Sunteți pe pagina 1din 42

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

15-Oct-14

13-Oct-16

15-Oct-14 A

13-Oct-16

19.13%

21.39%

MAJOR MILEST
MILESTONE

15-Oct-14

13-Oct-16

15-Oct-14 A

13-Oct-16

0%

0%

KEY MILESTONE
MILESTON

25-Jul-15

08-Sep-15

01-Aug-15

09-Sep-15

0%

0%

400

ENGINEERING

08-Apr-15

06-Dec-15

26-Mar-15 A

10-Nov-15

0%

0%

178

08-Apr-15

23-Nov-15

01-Apr-15 A

29-Oct-15

0%

0%

188

ARCHITECTURAL
ARCHITECTU

25-Jul-15

22-Oct-15

25-Jul-15 A

29-Oct-15

0%

0%

188

INTERNAL PAINT
PA

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

53

CONSTRUCTION, COMPLETION & MAINTENANCE


CONSTRUCTIO

MATERIAL SUBMITTAL
SU
& APPROVAL

ENG.MS.AR.12

Material Submittal - Internal Paint

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

53

ENG.MS.AR.19

Material Approval - Internal Paint

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

53

10-Aug-15

19-Sep-15

17-Aug-15

01-Oct-15

0%

0%

67

EPOXY PAINT
ENG.MS.AR.15

Material Submittal - Epoxy Paint

10-Aug-15

25-Aug-15

17-Aug-15

01-Sep-15

0%

0%

67

ENG.MS.AR.24

Material Approval - Epoxy Paint

26-Aug-15

19-Sep-15

02-Sep-15

01-Oct-15

0%

0%

67

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

127

CARPET MATERIALS
MAT
ENG.MS.AR.40

Material Submittal - Carpet

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

101

ENG.MS.AR.42

Material Approval - Carpet

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

127

22-Aug-15

06-Oct-15

29-Aug-15

13-Oct-15

0%

0%

150

MIRRORS & ACCESSORIES


A
ENG.MS.AR.51

Material Submittal - Mirrors

22-Aug-15

06-Sep-15

29-Aug-15

13-Sep-15

0%

0%

91

ENG.MS.AR.53

Material Approval - Mirrors

07-Sep-15

06-Oct-15

14-Sep-15

13-Oct-15

0%

0%

150

07-Sep-15

22-Oct-15

14-Sep-15

29-Oct-15

0%

0%

146

WOOD CHIPS MULCHING


ENG.MS.AR.60

Material Submittal - Wood Chips Mulching

07-Sep-15

22-Sep-15

14-Sep-15

05-Oct-15

0%

0%

146

ENG.MS.AR.61

Material Approval - Wood Chips Mulching

29-Sep-15

22-Oct-15

06-Oct-15

29-Oct-15

0%

0%

146

07-Sep-15

22-Oct-15

25-Jul-15 A

18-Oct-15

0%

0%

198

CRUSHED LIMESTONE
LI
ENG.MS.AR.62

Material Submittal - Crushed Limestone

07-Sep-15

22-Sep-15

25-Jul-15 A

05-Oct-15

0%

0%

167

ENG.MS.AR.63

Material Approval - Crushed Limestone

29-Sep-15

22-Oct-15

02-Aug-15 A

18-Oct-15

0%

0%

198

07-Sep-15

22-Sep-15

29-Sep-15

15-Oct-15

0%

0%

167

ROAD MARK
MARKING, SIGNAGES & ACCESSORIES
Date: 08-Aug-15 1/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

01-Aug-15
01-Aug-15,
23-Aug-15,
28-Aug-15,
31-Aug-15
09-Sep-15
09-Sep-15,

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

ENG.MS.AR.64

Activity Name

Baseline
Start

Baseline
Finish

Material Submittal - Road Marking

07-Sep-15

MEP WORKS
M.V MATERIAL
MATERIA & ACCESSORIES
M.V PANELS

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

22-Sep-15

29-Sep-15

15-Oct-15

0%

0%

167

08-Apr-15

23-Nov-15

01-Apr-15 A

28-Oct-15

0%

0%

168

18-Apr-15

30-Sep-15

23-Apr-15 A

07-Oct-15

0%

0%

88

18-Apr-15

30-Sep-15

23-Apr-15 A

07-Oct-15

0%

0%

88

ENG.MS.MV.1

Material Submittal to Consultant - M.V Panels

18-Apr-15

03-May-15

23-Apr-15 A

13-Aug-15

100%

0%

55

ENG.MS.MV.5

Material Approval from Consultant - M.V Panels

06-Aug-15

23-Aug-15

13-Aug-15

30-Aug-15

0%

0%

88

ENG.MS.MV.9

Material Submittal to Kharama - M.V Panels

23-Aug-15

08-Sep-15

30-Aug-15

15-Sep-15

0%

0%

88

08-Sep-15

30-Sep-15

15-Sep-15

07-Oct-15

0%

0%

88

05-Jul-15

13-Sep-15

28-Jun-15 A

01-Sep-15

0%

0%

55

ENG.MS.MV.12 Material Approval from Kharama - M.V Panels

FIBRE OPTIC CABLES & ACCESSORIES


ENG.MS.MV.3

Material Submittal to Consultant - Fibre Obtic


Cables

05-Jul-15

26-Jul-15

28-Jun-15 A

16-Aug-15

100%

0%

55

ENG.MS.MV.11

Material Submittal to QTEL - Fibre Obtic Cables

11-Aug-15

27-Aug-15

28-Jun-15 A

26-Aug-15

0%

0%

55

ENG.MS.MV.7

Material Approval from Consultant - Fibre Obtic


Cables

26-Jul-15

11-Aug-15

29-Jun-15 A

23-Aug-15

34.29%

0%

55

27-Aug-15

13-Sep-15

29-Jun-15 A

01-Sep-15

0%

0%

55

05-Sep-15

21-Oct-15

15-Jun-15 A

05-Sep-15

0%

0%

99

ENG.MS.MV.14 Material Approval from QTEL - Fibre Obtic Cables

DEHUMIDIFIER & ACCESSORIES


DEHUMIDIFIE
ENG.MS.AC.15

Material Submittal - Dehumidifier

05-Sep-15

21-Sep-15

15-Jun-15 A

23-Aug-15

0%

0%

99

ENG.MS.AC.16

Material Approval - Dehumidifier

21-Sep-15

21-Oct-15

22-Jun-15 A

05-Sep-15

0%

0%

99

13-Oct-15

07-Nov-15

28-May-15
A

01-Sep-15

0%

0%

133

13-Oct-15

07-Nov-15

28-May-15
A

01-Sep-15

0%

0%

133

13-Oct-15

23-Nov-15

21-May-15
A

07-Sep-15

0%

0%

146

EXHAUST FAN
FA & ACCESSORIES
ENG.MS.AC.20

Material Approval - Exhaust Fan & Accessories

CHILLED WATER
WA
PRESSURIZATION UNIT
ENG.MS.AC.27

Material Submittal - Pressurization Unit

13-Oct-15

29-Oct-15

21-May-15
A

27-Aug-15

0%

0%

129

ENG.MS.AC.28

Material Approval - Pressurization Unit

29-Oct-15

23-Nov-15

28-May-15
A

07-Sep-15

0%

0%

146

16-Aug-15

01-Oct-15

23-Aug-15

08-Oct-15

0%

0%

129

CHEMICAL DOSING
D
ENG.MS.AC.29

Material Submittal - Chemical Dosing

16-Aug-15

01-Sep-15

23-Aug-15

08-Sep-15

0%

0%

129

ENG.MS.AC.30

Material Approval - Chemical Dosing

01-Sep-15

01-Oct-15

08-Sep-15

08-Oct-15

0%

0%

129

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

205

BUILDING MANAGEMENT
MA
SYSTEM
Date: 08-Aug-15 2/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

