Documente Academic
Documente Profesional
Documente Cultură
FINANCIAL MANAGEMENT
Section – F2
Group Members:
Aarti Purohit
Arun Koshiya
Jai Shankar Patel
Pushpa Patel
Priyanka Biswas
Reshma Dsouza
Varun Maurya
1
1. INVENTORY MANAGEMENT: 3
• Basic about inventory, what do we mean by inventory, Objective etc.
1. NATURE OF INVENTORY: 7
• Raw material
• Work in progress
• Finished goods
1. TYPES OF INVENTORY: 9
• Transit Inventory
• Buffer Inventory
• Anticipation Inventory
• Decoupling Inventory
• Cycle Inventory
• MRO Goods Inventory
• Theoretical Inventory
• FIFO
• LIFO
• Weighted average cost method
• Standard price (cost) method
• Reports can be generated from the Inventory and Asset Management Systems
that would project the amount of revenue that can be generated through the sale
of surplus equipment, or to define the number of components that have a
criticality rating of ‘1’ so that you can project the costs associated with
3
maintaining duplicates of critical equipment at recovery sites. Combining the two
reports would allow you to reroute equipment being scheduled for termination to
the Recovery Facility and eliminate the additional costs associated with
purchasing duplicate
Why would a firm hold more inventory than is currently necessary to ensure the firm's
operation? The following is a list of reasons for maintaining what would appear to be
"excess" inventory.
4
Table 1
MEET DEMAND:
In order for a retailer to stay in business, it must have the products that the
customer wants on hand when the customer wants them. If not, the retailer
will have to back-order the product. If the customer can get the good from
some other source, he or she may choose to do so rather than electing to
allow the original retailer to meet demand later (through back-order).
Hence, in many instances, if a good is not in inventory, a sale is lost
forever.
KEEP OPERATIONS RUNNING:
A manufacturer must have certain purchased items (raw materials, components, or
subassemblies) in order to manufacture its product. Running out of only one item can
prevent a manufacturer from completing the production of its finished goods.
Inventory between successive dependent operations also serves to decouple the
dependency of the operations. A machine or work center is often dependent upon the
previous operation to provide it with parts to work on. If work ceases at a work center,
then all subsequent centers will shut down for lack of work. If a supply of work-in-
process inventory is kept between each work center, then each machine can maintain
its operations for a limited time, hopefully until operations resume the original center.
LEAD TIME:
Lead time is the time that elapses between the placing of an order (either a purchase
order or a production order issued to the shop or the factory floor) and actually receiving
the goods ordered.
If a supplier (an external firm or an internal department or plant) cannot supply the
required goods on demand, then the client firm must keep an inventory of the needed
goods. The longer the lead time, the larger the quantity of goods the firm must carry in
inventory.
Example:
HEDGE:
Inventory can also be used as a hedge against price increases and inflation. Salesmen
routinely call purchasing agents shortly before a price increase goes into effect. This
gives the buyer a chance to purchase material, in excess of current need, at a price that
is lower than it would be if the buyer waited until after the price increase occurs.
QUANTITY DISCOUNT:
Often firms are given a price discount when purchasing large quantities of a good. This
also frequently results in inventory in excess of what is currently needed to meet
demand. However, if the discount is sufficient to offset the extra holding cost incurred as
a result of the excess inventory, the decision to buy the large quantity is justified.
SMOOTHING REQUIREMENTS:
Sometimes inventory is used to smooth demand requirements in a market where
demand is somewhat erratic. Consider the demand forecast and production schedule
outlined in Table 1.
Notice how the use of inventory has allowed the firm to maintain a steady rate of output
(thus avoiding the cost of hiring and training new personnel), while building up inventory
in anticipation of an increase in demand. In fact, this is often called anticipation
inventory. In essence, the use of inventory has allowed the firm to move demand
requirements to earlier periods, thus smoothing the demand.
