02-Feb-12

Architecture

Landscaping

Foundations

External construction

Intenal construction

Roof

Services

Finishes

Key Handover and opening

20-Aug-12

08-Mar-13

24-Sep-13

New State Building


Tasks
Architecture
Landscaping
Foundations
External construction
Intenal construction
Roof
Services
Finishes
Key Handover and opening

Start Date
2-Feb-12
25-Mar-12
4-May-12
3-Jul
7-Jan-13
1-Jun-13
7-Jul-13
15-Sep-13
30-Oct-13

Duration
(days)
50
40
60
270
180
35
70
45
1

End Date
25-Mar-12
4-May-12
3-Jul-12
30-Mar-13
7-Jul-13
5-Jul-13
15-Sep-13
30-Oct-13
31-Oct-13