22
1,140.21
884.77
15.32
240.12
6.10
6.10
0.00
0.00
0.00
65,691.98

Pgina 17

Mano de obra 77 %

Pgina 18

Mano de obra 77 %

Pgina 19

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

67,954.11
ESTRUCTURAS
01
TRABAJOS PRELIMINARES
01.01
LIMPIEZA DEL TERRENO MANUAL
01.01.01
TRAZO Y REPLANTEO PRELIMINAR
01.01.02
TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO
01.01.03
MOVIMIENTO DE TIERRAS
01.02
EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO
01.02.01
EXCAV. MANUAL DE ZANJAS HASTA 1.40 M
01.02.02
EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA
01.02.03
EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS
01.02.04
RELLENO CON MATERIAL PROPIO
01.02.05
REFINE, NIVELACION Y COMPACTACION
01.02.06
RELLENO CON MATERIAL CLASIFICADO E=10 CM
01.02.07
ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.
01.02.08
ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km
01.02.09
CONCRETO SIMPLE
01.03
SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12
01.03.01
CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G
01.03.02
SOBRECIMIENTO CONCRETO 1:8+25% PM
01.03.03
SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m
01.03.04
FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)
01.03.05
VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL
01.03.06
VEREDA ENCOFRADO Y DESENCOFRADO
01.03.07
SARDINELES CONCRETO FC=175 KG/CM2
01.03.08
SARDINELES ENCOFRADO Y DESENCOFRADO
01.03.09
CONCRETO ARMADO
01.04
ZAPATAS
01.04.01
ZAPATAS CONCRETO F'C=210 kg/cm2
01.04.01.01
ZAPATAS ACERO F'Y=4200 KG/CM2
01.04.01.02
COLUMNAS
01.04.02
COLUMNAS CONCRETO F'C=210 kg/cm2
01.04.02.01
COLUMNAS ENCOFRADO Y DESENCOFRADO
01.04.02.02
COLUMNAS ACERO F'C=4200 KG/CM2
01.04.02.03
PLACAS DE CONCRETO
01.04.03
PLACA DE CONCRETO F'c=210 Kg/Cm2
01.04.03.01
PLACA ENCOFRADO Y DESENCOFRADO
01.04.03.02
PLACA ACERO F'c=4200 Kg/Cm2
01.04.03.03
VIGAS
01.04.04
VIGAS CONCRETO F'C=210 kg/cm2
01.04.04.01
VIGAS ENCOFRADO Y DESENCOFRADO
01.04.04.02
VIGAS ACERO FY=4200 KG/CM2
01.04.04.03
LOSAS ALIGERADAS
01.04.05
LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2
01.04.05.01
LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm
01.04.05.02
LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm
01.04.05.03
LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO
01.04.05.04
LOSA ALIGERADA ACERO FY=4200 KG/CM2
01.04.05.05
LOSAS MACIZAS
01.04.06
LOSA MACIZA CONCRETO f'c=210 kg/cm2
01.04.06.01
LOSA MACIZA ENCOFRADO Y DESENCOFRADO
01.04.06.02
LOSA MACIZA ACERO FY=4200 KG/CM2
01.04.06.03
ESCALERAS
01.04.07
ESCALERAS CONCRETO f'c=210 kg/cm2
01.04.07.01
ESCALERAS ENCOFRADO Y DESENCOFRADO
01.04.07.02
ESCALERA ACERO FY=4200 KG/CM2
01.04.07.03
RAMPAS
01.04.08
RAMPAS CONCRETO FC=210 KG/CM2
01.04.08.01
RAMPAS ENCOFRADO Y DESENCOFRADO
01.04.08.02
RAMPAS ACERO FY=4200 KG/CM2
01.04.08.03
DETALLES
01.04.09