ENG.MS.AC.31

Material Submittal - Building Management System

25-Jul-15

ENG.MS.AC.32

Material Approval - Building Management System

CHILLERS

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

56

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

205

22-Jun-15

05-Aug-15

16-Jun-15 A

31-Aug-15

0%

0%

56

ENG.MS.AC.22

Material Submittal - Chillers

22-Jun-15

07-Jul-15

16-Jun-15 A

22-Aug-15

100%

0%

56

ENG.MS.AC.25

Material Approval - Chillers

08-Jul-15

05-Aug-15

23-Jun-15 A

31-Aug-15

76.19%

0%

56

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

96

SANITARY W
WARES FITTINGS & ACCESSORIES
ENG.MS.PL.13

Material Submittal - Sanitary Wares Fittings &


Accessories

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

96

ENG.MS.PL.14

Material Approval - Sanitary Wares Fittings &


Accessories

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

96

16-Sep-15

15-Oct-15

14-Jun-15 A

22-Aug-15

0%

0%

112

16-Sep-15

15-Oct-15

14-Jun-15 A

22-Aug-15

0%

0%

112

10-Jun-15

26-Jul-15

27-Jun-15 A

19-Aug-15

0%

0%

101

GRP WATER TANK & FITTINGS


ENG.MS.PL.18

Material Approval - GRP Watertank

IPTV SYSTEM & ACCESSORIES


ENG.MS.EE.30

Material Submittal - IPTV System & Accessories

10-Jun-15

27-Jun-15

27-Jun-15 A

06-Aug-15

100%

0%

101

ENG.MS.EE.29

Material Approval - IPTV System & Accessories

27-Jun-15

26-Jul-15

04-Jul-15 A

19-Aug-15

100%

0%

101

25-May-15

22-Jul-15

07-May-15
A

19-Aug-15

0%

0%

72

LOW VOLTAGE
VOLTAG CABLE & ACCESSORIES
ENG.MS.EE.5

Material Submittal - Low Voltage Cable

25-May-15

09-Jun-15

07-May-15
A

06-Aug-15

100%

0%

17

ENG.MS.EE.7

Material Approval - Low Voltage Cable

23-Jun-15

22-Jul-15

28-Jun-15 A

19-Aug-15

100%

0%

72

27-Jun-15

02-Sep-15

07-May-15
A

09-Sep-15

0%

0%

53

CBS & LUMINAIRES


LUMIN
& ACCESSORIES
ENG.MS.EE.9

Material Submittal - CBS & Luminaires

27-Jun-15

12-Jul-15

07-May-15
A

16-Aug-15

100%

0%

17

ENG.MS.EE.10

Material Approval - CBS & Luminaires

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

53

04-Jul-15

02-Aug-15

27-Jun-15 A

05-Sep-15

0%

0%

58

VA SYSTEM & ACCESSORIES


ENG.MS.EE.12

Material Submittal - VA System

13-Jul-15

02-Aug-15

27-Jun-15 A

23-Aug-15

85.71%

0%

17

ENG.MS.EE.14

Material Approval - VA System

04-Jul-15

01-Aug-15

04-Jul-15 A

05-Sep-15

95.24%

0%

58

27-Jul-15

06-Sep-15

27-Jun-15 A

10-Sep-15

0%

0%

53

ACCESS CONTROL
CO
SYSTEM & ACCESSORIES
ENG.MS.EE.15

Material Submittal - Access Control System

27-Jul-15

12-Aug-15

27-Jun-15 A

30-Aug-15

24.29%

0%

17

ENG.MS.EE.16

Material Approval - Access Control System

12-Aug-15

06-Sep-15

04-Jul-15 A

10-Sep-15

0%

0%

53

Date: 08-Aug-15 3/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

DATA & TELEPHONE


TELE
SYSTEM & ACCESSORIES

Baseline
Start

Baseline
Finish

Start

Finish

12-Aug-15

Schedule %
Complete

Cost %
Complete

Total
Float

22-Sep-15

21-Jun-15 A

17-Sep-15

0%

0%

47

ENG.MS.EE.17

Material Submittal - Data & Telephone System

12-Aug-15

29-Aug-15

21-Jun-15 A

05-Sep-15

0%

0%

17

ENG.MS.EE.19

Material Approval - Data & Telephone System

29-Aug-15

22-Sep-15

28-Jun-15 A

17-Sep-15

0%

0%

47

29-Aug-15

14-Oct-15

27-Jun-15 A

29-Sep-15

0%

0%

42

CCTV & SECURITY


SEC
SYSTEM & ACCESSORIES
ENG.MS.EE.18

Material Submittal - CCTV & Security System

29-Aug-15

14-Sep-15

27-Jun-15 A

12-Sep-15

0%

0%

17

ENG.MS.EE.21

Material Approval - CCTV & Security System

14-Sep-15

14-Oct-15

04-Jul-15 A

29-Sep-15

0%

0%

42

05-Sep-15

21-Oct-15

12-Sep-15

28-Oct-15

0%

0%

17

LIGHT FITTINGS
FITTIN
& ACCESSORIES
ENG.MS.EE.20

Material Submittal - Light Fittings

05-Sep-15

21-Sep-15

12-Sep-15

04-Oct-15

0%

0%

17

ENG.MS.EE.23

Material Approval - Light Fittings

21-Sep-15

21-Oct-15

04-Oct-15

28-Oct-15

0%

0%

17

08-Apr-15

18-May-15

01-Apr-15 A

15-Aug-15

0%

0%

101

FIRE FIGHTING
FIGHTIN VALVES & FITTINGS
ENG.MS.FF.13

Material Submittal - Fire Fighting Valves & Fittings

08-Apr-15

23-Apr-15

01-Apr-15 A

11-Aug-15

100%

0%

101

ENG.MS.FF.14

Material Approval - Fire Fighting Valves & Fittings

25-Apr-15

18-May-15

16-Jun-15 A

15-Aug-15

100%

0%

101

09-Jun-15

16-Jul-15

09-Jun-15 A

19-Aug-15

0%

0%

165

FM 200 & ACCESSORIES


ACC
ENG.MS.FF.15

Material Submittal - FM 200

09-Jun-15

24-Jun-15

09-Jun-15 A

06-Aug-15

100%

0%

104

ENG.MS.FF.16

Material Approval - FM 200

22-Jun-15

16-Jul-15

16-Jun-15 A

19-Aug-15

100%

0%

165

22-Jun-15

06-Aug-15

09-Jun-15 A

25-Aug-15

0%

0%

131

SPRINKLER HEADS & ACCESSORIES


ENG.MS.FF.2

Material Submittal - Sprinkler Head & Accessories

22-Jun-15

08-Jul-15

09-Jun-15 A

13-Aug-15

100%

0%

104

ENG.MS.FF.4

Material Approval - Sprinkler Head & Accessories

08-Jul-15

06-Aug-15

16-Jun-15 A

25-Aug-15

72.86%

0%

131

08-Jul-15

23-Aug-15

09-Jun-15 A

01-Sep-15

0%

0%

126

FIRE BRIGADE
BRIGAD VALVE & FITTINGS
ENG.MS.FF.5

Material Submittal - Fire Brigade Valve & Fittings

08-Jul-15

29-Jul-15

09-Jun-15 A

19-Aug-15

100%

0%

104

ENG.MS.FF.6

Material Approval - Fire Brigade Valve & Fittings

29-Jul-15

23-Aug-15

16-Jun-15 A

01-Sep-15

6.19%

0%

126

29-Jul-15

08-Sep-15

09-Jun-15 A

07-Sep-15

0%

0%

104

FIRE HOSE R
REEL CABINET & ACCESSORIES
ENG.MS.FF.7

Material Submittal - Fire Hose Reel Cabinet

29-Jul-15

15-Aug-15

09-Jun-15 A

26-Aug-15

9.29%

0%

104

ENG.MS.FF.8

Material Approval - Fire Hose Reel Cabinet

15-Aug-15

08-Sep-15

16-Jun-15 A

07-Sep-15

0%

0%

104

08-Sep-15

25-Oct-15

09-Jun-15 A

01-Oct-15

0%

0%

104

FIRE EXTING
EXTINGUISHER
Date: 08-Aug-15 4/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

ENG.MS.FF.9

Material Submittal - Fire Extinguisher

08-Sep-15

14-Sep-15

0%

0%

104

ENG.MS.FF.10

Material Approval - Fire Extinguisher

16-Jun-15 A

01-Oct-15

0%

0%

104

06-Dec-15

02-Apr-15 A

10-Nov-15

0%

0%

146

21-May-15

06-Jul-15

02-Apr-15 A

08-Aug-15

0%

0%

30

21-May-15

06-Jul-15

02-Apr-15 A

08-Aug-15

0%

0%

30

ENG.MSS.ST.011 Method Statement Submittal - Steel Structure &


Metal Decking

21-May-15

07-Jun-15

02-Apr-15 A

01-Aug-15

100%

0%

30

ENG.MSS.ST.012 Method Statement Approval - Steel Structure &


Metal Decking

13-Jun-15

06-Jul-15

30-Jun-15 A

08-Aug-15

100%

0%

30

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

156

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

58

ENG.MSS.AR.16 Method Statement Submittal - Wood Veneered


MDF Panel

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

58

ENG.MSS.AR.20 Method Statement Approval - Wood Veneered


MDF Panel

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

58

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

105

ENG.MSS.AR.31 Method Statement Submittal - Wood Parquet


Flooring

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

105

ENG.MSS.AR.33 Method Statement Approval - Wood Parquet


Flooring

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

105

03-Sep-15

19-Oct-15

10-Sep-15

26-Oct-15

0%

0%

53

ENG.MSS.AR.15 Method Statement Submittal - Internal Paint

03-Sep-15

19-Sep-15

10-Sep-15

01-Oct-15

0%

0%

53

ENG.MSS.AR.19 Method Statement Approval - Internal Paint

20-Sep-15

19-Oct-15

03-Oct-15

26-Oct-15

0%

0%

53

20-Sep-15

11-Oct-15

03-Oct-15

18-Oct-15

0%

0%

67

20-Sep-15

11-Oct-15

03-Oct-15

18-Oct-15

0%

0%

67

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

128

ENG.MSS.AR.36 Method Statement Submittal - Kitchen Cabinet

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

128

ENG.MSS.AR.37 Method Statement Approval - Kitchen Cabinet

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

128

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

131

ENG.MSS.AR.32 Method Statement Submittal - Toilet Cubicle

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

131

ENG.MSS.AR.39 Method Statement Approval - Toilet Cubicle

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

131

METHOD STATEMENT
STAT
SUBMITTAL & APPROVAL
STRUCTURAL
STEEL STRUCTURE
STRU
& METAL DECKING

ARCHITECTURAL
ARCHITECTU
WOOD VENEERED
VENE
MDF PANEL

WOOD PARQUET
PARQ
FLOORING

INTERNAL PAINT
PA

EPOXY PAINT
ENG.MSS.AR.10 Method Statement Submittal - Epoxy Paint

PANTRY CABINET
CAB
& BASE CABINET

TOILET CUBICLE
CUB

Date: 08-Aug-15 5/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

30-Sep-15

09-Jun-15 A

30-Sep-15

25-Oct-15

21-May-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

03-Sep-15

26-Oct-15

0%

0%

127

ENG.MSS.AR.35 Method Statement Submittal - Carpet

10-Sep-15

01-Oct-15

0%

0%

127

ENG.MSS.AR.40 Method Statement Approval - Carpet

19-Oct-15

03-Oct-15

26-Oct-15

0%

0%

127

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

148

ENG.MSS.AR.41 Method Statement Submittal - Vanity Top

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

148

ENG.MSS.AR.42 Method Statement Approval - Vanity Top

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

148

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

105

ENG.MSS.AR.43 Method Statement Submittal - Wooden Doors

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

105

ENG.MSS.AR.44 Method Statement Approval - Wooden Doors

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

105

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

119

ENG.MSS.AR.45 Method Statement Submittal - Ironmongery

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

127

ENG.MSS.AR.46 Method Statement Approval - Ironmongery

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

119

25-Jul-15

17-Aug-15

01-Aug-15

24-Aug-15

0%

0%

112

ENG.MSS.AR.47 Method Statement Submittal - Steel Doors

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

112

ENG.MSS.AR.48 Method Statement Approval - Steel Doors

25-Jul-15

17-Aug-15

01-Aug-15

24-Aug-15

28.57%

0%

112

07-Sep-15

22-Oct-15

14-Sep-15

29-Oct-15

0%

0%

105

ENG.MSS.AR.50 Method Statement Submittal - Interlocking Tiles &


Kerbs

07-Sep-15

22-Sep-15

14-Sep-15

05-Oct-15

0%

0%

105

ENG.MSS.AR.52 Method Statement Approval - Interlocking Tiles &


Kerbs

29-Sep-15

22-Oct-15

06-Oct-15

29-Oct-15

0%

0%

105

07-Sep-15

22-Oct-15

14-Sep-15

29-Oct-15

0%

0%

91

ENG.MSS.AR.49 Method Statement Submittal - GRC Works

07-Sep-15

22-Sep-15

14-Sep-15

05-Oct-15

0%

0%

91

ENG.MSS.AR.51 Method Statement Approval - GRC Works

29-Sep-15

22-Oct-15

06-Oct-15

29-Oct-15

0%

0%

91

SOFT LANDSCAPE
LANDS
(PLANT, TREES, SHRUBS, GRAS 07-Sep-15 22-Oct-15

14-Sep-15

29-Oct-15

0%

0%

156

CARPET

VANITY TOP COUNTER

WOODEN DO
DOORS INCLUDING SUBFRAMES & ARC

IRON MONGERY
MONG

STEEL DOORS
DOOR INCLUDING SUBFRAMES & ARCHIT

INTERLOCKING TILES & KERBS


INTERLOCKI

GRC WORKS

Start

Finish

19-Oct-15

10-Sep-15

03-Sep-15

19-Sep-15

20-Sep-15

ENG.MSS.AR.53 Method Statement Submittal - Soft Landscape


(Plants, Trees, Shrubs, Grass, Ground Cover, etc)

07-Sep-15

22-Sep-15

14-Sep-15

05-Oct-15

0%

0%

156

ENG.MSS.AR.55 Method Statement Approval - Soft Landscape


(Plants, Trees, Shrubs, Grass, Ground Cover, etc)