ACHIEVING EFFICIENT PRODUCTION RUNS:
Maintenance of large inventories helps a firm in reducing the set up cost associated
with each production run. For example: if a set up cost is rs.200 and the run produces
200 units, the cost per unit comes toRs.1. In case, the run produce is 2ooo units, the set
up cost will stand reduce to Rs. 0.10 per unit. Thus, inventories assists the firm in
making sufficiently high run resulting in lowering down the set up cost.
Inventory example
While accountants often discuss inventory in terms of goods for sale, organizations
- manufacturers, service-providers and not-for-profits - also have inventories (fixtures,
furniture, supplies, ...) that they do not intend to sell. Manufacturers', distributors', and
wholesalers' inventory tends to cluster in warehouses. Retailers' inventory may exist in
a warehouse or in a shop or store accessible to customers. Inventories not intended for
sale to customers or to clients may be held in any premises an organization uses. Stock
ties up cash and if uncontrolled it will be impossible to know the actual level of stocks
and therefore impossible to control them.
While the reasons for holding stock are covered earlier, most manufacturing
organizations usually divide their "goods for sale" inventory into:
Raw materials - materials and components scheduled for use in making a product.
6
Work in process, WIP - materials and components that have begun their
transformation to finished goods.
Finished goods - goods ready for sale to customers.
Goods for resale - returned goods that are salable.
Spare parts
1. NATURE OF INVENTORY:
Inventory is defined as a stock or store of goods. These goods are maintained on hand
at or near a business's location so that the firm may meet demand and fulfill its reason
for existence. If the firm is a retail establishment, a customer may look elsewhere to
have his or her needs satisfied if the firm does not have the required item in stock when
the customer arrives. If the firm is a manufacturer, it must maintain some inventory of
raw materials and work-in-process in order to keep the factory running. In addition, it
must maintain some supply of finished goods in order to meet demand.
Sometimes, a firm may keep larger inventory than is necessary to meet demand and
keep the factory running under current conditions of demand. If the firm exists in a
volatile environment where demand is dynamic (i.e., rises and falls quickly), an on-hand
inventory could be maintained as a buffer against unexpected changes in demand. This
buffer inventory also can serve to protect the firm if a supplier fails to deliver at the
required time, or if the supplier's quality is found to be substandard upon inspection,
either of which would otherwise leave the firm without the necessary raw materials.
Other reasons for maintaining an unnecessarily large inventory include buying to take
advantage of quantity discounts (i.e., the firm saves by buying in bulk), or ordering more
in advance of an impending price increase.
Generally, inventory types can be grouped into four classifications: raw material, work-
in-process, finished goods, and MRO goods.
RAW MATERIALS:
Raw materials are inventory items that are used in the manufacturer's conversion
process to produce components, subassemblies, or finished products. These
inventory items may be commodities or extracted materials that the firm or its
subsidiary has produced or extracted. They also may be objects or elements that the
firm has purchased from outside the organization. Even if the item is partially
assembled or is considered a finished good to the supplier, the purchaser may
classify it as a raw material if his or her firm had no input into its production.
Typically, raw materials are commodities such as ore, grain, minerals, petroleum,
chemicals, paper, wood, paint, steel, and food items. However, items such as nuts
and bolts, ball bearings, key stock, casters, seats, wheels, and even engines may be
regarded as raw materials if they are purchased from outside the firm.
Generally, raw materials are used in the manufacture of components. These
components are then incorporated into the final product or become part of a
subassembly. Subassemblies are then used to manufacture or assemble the final
product. A part that goes into making another part is known as a component, while the
part it goes into is known as its parent. Any item that does not have a component is
regarded as a raw material or purchased item. From the product structure tree it is
apparent that the rolling cart's raw materials are steel, bars, wheels, ball bearings,
axles, and caster frames.
7
WORK-IN-PROCESS:
Work-in-process (WIP) is made up of all the materials, parts (components), assemblies,
and subassemblies that are being processed or are waiting to be processed within the
system. This generally includes all material—from raw material that has been released
for initial processing up to material that has been completely processed and is awaiting
final inspection and acceptance before inclusion in finished goods.