Mano de obra Propuesta

M2
M2
M2

217.29
217.29
217.29

M3
M3
M3
M3
M3
M2
M2
M3
M3

19.91
146.76
2.35
0.18
92.95
214.45
214.45
95.30
95.30

M2
M3
M3
M2
M2
M2
M2
M3
M2

91.72
27.67
3.91
52.18
160.65
53.80
16.27
3.88
31.02

M3
KG

56.49
1,323.67

M3
M2
KG

24.14
206.99
3,833.10

53.62
15.00

M3
M2
KG

2.33
23.30
161.11

107.23
19.07
0.61

M3
M2
KG

44.10
351.91
5,365.69

59.66
13.46
0.61

M3
M2
M2
M2
KG

30.95
208.72
156.10
364.82
1,713.28

46.15
5.54
5.54
11.30
0.61

M3
M2
KG

2.92
14.61
366.79

47.22
10.00
0.61

M3
M2
KG

0.84
16.35
145.16

43.67
30.50
0.80

M3
M2
KG

2.59
19.80
125.22

91.98
20.00
0.61

21.31
21.31

53.26
13.99
6.00
13.39
12.71
67.02
9.23

67,954.11
31,338.30
0.00
0.00
0.00
0.00
53.93
0.00
0.00
50.09
3.84
0.00
0.00
0.00
0.00
0.00
3,375.87
0.00
0.00
208.25
730.05
963.90
720.40
206.84
260.04
286.39
26,860.22
0.00
0.00
0.00
4,399.12
1,294.27
3,104.85
0.00
792.07
249.85
444.22
98.00
10,631.51
2,630.99
4,736.57
3,263.95
8,616.99
1,428.46
1,157.14
865.42
4,123.78
1,042.19
507.11
137.89
146.10
223.12
651.49
36.69
498.67
116.13
710.41
238.24
396.00
76.17
551.52

Pgina 20

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

DETALLES CONCRETO F'C= 175KG/CM2


01.04.09.01
DETALLES ENCOFRADO Y DESENCOFRADO
01.04.09.02
ESTRUCTURA DE MADERA Y COBERTURA
01.05
CORREAS DE MADERA 2" x 2"
01.05.01
COBERTURA TEJA ANDINA (0.72x1.14)
01.05.02
CUMBRERA TEJA ANDINA
01.05.03
LIMATESA TEJA ANDINA
01.05.04
ARQUITECTURA
02
MUROS Y TABIQUES DE ALBAILERIA
02.01
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4
02.01.01
REVOQUES ENLUCIDOS Y DERRAMES
02.02
TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)
02.02.01
TARRAJEO EN INTERIORES (MORTERO 1:5)
02.02.02
TARRAJEO EN EXTERIORES (MORTERO 1:5)
02.02.03
TARRAJEO EN COLUMNAS (MORTERO 1:5)
02.02.04
TARRAJEO EN VIGAS (MORTERO 1:5)
02.02.05
TARRAJEO EN PLACAS (MORTERO 1:5)
02.02.06
TARRAJEO C/IMPERMEABILIZANTE
02.02.07
DERRAMES E=15 cm (MORTERO 1:5)
02.02.08
CIELORRASOS
02.03
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
02.03.01
PISOS Y PAVIMENTOS
02.04
CONTRAPISO DE 48 mm, MEZCLA 1:5
02.04.01
PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM
02.04.02
PISO DE CEMENTO PULIDO BRUADO
02.04.03
ZOCALOS Y CONTRAZOCALOS
02.05
ZOCALO DE CERAMICO 20 x 30 CM
02.05.01
CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm
02.05.02
CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM
02.05.03
REVESTIMIENTOS DE GRADAS Y ESCALERAS
02.06
REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO
02.06.01
REVESTIMIENTO DE DESCANSOS DE CEMENTO
02.06.02
REVESTIMIENTO DE RAMPAS DE CEMENTO
02.06.03
VARIOS, LIMPIEZA Y JARDINERIA
02.12
JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.
02.12.01
SEALIZACION
02.12.02
TURBA Y PREPARACION DE SUSTRATO AGRICOLA
02.12.03
FLORES
02.12.04
COSTO DIRECTO TOTAL

Mano de obra Propuesta

Metrado

Costo
Unitario
(S/.)

M3
M2

1.05
23.65

34.43
21.79

ML
M2
ML
ML

244.30
232.50
21.45
16.00

2.09
2.16
1.14
0.57

M2

305.06

12.95

M2
M2
M2
M2
M2
M2
M2
ML

60.00
411.61
217.48
172.39
359.42
17.31
67.27
233.81

7.57
12.00
12.00
14.99
16.49
14.11
12.95
6.00

M2

364.82

11.35

M2
M2
M2

230.20
229.20
172.25

6.99
11.35
14.55

M2
ML
ML

60.00
93.55
74.10

9.46
6.85
5.70

ML
M2
M2

43.10
1.35
19.80

20.53
11.35
12.13

ML
UN
M3
UN

6.00
1.00
14.22
60.00

1.02

S/.

Costo
Parcial
(S/.)

36.16
515.36
1,048.28
511.66
503.06
24.44
9.12
36,615.81
3,950.95
3,950.95
19,031.25
454.15
4,939.32
2,609.76
2,584.45
5,925.29
244.18
871.24
1,402.86
4,140.63
4,140.63
6,716.27
1,609.47
2,601.37
2,505.43
1,630.40
567.80
640.38
422.22
1,140.21
884.77
15.32
240.12
6.10
6.10
0.00
0.00
0.00
67,954.11

Pgina 21

Mano de obra Propuesta

Pgina 22

Mano de obra Propuesta

Pgina 23

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

Metrado

Costo
Unitario
(S/.)

