Sunteți pe pagina 1din 15

RESUMEN DE VALORIZACION N 02

OBRA:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ

UBICACIN:

Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash

CONTRATISTA: EVANOR SAC.


SUPERVISOR:

ING. PEPE RAMOS CHOQUE

VAL N

DEL

7/7/2014

AL

8/6/2014

CON IGV
MONTO DEL CONTRATO VIGENTE

ITEM

SIN IGV

174,806.11

MONTO DEL CONTRATO ORIGINAL

CONCEPTOS

VALORIZACION
ACTUAL

148,140.77

S/. 174,806.11

S/. 148,140.77

VALORIZACION
ACUMULADA
ANTERIOR

VALORIZACION
ACUMULADA
ACTUAL

1.0

DE LAS VALORIZACIONES

1.1

VALORIZACIN CONTRATO PRINCIPAL

31,290.96

27,886.40

59,177.36

1.2

REAJUSTE VAL. CONTRATO PRINCIPAL

0.00

0.00

0.00

A.

TOTAL VALORIZACION REAJUSTADA

31,290.96

27,886.40

59,177.36

2.0

AMORTIZACIONES (1)

2.1

ADELANTO DIRECTO

0.00

0.00

0.00

2.2

ADELANTO DE MATERIALES

0.00

0.00

0.00

B.

TOTAL AMORTIZACIONES

0.00

0.00

0.00

3.0

DEDUCCIONES

3.1

POR EL ADELANTO DIRECTO

0.00

0.00

0.00

3.2

POR EL ADELANTO POR MATERIALES

0.00

0.00

0.00

C.

TOTAL DEDUCCIONES

0.00

0.00

0.00

4.0

IGV 18% DE (A-B-C)

5,632.37

5,019.55

10,651.92

5.0

LIQUIDO A PAGAR INC. IGV (A-B-C+I.G.V.)

36,923.33

32,905.95

69,829.28

31,290.96

27,886.40

59,177.36

5,632.37

5,019.55

10,651.92

6.0

MONTO A CANCELAR AL CONTRATISTA


A FAVOR DEL CONTRATISTA
POR CONCEPTO DE I.G.V

(1) EL CONTRATISTA NO HA SOLICITADO NINGN TIPO DE ADELANTO.

VALORIZACIN DE OBRA N 02 - JULIO


CONTRATO PRINCIPAL
VALORIZACION N:

02

DEL
CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
Plazo de Ejecucin:
90
Fecha de Inicio:
6/23/2014
Fecha de termino:
9/20/2014
A V A N C E S
ANTERIOR
ACTUAL
Metrado
Valorizado
Metrado
Valorizado
%
Metrado

NOMBRE DEL PROYECTO:


EVANOR SAC.
148140.77
Tinyash

CONTRATISTA
COSTO DEL PROYECTO (SIN IGV):
Ubicacin:
Part.

PRESUPUESTO

DESCRIPCION
Und

01
01.01
01.02
02
02.01
02.02
03
03.01
03.02
03.03
04
04.01
04.02
04.03
04.04
05
05.01
05.02
05.03
05.04
05.05
06
06.01
06.01.01
06.01.02
06.02
06.02.01
06.02.02
06.02.03
06.03
06.03.01
06.03.02
06.03.03
06.04
06.04.01
06.04.02
06.04.03
06.05
06.05.01
06.05.02
06.05.03
06.06
06.06.01
06.06.02
06.06.03
07
07.01
07.02
07.03

CONSTRUCCIONES PROVICIONALES
ALQUILER DE ALMACEN DE OBRA
CARTEL DE OBRA DE 2.4m x 3.6m Inc Transp y coloc.
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL
TRAZO Y REPLANTEO EN EDIFICACIONES
SEGURIDAD Y SALUD
EQUIPOS DE PROTECCION INDIVIDUAL
CAPACITACION DE SEGURIDAD Y SALUD
SEALIZACION TEMPORAL DE SEGURIDAD
MOVIMIENTO DE TIERRAS
EXCAVACION PARA CIMIENTOS Y ZAPATAS
RELLENO CON MATERIAL PROPIO MANUAL
ELIMINACION DE MATERIAL EXCEDENTE Dprom=30m
NIVELACION INTERIOR Y APISONADO MANUAL
CONCRETO SIMPLE
SOLADO PARA ZAPATA E=2" Mezcla 1:12 C:H
CONCRETO PARA CIMIENTO CORRIDO 1:10+30%PG
CONCRETO PARA SOBRECIMIENTOS 1:8 + 25%P M
ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO
CONCRETO EN FALSO PISO 4" Mezcla 1:8 C:H
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C=210 Kg/cm2 PARA ZAPATAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
VIGA DE CIMENTACION
ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210Kg/cm2 EN VIGAS DE CIMENTACION
COLUMNAS
ENCOFRADO Y DESENCOFRADO DE COLUMNAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA COLUMNAS
VIGAS Y DINTELES
ENCOFRADO Y DESENCOFRADO DE VIGAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA VIGAS
COLUMNETAS EN MUROS DE ALBAILERIA
ENCOFRADO Y DESENCOFRADO DE COLUMNETAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA COLUMNETAS
VIGAS DE REMATE DE PARAPETO Y ALFEIZER
ENCOFRADO Y DESENCOFRADO DE VIGA REMATE
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA VIGA REMATE
MUROS Y TABIQUES DE ALBAILERIA
MURO DE LADRILLO K.K. 18 huecos DE SOGA 1:5 x 1.5cm
MURO DE LADRILLO K.K. 18 huecos DE CABEZA 1:5 x 1.5cm
ACERO DE REFUERZO HORIZONTAL EN MUROS

Metrado

P.U.

P.P.