Any item that has a parent but is not a raw material is considered to be work-in-process.
A glance at the rolling cart product structure tree example reveals that work-in-process
in this situation consists of tops, leg assemblies, frames, legs, and casters. Actually, the
leg assembly and casters are labeled as subassemblies because the leg assembly
consists of legs and casters and the casters are assembled from wheels, ball bearings,
axles, and caster frames.
Case:
Work in process of any company will be depends on the capacity to produce the goods.
At Dulux paint Total time required to manufacture paint varies between 7-24hrs
depending on the type of goods. At one particular time only one size of product is
manufactured. Currently company has 150 kl of goods Work In Progress (WIP).
Company has capacity of 200kl WIP.
FINISHED GOODS:
A finished good is a completed part that is ready for a customer order. Therefore,
finished goods inventory is the stock of completed products. These goods have been
inspected and have passed final inspection requirements so that they can be
transferred out of work-in-process and into finished goods inventory. From this point,
finished goods can be sold directly to their final user, sold to retailers, sold to
wholesalers, sent to distribution centers, or held in anticipation of a customer order.
The levels of the above 3 kinds of inventories differ depending upon the nature of
business. For example: a manufacturer will have high level of all 3 kinds of
inventories. While a retailer or wholesaler will have level of inventories for finished
goods but will have no inventories of raw material or work-in –progress . more over
depending upon the nature of business, inventories may be durable or non-durable,
valuable or inexpensive, perishable or non-perishable etc.
Inventories can be further classified according to the purpose they serve. These types
include transit inventory, buffer inventory, anticipation inventory, decoupling inventory,
cycle inventory, and MRO goods inventory. Some of these also are know by other
names, such as speculative inventory, safety inventory, and seasonal inventory.
1. TYPES OF INVENTORY:
TRANSIT INVENTORY:
Transit inventories result from the need to transport items or material from one location
to another, and from the fact that there is some transportation time involved in getting
from one location to another. Sometimes this is referred to as pipeline inventory.
Merchandise shipped by truck or rail can sometimes take days or even weeks to go
from a regional warehouse to a retail facility. Some large firms, such as automobile
manufacturers, employ freight consolidators to pool their transit inventories coming from
8
various locations into one shipping source in order to take advantage of economies of
scale. Of course, this can greatly increase the transit time for these inventories, hence
an increase in the size of the inventory in transit.
Case:
Take the case of HPCL the transports are done from refinery to the customer through
different modes of transport i.e. Pipeline, Roadways (Tankers), Shipping, etc. the time
takes to reach a goods from refinery to the customer are called Transit inventory.
BUFFER INVENTORY:
As previously stated, inventory is sometimes used to protect against the uncertainties of
supply and demand, as well as unpredictable events such as poor delivery reliability or
poor quality of a supplier's products. These inventory cushions are often referred to as
safety stock. Safety stock or buffer inventory is any amount held on hand that is over
and above that currently needed to meet demand. Generally, the higher the level of
buffer inventory, the better the firm's customer service. This occurs because the firm
suffers fewer "stock-outs" (when a customer's order cannot be immediately filled from
existing inventory) and has less need to backorder the item, make the customer wait
until the next order cycle, or even worse, cause the customer to leave empty-handed to
find another supplier. Obviously, the better the customer service the greater the
likelihood of customer satisfaction.
ANTICIPATION INVENTORY:
Oftentimes, firms will purchase and hold inventory that is in excess of their current need
in anticipation of a possible future event. Such events may include a price increase, a
seasonal increase in demand, or even an impending labor strike. This tactic is
commonly used by retailers, who routinely build up inventory months before the
demand for their products will be unusually high (i.e., at Halloween, Christmas, or the
back-to-school season). For manufacturers, anticipation inventory allows them to build
up inventory when demand is low (also keeping workers busy during slack times) so
that when demand picks up the increased inventory will be slowly depleted and the firm
does not have to react by increasing production time (along with the subsequent
increase in hiring, training, and other associated labor costs). Therefore, the firm has
avoided both excessive overtime due to increased demand and hiring costs due to
increased demand. It also has avoided layoff costs associated with production cut-
backs, or worse, the idling or shutting down of facilities. This process is sometimes
called "smoothing" because it smoothes the peaks and valleys in demand, allowing the
firm to maintain a constant level of output and a stable workforce.