67,954.11
ESTRUCTURAS
01
TRABAJOS PRELIMINARES
01.01
LIMPIEZA DEL TERRENO MANUAL
01.01.01
M2
TRAZO Y REPLANTEO PRELIMINAR
01.01.02
M2
TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO
01.01.03
M2
MOVIMIENTO DE TIERRAS
01.02
EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO
01.02.01
M3
EXCAV. MANUAL DE ZANJAS HASTA 1.40 M
01.02.02
M3
EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA
01.02.03
M3
EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS
01.02.04
M3
RELLENO CON MATERIAL PROPIO
01.02.05
M3
REFINE, NIVELACION Y COMPACTACION
01.02.06
M2
RELLENO CON MATERIAL CLASIFICADO E=10 CM
01.02.07
M2
ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.
01.02.08
M3
ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 kmM3
01.02.09
CONCRETO SIMPLE
01.03
SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12
01.03.01
M2
CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G
01.03.02
M3
SOBRECIMIENTO CONCRETO 1:8+25% PM
01.03.03
M3
SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m M2
01.03.04
FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)
01.03.05
M2
VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL
01.03.06
M2
VEREDA ENCOFRADO Y DESENCOFRADO
01.03.07
M2
SARDINELES CONCRETO FC=175 KG/CM2
01.03.08
M3
SARDINELES ENCOFRADO Y DESENCOFRADO
01.03.09
M2
CONCRETO ARMADO
01.04
ZAPATAS
01.04.01
ZAPATAS CONCRETO F'C=210 kg/cm2
01.04.01.01
M3
ZAPATAS ACERO F'Y=4200 KG/CM2
01.04.01.02
KG
COLUMNAS
01.04.02
COLUMNAS CONCRETO F'C=210 kg/cm2
01.04.02.01
M3
COLUMNAS ENCOFRADO Y DESENCOFRADO
01.04.02.02
M2
COLUMNAS ACERO F'C=4200 KG/CM2
01.04.02.03
KG
PLACAS DE CONCRETO
01.04.03
PLACA DE CONCRETO F'c=210 Kg/Cm2
01.04.03.01
M3
PLACA ENCOFRADO Y DESENCOFRADO
01.04.03.02
M2
PLACA ACERO F'c=4200 Kg/Cm2
01.04.03.03
KG
VIGAS
01.04.04
VIGAS CONCRETO F'C=210 kg/cm2
01.04.04.01
M3
VIGAS ENCOFRADO Y DESENCOFRADO
01.04.04.02
M2
VIGAS ACERO FY=4200 KG/CM2
01.04.04.03
KG
LOSAS ALIGERADAS
01.04.05
LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2
01.04.05.01
M3
LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm
01.04.05.02
M2
LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm
01.04.05.03
M2
LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO
01.04.05.04
M2
LOSA ALIGERADA ACERO FY=4200 KG/CM2
01.04.05.05
KG
LOSAS MACIZAS
01.04.06
LOSA MACIZA CONCRETO f'c=210 kg/cm2
01.04.06.01
M3
LOSA MACIZA ENCOFRADO Y DESENCOFRADO
01.04.06.02
M2
LOSA MACIZA ACERO FY=4200 KG/CM2
01.04.06.03
KG
ESCALERAS
01.04.07
ESCALERAS CONCRETO f'c=210 kg/cm2
01.04.07.01
M3
ESCALERAS ENCOFRADO Y DESENCOFRADO
01.04.07.02
M2
ESCALERA ACERO FY=4200 KG/CM2
01.04.07.03
KG
RAMPAS
01.04.08
RAMPAS CONCRETO FC=210 KG/CM2
01.04.08.01
M3
RAMPAS ENCOFRADO Y DESENCOFRADO
01.04.08.02
M2
RAMPAS ACERO FY=4200 KG/CM2
01.04.08.03
KG
DETALLES
01.04.09

Val. M.O. Ago-Set

217.29
217.29
217.29
19.91
146.76
2.35
0.18
92.95
214.45
214.45
95.30
95.30
91.72
27.67
3.91
52.18
160.65
53.80
16.27
3.88
31.02