7/7/2014

Dpto.:
Provincia:
Distrito:
ACUMULADO
Valorizado

AL

7/22/2014

Ancash
Huaraz
Independencia
SALDO
%

Metrado

Valorizado

mes
und

3.00
1.00

150.00
560.00

450.00
560.00

0.50
1.00

75.00
560.00

0.50
0.00

75.00
0.00

16.67%
0.00%

1.00
1.00

150.00
560.00

33.33%
100.00%

2.00
0.00

300.00
0.00

66.67%
0.00%

m2
m2

200.00
200.00

1.10
0.85

220.00
170.00

200.00
200.00

220.00
170.00

0.00
0.00

0.00
0.00

0.00%
0.00%

200.00
200.00

220.00
170.00

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

glb
glb
glb

1.00
1.00
1.00

902.50
800.00
390.00

902.50
800.00
390.00

1.00
1.00
1.00

902.50
800.00
390.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

1.00
1.00
1.00

902.50
800.00
390.00

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

m3
m3
m3
m2

37.09
14.87
27.77
37.17

15.74
30.09
10.41
1.18

583.80
447.44
289.09
43.86

34.54
0.00
22.50
0.00

543.66
0.00
234.23
0.00

0.00
0.00
0.00
18.59

0.00
0.00
0.00
21.94

0.00%
0.00%
0.00%
50.01%

34.54
0.00
22.50
18.59

543.66
0.00
234.23
21.94

93.12%
0.00%
81.02%
50.02%

2.55
14.87
5.27
18.58

40.14
447.44
54.86
21.92

6.88%
100.00%
18.98%
49.98%

m2
m3
m3
m2
m2

12.60
19.66
3.13
33.79
157.98

19.68
206.16
254.56
35.87
29.49

247.97
4,053.11
796.77
1,212.05
4,658.83

12.60
19.66
0.00
0.00
0.00

247.97
4053.11
0.00
0.00
0.00

0.00
0.00
3.13
33.79
0.00

0.00
0.00
796.77
1,212.05
0.00

0.00%
0.00%
100.00%
100.00%
0.00%

12.60
19.66
3.13
33.79
0.00

247.97
4,053.11
796.77
1,212.05
0.00

100.00%
100.00%
100.00%
100.00%
0.00%

0.00
0.00
0.00
0.00
157.98

0.00
0.00
0.00
0.00
4,658.83

0.00%
0.00%
0.00%
0.00%
100.00%

m3
kg

7.56
152.46

325.48
5.71

2,460.63
870.55

7.56
152.46

2460.63
870.55

0.00
0.00

0.00
0.00

0.00%
0.00%

7.56
152.46

2,460.63
870.55

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

m2
kg
m3

25.14
459.96
3.14

35.87
5.71
325.48

901.77
2,626.37
1,022.01

5.76
459.96
0.00

206.61
2626.37
0.00

19.38
0.00
3.14

695.16
0.00
1,022.01

77.09%
0.00%
100.00%

25.14
459.96
3.14

901.77
2,626.37
1,022.01

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

m2
kg
m3

68.00
974.54
4.25

44.65
5.71
396.33

3,036.20
5,564.62
1,684.40

0.00
974.54
0.00

0.00
5564.62
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
974.54
0.00

0.00
5,564.62
0.00

0.00%
100.00%
0.00%

68.00
0.00
4.25

3,036.20
0.00
1,684.40

100.00%
0.00%
100.00%

m2
kg
m3

58.28
720.56
5.27

58.03
5.71
351.13

3,381.99
4,114.40
1,850.46

0.00
0.00
0.00

0.00
0.00
0.00

0.00
137.41
0.00

0.00
784.61
0.00

0.00%
19.07%
0.00%

0.00
137.41
0.00

0.00
784.61
0.00

0.00%
19.07%
0.00%

58.28
583.15
5.27

3,381.99
3,329.79
1,850.46

100.00%
80.93%
100.00%

m2
kg
m3

22.32
204.81
1.29

50.16
5.71
352.91

1,119.57
1,169.47
455.25

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

22.32
204.81
1.29

1,119.57
1,169.47
455.25

100.00%
100.00%
100.00%

m2
kg
m3

5.34
29.74
0.41

50.16
5.71
294.47

267.85
169.82
120.73

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

5.34
29.74
0.41

267.85
169.82
120.73

100.00%
100.00%
100.00%

m2
m2
kg

51.77
55.09
170.33

96.37
54.52
5.46

4,989.07
3,003.51
930.00

0.00
0.00
0.00

0.00
0.00
0.00

25.89
27.54
85.16

2,495.02
1,501.48
464.97

50.01%
49.99%
50.00%

25.89
27.54
85.16

2,495.02
1,501.48
464.97

50.01%
49.99%
50.00%

25.88
27.55
85.17

2,494.06
1,502.03
465.03

49.99%
50.01%
50.00%

VALORIZACIN DE OBRA N 02 - JULIO


CONTRATO PRINCIPAL
VALORIZACION N:

02

DEL
CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
Plazo de Ejecucin:
90
Fecha de Inicio:
6/23/2014
Fecha de termino:
9/20/2014
A V A N C E S
ANTERIOR
ACTUAL
Metrado
Valorizado
Metrado
Valorizado
%
Metrado

NOMBRE DEL PROYECTO:


EVANOR SAC.
148140.77
Tinyash

CONTRATISTA
COSTO DEL PROYECTO (SIN IGV):
Ubicacin:
Part.

PRESUPUESTO

DESCRIPCION
Und

07.04
08
08.01
08.02
08.03
08.04
08.05
09
09.01
09.02
09.03
10
10.01
10.02
10.03
10.04
11
11.01
11.02
12
12.01
12.02
12.02
12.02
13
13.01
14
14.01
15
15.01
16
16.01
17
17.01
17.02
17.03
18
18.01
18.02
18.03
19
19.01
19.02
20
20.01
20.02
21
21
22
22.01

Metrado

JUNTA DE CONSTRUCCION CON TECKNOPORT 1" PARA MUROS


m
27.00
REVOQUES, ENLUCIDOS Y DERRAMES
TARRAJEO EN INTERIOR 1.5cm MEZCLA 1:5
m2
112.10
TARRAJEO EN EXTERIOR 1.5cm MEZCLA 1:5
m2
86.55
TARRAJEO DE SUPERFICIE DE VIGAS 1.5cm M: 1:5
m2
43.74
TARRAJEO DE SUPERFICIE DE COLUMNAS 1.5cm M: 1:5
m2
46.23
VESTIDURA DE DERRAMES 1.5cm M:1:5
m
74.40
CIELORASO
CIELO RASO CON PLANCHA SUPERBOARD 4mm
m2
117.00
ALERO DE TECHO CON PLANCHA SUPERBOARD 4mm
m2
73.46
FRIZOS PLANCHA SUPERBOARD 6mm
m2
11.07
PISOS Y PAVIMENTOS
PISOS DE CEMENTO E=5cm, PULIDO, COLOREADO Y BRUADO
m2
105.00
ENCOFRADO Y DESENCOFRADO DE VEREDA
m2
17.34
VEREDA DE CONCRETO F'C=175 Kg/cm2 E=0.15m BRUADA+SARDINEL
m2 PASTA1.5cm
57.64
JUNTA ASFALTICA EN VEREDA E=1"
m
72.75
CONTRAZOCALOS
CONTRAZOCALO DE CEMENTO H=0.20m EN EXTERIORES
m
50.15
CONTRAZOCALO DE CEMENTO H=0.20m EN INTERIORES
m
57.30
CUBIERTA Y TECHO
CORREAS Y TIRANTES DE MADERA TORNILLO 2"x3"
m
166.74
TIJERALES DE MADERA L=9.1 S/DISEO inc Montaje
und
4.00
COBERTURA CON ETERNIT GRAN ONDA
m2
198.50
CUMBRERA DE ETERNIT GRAN ONDA
m
19.85
CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA TORNILLO
und
2.00
CARPINTERIA METALICA
VENTANA METALICA incl. instalacion
m2
25.07
CERRAJERIA
CERRADURA DE PUERTA 3 GOLPES
pza
2.00
VIDRIOS, CRISTALES Y SIMILARES
VIDRIO CATEDRAL INCOLORO SEMIDOBLE
p2
340.00
PINTURA
PINTURA EN EXTERIORES
m2
88.83
PINTURA EN INTERIORES
m2
221.97
PINTURA LATEX EN CIELORASO
m2
201.53
INSTALACIONES ELECTRICAS
SALIDA DE TECHO PARA CENTRO DE LUZ
pto
16.00
SALIDA PARA TOMACORRIENTE DOBLE
pto
4.00
TABLERO DE DISTRIBUCION METALICO
und
1.00
INSTALACIONES SANITARIAS
CANALETA DE ZINC DE D=6"
m
19.85
TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS
m
4.00
ARTEFACTOS
ARTEFACTO ELECTRICO FLUORECENTE 2x18W
und
4.00
ARTEFACTO ELECTRICO FLUORECENTE 2x36W
und
12.00
OTROS
PIZARRA ACRILICA 1.20mx4.0m
und
2.00
FLETE
FLETE TERRESTRE
glb
1.00
COSTO DIRECTO
GASTOS GENERALES
UTILIDAD
SUB TOTAL (SIN I.G.V.)
FACTOR DE RELACION
MONTO VALORIZADO (SIN I.G.V.)
IMPUESTO GENERAL A LA VENTA (IGV 18%)
TOTAL MONTO VALORIZADO

24.949150%
8.00%

P.U.

P.P.

7/7/2014

Dpto.:
Provincia:
Distrito:
ACUMULADO
Valorizado

AL

7/22/2014

Ancash
Huaraz
Independencia
SALDO
%

Metrado

Valorizado

5.96

160.92

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

27.00

160.92

100.00%

12.05
17.08
18.12
17.41
7.75

1,350.81
1,478.27
792.57
804.86
576.60

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%

112.10
86.55
43.74
46.23
74.40

1,350.81
1,478.27
792.57
804.86
576.60

100.00%
100.00%
100.00%
100.00%
100.00%

59.83
64.52
43.08

7,000.11
4,739.64
476.90

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

117.00
73.46
11.07

7,000.11
4,739.64
476.90

100.00%
100.00%
100.00%

14.78
21.67
57.84
3.80

1,551.90
375.76
3,333.90
276.45

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

105.00
17.34
57.64
72.75

1,551.90
375.76
3,333.90
276.45

100.00%
100.00%
100.00%
100.00%

6.68
6.68

335.00
382.76

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

50.15
57.30

335.00
382.76

100.00%
100.00%

10.82
1,371.68
32.82
36.25

1,804.13
5,486.72
6,514.77
719.56

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

166.74
4.00
198.50
19.85

1,804.13
5,486.72
6,514.77
719.56

100.00%
100.00%
100.00%
100.00%

428.12

856.24

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

856.24

100.00%

167.22

4,192.21

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

25.07

4,192.21

100.00%

77.65

155.30

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

155.30

100.00%

5.50

1,870.00

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

340.00

1,870.00

100.00%

6.51
6.51
6.84

578.28
1,445.02
1,378.47

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

88.83
221.97
201.53

578.28
1,445.02
1,378.47

100.00%
100.00%
100.00%

63.43
63.62
239.53

1,014.88
254.48
239.53

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

16.00
4.00
1.00

1,014.88
254.48
239.53

100.00%
100.00%
100.00%

21.69
36.06

430.55
144.24

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

19.85
4.00

430.55
144.24

100.00%
100.00%

71.63
79.60

286.52
955.20

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

4.00
12.00

286.52
955.20

100.00%
100.00%

200.00

400.00

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

400.00

100.00%

3,500.00

3,500.00

0.30

1050.00

0.28

980.00

28.00%

0.58

2,030.00

58.00%

0.42

1,470.00

42.00%

S/.
S/.
S/.
S/.
S/.
S/.
S/.