Case:
Let’s take a case of Dulux paint, in paint industry there will be a seasonality of
demand. Which means there production will be throughout the year and distribution
will be on pick time i.e. market demand will be more in the month of March to May and
June to Nov. this will be done for smooth distribution.
DECOUPLING INVENTORY:
9
Very rarely, if ever, will one see a production facility where every machine in the
process produces at exactly the same rate. In fact, one machine may process parts
several times faster than the machines in front of or behind it. Yet, if one walks through
the plant it may seem that all machines are running smoothly at the same time. It also
could be possible that while passing through the plant, one notices several machines
are under repair or are undergoing some form of preventive maintenance. Even so, this
does not seem to interrupt the flow of work-in-process through the system. The reason
for this is the existence of an inventory of parts between machines, a decoupling
inventory that serves as a shock absorber, cushioning the system against production
irregularities. As such it "decouples" or disengages the plant's dependence upon the
sequential requirements of the system (i.e., one machine feeds parts to the next
machine).
The more inventory a firm carries as a decoupling inventory between the various stages
in its manufacturing system (or even distribution system), the less coordination is
needed to keep the system running smoothly. Naturally, logic would dictate that an
infinite amount of decoupling inventory would not keep the system running in peak form.
A balance can be reached that will allow the plant to run relatively smoothly without
maintaining an absurd level of inventory. The cost of efficiency must be weighed against
the cost of carrying excess inventory so that there is an optimum balance between
inventory level and coordination within the system.
Case:
Take a case of Book making industry. The manager knows that paper making machine
will be not working after two days & production will be stop because of that so they will
be produce in advance the more quantity of papers and when the machine will not
working at that time binding will be done and distribution will not be affected by stopping
the production.
CYCLE INVENTORY:
Those who are familiar with the concept of economic order quantity (EOQ) know that
the EOQ is an attempt to balance inventory holding or carrying costs with the costs
incurred from ordering or setting up machinery. When large quantities are ordered or
produced, inventory holding costs are increased, but ordering/setup costs decrease.
Conversely, when lot sizes decrease, inventory holding/carrying costs decrease, but the
cost of ordering/setup increases since more orders/setups are required to meet
demand. When the two costs are equal (holding/carrying costs and ordering/setup
costs) the total cost (the sum of the two costs) is minimized. Cycle inventories,
sometimes called lot-size inventories, result from this process. Usually, excess material
is ordered and, consequently, held in inventory in an effort to reach this minimization
point. Hence, cycle inventory results from ordering in batches or lot sizes rather than
ordering material strictly as needed.
MRO GOODS INVENTORY:
Maintenance, repair, and operating supplies, or MRO goods, are items that are used to
support and maintain the production process and its infrastructure. These goods are
usually consumed as a result of the production process but are not directly a part of the
finished product.
Examples of MRO goods include oils, lubricants, coolants, janitorial supplies, uniforms,
gloves, packing material, tools, nuts, bolts, screws, shim stock, and key stock. Even
10
office supplies such as staples, pens and pencils, copier paper, and toner are
considered part of MRO goods inventory.
1) Carrying Costs:
The very fact that the items are required to be kept in stock means additional
expenditure to the organization. The different elements of costs involved in holding
inventory are as follows:
(a) Interest on capital / cost of capital / opportunity costs : When materials are kept in
stock money representing the value of materials is blocked. In a developing economy,
capital is extremely scarce and as such, the real value of capital is much higher than the
nominal rate of interest which the organization like Railways may be paying. The
,money which is blocked up is not available to the organization to do more business or
11
to use it for alternative productive investment. This opportunity to earn more profits
which we loose can be expressed as opportunity cost.