29-Sep-15

22-Oct-15

06-Oct-15

29-Oct-15

0%

0%

156

29-Aug-15

06-Dec-15

01-Jun-15 A

10-Nov-15

0%

0%

86

MEP WORKS
Date: 08-Aug-15 6/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

20-Sep-15

21-Oct-15

0%

0%

104

ENG.MSS.MEP.3 Method Statement Submittal - Fire Fighting Works

16-Jul-15 A

08-Oct-15

0%

0%

104

ENG.MSS.MEP.4 Method Statement Approval - Fire Fighting Works

04-Nov-15

30-Jul-15 A

21-Oct-15

0%

0%

104

29-Aug-15

14-Oct-15

16-Jul-15 A

29-Sep-15

0%

0%

123

ENG.MSS.MEP.5 Method Statement Submittal - HVAC Works

29-Aug-15

14-Sep-15

16-Jul-15 A

10-Sep-15

0%

0%

123

ENG.MSS.MEP.6 Method Statement Approval - HVAC Works

14-Sep-15

14-Oct-15

30-Jul-15 A

29-Sep-15

0%

0%

123

19-Nov-15

06-Dec-15

01-Jun-15 A

10-Nov-15

0%

0%

17

19-Nov-15

06-Dec-15

01-Jun-15 A

10-Nov-15

0%

0%

17

11-Apr-15

02-Dec-15

26-Mar-15 A

26-Oct-15

0%

0%

175

11-Apr-15

28-Jul-15

11-Apr-15 A

20-Aug-15

0%

0%

20

11-Apr-15

27-Jul-15

11-Apr-15 A

20-Aug-15

0%

0%

17

11-Apr-15

02-Jul-15

11-Apr-15 A

03-Aug-15

0%

0%

32

FIRE FIGHTIN
FIGHTING WORKS

HVAC WORKS
WORK

ELECTRICAL WORKS
ENG.MSS.MEP.9 Method Statement Submittal - Electrical Works

SHOP DRAWING
DRAWIN SUBMITTAL & APPROVAL
STRUCTURAL
STRUCTURAL LAYOUT & DETAILS
STRUCTURA
WALL DETAILS 1-3 (BUILDING-2)

Start

Finish

04-Nov-15

16-Jul-15 A

20-Sep-15

11-Oct-15

12-Oct-15

ENG.SD.ST.28

Shop Drawing Submittal - Wall Details 1-3

11-Apr-15

26-Apr-15

11-Apr-15 A

01-Aug-15

100%

0%

17

ENG.SD.ST.36

Shop Drawing Approval - Wall Details 1-3

08-Jun-15

02-Jul-15

25-Jun-15 A

03-Aug-15

100%

0%

32

31-May-15

06-Jul-15

16-May-15
A

04-Aug-15

0%

0%

31

WALL DETAILS 4-7 (BUILDING-2)


ENG.SD.ST.38

Shop Drawing Submittal - Wall Details 4-7

31-May-15

16-Jun-15

16-May-15
A

02-Aug-15

100%

0%

17

ENG.SD.ST.46

Shop Drawing Approval - Wall Details 4-7

11-Jun-15

06-Jul-15

25-Jun-15 A

04-Aug-15

100%

0%

31

08-Jun-15

14-Jul-15

16-May-15
A

12-Aug-15

0%

0%

24

WALL DETAILS 8-12 (BUILDING-2)


ENG.SD.ST.49

Shop Drawing Submittal - Wall Details 8-12

08-Jun-15

24-Jun-15

16-May-15
A

10-Aug-15

100%

0%

17

ENG.SD.ST.55

Shop Drawing Approval - Wall Details 8-12

20-Jun-15

14-Jul-15

25-Jun-15 A

12-Aug-15

100%

0%

24

16-Jun-15

27-Jul-15

16-May-15
A

20-Aug-15

0%

0%

17

WALL DETAILS 13-15 (BUILDING-2)


ENG.SD.ST.56

Shop Drawing Submittal - Wall Details 13-15

16-Jun-15

02-Jul-15

16-May-15
A

18-Aug-15

100%

0%

17

ENG.SD.ST.58

Shop Drawing Approval - Wall Details 13-15

28-Jun-15

27-Jul-15

25-Jun-15 A

20-Aug-15

100%

0%

17

29-Jun-15

28-Jul-15

08-Jun-15 A

02-Aug-15

0%

0%

37

29-Jun-15

28-Jul-15

08-Jun-15 A

02-Aug-15

100%

0%

37

STEEL STRUCTURE
STRU
& METAL DECKING
ENG.SD.ST.57

Shop Drawing Approval - Steel Structure

Date: 08-Aug-15 7/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

ARCHITECTURAL
ARCHITECTU
BLOCKWORK & OTHER ARCHITECTURAL
BLOCKWOR
BUILDING SEC
SECTION (BUILDING-1)

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

11-Jul-15

19-Oct-15

19-May-15
A

26-Oct-15

0%

0%

130

25-Jul-15

25-Aug-15

26-Jul-15 A

30-Aug-15

0%

0%

120

25-Jul-15

25-Aug-15

26-Jul-15 A

30-Aug-15

0%

0%

120

ENG.SD.AR.34

Shop Drawing Submittal - Building Section

25-Jul-15

09-Aug-15

26-Jul-15 A

13-Aug-15

42.86%

0%

120

ENG.SD.AR.37

Shop Drawing Approval - Building Section

10-Aug-15

25-Aug-15

13-Aug-15

30-Aug-15

0%

0%

120

03-Sep-15

19-Oct-15

10-Sep-15

26-Oct-15

0%

0%

58

WOOD VENEERED
VENE
MDF PANEL
ENG.SD.AR.51

Shop Drawing Submittal - Wood Veneered MDF


Panel

03-Sep-15

19-Sep-15

10-Sep-15

01-Oct-15

0%

0%

58

ENG.SD.AR.55

Shop Drawing Approval - Wood Veneered MDF


Panel

20-Sep-15

19-Oct-15

03-Oct-15

26-Oct-15

0%

0%

58

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

120

12.5MM THK. WOOD VENEERED MDF CEILING PANE 25-Jul-15


ENG.SD.AR.54

Shop Drawing Submittal - 12.5mm Wood


Veneered MDF Ceiling Panel

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

120

ENG.SD.AR.57

Shop Drawing Approval - 12.5mm Wood


Veneered MDF Ceiling Panel

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

120

11-Jul-15

25-Aug-15

19-May-15
A

19-Aug-15

0%

0%

125

600x600 PER
PERFORATED METAL PAN CEILING
ENG.SD.AR.56

Shop Drawing Submittal - 600x600 Per. Met. Pan


Ceiling

11-Jul-15

01-Aug-15

19-May-15
A

06-Aug-15

96.29%

0%

125

ENG.SD.AR.61

Shop Drawing Approval - 600x600 Per. Met. Pan


Ceiling

01-Aug-15

25-Aug-15

26-May-15
A

19-Aug-15

0%

0%

125

11-Jul-15

25-Aug-15

19-May-15
A

19-Aug-15

0%

0%

184

12.5MM THK. GYPSUM BOARD CEILING


ENG.SD.AR.60

Shop Drawing Submittal - 12.5mm Thk. Gypsum


Board Ceiling

11-Jul-15

01-Aug-15

19-May-15
A

06-Aug-15

96.29%

0%

184

ENG.SD.AR.64

Shop Drawing Approval - 12.5mm Thk. Gypsum


Board Ceiling

01-Aug-15

25-Aug-15

26-May-15
A

19-Aug-15

0%

0%

184

09-Aug-15

19-Sep-15

19-May-15
A

19-Aug-15

0%

0%

145

12.5MM THK. HUMIDITY RESISTANCE CEILING BOA


ENG.SD.AR.65

Shop Drawing Submittal - 12mm Thk. Humidity


Res. Ceiling Board

09-Aug-15

25-Aug-15

19-May-15
A

06-Aug-15

0%

0%

145

ENG.SD.AR.66

Shop Drawing Approval - 12mm Thk. Humidity


Res. Ceiling Board

25-Aug-15

19-Sep-15

26-May-15
A

19-Aug-15

0%

0%

145

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

105

WOOD PARQUET
PARQ
FLOORING
ENG.SD.AR.67

Shop Drawing Submittal - Wood Parquet Flooring

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

105

ENG.SD.AR.70

Shop Drawing Approval - Wood Parquet Flooring

10-Aug-15

02-Sep-15

17-Aug-15

09-Sep-15

0%

0%

105

25-Jul-15

02-Sep-15

01-Aug-15

09-Sep-15

0%

0%

105

25-Jul-15

09-Aug-15

01-Aug-15

16-Aug-15

42.86%

0%

105

WOODEN DO
DOORS INCLUDING SUBFRAMES & ARC
ENG.SD.AR.79

Shop Drawing Submittal - Wooden Doors

Date: 08-Aug-15 8/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Schedule %
Complete

Cost %
Complete

Total
Float

09-Sep-15

0%

0%

105

26-Mar-15 A

26-Oct-15

0%

0%

175

29-Aug-15

10-Jun-15 A

25-Aug-15

0%

0%

170

28-Jun-15

12-Aug-15

10-Jun-15 A

19-Aug-15

0%

0%

176

ENG.SD.DR.15 Shop Drawing Submittal - Drainage

28-Jun-15

14-Jul-15

10-Jun-15 A

06-Aug-15

100%

0%

119

ENG.SD.DR.18 Shop Drawing Approval - Drainage

14-Jul-15

12-Aug-15

17-Jun-15 A

19-Aug-15

49.52%

0%

176

14-Jul-15

29-Aug-15

10-Jun-15 A

25-Aug-15

0%

0%

170

ENG.SD.DR.19 Shop Drawing Submittal - Drainage

14-Jul-15

04-Aug-15

10-Jun-15 A

13-Aug-15

74.29%

0%

119

ENG.SD.DR.21 Shop Drawing Approval - Drainage

04-Aug-15

29-Aug-15

17-Jun-15 A

25-Aug-15

0%

0%

170

15-Jun-15

15-Jul-15

15-Jun-15 A

19-Aug-15

0%

0%

115

ENG.SD.AR.81

Activity Name

Baseline
Start

Baseline
Finish

Shop Drawing Approval - Wooden Doors

10-Aug-15

MEP WORKS
DRAINAGE SHOP
S
DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)

UPPER ROOF FLOOR LEVEL (BUILDING-1)

ROOF FLOOR LEVEL (BUILDING-2)