111,426.64
27,800.00
8,914.13
148,140.77
1.00
148,140.77
26,665.34
174,806.11

S/.
S/.
S/.
S/.
S/.
S/.
S/.

20,975.24
5,233.14
1,678.02
27,886.40
1.00
27,886.40
5,019.55
32,905.95

S/.
10,049.01
S/.
2,507.14
S/.
803.92
S/. 13,360.07
1.00
S/. 13,360.07
S/.
2,404.81
S/. 15,764.88

9.02%

9.02%

S/.
31,024.25
S/.
7,740.28
S/.
2,481.94
S/. 41,246.47
1.00
S/. 41,246.47
S/.
7,424.36
S/. 48,670.83

27.84%

S/.
S/.
S/.
S/.

27.84%

S/.
S/.
S/.

80,402.39
20,059.72
6,432.19
106,894.30
1.00
106,894.30
19,240.98
126,135.28

72.16%

72.16%

VALORIZACIN DE OBRA N 02 - JULIO


CONTRATO PRINCIPAL
VALORIZACION N:

02

DEL
CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
Plazo de Ejecucin:
90
Fecha de Inicio:
6/23/2014
Fecha de termino:
9/20/2014
A V A N C E S
ANTERIOR
ACTUAL
Metrado
Valorizado
Metrado
Valorizado
%
Metrado

NOMBRE DEL PROYECTO:


EVANOR SAC.
148140.77
Tinyash

CONTRATISTA
COSTO DEL PROYECTO (SIN IGV):
Ubicacin:
Part.

PRESUPUESTO

DESCRIPCION
Und

01
01.01
01.02
02
02.01
02.02
03
03.01
03.02
03.03
04
04.01
04.02
04.03
04.04
05
05.01
05.02
05.03
05.04
05.05
06
06.01
06.01.01
06.01.02
06.02
06.02.01
06.02.02
06.02.03
06.03
06.03.01
06.03.02
06.03.03
06.04
06.04.01
06.04.02
06.04.03
06.05
06.05.01
06.05.02
06.05.03
06.06
06.06.01
06.06.02
06.06.03
07
07.01
07.02
07.03

CONSTRUCCIONES PROVICIONALES
ALQUILER DE ALMACEN DE OBRA
CARTEL DE OBRA DE 2.4m x 3.6m Inc Transp y coloc.
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL
TRAZO Y REPLANTEO EN EDIFICACIONES
SEGURIDAD Y SALUD
EQUIPOS DE PROTECCION INDIVIDUAL
CAPACITACION DE SEGURIDAD Y SALUD
SEALIZACION TEMPORAL DE SEGURIDAD
MOVIMIENTO DE TIERRAS
EXCAVACION PARA CIMIENTOS Y ZAPATAS
RELLENO CON MATERIAL PROPIO MANUAL
ELIMINACION DE MATERIAL EXCEDENTE Dprom=30m
NIVELACION INTERIOR Y APISONADO MANUAL
CONCRETO SIMPLE
SOLADO PARA ZAPATA E=2" Mezcla 1:12 C:H
CONCRETO PARA CIMIENTO CORRIDO 1:10+30%PG
CONCRETO PARA SOBRECIMIENTOS 1:8 + 25%P M
ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO
CONCRETO EN FALSO PISO 4" Mezcla 1:8 C:H
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C=210 Kg/cm2 PARA ZAPATAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
VIGA DE CIMENTACION
ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210Kg/cm2 EN VIGAS DE CIMENTACION
COLUMNAS
ENCOFRADO Y DESENCOFRADO DE COLUMNAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA COLUMNAS
VIGAS Y DINTELES
ENCOFRADO Y DESENCOFRADO DE VIGAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA VIGAS
COLUMNETAS EN MUROS DE ALBAILERIA
ENCOFRADO Y DESENCOFRADO DE COLUMNETAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA COLUMNETAS
VIGAS DE REMATE DE PARAPETO Y ALFEIZER
ENCOFRADO Y DESENCOFRADO DE VIGA REMATE
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA VIGA REMATE
MUROS Y TABIQUES DE ALBAILERIA
MURO DE LADRILLO K.K. 18 huecos DE SOGA 1:5 x 1.5cm
MURO DE LADRILLO K.K. 18 huecos DE CABEZA 1:5 x 1.5cm
ACERO DE REFUERZO HORIZONTAL EN MUROS

Metrado

P.U.

P.P.

