Documente Academic
Documente Profesional
Documente Cultură
SAIC NUMBER
DATE APPROVED
SAIC-E-2001
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
QR NUMBER
25-May-05
MECH-
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
General Requirements
A1
Verify that the heat exchangers and coolers are within the scope of
SAES-E-004.
SAES-A-005
Para. 4.2
A2
The Safety Instruction Sheet, Saudi Aramco form 2713-ENG & 2713-MENG, has been completed in its entirety and approved by the Project
Manager. (SAES-E-004, Para. 14.3)
SAES-A-005
Para. 5.1
A3
SAES-A-005
Para. 7
A4
The "as built" thickness of all the pressure containing parts been
specified by the Design Engineer on the Safety Instruction Sheet after
the completion of fabrication.
SAES-E-004,
Para. 14.4
A5
The Safety Instruction Sheets and the applicable design data sheets
were submitted to the Manager, Consulting Services Department for
review and concurrence by his designated representative(s) when CSD
expertise has been required.
PASS
FAIL
N/A
RE-INSP DATE
SAES-A-005 Sec.
6
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-005 -- Safety Instruction Sheet, 31 December 2001
2. SAES-E-004 -- Design Criteria of Shell and Tube Heat Exchangers, 31 May 2003
3. SA Form 2713-ENG -- Data & Operating Limits-Shell & Tube Heat Exchangers, October 2002
4. SA Form 2713-M-ENG -- Data & Operating Limits-Shell & Tube Heat Exchangers, October 2002
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
T&I Witnessed
QC Record Reviewed
Work Verified
QC Inspector
PID Representative
Performed Inspection
QC Supervisor
Name, Organization,
Initials and Date:
Y = YES
Page 1 of 1
N = NO F = FAILED