Start

Finish

02-Sep-15

17-Aug-15

09-May-15

02-Dec-15

15-Jun-15

ENG.SD.DR.8

Shop Drawing Submittal - Drainage

15-Jun-15

30-Jun-15

15-Jun-15 A

06-Aug-15

100%

0%

109

ENG.SD.DR.11

Shop Drawing Approval - Drainage

22-Jun-15

15-Jul-15

22-Jun-15 A

19-Aug-15

100%

0%

115

22-Jun-15

05-Aug-15

15-Jun-15 A

25-Aug-15

0%

0%

109

ENG.SD.DR.12 Shop Drawing Submittal - Drainage

22-Jun-15

07-Jul-15

15-Jun-15 A

13-Aug-15

100%

0%

109

ENG.SD.DR.16 Shop Drawing Approval - Drainage

08-Jul-15

05-Aug-15

22-Jun-15 A

25-Aug-15

76.19%

0%

109

09-May-15

03-Aug-15

09-May-15
A

25-Aug-15

0%

0%

137

06-Jun-15

15-Jul-15

29-Jun-15 A

19-Aug-15

0%

0%

143

ENG.SD.WS.15 Shop Drawing Submittal - Water Supply

06-Jun-15

21-Jun-15

29-Jun-15 A

06-Aug-15

100%

0%

143

ENG.SD.WS.17 Shop Drawing Approval - Water Supply

22-Jun-15

15-Jul-15

05-Jul-15 A

19-Aug-15

100%

0%

143

09-May-15

13-Jul-15

09-May-15
A

19-Aug-15

0%

0%

90

UPPER ROOF FLOOR LEVEL (BUILDING-2)

WATER SUPPLY
SUPP SHOP DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)

GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.WS.4

Shop Drawing Submittal - Water Supply

09-May-15

24-May-15

09-May-15
A

06-Aug-15

100%

0%

90

ENG.SD.WS.7

Shop Drawing Approval - Water Supply

18-Jun-15

13-Jul-15

17-Jun-15 A

19-Aug-15

100%

0%

90

04-Jul-15

03-Aug-15

04-Jul-15 A

25-Aug-15

0%

0%

109

Shop Drawing Submittal - Water Supply

04-Jul-15

23-Jul-15

04-Jul-15 A

13-Aug-15

100%

0%

109

ENG.SD.WS.12 Shop Drawing Approval - Water Supply

05-Jul-15

03-Aug-15

11-Jul-15 A

25-Aug-15

89.52%

0%

109

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.WS.8

Date: 08-Aug-15 9/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

POWER SHOP
SHO DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)

Baseline
Start

Baseline
Finish

Start

Finish

09-May-15

Schedule %
Complete

Cost %
Complete

Total
Float

01-Oct-15

04-Jun-15 A

08-Oct-15

0%

0%

45

08-Jul-15

22-Aug-15

18-Jul-15 A

19-Aug-15

0%

0%

84

ENG.SD.PO.15

Shop Drawing Submittal - Electrical Power

08-Jul-15

28-Jul-15

18-Jul-15 A

06-Aug-15

100%

0%

78

ENG.SD.PO.18

Shop Drawing Approval - Electrical Power

29-Jul-15

22-Aug-15

25-Jul-15 A

19-Aug-15

9.52%

0%

84

29-Jul-15

07-Sep-15

18-Jul-15 A

25-Aug-15

0%

0%

78

UPPER ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.PO.19

Shop Drawing Submittal - Electrical Power

29-Jul-15

13-Aug-15

18-Jul-15 A

13-Aug-15

14.29%

0%

78

ENG.SD.PO.21

Shop Drawing Approval - Electrical Power

15-Aug-15

07-Sep-15

25-Jul-15 A

25-Aug-15

0%

0%

78

09-May-15

14-Jul-15

04-Jun-15 A

19-Aug-15

0%

0%

73

GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.PO.4

Shop Drawing Submittal - Electrical Power

09-May-15

24-May-15

04-Jun-15 A

06-Aug-15

100%

0%

45

ENG.SD.PO.7

Shop Drawing Approval - Electrical Power

20-Jun-15

14-Jul-15

11-Jun-15 A

19-Aug-15

100%

0%

73

30-Jul-15

09-Sep-15

06-Aug-15

16-Sep-15

0%

0%

59

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.PO.8

Shop Drawing Submittal - Electrical Power

30-Jul-15

16-Aug-15

06-Aug-15

23-Aug-15

2.86%

0%

45

ENG.SD.PO.11

Shop Drawing Approval - Electrical Power

16-Aug-15

09-Sep-15

23-Aug-15

16-Sep-15

0%

0%

59

16-Aug-15

01-Oct-15

23-Aug-15

08-Oct-15

0%

0%

45

UPPER ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.PO.12

Shop Drawing Submittal - Electrical Power

16-Aug-15

01-Sep-15

23-Aug-15

08-Sep-15

0%

0%

45

ENG.SD.PO.16

Shop Drawing Approval - Electrical Power

01-Sep-15

01-Oct-15

08-Sep-15

08-Oct-15

0%

0%

45

09-May-15

04-Aug-15

08-Jun-15 A

25-Aug-15

0%

0%

120

09-May-15

14-Jul-15

15-Jul-15 A

19-Aug-15

0%

0%

75

LIGHTING SH
SHOP DRAWINGS
ROOF FLOOR LEVEL (BUILDING-1)
ENG.SD.LI.15

Shop Drawing Submittal - Electrical Lighting

09-May-15

24-May-15

15-Jul-15 A

06-Aug-15

100%

0%

69

ENG.SD.LI.18

Shop Drawing Approval - Electrical Lighting

20-Jun-15

14-Jul-15

22-Jul-15 A

19-Aug-15

100%

0%

75

20-Jun-15

04-Aug-15

15-Jul-15 A

25-Aug-15

0%

0%

69

UPPER ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.LI.19

Shop Drawing Submittal - Electrical Lighting

20-Jun-15

06-Jul-15

15-Jul-15 A

13-Aug-15

100%

0%

69

ENG.SD.LI.21

Shop Drawing Approval - Electrical Lighting

06-Jul-15

04-Aug-15

22-Jul-15 A

25-Aug-15

82.86%

0%

69

09-May-15

14-Jul-15

08-Jun-15 A

19-Aug-15

0%

0%

115

09-May-15

24-May-15

08-Jun-15 A

06-Aug-15

100%

0%

115

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.LI.8

Shop Drawing Submittal - Electrical Lighting

Date: 08-Aug-15 10/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

ENG.SD.LI.11

Activity Name

Baseline
Start

Baseline
Finish

Shop Drawing Approval - Electrical Lighting

20-Jun-15

UPPER ROOF FLOOR LEVEL (BUILDING-2)

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

14-Jul-15

15-Jun-15 A

19-Aug-15

100%

0%

115

20-Jun-15

04-Aug-15

08-Jun-15 A

25-Aug-15

0%

0%

120

ENG.SD.LI.12

Shop Drawing Submittal - Electrical Lighting

20-Jun-15

06-Jul-15

08-Jun-15 A

13-Aug-15

100%

0%

120

ENG.SD.LI.16

Shop Drawing Approval - Electrical Lighting

06-Jul-15

04-Aug-15

15-Jun-15 A

25-Aug-15

82.86%

0%

120

06-Jun-15

18-Oct-15

07-Jul-15 A

25-Oct-15

0%

0%

176

06-Jun-15

15-Jul-15

07-Jul-15 A

19-Aug-15

0%

0%

75

ENG.SD.CCTV.1 Shop Drawing Submittal - CCTV & Security System 06-Jun-15

21-Jun-15

07-Jul-15 A

06-Aug-15

100%

0%

35

ENG.SD.CCTV.3 Shop Drawing Approval - CCTV & Security System 22-Jun-15

15-Jul-15

14-Jul-15 A

19-Aug-15

100%

0%

75

05-Aug-15

07-Jul-15 A

25-Aug-15

0%

0%

95

ENG.SD.CCTV.2 Shop Drawing Submittal - CCTV & Security System 22-Jun-15

07-Jul-15

07-Jul-15 A

13-Aug-15

100%

0%

75

ENG.SD.CCTV.5 Shop Drawing Approval - CCTV & Security System 08-Jul-15

05-Aug-15

14-Jul-15 A

25-Aug-15

76.19%

0%

95

06-Aug-15

16-Sep-15

13-Aug-15

29-Sep-15

0%

0%

84

ENG.SD.CCTV.6 Shop Drawing Submittal - CCTV & Security System 06-Aug-15

23-Aug-15

13-Aug-15

30-Aug-15

0%

0%

75

ENG.SD.CCTV.9 Shop Drawing Approval - CCTV & Security System 23-Aug-15

16-Sep-15

30-Aug-15

29-Sep-15

0%

0%

84

08-Oct-15

30-Aug-15

15-Oct-15

0%

0%

75

ENG.SD.CCTV.10Shop Drawing Submittal - CCTV & Security System 23-Aug-15

08-Sep-15

30-Aug-15

15-Sep-15

0%

0%

75

ENG.SD.CCTV.13Shop Drawing Approval - CCTV & Security System 08-Sep-15

08-Oct-15

15-Sep-15

15-Oct-15

0%

0%

75

30-Sep-15

17-Oct-15

07-Oct-15

24-Oct-15

0%

0%

142

ENG.SD.CCTV.19Shop Drawing Submittal - CCTV & Security System 30-Sep-15

17-Oct-15

07-Oct-15

24-Oct-15

0%

0%

142

08-Sep-15

30-Sep-15

15-Sep-15

07-Oct-15

0%

0%

98

ENG.SD.CCTV.15Shop Drawing Submittal - CCTV & Security System 08-Sep-15

30-Sep-15

15-Sep-15

07-Oct-15

0%

0%

98

30-Jul-15

09-Sep-15

06-Aug-15

16-Sep-15

0%

0%

69

ENG.SD.CCTV.4 Shop Drawing Submittal - CCTV & Security System 30-Jul-15

16-Aug-15

06-Aug-15

23-Aug-15

2.86%

0%

69

ENG.SD.CCTV.7 Shop Drawing Approval - CCTV & Security System 16-Aug-15

09-Sep-15

23-Aug-15

16-Sep-15

0%

0%

69

01-Oct-15

23-Aug-15

08-Oct-15

0%

0%

76

CCTV & SECURITY


SEC
SYSTEM SHOP DRAWINGS
GROUND FLOOR
FLOO LEVEL (BUILDING-1)

22-Jun-15

FIRST FLOOR LEVEL (BUILDING-1)

SECOND FLOO
FLOOR LEVEL (BUILDING-1)

23-Aug-15

THIRD FLOOR LEVEL (BUILDING-1)

UPPER ROOF FLOOR LEVEL (BUILDING-1)

ROOF FLOOR LEVEL (BUILDING-1)

GROUND FLOOR
FLOO LEVEL (BUILDING-2)

16-Aug-15

ROOF FLOOR LEVEL (BUILDING-2)


Date: 08-Aug-15 11/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

ENG.SD.CCTV.8 Shop Drawing Submittal - CCTV & Security System 16-Aug-15

01-Sep-15

23-Aug-15

08-Sep-15

0%

0%

76

ENG.SD.CCTV.11Shop Drawing Approval - CCTV & Security System 01-Sep-15

01-Oct-15

08-Sep-15

08-Oct-15

0%

0%

76

01-Sep-15

18-Oct-15

08-Sep-15

25-Oct-15

0%

0%

176

ENG.SD.CCTV.12Shop Drawing Submittal - CCTV & Security System 01-Sep-15

17-Sep-15

08-Sep-15

30-Sep-15

0%

0%

162

ENG.SD.CCTV.16Shop Drawing Approval - CCTV & Security System 17-Sep-15

18-Oct-15

30-Sep-15

25-Oct-15

0%

0%

176

17-Sep-15

10-Oct-15

30-Sep-15

17-Oct-15

0%

0%

162

ENG.SD.CCTV.14Shop Drawing Submittal - CCTV & Security System 17-Sep-15

10-Oct-15

30-Sep-15

17-Oct-15

0%

0%

162

TELEPHONE, DATA & TV SYSTEM SHOP DRAWINGS 22-Jun-15


TELEPHONE

02-Dec-15

07-Jul-15 A

21-Oct-15

0%

0%

107

22-Jun-15

05-Aug-15

07-Jul-15 A

13-Aug-15

0%

0%

71

UPPER ROOF FLOOR LEVEL (BUILDING-2)