7/23/2014

Dpto.:
Provincia:
Distrito:
ACUMULADO
Valorizado

AL

8/6/2014

Ancash
Huaraz
Independencia
SALDO
%

Metrado

Valorizado

mes
und

3.00
1.00

150.00
560.00

450.00
560.00

1.00
1.00

150.00
560.00

0.50
0.00

75.00
0.00

16.67%
0.00%

1.50
1.00

225.00
560.00

50.00%
100.00%

1.50
0.00

225.00
0.00

50.00%
0.00%

m2
m2

200.00
200.00

1.10
0.85

220.00
170.00

200.00
200.00

220.00
170.00

0.00
0.00

0.00
0.00

0.00%
0.00%

200.00
200.00

220.00
170.00

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

glb
glb
glb

1.00
1.00
1.00

902.50
800.00
390.00

902.50
800.00
390.00

1.00
1.00
1.00

902.50
800.00
390.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

1.00
1.00
1.00

902.50
800.00
390.00

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

m3
m3
m3
m2

37.09
14.87
27.77
37.17

15.74
30.09
10.41
1.18

583.80
447.44
289.09
43.86

34.54
0.00
22.50
18.59

543.66
0.00
234.23
21.94

0.00
14.87
3.13
18.58

0.00
447.44
32.58
21.92

0.00%
100.00%
11.27%
49.99%

34.54
14.87
25.63
37.17

543.66
447.44
266.81
43.86

93.12%
100.00%
92.29%
100.00%

2.55
0.00
2.14
0.00

40.14
0.00
22.28
0.00

6.88%
0.00%
7.71%
0.00%

m2
m3
m3
m2
m2

12.60
19.66
3.13
33.79
157.98

19.68
206.16
254.56
35.87
29.49

247.97
4,053.11
796.77
1,212.05
4,658.83

12.60
19.66
3.13
33.79
0.00

247.97
4053.11
796.77
1212.05
0.00

0.00
0.00
0.00
0.00
105.00

0.00
0.00
0.00
0.00
3,096.45

0.00%
0.00%
0.00%
0.00%
66.46%

12.60
19.66
3.13
33.79
105.00

247.97
4,053.11
796.77
1,212.05
3,096.45

100.00%
100.00%
100.00%
100.00%
66.46%

0.00
0.00
0.00
0.00
52.98

0.00
0.00
0.00
0.00
1,562.38

0.00%
0.00%
0.00%
0.00%
33.54%

m3
kg

7.56
152.46

325.48
5.71

2,460.63
870.55

7.56
152.46

2460.63
870.55

0.00
0.00

0.00
0.00

0.00%
0.00%

7.56
152.46

2,460.63
870.55

100.00%
100.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

m2
kg
m3

25.14
459.96
3.14

35.87
5.71
325.48

901.77
2,626.37
1,022.01

25.14
459.96
3.14

901.77
2626.37
1022.01

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

25.14
459.96
3.14

901.77
2,626.37
1,022.01

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

m2
kg
m3

68.00
974.54
4.25

44.65
5.71
396.33

3,036.20
5,564.62
1,684.40

0.00
974.54
0.00

0.00
5564.62
0.00

12.00
0.00
0.75

535.80
0.00
297.25

17.65%
0.00%
17.65%

12.00
974.54
0.75

535.80
5,564.62
297.25

17.65%
100.00%
17.65%

56.00
0.00
3.50

2,500.40
0.00
1,387.16

82.35%
0.00%
82.35%

m2
kg
m3

58.28
720.56
5.27

58.03
5.71
351.13

3,381.99
4,114.40
1,850.46

0.00
137.41
0.00

0.00
784.61
0.00

0.00
137.41
0.00

0.00
784.61
0.00

0.00%
19.07%
0.00%

0.00
274.82
0.00

0.00
1,569.22
0.00

0.00%
38.14%
0.00%

58.28
445.74
5.27

3,381.99
2,545.18
1,850.46

100.00%
61.86%
100.00%

m2
kg
m3

22.32
204.81
1.29

50.16
5.71
352.91

1,119.57
1,169.47
455.25

0.00
0.00
0.00

0.00
0.00
0.00

15.68
185.32
1.02

786.51
1,058.18
359.97

70.25%
90.48%
79.07%

15.68
185.32
1.02

786.51
1,058.18
359.97

70.25%
90.48%
79.07%

6.64
19.49
0.27

333.06
111.29
95.29

29.75%
9.52%
20.93%

m2
kg
m3

5.34
29.74
0.41

50.16
5.71
294.47

267.85
169.82
120.73

0.00
0.00
0.00

0.00
0.00
0.00

0.00
29.74
0.00

0.00
169.82
0.00

0.00%
100.00%
0.00%

0.00
29.74
0.00

0.00
169.82
0.00

0.00%
100.00%
0.00%

5.34
0.00
0.41

267.85
0.00
120.73

100.00%
0.00%
100.00%

m2
m2
kg

51.77
55.09
170.33

96.37
54.52
5.46

4,989.07
3,003.51
930.00

25.89
27.54
85.16

2495.02
1501.48
464.97

25.88
27.55
85.17

2,494.06
1,502.03
465.03

49.99%
50.01%
50.00%

51.77
55.09
170.33

4,989.07
3,003.51
930.00

100.00%
100.00%
100.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

VALORIZACIN DE OBRA N 02 - JULIO


CONTRATO PRINCIPAL
VALORIZACION N:

02

DEL
CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
Plazo de Ejecucin:
90
Fecha de Inicio:
6/23/2014
Fecha de termino:
9/20/2014
A V A N C E S
ANTERIOR
ACTUAL
Metrado
Valorizado
Metrado
Valorizado
%
Metrado

NOMBRE DEL PROYECTO:


EVANOR SAC.
148140.77
Tinyash

CONTRATISTA
COSTO DEL PROYECTO (SIN IGV):
Ubicacin:
Part.

PRESUPUESTO

DESCRIPCION
Und

07.04
08
08.01
08.02
08.03
08.04
08.05
09
09.01
09.02
09.03
10
10.01
10.02
10.03
10.04
11
11.01
11.02
12
12.01
12.02
12.02
12.02
13
13.01
14
14.01
15
15.01
16
16.01
17
17.01
17.02
17.03
18
18.01
18.02
18.03
19
19.01
19.02
20
20.01
20.02
21
21
22
22.01

Metrado

JUNTA DE CONSTRUCCION CON TECKNOPORT 1" PARA MUROS


m
27.00
REVOQUES, ENLUCIDOS Y DERRAMES
TARRAJEO EN INTERIOR 1.5cm MEZCLA 1:5
m2
112.10
TARRAJEO EN EXTERIOR 1.5cm MEZCLA 1:5
m2
86.55
TARRAJEO DE SUPERFICIE DE VIGAS 1.5cm M: 1:5
m2
43.74
TARRAJEO DE SUPERFICIE DE COLUMNAS 1.5cm M: 1:5
m2
46.23
VESTIDURA DE DERRAMES 1.5cm M:1:5
m
74.40
CIELORASO
CIELO RASO CON PLANCHA SUPERBOARD 4mm
m2
117.00
ALERO DE TECHO CON PLANCHA SUPERBOARD 4mm
m2
73.46
FRIZOS PLANCHA SUPERBOARD 6mm
m2
11.07
PISOS Y PAVIMENTOS
PISOS DE CEMENTO E=5cm, PULIDO, COLOREADO Y BRUADO
m2
105.00
ENCOFRADO Y DESENCOFRADO DE VEREDA
m2
17.34
VEREDA DE CONCRETO F'C=175 Kg/cm2 E=0.15m BRUADA+SARDINEL
m2 PASTA1.5cm
57.64
JUNTA ASFALTICA EN VEREDA E=1"
m
72.75
CONTRAZOCALOS
CONTRAZOCALO DE CEMENTO H=0.20m EN EXTERIORES
m
50.15
CONTRAZOCALO DE CEMENTO H=0.20m EN INTERIORES
m
57.30
CUBIERTA Y TECHO
CORREAS Y TIRANTES DE MADERA TORNILLO 2"x3"
m
166.74
TIJERALES DE MADERA L=9.1 S/DISEO inc Montaje
und
4.00
COBERTURA CON ETERNIT GRAN ONDA
m2
198.50
CUMBRERA DE ETERNIT GRAN ONDA
m
19.85
CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA TORNILLO
und
2.00
CARPINTERIA METALICA
VENTANA METALICA incl. instalacion
m2
25.07
CERRAJERIA
CERRADURA DE PUERTA 3 GOLPES
pza
2.00
VIDRIOS, CRISTALES Y SIMILARES
VIDRIO CATEDRAL INCOLORO SEMIDOBLE
p2
340.00
PINTURA
PINTURA EN EXTERIORES
m2
88.83
PINTURA EN INTERIORES
m2
221.97
PINTURA LATEX EN CIELORASO
m2
201.53
INSTALACIONES ELECTRICAS
SALIDA DE TECHO PARA CENTRO DE LUZ
pto
16.00
SALIDA PARA TOMACORRIENTE DOBLE
pto
4.00
TABLERO DE DISTRIBUCION METALICO
und
1.00
INSTALACIONES SANITARIAS
CANALETA DE ZINC DE D=6"
m
19.85
TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS
m
4.00
ARTEFACTOS
ARTEFACTO ELECTRICO FLUORECENTE 2x18W
und
4.00
ARTEFACTO ELECTRICO FLUORECENTE 2x36W
und
12.00
OTROS
PIZARRA ACRILICA 1.20mx4.0m
und
2.00
FLETE
FLETE TERRESTRE
glb
1.00
COSTO DIRECTO
GASTOS GENERALES
UTILIDAD
SUB TOTAL (SIN I.G.V.)
FACTOR DE RELACION
MONTO VALORIZADO (SIN I.G.V.)
IMPUESTO GENERAL A LA VENTA (IGV 18%)
TOTAL MONTO VALORIZADO

24.949150%
8.00%

P.U.

P.P.

7/23/2014

Dpto.:
Provincia:
Distrito:
ACUMULADO
Valorizado

AL

8/6/2014

Ancash
Huaraz
Independencia
SALDO
%

Metrado

Valorizado

5.96

160.92

0.00

0.00

27.00

160.92

100.00%

27.00

160.92

100.00%

0.00

0.00

0.00%

12.05
17.08
18.12
17.41
7.75

1,350.81
1,478.27
792.57
804.86
576.60

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%
0.00%

112.10
86.55
43.74
46.23
74.40

1,350.81
1,478.27
792.57
804.86
576.60

100.00%
100.00%
100.00%
100.00%
100.00%

59.83
64.52
43.08

7,000.11
4,739.64
476.90

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

117.00
73.46
11.07

7,000.11
4,739.64
476.90

100.00%
100.00%
100.00%

14.78
21.67
57.84
3.80

1,551.90
375.76
3,333.90
276.45

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

105.00
17.34
57.64
72.75

1,551.90
375.76
3,333.90
276.45

100.00%
100.00%
100.00%
100.00%

6.68
6.68

335.00
382.76

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

50.15
57.30

335.00
382.76

100.00%
100.00%

10.82
1,371.68
32.82
36.25

1,804.13
5,486.72
6,514.77
719.56

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00%
0.00%
0.00%
0.00%

166.74
4.00
198.50
19.85

1,804.13
5,486.72
6,514.77
719.56

100.00%
100.00%
100.00%
100.00%

428.12

856.24

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

856.24

100.00%

167.22

4,192.21

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

25.07

4,192.21

100.00%

77.65

155.30

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

155.30

100.00%

5.50

1,870.00

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

340.00

1,870.00

100.00%

6.51
6.51
6.84

578.28
1,445.02
1,378.47

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

0.00
0.00
0.00

0.00
0.00
0.00

0.00%
0.00%
0.00%

88.83
221.97
201.53

578.28
1,445.02
1,378.47

100.00%
100.00%
100.00%

63.43
63.62
239.53

1,014.88
254.48
239.53

0.00
0.00
0.00

0.00
0.00
0.00

0.00
4.00
0.00

0.00
254.48
0.00

0.00%
100.00%
0.00%

0.00
4.00
0.00

0.00
254.48
0.00

0.00%
100.00%
0.00%

16.00
0.00
1.00

1,014.88
0.00
239.53

100.00%
0.00%
100.00%

21.69
36.06

430.55
144.24

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

19.85
4.00

430.55
144.24

100.00%
100.00%

71.63
79.60

286.52
955.20

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00%
0.00%

0.00
0.00

0.00
0.00

0.00%
0.00%

4.00
12.00

286.52
955.20

100.00%
100.00%

200.00

400.00

0.00

0.00

0.00

0.00

0.00%

0.00

0.00

0.00%

2.00

400.00

100.00%

3,500.00

3,500.00

0.58

2030.00

0.27

945.00

27.00%

0.85

2,975.00

85.00%

0.15

525.00

15.00%

S/.
S/.
S/.
S/.
S/.
S/.
S/.