○ While working out the inventory carrying cost in an organization, the
higher of the three factors viz., interest, cost of capital or opportunity cost
should, be taken into consideration. This may be roughly 20% per annum.
(b) Obsolescence and depreciation : The costs because of obsolescence and
depreciation, are very important even though they are very difficult to assess. This
factor is relatively higher for spare parts inventory as against raw material inventory.
Larger the stock we keep more the risk of obsolescence and as such, the costs are
expressed as the percentage costs to the average inventory holding and can be
between 2 to 5%.
(c) The cost of storage, handling and stock verification : There are additional costs
because of the clerical work involved in handling of materials in the ward, in stock
verification, in preservation of materials as well as the costs because of various
equipments and facilities created for the purpose of materials. A part of this cost is of a
fixed nature. The major portion of the cost including the cost of staff, however, can be
treated as variable costs at least in the long run. This cost can be roughly 3 to 5% of the
inventory holding.
(d) Insurance Costs : Materials in stocks are either insured against theft, fire etc., or we
may have to employ watch & ward organization and also fire fighting organizations.
Cost of this may also be 1 to 2%. The average inventory carrying costs can, therefore,
be as follows:
Interest/costs of capital/opportunity cost 15 to 25%
Obsolescence and depreciation cost 2 to 5%
Storage, handling etc. 3 to 5%
Insurance costs 1 to 2%
Total 21 to 37%
In the Indian Railways, the reasonable assessment of inventory
carrying costs shall be about 20 to 25% per year of the average
inventory holding. It is again clarified here that these costs are not
normally reflected in our accounting system and as such are
required to be established by individual Railway.
1) Shortage Or Stock Out Costs :
Whenever an item is out of stock and as such cannot be supplied, it means that some
work or the other is delayed and this, in turn, leads to financial loss associated with
such stoppage or delay of work.
○ For example, if a locomotive remains idle for want of spare parts, the
earning capacity of the locomotive is lost for the duration of this period. On
the other hand, the spare parts required will have to be purchased on
emergency basis or have to be specially manufactured resulting in
additional costs.
○ Stock out costs can vary from item to item and from situation to situation
depending upon the emergency action possible. No attempt therefore, is
normally made to evaluate a stock out cost of an item. Nevertheless, it is
important to understand the concept of stock out costs, even though the
12
actual quantification is not possible. We should have a rough grading of
the items depending upon the possible stock out costs.
1) Systems Costs :
These are the costs which are associated with the nature of the control systems
selected. If a very sophisticated model of the relationship between stock out costs,
inventory holding cost and cost of ordering is used and operated with the help of a
computer, it may give the theoretical minimum of the other costs but the cost of such
control system may be sufficiently high to offset the advantages achieved.
○ In most of the situations, however, there is no substantial increase in costs
because of the proposed control system and in such cases, these costs
can be overlooked.
13
Figure 3: Overview of an integrated Inventory Management System
The utilization of Inventory Management Systems to control the purchase and
installation of assets can aid in the control of the business environment, while assisting
in the assignment of personnel to perform asset related work functions. This
methodology will result in a work-flow and asset management system.
FIFO method:
This method assumes that the order in which materials are received in the stores is the
order in which materials are issued from the stores. Hence, the materials which is
issued first is priced on the basis of the cost of material received earliest, so on and so
forth. The advantages of this method seemed to be: 1. The pricing of material is
perhaps consistent with the practice of issuing oldest material first followed in many
manufacturing organization. 2. The value of material in stock is fairly closed to the
current cost. The disadvantages of this method are: 1. Issue of material at different
prices complicates stores accounting. 2. Comparision of job cost becomes difficult
when similar jobs may be charged with different prices for the same material. 3. In this
period of rising prices, the charge to production is low. This tends to inflate reported
profits, increase tax burden & push up dividends-as a consequence, the firm is sapped
financially.