21.31
21.31

53.26
13.99
6.00
13.39
12.71
67.02
9.23

56.49
1,323.67
24.14
206.99
3,833.10

53.62
15.00

2.33
23.30
161.11

107.23
19.07
0.61

44.10
351.91
5,365.69

59.66
13.46
0.61

30.95
208.72
156.10
364.82
1,713.28

46.15
5.54
5.54
11.30
0.61

2.92
14.61
366.79

47.22
10.00
0.61

0.84
16.35
145.16

43.67
30.50
0.80

2.59
19.80
125.22

91.98
20.00
0.61

67,954.11
31,338.30
0.00
0.00
0.00
0.00
53.93
0.00
0.00
50.09
3.84
0.00
0.00
0.00
0.00
0.00
3,375.87
0.00
0.00
208.25
730.05
963.90
720.40
206.84
260.04
286.39
26,860.22
0.00
0.00
0.00
4,399.12
1,294.27
3,104.85
0.00
792.07
249.85
444.22
98.00
10,631.51
2,630.99
4,736.57
3,263.95
8,616.99
1,428.46
1,157.14
865.42
4,123.78
1,042.19
507.11
137.89
146.10
223.12
651.49
36.69
498.67
116.13
710.41
238.24
396.00
76.17
551.52

21.31
21.31

3.91
52.18
160.65

53.26
13.99
6.00
13.39
12.71
67.02
9.23

16.10
157.08

53.62
15.00

107.23
19.07
0.61
16.57
132.24
2,606.30

59.66
13.46
0.61

208.72
1,150.53

46.15
5.54
5.54
11.30
0.61

14.61
367.19

47.22
10.00
0.61

208.72

43.67
30.50
0.80
91.98
20.00
0.61

Pgina 24

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

DETALLES CONCRETO F'C= 175KG/CM2


01.04.09.01
DETALLES ENCOFRADO Y DESENCOFRADO
01.04.09.02
ESTRUCTURA DE MADERA Y COBERTURA
01.05
CORREAS DE MADERA 2" x 2"
01.05.01
COBERTURA TEJA ANDINA (0.72x1.14)
01.05.02
CUMBRERA TEJA ANDINA
01.05.03
LIMATESA TEJA ANDINA
01.05.04
ARQUITECTURA
02
MUROS Y TABIQUES DE ALBAILERIA
02.01
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4
02.01.01
REVOQUES ENLUCIDOS Y DERRAMES
02.02
TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)
02.02.01
TARRAJEO EN INTERIORES (MORTERO 1:5)
02.02.02
TARRAJEO EN EXTERIORES (MORTERO 1:5)
02.02.03
TARRAJEO EN COLUMNAS (MORTERO 1:5)
02.02.04
TARRAJEO EN VIGAS (MORTERO 1:5)
02.02.05
TARRAJEO EN PLACAS (MORTERO 1:5)
02.02.06
TARRAJEO C/IMPERMEABILIZANTE
02.02.07
DERRAMES E=15 cm (MORTERO 1:5)
02.02.08
CIELORRASOS
02.03
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
02.03.01
PISOS Y PAVIMENTOS
02.04
CONTRAPISO DE 48 mm, MEZCLA 1:5
02.04.01
PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM
02.04.02
PISO DE CEMENTO PULIDO BRUADO
02.04.03
ZOCALOS Y CONTRAZOCALOS
02.05
ZOCALO DE CERAMICO 20 x 30 CM
02.05.01
CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm
02.05.02
CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM
02.05.03
REVESTIMIENTOS DE GRADAS Y ESCALERAS
02.06
REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO
02.06.01
REVESTIMIENTO DE DESCANSOS DE CEMENTO
02.06.02
REVESTIMIENTO DE RAMPAS DE CEMENTO
02.06.03
VARIOS, LIMPIEZA Y JARDINERIA
02.12
JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.
02.12.01
SEALIZACION
02.12.02
TURBA Y PREPARACION DE SUSTRATO AGRICOLA
02.12.03
FLORES
02.12.04
COSTO DIRECTO TOTAL

Val. M.O. Ago-Set

Metrado

Costo
Unitario
(S/.)

M3
M2

1.05
23.65

34.43
21.79

ML
M2
ML
ML

244.30
232.50
21.45
16.00

2.09
2.16
1.14
0.57

M2

305.06

12.95

M2
M2
M2
M2
M2
M2
M2
ML

60.00
411.61
217.48
172.39
359.42
17.31
67.27
233.81

7.57
12.00
12.00
14.99
16.49
14.11
12.95
6.00

M2

364.82

11.35

M2
M2
M2

230.20
229.20
172.25

6.99
11.35
14.55

M2
ML
ML

60.00
93.55
74.10

9.46
6.85
5.70

ML
M2
M2

43.10
1.35
19.80

20.53
11.35
12.13

ML
UN
M3
UN

6.00
1.00
14.22
60.00

1.02

S/.

Costo
Parcial
(S/.)

36.16
515.36
1,048.28
511.66
503.06
24.44
9.12
36,615.81
3,950.95
3,950.95
19,031.25
454.15
4,939.32
2,609.76
2,584.45
5,925.29
244.18
871.24
1,402.86
4,140.63
4,140.63
6,716.27
1,609.47
2,601.37
2,505.43
1,630.40
567.80
640.38
422.22
1,140.21
884.77
15.32
240.12
6.10
6.10
0.00
0.00
0.00
67,954.11

Metrado

Costo
Unitario
(S/.)