111,426.64
27,800.00
8,914.13
148,140.77
1.00
148,140.77
26,665.34
174,806.11

S/.
S/.
S/.
S/.
S/.
S/.
S/.

31,024.25
7,740.29
2,481.94
41,246.48
1.00
41,246.48
7,424.37
48,670.85

S/.
13,487.03
S/.
3,364.90
S/.
1,078.96
S/. 17,930.89
1.00
S/. 17,930.89
S/.
3,227.56
S/. 21,158.45

12.10%

12.10%

S/.
44,511.28
S/.
11,105.19
S/.
3,560.90
S/. 59,177.37
1.00
S/. 59,177.37
S/.
10,651.93
S/. 69,829.30

39.95%

S/.
S/.
S/.
S/.

39.95%

S/.
S/.
S/.

66,915.36
16,694.81
5,353.23
88,963.40
1.00
88,963.40
16,013.41
104,976.81

60.05%

60.05%

RESUMEN DE METRADOS EJECUTADOS


CONTRATO PRINCIPAL

Part.
01
01.01
01.02
02.00
02.01
02.02
03.00
03.01
03.02
03.03
04.00
04.01
04.02
04.03
04.04
05.00
05.01
05.02
05.03
05.04
05.05
06.00
06.01
06.01.01
06.01.02
06.02
06.02.01
06.02.02
06.02.03
06.03
06.03.01
06.03.02
06.03.03
06.04
06.04.01
06.04.02
06.04.03
06.05
06.05.01
06.05.02
06.05.03
06.06
06.06.01
06.06.02
06.06.03
07.00
07.01
07.02

VALORIZACION N:

02

NOMBRE DEL PROYECTO:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ

CONTRATISTA:

EVANOR SAC.

COSTO DEL PROYECTO (SIN IGV):

S/.

Ubicacin:

Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash

148,140.77

METRADO

DESCRIPCION
CONSTRUCCIONES PROVICIONALES
ALQUILER DE ALMACEN DE OBRA
CARTEL DE OBRA DE 2.4m x 3.6m Inc Transp y coloc.
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL
TRAZO Y REPLANTEO EN EDIFICACIONES
SEGURIDAD Y SALUD
EQUIPOS DE PROTECCION INDIVIDUAL
CAPACITACION DE SEGURIDAD Y SALUD
SEALIZACION TEMPORAL DE SEGURIDAD
MOVIMIENTO DE TIERRAS
EXCAVACION PARA CIMIENTOS Y ZAPATAS
RELLENO CON MATERIAL PROPIO MANUAL
ELIMINACION DE MATERIAL EXCEDENTE Dprom=30m
NIVELACION INTERIOR Y APISONADO MANUAL
CONCRETO SIMPLE
SOLADO PARA ZAPATA E=2" Mezcla 1:12 C:H
CONCRETO PARA CIMIENTO CORRIDO 1:10+30%PG
CONCRETO PARA SOBRECIMIENTOS 1:8 + 25%P M
ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO
CONCRETO EN FALSO PISO 4" Mezcla 1:8 C:H
CONCRETO ARMADO
ZAPATAS
CONCRETO F'C=210 Kg/cm2 PARA ZAPATAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
VIGA DE CIMENTACION
ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210Kg/cm2 EN VIGAS DE CIMENTACION
COLUMNAS
ENCOFRADO Y DESENCOFRADO DE COLUMNAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA COLUMNAS
VIGAS Y DINTELES
ENCOFRADO Y DESENCOFRADO DE VIGAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=210 Kg/cm2 PARA VIGAS
COLUMNETAS EN MUROS DE ALBAILERIA
ENCOFRADO Y DESENCOFRADO DE COLUMNETAS
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA COLUMNETAS
VIGAS DE REMATE DE PARAPETO Y ALFEIZER
ENCOFRADO Y DESENCOFRADO DE VIGA REMATE
ACERO DE REFUERZO F'y=4200 Kg/cm2
CONCRETO F'C=175 Kg/cm2 PARA VIGA REMATE
MUROS Y TABIQUES DE ALBAILERIA
MURO DE LADRILLO K.K. 18 huecos DE SOGA 1:5 x 1.5cm
MURO DE LADRILLO K.K. 18 huecos DE CABEZA 1:5 x 1.5cm

Und

1Q

2Q

Metrado

mes
und

0.50
0.00

0.50
0.00

1.00
0.00

m2
m2

0.00
0.00

0.00
0.00

0.00
0.00

glb
glb
glb

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

m3
m3
m3
m2

0.00
0.00
0.00
18.59

0.00
14.87
3.13
18.58

0.00
14.87
3.13
37.17

m2
m3
m3
m2
m2

0.00
0.00
3.13
33.79
0.00

0.00
0.00
0.00
0.00
105.00

0.00
0.00
3.13
33.79
105.00

m3
kg

0.00
0.00

0.00
0.00

0.00
0.00

m2
kg
m3

19.38
0.00
3.14

0.00
0.00
0.00

19.38
0.00
3.14

m2
kg
m3

0.00
0.00
0.00

12.00
0.00
0.75

12.00
0.00
0.75

m2
kg
m3

0.00
137.41
0.00

0.00
137.41
0.00

0.00
274.82
0.00

m2
kg
m3

0.00
0.00
0.00

15.68
185.32
1.02

15.68
185.32
1.02

m2
kg
m3

0.00
0.00
0.00

0.00
29.74
0.00

0.00
29.74
0.00

m2
m2

25.89
27.54

25.88
27.55

51.77
55.09

RESUMEN DE METRADOS EJECUTADOS


CONTRATO PRINCIPAL

Part.

VALORIZACION N:

02

NOMBRE DEL PROYECTO:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ

CONTRATISTA:

EVANOR SAC.

COSTO DEL PROYECTO (SIN IGV):

S/.

Ubicacin:

Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash

148,140.77

METRADO

DESCRIPCION
Und

07.03
07.04
08.00
08.01
08.02
08.03
08.04
08.05
09.00
09.01
09.02
09.03
10.00
10.01
10.02
10.03
10.04
11.00
11.01
11.02
12.00
12.01
12.02
12.02
12.02
13.00
13.01
14.00
14.01
15.00
15.01
16.00
16.01
17.00
17.01
17.02
17.03
18.00
18.01
18.02
18.03
19.00
19.01
19.02
20.00
20.01
20.02
21.00
21.01
22.00
22.01