DRAWING DETAILS
DET
(BUILDING-2)

GROUND FLOOR
FLOO LEVEL (BUILDING-1)
ENG.SD.TEL.1

Shop Drawing Submittal - Telephone, Data & TV


System

22-Jun-15

07-Jul-15

07-Jul-15 A

08-Aug-15

100%

0%

35

ENG.SD.TEL.3

Shop Drawing Approval - Telephone, Data & TV


System

08-Jul-15

05-Aug-15

14-Jul-15 A

13-Aug-15

76.19%

0%

71

08-Jul-15

22-Aug-15

07-Jul-15 A

15-Aug-15

0%

0%

104

FIRST FLOOR LEVEL (BUILDING-1)


ENG.SD.TEL.2

Shop Drawing Submittal - Telephone, Data & TV


System

08-Jul-15

28-Jul-15

07-Jul-15 A

10-Aug-15

100%

0%

104

ENG.SD.TEL.5

Shop Drawing Approval - Telephone, Data & TV


System

29-Jul-15

22-Aug-15

14-Jul-15 A

15-Aug-15

9.52%

0%

104

12-Aug-15

22-Sep-15

20-Jul-15 A

29-Aug-15

0%

0%

105

SECOND FLOO
FLOOR LEVEL (BUILDING-1)
ENG.SD.TEL.6

Shop Drawing Submittal - Telephone, Data & TV


System

12-Aug-15

29-Aug-15

20-Jul-15 A

16-Aug-15

0%

0%

105

ENG.SD.TEL.9

Shop Drawing Approval - Telephone, Data & TV


System

29-Aug-15

22-Sep-15

03-Aug-15 A 29-Aug-15

0%

0%

105

29-Aug-15

14-Oct-15

20-Jul-15 A

05-Sep-15

0%

0%

105

ENG.SD.TEL.10 Shop Drawing Submittal - Telephone, Data & TV


System

29-Aug-15

14-Sep-15

20-Jul-15 A

23-Aug-15

0%

0%

105

ENG.SD.TEL.13 Shop Drawing Approval - Telephone, Data & TV


System

14-Sep-15

14-Oct-15

03-Aug-15 A 05-Sep-15

0%

0%

105

14-Sep-15

31-Oct-15

20-Jul-15 A

10-Sep-15

0%

0%

137

ENG.SD.TEL.15 Shop Drawing Submittal - Telephone, Data & TV


System

14-Sep-15

06-Oct-15

20-Jul-15 A

30-Aug-15

0%

0%

107

ENG.SD.TEL.18 Shop Drawing Approval - Telephone, Data & TV


System

06-Oct-15

31-Oct-15

03-Aug-15 A 10-Sep-15

0%

0%

137

06-Oct-15

16-Nov-15

20-Jul-15 A

17-Sep-15

0%

0%

131

06-Oct-15

22-Oct-15

20-Jul-15 A

05-Sep-15

0%

0%

107

THIRD FLOOR LEVEL (BUILDING-1)

ROOF FLOOR LEVEL (BUILDING-1)

UPPER ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.TEL.19 Shop Drawing Submittal - Telephone, Data & TV
System
Date: 08-Aug-15 12/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

22-Oct-15

16-Nov-15

22-Oct-15

02-Dec-15

05-Sep-15

ENG.SD.TEL.20 Shop Drawing Submittal - Telephone, Data & TV


System

22-Oct-15

08-Nov-15

ENG.SD.TEL.22 Shop Drawing Approval - Telephone, Data & TV


System

08-Nov-15

ENG.SD.TEL.21 Shop Drawing Approval - Telephone, Data & TV


System

DRAWING DETAILS
DET
(BUILDING-1)

GROUND FLOOR
FLOO LEVEL (BUILDING-2)

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

0%

0%

131

21-Oct-15

0%

0%

107

05-Sep-15

21-Sep-15

0%

0%

107

02-Dec-15

21-Sep-15

21-Oct-15

0%

0%

107

06-Aug-15

16-Sep-15

20-Jul-15 A

27-Aug-15

0%

0%

87

03-Aug-15 A 17-Sep-15

ENG.SD.TEL.4

Shop Drawing Submittal - Telephone, Data & TV


System

06-Aug-15

23-Aug-15

20-Jul-15 A

15-Aug-15

0%

0%

87

ENG.SD.TEL.7

Shop Drawing Approval - Telephone, Data & TV


System

23-Aug-15

16-Sep-15

03-Aug-15 A 27-Aug-15

0%

0%

87

23-Aug-15

08-Oct-15

20-Jul-15 A

02-Sep-15

0%

0%

102

Shop Drawing Submittal - Telephone, Data & TV


System

23-Aug-15

08-Sep-15

20-Jul-15 A

22-Aug-15

0%

0%

96

ENG.SD.TEL.11 Shop Drawing Approval - Telephone, Data & TV


System

08-Sep-15

08-Oct-15

03-Aug-15 A 02-Sep-15

0%

0%

102

08-Sep-15

25-Oct-15

20-Jul-15 A

09-Sep-15

0%

0%

96

ENG.SD.TEL.12 Shop Drawing Submittal - Telephone, Data & TV


System

08-Sep-15

30-Sep-15

20-Jul-15 A

27-Aug-15

0%

0%

96

ENG.SD.TEL.16 Shop Drawing Approval - Telephone, Data & TV


System

30-Sep-15

25-Oct-15

03-Aug-15 A 09-Sep-15

0%

0%

96

30-Sep-15

10-Nov-15

27-Aug-15

13-Oct-15

0%

0%

114

ENG.SD.TEL.14 Shop Drawing Submittal - Telephone, Data & TV


System

30-Sep-15

17-Oct-15

27-Aug-15

13-Sep-15

0%

0%

114

ENG.SD.TEL.17 Shop Drawing Approval - Telephone, Data & TV


System

17-Oct-15

10-Nov-15

13-Sep-15

13-Oct-15

0%

0%

114

FIRE ALARM SHOP DRAWINGS

06-Aug-15

31-Oct-15

09-Aug-15

26-Oct-15

0%

0%

55

THIRD FLOOR LEVEL (BUILDING-1)

12-Aug-15

22-Sep-15

09-Aug-15

17-Sep-15

0%

0%

83

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.TEL.8

UPPER ROOF FLOOR LEVEL (BUILDING-2)

DRAWING DETAILS
DET
(BUILDING-2)

ENG.SD.FA.10

Shop Drawing Submittal - Fire Alarm System

12-Aug-15

29-Aug-15

09-Aug-15

24-Aug-15

0%

0%

55

ENG.SD.FA.13

Shop Drawing Approval - Fire Alarm System

29-Aug-15

22-Sep-15

25-Aug-15

17-Sep-15

0%

0%

83

29-Aug-15

14-Oct-15

25-Aug-15

10-Oct-15

0%

0%

69

ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.FA.15

Shop Drawing Submittal - Fire Alarm System

29-Aug-15

14-Sep-15

25-Aug-15

09-Sep-15

0%

0%

55

ENG.SD.FA.18

Shop Drawing Approval - Fire Alarm System

14-Sep-15

14-Oct-15

10-Sep-15

10-Oct-15

0%

0%

69

14-Sep-15

31-Oct-15

10-Sep-15

26-Oct-15

0%

0%

55

14-Sep-15

06-Oct-15

10-Sep-15

01-Oct-15

0%

0%

55

UPPER ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.FA.19

Shop Drawing Submittal - Fire Alarm System

Date: 08-Aug-15 13/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

ENG.SD.FA.21

Activity Name

Baseline
Start

Baseline
Finish

Shop Drawing Approval - Fire Alarm System

06-Oct-15

GROUND FLOOR
FLOO LEVEL (BUILDING-2)

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

31-Oct-15

03-Oct-15

26-Oct-15

0%

0%

55

06-Aug-15

16-Sep-15

09-Aug-15

17-Sep-15

0%

0%

68

ENG.SD.FA.4

Shop Drawing Submittal - Fire Alarm System

06-Aug-15

23-Aug-15

09-Aug-15

24-Aug-15

0%

0%

41

ENG.SD.FA.7

Shop Drawing Approval - Fire Alarm System

23-Aug-15

16-Sep-15

25-Aug-15

17-Sep-15

0%

0%

68

23-Aug-15

08-Oct-15

25-Aug-15

10-Oct-15

0%

0%

69

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.FA.8

Shop Drawing Submittal - Fire Alarm System

23-Aug-15

08-Sep-15

25-Aug-15

09-Sep-15

0%

0%

41

ENG.SD.FA.11

Shop Drawing Approval - Fire Alarm System

08-Sep-15

08-Oct-15

10-Sep-15

10-Oct-15

0%

0%

69

08-Sep-15

25-Oct-15

10-Sep-15

26-Oct-15

0%

0%

55

UPPER ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.FA.12

Shop Drawing Submittal - Fire Alarm System

08-Sep-15

30-Sep-15

10-Sep-15

01-Oct-15

0%

0%

41

ENG.SD.FA.16

Shop Drawing Approval - Fire Alarm System

30-Sep-15

25-Oct-15

03-Oct-15

26-Oct-15

0%

0%

55

30-Sep-15

17-Oct-15

03-Oct-15

18-Oct-15

0%

0%

41

30-Sep-15

17-Oct-15

03-Oct-15

18-Oct-15

0%

0%

41

28-May-15

07-Nov-15

26-Mar-15 A

07-Oct-15

0%

0%

71

03-Jun-15

28-Jun-15

26-Mar-15 A

12-Aug-15

0%

0%

103

03-Jun-15

28-Jun-15

26-Mar-15 A

12-Aug-15

100%

0%

103

10-Jun-15

25-Jul-15

27-Apr-15 A

27-Aug-15

0%

0%

91

DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.FA.14

Shop Drawing Submittal - Fire Alarm System

FIRE FIGHTIN
FIGHTING SHOP DRAWINGS
FIRST FLOOR LEVEL (BUILDING-1)
ENG.SD.FF.5

Shop Drawing Approval - Fire Fighting

SECOND FLOO
FLOOR LEVEL (BUILDING-1)
ENG.SD.FF.6

Shop Drawing Submittal - Fire Fighting

10-Jun-15

25-Jun-15

27-Apr-15 A

15-Aug-15

100%

0%

79

ENG.SD.FF.9

Shop Drawing Approval - Fire Fighting

27-Jun-15

25-Jul-15

28-Apr-15 A

27-Aug-15

100%

0%

91

27-Jun-15

18-Aug-15

27-Apr-15 A

08-Sep-15

0%

0%

91

THIRD FLOOR LEVEL (BUILDING-1)