34.43
21.79
2.09
2.16
1.14
0.57

141.76

12.95
7.57
12.00
12.00
14.99
16.49
14.11
12.95
6.00
11.35
6.99
11.35
14.55
9.46
6.85
5.70
20.53
11.35
12.13
1.02

S/.

Pgina 25

N GENERAL

Costo
Parcial
(S/.)

15,897.22
15,897.22
14,061.23
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,902.20
0.00
0.00
208.25
730.05
963.90
0.00
0.00
0.00
0.00
12,159.03
0.00
0.00
0.00
3,219.40
863.20
2,356.20
0.00
0.00
0.00
0.00
0.00
4,353.87
988.56
1,779.90
1,585.41
4,216.30
0.00
1,157.14
0.00
2,359.29
699.87
369.46
0.00
146.10
223.36
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00

COLUMNAS
COLUMNAS CONCRETO F'C=210 kg/cm2
COLUMNAS ENCOFRADO Y DESENCOFRADO
COLUMNETAS
COLUMNETAS CONCRETO F'C=210 kg/cm2
COLUMNETAS ENCOFRADO Y DESENCOFRADO

CONCRETO FC=210 KG/CM2


ENCOFRADO Y DESENCOFRADO

13.24
119.28

2.86
37.80

16.10
157.08

Val. M.O. Ago-Set

Pgina 26

N GENERAL

Costo
Parcial
(S/.)

0.00
0.00
0.00
0.00
0.00
0.00
0.00
1,835.99
1,835.99
1,835.99
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
15,897.22

Nota: la presente valorizacin es de acuerdo a la propuesta del contratista


deber de ser reagustada a la propuesta final porque el contratista se ha bajado

Val. M.O. Ago-Set

Pgina 27

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

ESTRUCTURAS
01
TRABAJOS PRELIMINARES
01.01
LIMPIEZA DEL TERRENO MANUAL
01.01.01
TRAZO Y REPLANTEO PRELIMINAR
01.01.02
TRAZO NIVELACION Y REPLANTEO DURANTE EL PROCESO
01.01.03
MOVIMIENTO DE TIERRAS
01.02
EXCAV. MANUAL DE ZANJAS EN MATERIAL SUELTO
01.02.01
EXCAV. MANUAL DE ZANJAS HASTA 1.40 M
01.02.02
EXCAV. MANUAL DE ZANJAS P/SARDINELES DE VEREDA
01.02.03
EXCAV. DE ZANJAS PARA ESCALERAS Y RAMPAS
01.02.04
RELLENO CON MATERIAL PROPIO
01.02.05
REFINE, NIVELACION Y COMPACTACION
01.02.06
RELLENO CON MATERIAL CLASIFICADO E=10 CM
01.02.07
ELIMIN. DE MATERIAL -MANUAL DIST. PROMD. D=30M.
01.02.08
ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km
01.02.09
CONCRETO SIMPLE
01.03
SOLADOS PARA ZAPATAS E=4" CONCRETO 1:12
01.03.01
CIMIENTO CORRIDO CONCRETO 1:10 + 30% P G
01.03.02
SOBRECIMIENTO CONCRETO 1:8+25% PM
01.03.03
SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO HASTA 0.30 m
01.03.04
FALSO PISO E=4" (MEZCLA 1:10 CEMENTO HORMIGON)
01.03.05
VEREDA CONCRETO FC=175 KG/CM E= 4" + SARDINEL
01.03.06
VEREDA ENCOFRADO Y DESENCOFRADO
01.03.07
SARDINELES CONCRETO FC=175 KG/CM2
01.03.08
SARDINELES ENCOFRADO Y DESENCOFRADO
01.03.09
CONCRETO ARMADO
01.04
ZAPATAS
01.04.01
ZAPATAS CONCRETO F'C=210 kg/cm2
01.04.01.01
ZAPATAS ACERO F'Y=4200 KG/CM2
01.04.01.02
COLUMNAS
01.04.02
COLUMNAS CONCRETO F'C=210 kg/cm2
01.04.02.01
COLUMNAS ENCOFRADO Y DESENCOFRADO
01.04.02.02
COLUMNAS ACERO F'C=4200 KG/CM2
01.04.02.03
PLACAS DE CONCRETO
01.04.03
PLACA DE CONCRETO F'c=210 Kg/Cm2
01.04.03.01
PLACA ENCOFRADO Y DESENCOFRADO
01.04.03.02
PLACA ACERO F'c=4200 Kg/Cm2
01.04.03.03
VIGAS
01.04.04
VIGAS CONCRETO F'C=210 kg/cm2
01.04.04.01
VIGAS ENCOFRADO Y DESENCOFRADO
01.04.04.02
VIGAS ACERO FY=4200 KG/CM2
01.04.04.03
LOSAS ALIGERADAS
01.04.05
LOSAS ALIGERADA CONCRETO f'c=210 kg/cm2
01.04.05.01
LOSA ALIGERADA LADRILLO ARCILLA 15X30X30 cm
01.04.05.02
LOSA ALIGERADA LADRILLO ARCILLA 12X30X30 cm
01.04.05.03
LOSA ALIGERADA ENCOFRADO Y DESENCOFRADO
01.04.05.04
LOSA ALIGERADA ACERO FY=4200 KG/CM2
01.04.05.05
LOSAS MACIZAS
01.04.06
LOSA MACIZA CONCRETO f'c=210 kg/cm2
01.04.06.01
LOSA MACIZA ENCOFRADO Y DESENCOFRADO
01.04.06.02
LOSA MACIZA ACERO FY=4200 KG/CM2
01.04.06.03
ESCALERAS
01.04.07
ESCALERAS CONCRETO f'c=210 kg/cm2
01.04.07.01
ESCALERAS ENCOFRADO Y DESENCOFRADO
01.04.07.02
ESCALERA ACERO FY=4200 KG/CM2
01.04.07.03
RAMPAS
01.04.08
RAMPAS CONCRETO FC=210 KG/CM2
01.04.08.01
RAMPAS ENCOFRADO Y DESENCOFRADO
01.04.08.02
RAMPAS ACERO FY=4200 KG/CM2
01.04.08.03
DETALLES
01.04.09