ACERO DE REFUERZO HORIZONTAL EN MUROS


kg
JUNTA DE CONSTRUCCION CON TECKNOPORT 1" PARA MUROS
m
REVOQUES, ENLUCIDOS Y DERRAMES
TARRAJEO EN INTERIOR 1.5cm MEZCLA 1:5
m2
TARRAJEO EN EXTERIOR 1.5cm MEZCLA 1:5
m2
TARRAJEO DE SUPERFICIE DE VIGAS 1.5cm M: 1:5
m2
TARRAJEO DE SUPERFICIE DE COLUMNAS 1.5cm M: 1:5
m2
VESTIDURA DE DERRAMES 1.5cm M:1:5
m
CIELORASO
CIELO RASO CON PLANCHA SUPERBOARD 4mm
m2
ALERO DE TECHO CON PLANCHA SUPERBOARD 4mm
m2
FRIZOS PLANCHA SUPERBOARD 6mm
m2
PISOS Y PAVIMENTOS
PISOS DE CEMENTO E=5cm, PULIDO, COLOREADO Y BRUADO
m2
ENCOFRADO Y DESENCOFRADO DE VEREDA
m2
VEREDA DE CONCRETO F'C=175 Kg/cm2 E=0.15m BRUADA+SARDINEL PASTA1.5cm
m2
JUNTA ASFALTICA EN VEREDA E=1"
m
CONTRAZOCALOS
CONTRAZOCALO DE CEMENTO H=0.20m EN EXTERIORES
m
CONTRAZOCALO DE CEMENTO H=0.20m EN INTERIORES
m
CUBIERTA Y TECHO
CORREAS Y TIRANTES DE MADERA TORNILLO 2"x3"
m
TIJERALES DE MADERA L=9.1 S/DISEO inc Montaje
und
COBERTURA CON ETERNIT GRAN ONDA
m2
CUMBRERA DE ETERNIT GRAN ONDA
m
CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA TORNILLO
und
CARPINTERIA METALICA
VENTANA METALICA incl. instalacion
m2
CERRAJERIA
CERRADURA DE PUERTA 3 GOLPES
pza
VIDRIOS, CRISTALES Y SIMILARES
VIDRIO CATEDRAL INCOLORO SEMIDOBLE
p2
PINTURA
PINTURA EN EXTERIORES
m2
PINTURA EN INTERIORES
m2
PINTURA LATEX EN CIELORASO
m2
INSTALACIONES ELECTRICAS
SALIDA DE TECHO PARA CENTRO DE LUZ
pto
SALIDA PARA TOMACORRIENTE DOBLE
pto
TABLERO DE DISTRIBUCION METALICO
und
INSTALACIONES SANITARIAS
CANALETA DE ZINC DE D=6"
m
TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS
m
ARTEFACTOS
ARTEFACTO ELECTRICO FLUORECENTE 2x18W
und
ARTEFACTO ELECTRICO FLUORECENTE 2x36W
und
OTROS
PIZARRA ACRILICA 1.20mx4.0m
und
FLETE
FLETE TERRESTRE
glb

1Q

2Q

Metrado

85.16
0.00

85.17
27.00

170.33
27.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00

0.00
4.00
0.00

0.00
4.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00

0.00

0.00

0.00

0.28

0.27

0.55

RESUMEN TOTAL DE PAGOS A CUENTA POR VALORIZACIONES

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ
Monto de Contrato Vigente: S/. 174,806.11 (INC. IGV)
Ejecuta: EVANOR SAC.
Fecha de Inicio: 6/23/2014

VALORIZACIN N

PORCENTAJE
VALORIZADO

01

18.82%

S/.

27,886.40

S/.

5,019.55

02

21.13%

S/.

31,290.96

S/.

5,632.37

S/.

59,177.36

S/.

10,651.92

TOTAL

VALORIZACION
(SIN IGV)

Notas:

1. EL CONTRATISTA NO HA SOLICITADO NINGN TIPO DE ADELANTO.

MONTO PAGADO AL
CONTRATISTA
(INC. IGV)

RETENCIN
(INC IGV)

IGV (18%)

S/.

S/.

S/.

32,905.95

S/.

36,923.33

S/.

69,829.28

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA


CONTRATO PRINCIPAL

EJECUTOR:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ
Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash
EVANOR SAC.

Id

Nombre

PROYECTO:
LUGAR:

PROGRAMACIN DE OBRA

Duracin Inicio
88

Fin

Quincena 1

lun 23/06/14

sb 20/09/14

CONSTRUCCIONES PROVICIONALES

1 da

lun 23/06/14

mar 24/06/14

1.01

ALQUILER DE ALMACEN DE OBRA

1 da

mar 24/06/14

mar 24/06/14

1.02

CARTEL DE OBRA DE 2.4m x 3.6m Inc Transp y coloc.

1 da

lun 23/06/14

lun 23/06/14
sb 28/06/14

6 das

lun 23/06/14

2.01

LIMPIEZA DE TERRENO MANUAL

4 das

lun 23/06/14

jue 26/06/14

2.02

TRAZO Y REPLANTEO EN EDIFICACIONES

2 das

vie 27/06/14

sb 28/06/14

TRABAJOS PRELIMINARES

1 da

mar 24/06/14

mar 24/06/14

3.01

EQUIPOS DE PROTECCION INDIVIDUAL

1 da

mar 24/06/14

mar 24/06/14

3.02

CAPACITACION DE SEGURIDAD Y SALUD

1 da

mar 24/06/14

mar 24/06/14

3.03
4

SEGURIDAD Y SALUD

SEALIZACION TEMPORAL DE SEGURIDAD


MOVIMIENTO DE TIERRAS

1 da

mar 24/06/14

mar 24/06/14

15 das

lun 30/06/14

mi 16/07/14

4.01

EXCAVACION PARA CIMIENTOS Y ZAPATAS

7 das

lun 30/06/14

lun 07/07/14

4.02

RELLENO CON MATERIAL PROPIO MANUAL

2 das

mar 08/07/14

mi 09/07/14

4.03

ELIMINACION DE MATERIAL EXCEDENTE Dprom=30m

5 das

vie 11/07/14

mi 16/07/14

4.04

NIVELACION INTERIOR Y APISONADO MANUAL

1 da

jue 10/07/14

jue 10/07/14

21 das

vie 11/07/14

lun 04/08/14

CONCRETO SIMPLE

5.01

SOLADO PARA ZAPATA E=2" Mezcla 1:12 C:H

1 da

vie 11/07/14

vie 11/07/14

5.02

CONCRETO PARA CIMIENTO CORRIDO 1:10+30%PG

1 da

mar 15/07/14

mar 15/07/14

5.03

CONCRETO PARA SOBRECIMIENTOS 1:8 + 25%P M

1 da

sb 19/07/14

sb 19/07/14

5.04

ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO

3 das

mi 16/07/14

vie 18/07/14

5.05

CONCRETO EN FALSO PISO 4" Mezcla 1:8 C:H

2 das

sb 02/08/14

lun 04/08/14

27 das

sb 12/07/14

lun 11/08/14
lun 14/07/14

CONCRETO ARMADO

Quincena 2

Quincena 3

Quincena 4

S/. 450.00
S/. 560.00
S/. 220.00
S/. 170.00
S/. 902.50
S/. 800.00
S/. 390.00
S/. 500.40

S/. 83.40
S/. 447.44
S/. 289.09
S/. 43.86
S/. 247.97
S/. 4,053.11
S/. 796.77
S/. 1,212.05
S/. 2,329.42

6.01

ZAPATAS

2 das

sb 12/07/14

06.01.01

CONCRETO F'C=210 Kg/cm2 PARA ZAPATAS

1 da

lun 14/07/14

lun 14/07/14

06.01.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

1 da

sb 12/07/14

sb 12/07/14

6.02

VIGA DE CIMENTACION

8 das

lun 14/07/14

mar 22/07/14

06.02.01

ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION

5 das

mi 16/07/14

lun 21/07/14

06.02.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

2 das

lun 14/07/14

mar 15/07/14

06.02.03

CONCRETO F'C=210Kg/cm2 EN VIGAS DE CIMENTACION

1 da

mar 22/07/14

mar 22/07/14

6.03

COLUMNAS

11 das

mi 23/07/14

lun 04/08/14

06.03.01

ENCOFRADO Y DESENCOFRADO DE COLUMNAS

5 das

lun 28/07/14

vie 01/08/14

S/. 3,036.20

06.03.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

4 das

mi 23/07/14

sb 26/07/14

06.03.03

CONCRETO F'C=210 Kg/cm2 PARA COLUMNAS

2 das

sb 02/08/14

lun 04/08/14

S/. 5,564.62
S/. 842.20

6.04

VIGAS Y DINTELES

7 das

mar 05/08/14

lun 11/08/14

06.04.01

ENCOFRADO Y DESENCOFRADO DE VIGAS

3 das

jue 07/08/14

sb 09/08/14

06.04.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

3 das

mar 05/08/14

mi 06/08/14

06.04.03

CONCRETO F'C=210 Kg/cm2 PARA VIGAS

1 da

lun 11/08/14

lun 11/08/14

6.05

COLUMNETAS EN MUROS DE ALBAILERIA

5 das

mar 22/07/14

sb 26/07/14

06.05.01

ENCOFRADO Y DESENCOFRADO DE COLUMNETAS

3 das

mi 23/07/14

vie 25/07/14

06.05.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

1 da

mar 22/07/14

mar 22/07/14

06.05.03

CONCRETO F'C=175 Kg/cm2 PARA COLUMNETAS

1 da

sb 26/07/14

sb 26/07/14

S/. 2,329.42

S/. 2,460.63
S/. 870.55
S/. 721.42
S/. 2,626.37

S/. 180.35
S/. 1,022.01

S/. 842.20
S/. 3,381.99
S/. 4,114.40
S/. 1,850.46

S/. 1,119.57
S/. 1,169.47
S/. 455.25

Quincena 5

Quincena 6

Quincena 7

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA


CONTRATO PRINCIPAL

EJECUTOR:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ
Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash
EVANOR SAC.