LIFO method:
This method is the opposite of FIFO method: It assumes that the material which is
acquired last is issued first. Hence material issues are priced on the basis of the cost of
most recent material purchases.
14
The advantages associated with this method are: 1. The cost of production reflects the
current cost of materials better. 2. In a period of rising prices, reported profits are
depressed, dividends are kept low, & working capital is conserved. The disadvantages
of this method are: 1. Issue of material at different prices complicates stores accounting.
2. The pricing of materials is not consistent with the commonly followed practice of
issuing the oldest material first. 3. Comparison of job cost becomes difficult when
similar jobs may be charged for the same material at different prices.
Weighted Average Cost Method:
Under this method, material issues are priced at a weighted average cost of materials in
stock. To get an up-to-date weighted average cost figure, a new weighted average cost
is calculated each time a delivery is received.
The merits of this method are: (i) It tends to smooth out price fluctuations. (ii) It provides
a fairly acceptable figure for stock values. The limitations of this method may be the
tedium involved in calculating the weighted average cost each time a new delivery is
obtained.
Standard Price (cost) Method:
Under this method a standard price is predetermined. When materials are purchased
the stock amount is debited with the standard price. The difference between the actual
price & standard price is carried to a variance account. Material issued are charged as
per the standard price.
The advantages of this method are: (i) All material issued are priced identically. The
possibility of jobs using the same material being charged with different cost-a problem
with the FIFO or LIFO method does not exist. (ii) Stock accounting is fairly simplified.
There is no need for specific prices attributable to specific issues of materials. The short
comings of this method are: (i) Determining the standard price may be somewhat
difficult, particularly when prices tend to increase somewhat unpredictably or are
characterized by wide fluctuations. (ii) the issue of how variance should be treated may
be thorny.
The first question, ‘how much to order’ relates to the problem of determining economic
order quantity (EOQ) and answered with an analysis of costs of maintaining certain
15
level of inventories. The second question, when to order, arises because of uncertainty
and is a problem of determining the re‐order point.
1) Ordering Costs:
The term ordering costs is used in case of raw materials (or supplies) and includes the
entire costs incurred in the following activities:
• Requisition
• Purchase
• Ordering
• Transporting
• Receiving
• Inspecting
• Storing (store placement)
Ordering costs increase in proportion to the number of orders placed. The clerical and
staff costs, however, do not have to vary in proportion to the number of orders placed,
and one view is that so long as they are committed costs, they need not be reckoned in
computing ordering cost. Alternatively, it may be argued that as the number of order
increases, the clerical and staff costs tend to increase. If the number of orders are
drastically reduced, the clerical and staff force release now can be used in other
departments. Thus, these costs may be included in the ordering costs. It is more
appropriate to include clerical and staff costs on a pro‐rata basis. Ordering costs
increase with the number of orders, thus the more frequently inventory is acquired, the
higher the firm’s ordering costs. On the other hand, if the firm maintains a large
inventory levels, there will be few orders placed and ordering costs will be relatively
small. Thus, ordering costs decrease with the increasing size of inventory.
1) Carrying Costs:
Costs incurred for maintaining a given level of inventory are called carrying costs. They
include storage, insurance, taxes, deterioration and adolescence. The storage costs
comprise cost of storage space (warehousing cost), stores handling costs and clerical
and staff service costs (administrative costs) incurred in recording and providing special
facilities such as fencing, lines, racks etc. Carrying costs vary with inventory size. This
behavior is contrary to that of ordering costs which decline with increase in inventory
16
size. The economic size of inventory would thus depend on trade‐off between carrying
costs and ordering costs.
2) Re‐order point:
The re‐order point is that inventory level at which an order should be placed to replenish
the inventory. To determine the re‐order point under certainty, we should know:
• Lead time
• Average usage
• Economic order quantity
Lead time:
Lead time is the time normally taken in replenishing the inventory after the order has
been placed. By certainty we mean that uses and lead time do not fluctuate. Under
such a situation reorder point is simply that inventory level which will be maintained for
consumption during the lead time .i. e ,
Reorder point = Lead * Average usage.