Metrados

Metrado

M2
M2
M2

217.29
217.29
217.29

M3
M3
M3
M3
M3
M2
M2
M3
M3

19.91
146.76
2.35
0.18
92.95
214.45
214.45
95.30
95.30

M2
M3
M3
M2
M2
M2
M2
M3
M2

91.72
27.67
3.91
52.18
160.65
53.80
16.27
3.88
31.02

M3
KG

56.49
1,323.67

M3
M2
KG

24.14
206.99
3,833.10

M3
M2
KG

2.33
23.30
161.11

M3
M2
KG

44.10
351.91
5,365.69

M3
M2
M2
M2
KG

30.95
208.72
156.10
364.82
1,713.28

M3
M2
KG

2.92
14.61
366.79

M3
M2
KG

0.84
16.35
145.16

M3
M2
KG

2.59
19.80
125.22

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

Pgina 28

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

DETALLES CONCRETO F'C= 175KG/CM2


01.04.09.01
DETALLES ENCOFRADO Y DESENCOFRADO
01.04.09.02
ESTRUCTURA DE MADERA Y COBERTURA
01.05
CORREAS DE MADERA 2" x 2"
01.05.01
COBERTURA TEJA ANDINA (0.72x1.14)
01.05.02
CUMBRERA TEJA ANDINA
01.05.03
LIMATESA TEJA ANDINA
01.05.04
ARQUITECTURA
02
MUROS Y TABIQUES DE ALBAILERIA
02.01
MURO LADRILLO KING-KONG (9x12x24) SOGA J/1.5CM C:A/1:4
02.01.01
REVOQUES ENLUCIDOS Y DERRAMES
02.02
TARRAJEO PRIMARIO RAYADO (MORTERO 1:5)
02.02.01
TARRAJEO EN INTERIORES (MORTERO 1:5)
02.02.02
TARRAJEO EN EXTERIORES (MORTERO 1:5)
02.02.03
TARRAJEO EN COLUMNAS (MORTERO 1:5)
02.02.04
TARRAJEO EN VIGAS (MORTERO 1:5)
02.02.05
TARRAJEO EN PLACAS (MORTERO 1:5)
02.02.06
TARRAJEO C/IMPERMEABILIZANTE
02.02.07
DERRAMES E=15 cm (MORTERO 1:5)
02.02.08
CIELORRASOS
02.03
CIELORRASOS CON MEZCLA DE CEMENTO-ARENA
02.03.01
PISOS Y PAVIMENTOS
02.04
CONTRAPISO DE 48 mm, MEZCLA 1:5
02.04.01
PISO DE CERAMICO ANTIDESLIZANTE 30 x30 CM
02.04.02
PISO DE CEMENTO PULIDO BRUADO
02.04.03
ZOCALOS Y CONTRAZOCALOS
02.05
ZOCALO DE CERAMICO 20 x 30 CM
02.05.01
CONTRAZOCALO CEMENTO S/N COLOREAR H = 30 cm
02.05.02
CONTRAZOCALO DE PORCELANATO MARMOL.50x50CM H= 10 CM
02.05.03
REVESTIMIENTOS DE GRADAS Y ESCALERAS
02.06
REVESTIMIENTO DE GRADAS Y ESCALERAS DE CEMENTO
02.06.01
REVESTIMIENTO DE DESCANSOS DE CEMENTO
02.06.02
REVESTIMIENTO DE RAMPAS DE CEMENTO
02.06.03
CARPINTERIA DE MADERA
02.07
PUERTA APANELADA DE MADERA (INC. PUERTA/M2)
02.07.01
CARPINTERIA METALICA Y HERRERIA
02.08
VENTANA DE ALUMINIO C/TUBO 3 1/4" x 1 1/2" INC. NAVES, BRAZO, BURDETE Y CIERRE
02.08.01