Id

Nombre

PROYECTO:
LUGAR:

Duracin Inicio

Fin

Quincena 1

6.06

VIGAS DE REMATE DE PARAPETO Y ALFEIZER

3 das

06.06.01

ENCOFRADO Y DESENCOFRADO DE VIGA REMATE

1 da

lun 28/07/14

lun 28/07/14

06.06.02

ACERO DE REFUERZO F'y=4200 Kg/cm2

1 da

mar 29/07/14

mar 29/07/14
mi 30/07/14

06.06.03
7

CONCRETO F'C=175 Kg/cm2 PARA VIGA REMATE


MUROS Y TABIQUES DE ALBAILERIA

lun 28/07/14

1 da

mi 30/07/14

11 das

lun 21/07/14

vie 01/08/14

7.01

MURO DE LADRILLO K.K. 18 huecos DE SOGA 1:5 x 1.5cm

9 das

lun 21/07/14

mi 30/07/14

7.02

MURO DE LADRILLO K.K. 18 huecos DE CABEZA 1:5 x 1.5cm

6 das

lun 21/07/14

sb 26/07/14

7.03

ACERO DE REFUERZO HORIZONTAL EN MUROS

1 da

lun 21/07/14

lun 21/07/14

7.04

JUNTA DE CONSTRUCCION CON TECKNOPORT 1" PARA MUROS

2 das

jue 31/07/14

vie 01/08/14

19 das

sb 02/08/14

jue 21/08/14

REVOQUES, ENLUCIDOS Y DERRAMES

8.01

TARRAJEO EN INTERIOR 1.5cm MEZCLA 1:5

7 das

sb 02/08/14

sb 09/08/14

8.02

TARRAJEO EN EXTERIOR 1.5cm MEZCLA 1:5

8 das

sb 02/08/14

lun 11/08/14

8.03

TARRAJEO DE SUPERFICIE DE VIGAS 1.5cm M: 1:5

5 das

mar 12/08/14

vie 15/08/14

8.04

TARRAJEO DE SUPERFICIE DE COLUMNAS 1.5cm M: 1:5

4 das

mar 05/08/14

jue 07/08/14

VESTIDURA DE DERRAMES 1.5cm M:1:5

5 das

sb 16/08/14

jue 21/08/14

9 das

sb 23/08/14

mar 02/09/14

8.05
9

CIELORASO

9.01

CIELO RASO CON PLANCHA SUPERBOARD 4mm

8 das

sb 23/08/14

lun 01/09/14

9.02

ALERO DE TECHO CON PLANCHA SUPERBOARD 4mm

7 das

sb 23/08/14

sb 30/08/14

9.03
10

FRIZOS PLANCHA SUPERBOARD 6mm


PISOS Y PAVIMENTOS

1 da

mar 02/09/14

mar 02/09/14

11 das

vie 22/08/14

mi 03/09/14

10.01

PISOS DE CEMENTO E=5cm, PULIDO, COLOREADO Y BRUADO

1 da

vie 22/08/14

vie 22/08/14

10.02

ENCOFRADO Y DESENCOFRADO DE VEREDA

2 das

vie 29/08/14

sb 30/08/14

10.03

VEREDA DE CONCRETO F'C=175 Kg/cm2 E=0.15m BRUADA+SARDINEL PASTA1.5cm

2 das

lun 01/09/14

mar 02/09/14

10.04

JUNTA ASFALTICA EN VEREDA E=1"

1 da

mi 03/09/14

mi 03/09/14

6 das

vie 22/08/14

jue 28/08/14

11.01

CONTRAZOCALO DE CEMENTO H=0.20m EN EXTERIORES

3 das

vie 22/08/14

lun 25/08/14

11.02

CONTRAZOCALO DE CEMENTO H=0.20m EN INTERIORES

3 das

mar 26/08/14

jue 28/08/14

11

CONTRAZOCALOS

10 das

mar 12/08/14

vie 22/08/14

12.01

CORREAS Y TIRANTES DE MADERA TORNILLO 2"x3"

2 das

sb 16/08/14

lun 18/08/14

12.02

TIJERALES DE MADERA L=9.1 S/DISEO inc Montaje

4 das

mar 12/08/14

vie 15/08/14

12.02

COBERTURA CON ETERNIT GRAN ONDA

3 das

mar 19/08/14

jue 21/08/14

12.02

CUMBRERA DE ETERNIT GRAN ONDA

1 da

vie 22/08/14

vie 22/08/14

1 da

jue 18/09/14

jue 18/09/14

1 da

jue 18/09/14

jue 18/09/14

7 das

vie 12/09/14

mi 17/09/14

7 das

vie 12/09/14

mi 17/09/14

1 da

vie 19/09/14

vie 19/09/14

12

13
13.01
14
14.01
15
15.01
16
16.01
17

CUBIERTA Y TECHO

CARPINTERIA DE MADERA
PUERTA APANELADA DE MADERA TORNILLO
CARPINTERIA METALICA
VENTANA METALICA incl. instalacion
CERRAJERIA
CERRADURA DE PUERTA 3 GOLPES
VIDRIOS, CRISTALES Y SIMILARES
VIDRIO CATEDRAL INCOLORO SEMIDOBLE
PINTURA

Quincena 2

Quincena 3

Quincena 4

Quincena 5

Quincena 6

Quincena 7

mi 30/07/14

1 da

vie 19/09/14

vie 19/09/14

3 das

jue 18/09/14

vie 19/09/14

3 das

jue 18/09/14

vie 19/09/14

17 das

vie 29/08/14

jue 11/09/14

17.01

PINTURA EN EXTERIORES

5 das

vie 29/08/14

mar 02/09/14

17.02

PINTURA EN INTERIORES

7 das

mi 03/09/14

sb 06/09/14

S/. 267.85
S/. 169.82
S/. 120.73
S/. 4,989.07
S/. 3,003.51
S/. 930.00
S/. 160.92
S/. 192.97
S/. 184.78

S/. 1,157.84
S/. 1,293.48
S/. 792.57
S/. 804.86
S/. 115.32

S/. 461.28
S/. 6,125.09
S/. 4,739.64

S/. 875.01
S/. 476.90

S/. 1,551.90
S/. 375.76
S/. 3,333.90
S/. 276.45
S/. 335.00
S/. 382.76
S/. 902.07
S/. 5,486.72

S/. 902.07
S/. 6,514.77
S/. 719.56
S/. 856.24

S/. 1,676.88

S/. 2,515.33
S/. 155.30
S/. 1,870.00

S/. 289.14

S/. 289.14
S/. 1,445.02

CRONOGRAMA VALORIZADO DE AVANCE DE OBRA


CONTRATO PRINCIPAL

EJECUTOR:

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ
Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash
EVANOR SAC.

Id

Nombre

PROYECTO:
LUGAR:

17.03

PINTURA LATEX EN CIELORASO

Duracin Inicio

Fin

5 das

lun 08/09/14

Quincena 1

6 das

vie 12/09/14

jue 18/09/14

18.01

SALIDA DE TECHO PARA CENTRO DE LUZ

4 das

vie 12/09/14

mar 16/09/14

18.02

SALIDA PARA TOMACORRIENTE DOBLE

1 da

mi 17/09/14

mi 17/09/14
jue 18/09/14

18

18.03
19

INSTALACIONES ELECTRICAS

TABLERO DE DISTRIBUCION METALICO


INSTALACIONES SANITARIAS

1 da

jue 18/09/14

2 das

mi 03/09/14

jue 04/09/14

19.01

CANALETA DE ZINC DE D=6"

1 da

mi 03/09/14

mi 03/09/14

19.02

TUBERIA DE BAJADA PVC - SAL 3" P/ LLUVIAS

1 da

jue 04/09/14

jue 04/09/14
vie 19/09/14

20

19 das

vie 05/09/14

20.01

ARTEFACTO ELECTRICO FLUORECENTE 2x18W

1 da

vie 19/09/14

vie 19/09/14

20.02

ARTEFACTO ELECTRICO FLUORECENTE 2x36W

2 das

vie 05/09/14

sb 06/09/14

1 da

sb 20/09/14

sb 20/09/14

1 da

sb 20/09/14

sb 20/09/14

1 da

mar 24/06/14

mar 24/06/14

mar 24/06/14

mar 24/06/14

21
21.01
22
22.01

ARTEFACTOS

OTROS
PIZARRA ACRILICA 1.20mx4.0m
FLETE
FLETE TERRESTRE

1 da

COSTO DIRECTO

Quincena 3

Quincena 4

Quincena 5

Quincena 6

Quincena 7

S/. 1,378.47
S/. 507.44

S/. 507.44
S/. 254.48
S/. 239.53

S/. 430.55
S/. 144.24
S/. 286.52

S/. 955.20
S/. 400.00
S/. 3,500.00
S/.