1) Safety stock:
The demand for material may fluctuate from day‐to‐day or from week‐to‐week.
Similarly, the actual delivery time may be different from the normal lead time. If the
actual usage increases or the delivery of inventory is delayed, the firms can a problem
of stock‐out which can prove to be costly for a firm. Therefore, in order to guard against
the stock out, the firm may maintain a safety stock. It is the minimum or buffer inventory
as cushion against expected increased usage and/or delay in delivery time.
When asked, the cashier/owner of the store told that they maintain stocks of FMCG as
well as pharmaceuticals as per the requirement of the locality. The consumption of
FMCG is informed to be very high.
• The store has installation of computerized inventory management system.
• A database of inventories is automatically maintained by the system.
• It keeps track of what comes in and what goes out.
• As soon as the inventory reaches the re‐order point, the system automatically
reminds them to order that particular commodity.
• They, then place the required order using telephonic communication.
Three most selling FMCG goods have been identified and have been studied for the
inventory management:
17
Min. Average Max.
Shampoo
➢ Sunsilk 5 20 25
➢ Garnier 5 35 40
➢ Head and shoulder 5 25 30
➢ Dove 5 30 35
Soap
➢ Lux body wash 10 90 100
➢ Lux 10 90 100
➢ Life boy 10 80 90
➢ Dettol 10 110 120
➢ Dove 10 90 100
Toothpaste
➢ Close-up 5 50 55
➢ Colgate 5 60 65
➢ Pepsodent 5 40 45
Ordering Costs:
It is nil for this store as the supplier charges no delivery costs to them.
Carrying costs:
Was not disclosed. The store owner looked more haphazard, when asked about it.
Re‐order point:
The Computerized inventory management system automatically reminds to place an
order when the inventory reaches the min. point.
Lead time:
It was informed to be 48 hrs.
Safety stock:
The store does not have any such concept, instead it does have a minimum and a
maximum limit. It just tries to maintain the max. limit of the stock.
An example:
A small firm inventories only ten items, but decides to setup an ABC inventory system
With 20 % A items, 30 % B items, and 50 % C items. The company records provide the
information shown below.
19
Part 1 2 3 4 5 6 7 8 9 10
No
Unit 1100 600 100 1300 100 10 100 1500 200 500 5510
Usag
e
Unit 20 400 40 10 600 250 20 20 20 10
Cost
AUV 2200 24000 400 1300 6000 250 200 3000 400 500 38250
0 0 0 0 0 0 0 0 0 0 0
order
2 240000 240000 62.75 10 A
5 60000 300000 78.43 20 A
8 30000 330000 86.27 30 B
1 22000 352000 92.03 40 B
4 13000 365000 95.42 50 B
1 5000 370000 96.73 60 C
3 4000 374000 97.77 70 C
9 4000 378000 98.82 80 C
6 2500 380500 99.48 90 C
7 2000 382500 100 100 C
Table: ABC Analysis
20
Just-In-Time(JIT) systems:
Japanese firms popularize the just-in –time (JIT)system in the world. In a JIT system
material or manufactured components and parts arrive to the manufacturing sites or
stores just few hours before they are put to use. The delivery of material is
synchronized with the manufacturing cycle and speed. JIT system eliminates the
necessity of carrying large inventories, and thus , saves carrying other related cost to
the manufacturer. The system requires perfect understanding and co-ordination
between the manufacturer and the suppliers in terms of the timing of delivery and
quality of the material. Poor quality material and components could halt the production.
The JIT inventory system complements the total quality management (TQM). The
success of the system depends on how well a company manages its suppliers. The
system puts tremendous pressure on suppliers. They will have to develop adequate
systems and procedures to satisfactory meet the needs of manufacturers.
Example:
One truck transportation company obtains much of its business by catering to
companies that must deliver parts to other companies “just in time”. The Toyota
Company in Japan has developed a scheduling discipline for internal control of in
process material movement, called kanban, which substantially reduces WIP
Inventories and hence reduces the associated costs.