MAMPARA C/ESTRUCTURA DE ALUMINIO 3 1/4"x2"
02.08.02
PUERTA METALICA (INC. PUERTA/M2)
02.08.03
BARANDA EN ESCALERA C/TUBO 2" Y 1"
02.08.04
CERRAJERIA
02.09
BISAGRA ALUMINIZADA CAPUCHINA DE 4" X 4"
02.09.01
CERRADURA PARCHE 2 GOLPES
02.09.02
CERRADURA DE PERILLA LIVIANA
02.09.03
VIDRIOS, CRISTALES Y SIMILARES
02.10
VIDRIO TEMPLADO DE 6MM
02.10.01
VIDRIO TEMPLADO DE 10MM
02.10.02
PINTURA
02.11
PINTURA EN CIELORASOS AL LATEX
02.11.01
PINTURA EN COLUMNAS AL LATEX
02.11.02
PINTURA EN VIGAS AL LATEX
02.11.03
PINTURA EN MUROS INTERIORES AL LATEX
02.11.04
PINTURA EN MUROS EXTERIORES AL LATEX
02.11.05
PINTURA LATEX EN DERRAMES DE A=15CM.
02.11.06
PINTURA EN CONTRAZOCALO C/ESMALTE H=0.20 M
02.11.07
PINTURA EN CARPINTERIA DE MADERA CON BARNIZ
02.11.08
PINTURA EN CARPINTERIA METALICA C/ESMALTE
02.11.09
PINTURA EN BARANDAS C/ESMALTE
02.11.10
VARIOS, LIMPIEZA Y JARDINERIA
02.12
JUNTA DE DILATACION EN PISO EXT. C/SELLO ASFALT.
02.12.01
SEALIZACION
02.12.02
TURBA Y PREPARACION DE SUSTRATO AGRICOLA
02.12.03

Metrados

Metrado

M3
M2

1.05
23.65

ML
M2
ML
ML

244.30
232.50
21.45
16.00

M2

305.06

M2
M2
M2
M2
M2
M2
M2
ML

60.00
411.61
217.48
172.39
359.42
17.31
67.27
233.81

M2

364.82

M2
M2
M2

230.20
229.20
172.25

M2
ML
ML

60.00
93.55
74.10

ML
M2
M2

43.10
1.35
19.80

M2

7.98

M2
M2
M2
ML

62.42
26.76
6.36
42.35

UN
UN
UN

32.00
3.00
4.00

M2
M2

63.32
26.72

M2
M2
M2
M2
M2
ML
ML
M2
M2
ML

364.82
172.39
359.42
411.61
217.48
233.81
93.55
15.96
12.73
135.05

ML
UN
M3

6.00
1.00
14.22

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

Pgina 29

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Ejecuta :
Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

02.12.04
03
03.01
03.01.01
03.01.02
03.01.03
03.01.04
03.01.05
03.01.06
03.01.07
03.02
03.02.01
03.02.02
03.02.03
03.02.04
03.02.05
03.02.06
03.02.07
03.02.08
03.02.09
03.02.10
03.02.11
03.02.12
03.02.13
03.02.14
03.02.15
03.03
03.03.01
03.03.02
03.03.03
03.03.04
03.03.05
03.04
03.04.01
03.04.02
04
04.01
04.01.01
04.01.02
04.01.03
04.01.04
04.01.05
04.01.06
04.01.07
04.02
04.02.01
04.03
04.03.01
04.03.02
04.04
04.04.01
04.04.02
04.04.03
04.04.04
04.05
04.05.01
04.05.02
04.06
04.06.01

Partidas

Und.