7,492.90

S/.

13,852.66

S/.

25,738.74

S/.

23,071.33

S/.

22,396.97

S/.

11,789.20

S/.

7,084.84

S/.

1,869.41

S/.

3,456.12

S/.

6,421.60

S/.

5,756.10

S/.

5,587.85

S/.

2,941.31

S/.

1,767.61

UTILIDAD (8%)

S/.

599.43

S/.

1,108.21

S/.

2,059.10

S/.

1,845.71

S/.

1,791.76

S/.

943.14

S/.

566.78

SUB TOTAL

S/.

9,961.74

S/.

18,416.99

S/.

34,219.44

S/.

30,673.14

S/.

29,776.58

S/.

15,673.65

S/.

9,419.23

IGV

S/.

0.2494915 GASTOS GENERALES (24.949%)


8.00%

Quincena 2

jue 11/09/14

18%

1,793.11

S/.

3,315.06

S/.

6,159.50

S/.

5,521.17

S/.

5,359.78

S/.

2,821.26

S/.

1,695.46

VALORIZACION QUINCENAL

S/. 11,754.85

S/.

21,732.05

S/.

40,378.94

S/.

36,194.31

S/.

35,136.36

S/.

18,494.91

S/.

11,114.69

VALORIZACION ACUMULADA

S/. 11,754.85

S/.

33,486.90

S/.

73,865.84

S/. 110,060.15

S/.

145,196.51

S/.

163,691.42

S/.

174,806.11

PORCENTAJE QUINCENAL

6.72%

12.43%

23.10%

20.71%

20.10%

10.58%

6.36%

PORCENTAJE ACUMULADO

6.72%

19.15%

42.25%

62.96%

83.06%

93.64%

100.00%

CONDICIN DE LA OBRA - CURVA "S"


CONTRATO PRINCIPAL
CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
MONTO CONT. (SIN IGV)

S/.148,140.77

Inicio:

Plazo:

6/23/2014

Trmino:

90

Departamento:

Ancash

Distrito:

Provincia:

Huaraz

Localidad:

9/20/2014

Independencia
Tinyash

CURVA "S"
Programado vs Ejecutado
GENERAL
100%

90%

80%

70%

60%

50%

40%

30%
% de Avance Acumulado Programado
20%

% de Avance Acumulado Ejecutado

10%

0%
inicio de obra

Quincena 1

Quincena 2

PERIODO

Quincena 3

Quincena 4

Quincena 5

Quincena 6

Quincena 7

Quincena
inicio
de obra 1

Quincena 2

Quincena 3

Quincena 4

Quincena 5

Quincena 6

Quincena 7

Monto mes

S/. 9,961.74

S/. 18,416.99

S/. 30,673.14

S/. 29,776.58

Monto Acumulados

S/. 9,961.74

S/. 28,378.73

S/. 59,051.87

S/. 88,828.45

S/. 15,673.65

S/. 9,419.23

S/. 148,140.77

S/. 104,502.10

S/. 113,921.33

% de avance Quincena

6.72%

12.43%

23.10%

20.71%

20.10%

10.58%

S/. 262,062.10
6.36%

% de Avance Acumulado Programado

6.72%

19.15%

42.25%

62.96%

83.06%

93.64%

100.00%

AVANCE PROGRAMADO

Quincena 1

Quincena 2

Quincena 3

Quincena 4

Quincena 5

Quincena 6

Quincena 7

Monto Quincena

AVANCE EJECUTADO

S/. 27,886.40

S/. 13,360.07

S/. 17,930.89

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

Monto Acumulados

S/. 27,886.40

S/. 41,246.47

S/. 59,177.36

S/. 0.00

S/. 0.00

S/. 0.00

S/. 0.00

% de avance Quincena

18.82%

9.02%

12.10%

0.00%

0.00%

0.00%

0.00%

% de Avance Acumulado Ejecutado

18.82%

27.84%

39.94%

0.00%

0.00%

0.00%

0.00%

148140.77

CONDICIN DE OBRA

Adelantada

Adelantada

Retrasada

CUADRO DE RESUMEN DE REAJUSTE


OBRA

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ

UBICACIN

Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash

CONTRATISTA

EVANOR SAC.

MODALIDAD
FECHA PRESUPUESTO

A suma alzada
11/21/2013

AREA GEOGRAFICA

ZONA 02

DESCRIPCION

PRESUPUESTO CONTRATO PRINCIPAL

REAJUSTE
ACUMULADO
ACTUAL

0.00

REAJUSTE
ACUMULADO
ANTERIOR

0.00

REAJUSTE
RECONOCIDO DEL
MES

0.00

REAJUSTE
CALCULADO PARA
EL MES

35.86

REAJUSTE POR LOS


MESES ANTERIORES

-35.86

CALCULO DEL REAJUSTE RECONOCIDO


CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL
DE TINYASH
- INDEPENDENCIA - HUARAZ
Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash
EVANOR SAC.
A suma alzada
11/21/2013
ZONA 02

OBRA
UBICACIN
CONTRATISTA
MODALIDAD
FECHA PRESUPUESTO
AREA GEOGRAFICA
1. CONTRATO PRINCIPAL
EJECUTADO
VAL

REAL

REAL
ACUMULADO

PROGRAMADO
PROGRAMADO

"K" del mes

PROG.
ACUMULADO

MES

REAJUSTES (V*(K-1))
REAL

REAL
ACUMULADO

PROGRAM

PROG.
ACUMULADO

REAJUSTE
RECONOCIDO

VAL N 01 (Ene)

101,739.79

101,739.79

9,961.74

9,961.74

Jan-14

1.002

203.48

203.48

19.92

19.92

203.48

VAL N 02 (Feb)

17,930.89

119,670.68

18,416.99

28,378.73

Jan-14

1.002

35.86

239.34

36.83

56.75

35.86

VAL N 03 (Mar)
TOTAL

119,670.68

28,378.73

* Por estar la obra adelantada permanentemente se paga el reajuste calculado

239.34

56.75

239.34

CALCULO DEL K - CONTRATO PRINCIPAL


OBRA

CONSTRUCCION DE DOS AULAS EN LA I.E. DEL CASERIO SAN MIGUEL


DE TINYASH
- INDEPENDENCIA - HUARAZ

UBICACIN

Dist. de Independencia - Prov. de Huaraz - Dept. de Ancash

CONTRATISTA

EVANOR SAC.

MODALIDAD

A suma alzada

FECHA PRESUPUESTO

11/21/2013

AREA GEOGRAFICA

ZONA 02

K = 0.305*(Ir / Io) + 0.257*(Jr / Jo) + 0.137*(Cr / Co) + 0.135*(Ar / Ao) + 0.101*(Mr / Mo) + 0.065*(ACr / ACo)

DESCRIPCION

INDICE

FACTOR

Dec-13

Jan-14

SIMB.

INDICE GENERAL DE PRECIOS AL CONSUMIDOR

39

0.305

100.00%

391.57

392.22

0.306

393.46

0.306

MANO DE OBRA INC. LEYES SOCIALES

47

0.257

100.00%

497.55

497.55

0.257

498.10

0.257

CEMENTO PORTLAND TIPO I

21

0.137

100.00%

339.42

339.42

0.137

339.42

0.137

AGREGADO GRUESO

05

0.135

100.00%

218.16

218.23

0.135

218.23

0.135

MAQUINARIA Y EQUIPO IMPORTADO

49

0.101

100.00%

248.12

246.97

0.101

249.28

0.101

AC

ACERO DE CONSTRUCCION LISO

02

0.065

100.00%

480.08

478.63

0.065

479.33

0.065

(f)

Nov-13

MONOMIO

IU

FACTOR DE REAJUSTE = K =

IU

K PARCIAL

1.000

IU

K PARCIAL

1.002

S-ar putea să vă placă și