ENG.SD.FF.10

Shop Drawing Submittal - Fire Fighting

27-Jun-15

12-Jul-15

27-Apr-15 A

22-Aug-15

100%

0%

79

ENG.SD.FF.16

Shop Drawing Approval - Fire Fighting

26-Jul-15

18-Aug-15

28-Apr-15 A

08-Sep-15

23.81%

0%

91

26-Jul-15

05-Sep-15

09-Jun-15 A

09-Sep-15

0%

0%

90

ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.FF.14

Shop Drawing Submittal - Fire Fighting

26-Jul-15

11-Aug-15

09-Jun-15 A

27-Aug-15

34.29%

0%

79

ENG.SD.FF.18

Shop Drawing Approval - Fire Fighting

11-Aug-15

05-Sep-15

16-Jun-15 A

09-Sep-15

0%

0%

90

11-Aug-15

21-Sep-15

09-Jun-15 A

15-Sep-15

0%

0%

84

UPPER ROOF FLOOR LEVEL (BUILDING-1)


Date: 08-Aug-15 14/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

ENG.SD.FF.19

Shop Drawing Submittal - Fire Fighting

11-Aug-15

ENG.SD.FF.21

Shop Drawing Approval - Fire Fighting

DRAWING DETAILS
DET
(BUILDING-1)

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

27-Aug-15

09-Jun-15 A

03-Sep-15

0%

0%

79

27-Aug-15

21-Sep-15

16-Jun-15 A

15-Sep-15

0%

0%

84

21-Sep-15

07-Nov-15

23-Jul-15 A

07-Oct-15

0%

0%

71

ENG.SD.FF.20

Shop Drawing Submittal - Fire Fighting

21-Sep-15

13-Oct-15

23-Jul-15 A

09-Sep-15

0%

0%

79

ENG.SD.FF.22

Shop Drawing Approval - Fire Fighting

13-Oct-15

07-Nov-15

30-Jul-15 A

07-Oct-15

0%

0%

71

28-May-15

22-Jun-15

06-Apr-15 A

11-Aug-15

0%

0%

115

28-May-15

22-Jun-15

06-Apr-15 A

11-Aug-15

100%

0%

115

08-Jul-15

22-Aug-15

09-Jun-15 A

27-Aug-15

0%

0%

101

GROUND FLOOR
FLOO LEVEL (BUILDING-2)
ENG.SD.FF.7

Shop Drawing Approval - Fire Fighting

ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.FF.8

Shop Drawing Submittal - Fire Fighting

08-Jul-15

28-Jul-15

09-Jun-15 A

15-Aug-15

100%

0%

71

ENG.SD.FF.11

Shop Drawing Approval - Fire Fighting

29-Jul-15

22-Aug-15

16-Jun-15 A

27-Aug-15

9.52%

0%

101

29-Jul-15

07-Sep-15

09-Jun-15 A

02-Sep-15

0%

0%

95

UPPER ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.FF.12

Shop Drawing Submittal - Fire Fighting

29-Jul-15

13-Aug-15

09-Jun-15 A

22-Aug-15

14.29%

0%

71

ENG.SD.FF.15

Shop Drawing Approval - Fire Fighting

15-Aug-15

07-Sep-15

16-Jun-15 A

02-Sep-15

0%

0%

95

19-Aug-15

05-Oct-15

22-Aug-15

07-Oct-15

0%

0%

71

DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.FF.13

Shop Drawing Submittal - Fire Fighting

19-Aug-15

05-Sep-15

22-Aug-15

07-Sep-15

0%

0%

71

ENG.SD.FF.17

Shop Drawing Approval - Fire Fighting

05-Sep-15

05-Oct-15

07-Sep-15

07-Oct-15

0%

0%

71

08-Jul-15

29-Sep-15

16-Jun-15 A

30-Sep-15

0%

0%

35

08-Jul-15

22-Aug-15

27-Jun-15 A

27-Aug-15

0%

0%

60

HVAC SHOP DRAWINGS


ROOF FLOOR LEVEL (BUILDING-1)
ENG.SD.AC.15

Shop Drawing Submittal - HVAC Shop Drawing

08-Jul-15

28-Jul-15

27-Jun-15 A

15-Aug-15

100%

0%

48

ENG.SD.AC.18

Shop Drawing Approval - HVAC Shop Drawing

29-Jul-15

22-Aug-15

04-Jul-15 A

27-Aug-15

9.52%

0%

60

29-Jul-15

07-Sep-15

27-Jun-15 A

02-Sep-15

0%

0%

54

UPPER ROOF FLOOR LEVEL (BUILDING-1)


ENG.SD.AC.19

Shop Drawing Submittal - HVAC Shop Drawing

29-Jul-15

13-Aug-15

27-Jun-15 A

22-Aug-15

14.29%

0%

48

ENG.SD.AC.21

Shop Drawing Approval - HVAC Shop Drawing

15-Aug-15

07-Sep-15

04-Jul-15 A

02-Sep-15

0%

0%

54

15-Aug-15

29-Sep-15

16-Jun-15 A

09-Sep-15

0%

0%

48

15-Aug-15

30-Aug-15

16-Jun-15 A

27-Aug-15

0%

0%

48

DRAWING DETAILS
DET
(BUILDING-1)
ENG.SD.AC.20

Shop Drawing Submittal - HVAC Shop Drawing

Date: 08-Aug-15 15/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

ENG.SD.AC.22

Activity Name

Baseline
Start

Baseline
Finish

Shop Drawing Approval - HVAC Shop Drawing

31-Aug-15

ROOF FLOOR LEVEL (BUILDING-2)

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

29-Sep-15

23-Jun-15 A

09-Sep-15

0%

0%

48

08-Jul-15

22-Aug-15

22-Jun-15 A

27-Aug-15

0%

0%

60

ENG.SD.AC.8

Shop Drawing Submittal - HVAC Shop Drawing

08-Jul-15

28-Jul-15

22-Jun-15 A

15-Aug-15

100%

0%

35

ENG.SD.AC.11

Shop Drawing Approval - HVAC Shop Drawing

29-Jul-15

22-Aug-15

29-Jun-15 A

27-Aug-15

9.52%

0%

60

12-Aug-15

22-Sep-15

15-Aug-15

30-Sep-15

0%

0%

35

UPPER ROOF FLOOR LEVEL (BUILDING-2)


ENG.SD.AC.12

Shop Drawing Submittal - HVAC Shop Drawing

12-Aug-15

29-Aug-15

15-Aug-15

31-Aug-15

0%

0%

35

ENG.SD.AC.16

Shop Drawing Approval - HVAC Shop Drawing

29-Aug-15

22-Sep-15

31-Aug-15

30-Sep-15

0%

0%

35

15-Aug-15

29-Sep-15

22-Jun-15 A

30-Sep-15

0%

0%

35

DRAWING DETAILS
DET
(BUILDING-2)
ENG.SD.AC.14

Shop Drawing Submittal - HVAC Shop Drawing

15-Aug-15

30-Aug-15

22-Jun-15 A

07-Sep-15

0%

0%

40

ENG.SD.AC.17

Shop Drawing Approval - HVAC Shop Drawing

31-Aug-15

29-Sep-15

29-Jun-15 A

30-Sep-15

0%

0%

35

06-Jun-15

07-Nov-15

28-May-15
A

29-Oct-15

0%

0%

238

25-Jul-15

21-Aug-15

01-Aug-15

28-Aug-15

0%

0%

111

25-Jul-15

21-Aug-15

01-Aug-15

28-Aug-15

0%

0%

111

25-Jul-15

21-Aug-15

01-Aug-15

28-Aug-15

0%

0%

111

PROCUREMENT
SUBCONTRACTOR/SUPPLIER PREQUALIFICATION
SUBCONTRAC
ARCHITECTURAL
ARCHITECTU
MIRRORS
PRO.SS.AR.21

Subcontractor Submission - Mirrror

25-Jul-15

07-Aug-15

01-Aug-15

14-Aug-15

50%

0%

111

PRO.SS.AR.22

Subcontractor Approval - Mirrror

08-Aug-15

21-Aug-15

15-Aug-15

28-Aug-15

0%

0%

111

06-Jun-15

07-Nov-15

28-May-15
A

29-Oct-15

0%

0%

238

07-Jul-15

22-Oct-15

28-May-15
A

29-Oct-15

0%

0%

151

07-Jul-15

30-Sep-15

28-May-15
A

07-Oct-15

0%

0%

35

07-Jul-15

30-Sep-15

28-May-15
A

07-Oct-15

0%

0%

35

07-Jul-15

19-Sep-15

28-May-15
A

07-Oct-15

33.33%

0%

35

07-Oct-15

0%

0%

35

MANUFACTURE/PURCHASE/DELIVERY
MANUFACTUR
LONG LEAD ITEMS
I
STRUCTURAL
STEEL STRUC
STRUCTURE & METAL DECKING
PRO.PD.ST.20

Manufacture & Delivery Period - Steel Structure &


Metal Decking

PRO.PD.ST.32

Materials Available on Site - Steel Structure &


Metal Decking

ARCHITECTURAL
ARCHITECTU
WOOD PARQUET
PARQU
FLOORING
PRO.PD.AR.012 Manufacture & Delivery Period - Wood Parquet
Flooring
Date: 08-Aug-15 16/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

30-Sep-15
25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

151

10-Aug-15

18-Oct-15

17-Aug-15

25-Oct-15

0%

0%

128

10-Aug-15

18-Oct-15

17-Aug-15

25-Oct-15

0%

0%

128

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

07-Oct-15, , 07-Oct-15

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

PRO.PD.AR.026 Materials Available on Site - Wood Parquet


Flooring

WALL & FLOOR


FLOO CERAMIC TILES
PRO.PD.AR.02

Materials Order & Delivery Period - Ceramic Tiles

18-Oct-15

PRO.PD.AR.03

Materials Order & Delivery Period - Marble Tiles

PRO.PD.AR.04

Materials Order & Delivery Period - Mosaic Tiles

PRO.PD.AR.013 Manufacture & Delivery Period - Kitchen Cabinet

Cost %
Complete

Total
Float

25-Oct-15

0%

0%

128

01-Aug-15

29-Sep-15

0%

0%

125

25-Jul-15

22-Sep-15

01-Aug-15

29-Sep-15

11.67%

0%

125

29-Sep-15

0%

0%

125

22-Sep-15
25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

112

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

7.78%

0%

112

29-Oct-15

0%

0%

112

22-Oct-15
25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

140

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

7.78%

0%

140

29-Oct-15

0%

0%

140

PRO.PD.AR.017 Materials Available on Site - Mosaic Tiles

PANTRY CABINET
CABIN
& BASE CABINET

Schedule %
Complete

22-Sep-15

PRO.PD.AR.015 Materials Available on Site - Marble Tiles

MOSAIC TILES

Finish

25-Jul-15

PRO.PD.AR.010 Materials Available on Site - Ceramic Tiles

MARBLE TILES

Start

22-Oct-15
10-Aug-15

18-Oct-15

17-Aug-15

25-Oct-15

0%

0%

155

10-Aug-15

18-Oct-15

17-Aug-15

25-Oct-15

0%

0%

155

25-Oct-15

0%

0%

155

PRO.PD.AR.029 Materials Available on Site - Kitchen Cabinet

18-Oct-15
06-Jun-15

07-Nov-15

06-Jun-15 A

29-Oct-15

0%

0%

238

06-Jun-15

22-Oct-15

06-Jun-15 A

29-Oct-15

0%

0%

122

WATER PROO
PROOFING WORKS

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

122

WET AREA WATERPROOFING


WAT

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

79

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

7.78%

0%

79

29-Oct-15

0%

0%

79

SHORT LEAD ITEMS


STRUCTURAL

PRO.PD.ST.15 Manufacture & Delivery Period - Waterproofing to


Wet Areas
PRO.PD.ST.28 Materials on Site Storage - Waterproofing to Wet
Areas
ROOF WATERPROOFING
WATERPR