FLORES
INSTALACIONES SANITARIAS
APARATOS Y ACCESORIOS SANITARIOS
INODORO TOP PICCE C/FLUXOMETRO
LAVATORIO DE LOZA BLANCA 20"X16"
URINARIOS DE LOZA DE PICO BLANCO
LAVADERO DE ACERO INOXIDABLE, 01 P0ZA C/ESCURRIDERO+ACCES.
LLAVE CROMADO 1/2" PARA LAVATORIO
LLAVE TIPO CUELLO DE CISNE CROMADO DE 1/2"
LLAVE CROMADO PARA URINARIO
SISTEMA DE DESAGUE
SALIDA DE DESAGUE PVC D=4"
SALIDA DE DESAGUE PVC D=2"
SALIDA DE VENTILACION PVC D=2"
REGISTROS DE BRONCE 4"
SUMIDEROS DE 2"
TUBERIA DE PVC SAL 4"
TUBERIA DE PVC SAL 2"
YEE PVC SAL 4"
YEE PVC SAL 2"
YEE PVC SAL 4" x 2"
TEE PVC SAL 2"
CODO PVC SAL 2"X45
CODO PVC SAL 4" x 45
REDUCCION PVC SAL 4" A 2"
CAJA DE REGISTRO DE 12" X 24"
SISTEMA DE AGUA FRIA
SALIDA DE AGUA FRIA DE 1/2"
TUBERIA PVC CLASE 10 DE 1/2"
CODO PVC SAP 1/2" x 90
TEE PVC SAP 1/2"
VALVULAS DE COMPUERTA DE BRONCE DE 1/2"
SISTEMA DE AGUA DE LLUVIA
TUBERIA PVC SAL 4" D/PLUVIAL
CODO PVC SAL 4" x 90
INSTALACIONES ELECTRICAS
INSTALACIONES ELECTRICAS Y MECANICAS
SALIDA PARA CENTRO DE LUZ
SALIDA DE PARED (BRAQUETES) CON PVC
SALIDA P/TOMACORRIENTE SIMPLE PARA LUZ DE EMERGENCIA
SALIDA PARA INTERRUPTOR SIMPLE
SALIDA PARA INTERRUPTOR DOBLE
SALIDA P/TOMACORRIENTE DOBLE, CON LINEA TIERRA
SALIDA P/TOMACORRIENTE DOBLE, C/ LINEA TIERRA P/AGUA
CANALIZACIONES, CONDUCTOS O TUBERIAS
TUBO 20MM D' PVC SEL
CONDUCTORES Y CABLES DE ENERGIA EN TUBERIAS
CABLE NH - 80 2 x 4 + 1x4 MM2
CABLE NH - 80 2 x 2.5 MM2
ARTEFACTOS ELECTRICOS
ARTEFACTO FLUORESCENTE 2/36W +CAJA C/REJILLA
ARTEFACTO FLUORESCENTE 4 x 18 W C/EQ
ARTEFACTO BRAQUET GLOBO
ARTEFACTO SPOT-LIGHT C/DOBLE LAMPARA AHORRADOR
TABLEROS DE DISTRIBUCION
TABLERO GENERAL 4
TABLERO DISTRIBUCION 41
EQUIPOS ELECTRICOS Y MECANICOS
POZO A TIERRA C/C CU 16MM2 CC

Metrado

UN

60.00

UN
UN
PZA
UN
UN
UN
UN

2.00
3.00
1.00
2.00
3.00
2.00
1.00

PTO
PTO
PTO
UN
UN
ML
ML
PZA
PZA
PZA
PZA
PZA
UN
PZA
UN

2.00
6.00
2.00
3.00
5.00
14.21
23.90
1.00
5.00
2.00
5.00
2.00
2.00
4.00
1.00

PTO
ML
UN
UN
UN

8.00
17.80
11.00
4.00
2.00

ML
UN

41.40
18.00

PTO
PTO
PTO
PTO
PTO
PTO
PTO

34.00
3.00
18.00
9.00
3.00
21.00
4.00

ML

626.40

ML
ML

338.40
288.00

UN
UN
UN
UN

24.00
6.00
3.00
3.00

UN
UN

1.00
1.00

UN

2.00

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

COSTO DIRECTO TOTAL

Metrados

Pgina 30

COSTO DE LA MANO DE OBRA POR SUB-CONTRATA.


Nombre del Proyecto :
Nombre del Sub - Proyecto N 03 :
Ejecuta :

CONSTRUCCION DE COMEDOR, SALA DE MUSICA Y ALMACEN GENERAL


MUNICIPALIDAD DISTRITAL DE HUACHOCOLPA

Financiamiento:

GOBIERNO REGIONAL DE HUANCAVELICA

Residente de Obra

Ing. Clfor Hctor Garca Corzo

Supervisor

Arq. Hugo Abel Villaverde Rafael

tem

Partidas

Und.

Metrados

Metrado

Costo
Unitario
(S/.)

Costo
Parcial
(S/.)

Pgina 31

Metrados

Pgina 32

Metrados

Pgina 33

Metrados

Pgina 34

Metrados

Pgina 35

S-ar putea să vă placă și