Outsourcing:
A few years ago there was a tendency on the parts of many companies to manufacture
all components in house. Now more companies are adopting the practice out sourcing.
Out sourcing is a system of buying parts and components from outside rather than
manufacturing them internally. Many companies develop a single source of supply, and
21
many others help developing small and middle size suppliers of components that they
require.
Example:
Tata motors has, developed number of ancillaries are able to maintain the high quality
of the manufactured components. The car manufacturing company, Maruti, which is
now controlled by Suzuki of Japan has the similar system of supply.
24
facilities yields obvious benefits. Likewise, within a single tier of DCs, not every SKU
deserves to be stocked in every DC.
18. Extend Payment Terms: When negotiating long- term purchase agreements,
getting the best payment terms at a given unit price is the most direct way to increase
the portion of inventory funded by the vendor. If improving payment terms can be
coupled with increased turnover, then the improvement in working capital effectiveness
is significant.
19. Take Advantage of Price/Quantity Breaks: Taking price/quantity breaks
into account when purchasing for replenishment seems an obvious way to reduce the
inventory investment, but seems to be frequently overlooked. Often this is a result of
either not quantifying breaks at the time of sourcing or negotiation, not having an
effortless way to take them into account, or through lack of understanding of the impact
of purchasing larger quantities at reduced unit cost.
20. Transfer Instead of Purchase: When inventory of an overstock SKU in one
location needs to be purchased to replenish inventory in another location, transfers are
a smart way to reduce inventory. Be careful that additional warehousing and
transportation expenses aren't unnecessarily incurred so the reduction in holding cost
does not exceed the cost to transfer.
21. Consider Liquidation: Although there will always be a short-term price to pay
on the P&L and the balance sheet, when it is absolutely clear that the value to be
gained through liquidation-whether through sale at reduced price, sale as distressed
product, salvage, or charitable donation-is greater than the most optimistic estimate of
future gross margin from conventional product sales, then liquidation is the best
decision.
22. Try Merge-In-Transit: The concept of in-transit product merging-where, for
example, two things are shipped from different locations and then married in transit so
that they reach the customer as a single shipment-can be seen as a technique for
reducing inventory if the need for the customer to simultaneously receive multiple SKUs
is taken as a requirement. If the need for simultaneous receipt is a given, then the
concept eliminates the need for inventorying the individual SKUs together. To some
extent, merge-in-transit represents an extension of postponement beyond the
distribution center walls.
23. Get Help From Friends: Collaborative Planning and Replenishment (CPFR) is
an open set of pre-defined business processes and IT/communications standards
created to facilitate collaboration between supply chain partners. CPFR can reduce
inventories through inventory balance, forecast, demand and other data visibility and
associated collaboration in the planning area.
24. Use Vendor-managed Inventory (VMI): With the appropriate incentives,
allowing suppliers to assume the responsibility for replenishment of your inventory,
because of their visibility into both their own inventory and production schedule and
your demand data, can almost always reduce your inventory.
25. Implement Vendor Stocking Programs (VSP): Used primarily for
maintenance inventories but applicable to all, VSPs require a supplier to commit to an
extremely high service level for delivery of specific SKUs within a fixed time at a pre-
25
defined mark-up over cost. VSPs can reduce or eliminate inventories for slow-moving
products.
There are numerous ways to take better control of inventory and decrease its
associated costs. The key to managing inventory successfully is to continuously
measure your performance and look for new ways to improve. These 25 strategies
should get your organization thinking about what it can do to lower inventory costs.
Many of these strategies may seem challenging to implement. This is when it is wise to
seek outside help for insight on how to put these strategies to work for you.
References:
Financial Management, 9th edition by I.M. Pandey.
http://en.wikipedia.org/wiki/Inventory_control_system
http://en.wikipedia.org/wiki/Inventory
http://rapidlibrary.com
27