PRO.PD.ST.29 Manufacture & Delivery Period - Waterproofing to


Roof

22-Oct-15
25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

0%

0%

122

25-Jul-15

22-Oct-15

01-Aug-15

29-Oct-15

7.78%

0%

122

29-Oct-15

0%

0%

122

PRO.PD.ST.34 Materials on Site Storage - Waterproofing to Roof

REINFORCING STEEL
THIRD FLOOR ((BUILDING-1)

22-Oct-15
06-Jun-15

07-Sep-15

06-Jun-15 A

14-Sep-15

0%

0%

110

06-Jun-15

15-Aug-15

06-Jun-15 A

22-Aug-15

0%

0%

38

05-Jul-15

06-Jun-15 A

15-Aug-15

100%

0%

38

PRO.PD.ST.24 Manufacture & Delivery Period - Third Floor Slab & 06-Jun-15
Verticals
Date: 08-Aug-15 17/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

25-Oct-15, , 25-Oct-15

29-Sep-15, , 29-Sep-15

29-Oct-15, , 29-Oct-15

29-Oct-15, , 29-Oct-15

25-Oct-15, , 25-Oct-15

29-Oct-15, , 29-Oct-15

29-Oct-15, , 29-Oct-15

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

15-Aug-15

16-Aug-15

22-Aug-15

0%

0%

38

25-Jul-15

30-Aug-15

01-Aug-15

06-Sep-15

0%

0%

58

PRO.PD.ST.27 Manufacture & Delivery Period - Roof Floor Slab & 25-Jul-15
Verticals

23-Aug-15

01-Aug-15

30-Aug-15

23.33%

0%

58

PRO.PD.ST.30 Materials on Site Storage - Roof Floor Slab &


Verticals

24-Aug-15

30-Aug-15

31-Aug-15

06-Sep-15

0%

0%

58

25-Jul-15

30-Aug-15

01-Aug-15

06-Sep-15

0%

0%

104

PRO.PD.ST.31 Manufacture & Delivery Period - Upper Roof Floor


Slab & Verticals

25-Jul-15

23-Aug-15

01-Aug-15

30-Aug-15

23.33%

0%

104

PRO.PD.ST.33 Materials on Site Storage - Upper Roof Floor Slab


& Verticals

24-Aug-15

30-Aug-15

31-Aug-15

06-Sep-15

0%

0%

104

25-Jul-15

07-Sep-15

01-Aug-15

14-Sep-15

0%

0%

23

PRO.PD.ST.17 Manufacture & Delivery Period - Roof Floor Slab & 25-Jul-15
Verticals

23-Aug-15

01-Aug-15

30-Aug-15

23.33%

0%

23

PRO.PD.ST.21 Materials on Site Storage - Roof Floor Slab &


Verticals

24-Aug-15

07-Sep-15

31-Aug-15

14-Sep-15

0%

0%

23

25-Jul-15

07-Sep-15

01-Aug-15

14-Sep-15

0%

0%

110

25-Jul-15

07-Sep-15

01-Aug-15

14-Sep-15

15.56%

0%

110

14-Sep-15

0%

0%

110

PRO.PD.ST.26 Materials on Site Storage - Third Floor Slab &


Verticals
ROOF FLOOR (BUILDING-1)
(

UPPER ROOF F
FLOOR (BUILDING-1)

ROOF FLOOR (BUILDING-2)


(

UPPER ROOF F
FLOOR (BUILDING-2)

PRO.PD.ST.22 Manufacture & Delivery Period - Upper Roof Floor


Slab & Verticals

Baseline
Start

Baseline
Finish

09-Aug-15

PRO.PD.ST.25 Materials on Site Storage - Upper Roof Floor Slab


& Verticals

ARCHITECTURAL
ARCHITECTU
INTERNAL PAINT
PAI
PRO.PD.AR.1

Material Order & Delivery Period - Internal Paint

PRO.PD.AR.5

Materials Available on Site - Internal Paint

12.5MM THK. GYPSUM


G
BOARD CEILING
PRO.PD.AR.15

Materials Order & Delivery Period - 12.5mm Thk.


Gypsum Board Ceiling

PRO.PD.AR.37

Materials Available on Site - 12.5mm Thk. Gypsum


Board Ceiling

07-Sep-15
12-Aug-15

19-Oct-15

19-Aug-15

26-Oct-15

0%

0%

197

20-Sep-15

19-Oct-15

27-Sep-15

26-Oct-15

0%

0%

62

20-Sep-15

19-Oct-15

27-Sep-15

26-Oct-15

0%

0%

62

26-Oct-15

0%

0%

62

19-Oct-15
12-Aug-15

26-Sep-15

19-Aug-15

03-Oct-15

0%

0%

221

12-Aug-15

26-Sep-15

19-Aug-15

03-Oct-15

0%

0%

221

03-Oct-15

0%

0%

221

26-Sep-15
25-Jul-15

07-Nov-15

01-Aug-15

24-Oct-15

0%

0%

243

ELECTRICAL M
MATERIALS

25-Jul-15

02-Oct-15

01-Aug-15

03-Oct-15

0%

0%

159

POWER & LIGHT


LIGHTING CABLE

25-Jul-15

07-Sep-15

01-Aug-15

14-Sep-15

0%

0%

130

25-Jul-15

07-Sep-15

01-Aug-15

14-Sep-15

15.56%

0%

130

14-Sep-15

0%

0%

130

MEP WORKS

PRO.PD.EE.3

Manufacture & Delivery Period - Power Cable

PRO.PD.EE.6

Materials on Site - Power Cable

Date: 08-Aug-15 18/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

07-Sep-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

14-Sep-15, , 14-Sep-15

26-Oct-15, , 26-Oct-15

03-Oct-15, , 03-Oct-15

14-Sep-15, , 14-Sep-15

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name
LOW VOLTAGE CABLE

PRO.PD.EE.8

Manufacture & Delivery Period - Low Voltage


Cable

Baseline
Start

Baseline
Finish

18-Aug-15
18-Aug-15

PRO.PD.EE.17 Materials on Site Storage - Low Voltage Cable

Start

Finish

02-Oct-15

19-Aug-15

02-Oct-15

19-Aug-15

02-Oct-15

Schedule %
Complete

Cost %
Complete

Total
Float

03-Oct-15

0%

0%

159

03-Oct-15

0%

0%

159

03-Oct-15

0%

0%

159

18-Aug-15

02-Oct-15

19-Aug-15

03-Oct-15

0%

0%

100

PRO.PD.EE.2

Manufacture & Delivery Period - MDB, SMDB & DB 18-Aug-15

02-Oct-15

19-Aug-15

03-Oct-15

0%

0%

100

PRO.PD.EE.5

Materials on Site - MDB, SMDB & DB

02-Oct-15

03-Oct-15

0%

0%

100

MBD's, SMBD's, MCC & DB's

FIRE FIGHTING MATERIALS

08-Oct-15

07-Nov-15

07-Sep-15

07-Oct-15

0%

0%

160

SPRINKLER PIPES
PIP
& FITTINGS

08-Oct-15

07-Nov-15

07-Sep-15

07-Oct-15

0%

0%

160

PRO.PD.FF.1

Materials Order & Delivery Period - Sprinkler Pipes 08-Oct-15


& Fittings

07-Nov-15

07-Sep-15

07-Oct-15

0%

0%

160

PRO.PD.FF.6

Materials on Site Storage - Sprinkler Pipes &


Fittings

07-Nov-15

07-Oct-15

0%

0%

160

18-Aug-15

17-Oct-15

25-Aug-15

24-Oct-15

0%

0%

243

03-Sep-15

17-Oct-15

10-Sep-15

24-Oct-15

0%

0%

243

PRO.PD.PL.11 Materials Order & Delivery Period - GRP Watertank 03-Sep-15

17-Oct-15

10-Sep-15

24-Oct-15

0%

0%

243

PRO.PD.PL.18 Materials on Site Storage - GRP Watertank

17-Oct-15

24-Oct-15

0%

0%

243

PLUMBING MATERIALS
MA
GRP WATER TANK
TA

FLOOR DRAIN & COVER

PRO.PD.PL.8

Materials Order & Delivery Period - Floor Drain &


Cover

18-Aug-15

02-Oct-15

25-Aug-15

09-Oct-15

0%

0%

179

18-Aug-15

02-Oct-15

25-Aug-15

09-Oct-15

0%

0%

179

09-Oct-15

0%

0%

179

PRO.PD.PL.13 Materials on Site Storage - Floor Drain & Cover


FLOOR TRAP & FITTINGS

PRO.PD.PL.7

Materials Order & Delivery Period - Floor Trap &


Fittings

02-Oct-15
18-Aug-15

02-Oct-15

25-Aug-15

09-Oct-15

0%

0%

179

18-Aug-15

02-Oct-15

25-Aug-15

09-Oct-15

0%

0%

133

09-Oct-15

0%

0%

179

PRO.PD.PL.12 Materials on Site Storage - Floor Trap & Fittings

HVAC MATERIALS
MATERI
CHILLED WATER PIPE INSULATION

PRO.PD.AC.12 Materials Order & Delivery Period - Insulation


Chilled Water Pipes

02-Oct-15
07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

144

07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

144

07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

144

24-Oct-15

0%

0%

144

24-Oct-15

0%

0%

115

PRO.PD.AC.23 Materials Available on Site - Insulation Chilled


Water Pipes
07-Sep-15

VOLUME CONTR
CONTROL DAMPER (VCD)

Date: 08-Aug-15 19/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

22-Oct-15
22-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

09-Sep-15

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

03-Oct-15, , 03-Oct-15

03-Oct-15, , 03-Oct-15

07-Oct-15, , 07-Oct-15

24-Oct-15, , 24-Oct-15

09-Oct-15, , 09-Oct-15

09-Oct-15, , 09-Oct-15

24-Oct-15, , 24-Oct-15

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

PRO.PD.AC.2

Baseline
Start

Baseline
Finish

Materials Order & Delivery Period - Volume Control 07-Sep-15


Damper

PRO.PD.AC.17 Materials Available on Site - Volume Control


Damper
SOUND ATTENUATORS
ATTENU

PRO.PD.AC.7

Materials Order & Delivery Period - Sound


Attenuators

PRO.PD.AC.5

Materials Order & Delivery Period - Supply &


Return Duct

Finish

09-Sep-15

22-Oct-15

Schedule %
Complete

Cost %
Complete

Total
Float

24-Oct-15

0%

0%

115

24-Oct-15

0%

0%

115

07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

115

07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

115

24-Oct-15

0%

0%

115

PRO.PD.AC.18 Materials Available on Site - Sound Attenuators


SUPPLY, RETUR
RETURN & EXHAUST DUCT

22-Oct-15

Start

22-Oct-15
07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

99

07-Sep-15

22-Oct-15

09-Sep-15

24-Oct-15

0%

0%

99

24-Oct-15

0%

0%

99

PRO.PD.AC.15 Materials Available on Site - Supply & Return Duct

22-Oct-15

CONSTRUCTION
CONSTRUCTIO

15-Oct-14

13-Oct-16

15-Oct-14 A

13-Oct-16

19.13%

21.39%

PRELIMINARIES
PRELIMINARIE

15-Oct-14

13-Oct-16

15-Oct-14 A

13-Oct-16

39.73%

39.9%

C1-OFFICERS BUILDING-1

14-Jul-15

06-Nov-15

14-Jul-15 A

30-Oct-15

3.67%

6.8%

156

SUBSTRUCTURE WORK
SUBSTRUCTU

25-Jul-15

28-Jul-15

01-Aug-15

04-Aug-15

100%

0%

30

25-Jul-15

28-Jul-15

01-Aug-15

04-Aug-15

100%

0%

30

AREA-1 (EARTHWORKS
(EART
& CONCRETE WORKS)

25-Jul-15

28-Jul-15

01-Aug-15

04-Aug-15

100%

0%

30

AREA-2 (EARTHWORKS
(EART
& CONCRETE WORKS)

25-Jul-15

28-Jul-15

01-Aug-15

04-Aug-15

100%

0%

30

AREA-3 (EARTHWORKS
(EART
& CONCRETE WORKS)

25-Jul-15

28-Jul-15

01-Aug-15

04-Aug-15

100%

0%

30

14-Jul-15

06-Nov-15

14-Jul-15 A

30-Oct-15

3.94%

7.54%

34

17-Aug-15

10-Sep-15

16-Jul-15 A

25-Aug-15

0%

75.52%

39

17-Aug-15

10-Sep-15

16-Jul-15 A

25-Aug-15

0%

75.52%

39

17-Aug-15

23-Aug-15

26-Jul-15 A

14-Aug-15

0%

70.75%

34

B1CSGA1.SC.1 Steel Reinforcement for Staircase-1

17-Aug-15

21-Aug-15

26-Jul-15 A

12-Aug-15

0%

80%

34

B1CSGA1.SC.2 Shuttering for Staircase-1

18-Aug-15

22-Aug-15

27-Jul-15 A

13-Aug-15

0%

72%

34

B1CSGA1.SC.3 Pouring of Concrete for Staircase-1

22-Aug-15

23-Aug-15

30-Jul-15 A

14-Aug-15

0%

60%

34

01-Sep-15

10-Sep-15

16-Jul-15 A

25-Aug-15

0%

83.35%

39

06-Sep-15

10-Sep-15

16-Jul-15 A

24-Aug-15

0%

97%

39

CIVIL WORKS

SUPERSTRUCTURE WORKS
SUPERSTRUC
GROUND FLOOR
FL
LEVEL
STAIRCASE
STAIRCASE-01

STAIRCASE-02

B1CSGA2.SC.1 Steel Reinforcement for Staircase-2

Date: 08-Aug-15 20/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

24-Oct-15, , 24-Oct-15

24-Oct-15, , 24-Oct-15

24-Oct-15, , 24-Oct-15

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Schedule %
Complete

Cost %
Complete

Total
Float

25-Aug-15

0%

70%

39

14-Jul-15 A

21-Oct-15

13.08%

26.52%

12

17-Sep-15

14-Jul-15 A

10-Sep-15

14.99%

35.08%

15

14-Jul-15

20-Aug-15

14-Jul-15 A

20-Aug-15

61.9%

79.55%

16

14-Jul-15

28-Jul-15

14-Jul-15 A

01-Aug-15

100%

95%

B1CS1A3.BS.3 Steel Reinforcement for Beams & Suspended Slab 22-Jul-15

01-Aug-15

22-Jul-15 A

03-Aug-15

92.5%

95%

B1CS1A3.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 29-Jul-15

30-Jul-15

23-Jul-15 A

03-Aug-15

100%

0%

B1CS1A3.BS.5 Pouring of Concrete for Beams & Suspended Slab 02-Aug-15

03-Aug-15

01-Aug-15 A 03-Aug-15

0%

50%

B1CS1A3.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

03-Aug-15

20-Aug-15

03-Aug-15

20-Aug-15

0%

0%

16

14-Jul-15

27-Aug-15

14-Jul-15 A

25-Aug-15

38.59%

50.95%

13

B1CS1A4.BS.1 Shuttering for Beams & Suspended Slab

14-Jul-15

27-Jul-15

14-Jul-15 A

01-Aug-15

100%

90%

B1CS1A4.BS.2 MEP Works Related to Structure

27-Jul-15

03-Aug-15

21-Jul-15 A

04-Aug-15

56.67%

60%

B1CS1A4.BS.3 Steel Reinforcement for Beams & Suspended Slab 29-Jul-15

05-Aug-15

25-Jul-15 A

06-Aug-15

23.33%

60%

B1CS1A4.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 08-Aug-15

09-Aug-15

26-Jul-15 A

06-Aug-15

0%

0%

B1CS1A4.BS.5 Pouring of Concrete for Beams & Suspended Slab 09-Aug-15

10-Aug-15

06-Aug-15

08-Aug-15

0%

0%

B1CS1A4.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

10-Aug-15

27-Aug-15

08-Aug-15

25-Aug-15

0%

0%

13

30-Jul-15

03-Sep-15

30-Jul-15 A

30-Aug-15

0.14%

15.98%

17

B1CS1A5.BS.1 Shuttering for Beams & Suspended Slab

30-Jul-15

09-Aug-15

30-Jul-15 A

04-Aug-15

0.63%

70%

B1CS1A5.BS.2 MEP Works Related to Structure

09-Aug-15

15-Aug-15

04-Aug-15

10-Aug-15

0%

0%

B1CS1A5.BS.3 Steel Reinforcement for Beams & Suspended Slab 10-Aug-15

16-Aug-15

05-Aug-15

11-Aug-15

0%

0%

B1CS1A5.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 15-Aug-15

16-Aug-15

10-Aug-15

11-Aug-15

0%

0%

B1CS1A5.BS.5 Pouring of Concrete for Beams & Suspended Slab 16-Aug-15

17-Aug-15

11-Aug-15

12-Aug-15

0%

0%

B1CS1A5.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

17-Aug-15

03-Sep-15

12-Aug-15

30-Aug-15

0%

0%

17

05-Aug-15

03-Sep-15

14-Jul-15 A

30-Aug-15

0%

67.3%

17

05-Aug-15

15-Aug-15

14-Jul-15 A

04-Aug-15

0%

95%

14

B1CSGA2.SC.3 Pouring of Concrete for Staircase-2

FIRST FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
AREA-3 - BEAMS
BEAM & SLAB

B1CS1A3.BS.2 MEP Works Related to Structure

AREA-4 - BEAMS
BEAM & SLAB

AREA-5 - BEAMS
BEAM & SLAB

AREA-6 - BEAMS
BEAM & SLAB

B1CS1A6.BS.1 Shuttering for Beams & Suspended Slab

Date: 08-Aug-15 21/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

Start

Finish

01-Sep-15

02-Sep-15

22-Jul-15 A

14-Jul-15

21-Oct-15

14-Jul-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

16-Aug-15

21-Jul-15 A

05-Aug-15

0%

90%

19

B1CS1A6.BS.3 Steel Reinforcement for Beams & Suspended Slab 11-Aug-15

17-Aug-15

22-Jul-15 A

06-Aug-15

0%

90%

19

B1CS1A6.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 13-Aug-15

15-Aug-15

25-Jul-15 A

06-Aug-15

0%

0%

19

B1CS1A6.BS.5 Pouring of Concrete for Beams & Suspended Slab 15-Aug-15

16-Aug-15

06-Aug-15

08-Aug-15

0%

0%

19

B1CS1A6.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

17-Aug-15

03-Sep-15

12-Aug-15

30-Aug-15

0%

0%

17

13-Aug-15

09-Sep-15

23-Jul-15 A

02-Sep-15

0%

6.85%

14

B1CS1A7.BS.1 Shuttering for Beams & Suspended Slab

15-Aug-15

24-Aug-15

23-Jul-15 A

11-Aug-15

0%

30%

14

B1CS1A7.BS.2 MEP Works Related to Structure

13-Aug-15

19-Aug-15

06-Aug-15

12-Aug-15

0%

0%

14

B1CS1A7.BS.3 Steel Reinforcement for Beams & Suspended Slab 16-Aug-15

22-Aug-15

09-Aug-15

15-Aug-15

0%

0%

14

B1CS1A7.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 20-Aug-15

22-Aug-15

13-Aug-15

15-Aug-15

0%

0%

14

B1CS1A7.BS.5 Pouring of Concrete for Beams & Suspended Slab 22-Aug-15

23-Aug-15

15-Aug-15

16-Aug-15

0%

0%

14

B1CS1A7.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

23-Aug-15

09-Sep-15

16-Aug-15

02-Sep-15

0%

0%

14

18-Aug-15

17-Sep-15

11-Aug-15

10-Sep-15

0%

0%

15

B1CS1A8.BS.1 Shuttering for Beams & Suspended Slab

18-Aug-15

27-Aug-15

11-Aug-15

20-Aug-15

0%

0%

15

B1CS1A8.BS.2 MEP Works Related to Structure

23-Aug-15

29-Aug-15

16-Aug-15

22-Aug-15

0%

0%

15

B1CS1A8.BS.3 Steel Reinforcement for Beams & Suspended Slab 24-Aug-15

30-Aug-15

17-Aug-15

23-Aug-15

0%

0%

15

B1CS1A8.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 29-Aug-15

30-Aug-15

22-Aug-15

23-Aug-15

0%

0%

15

B1CS1A8.BS.5 Pouring of Concrete for Beams & Suspended Slab 30-Aug-15

31-Aug-15

23-Aug-15

24-Aug-15

0%

0%

15

B1CS1A8.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

31-Aug-15

17-Sep-15

24-Aug-15

10-Sep-15

0%

0%

15

15-Jul-15

06-Oct-15

14-Jul-15 A

06-Oct-15

9.49%

8.19%

15-Jul-15

27-Jul-15

14-Jul-15 A

01-Aug-15

100%

86.36%

B1CS1A2.CO.2 Shuttering for Columns

15-Jul-15

26-Jul-15

14-Jul-15 A

01-Aug-15

100%

90%

B1CS1A2.CO.3 Pouring of Concrete for Columns

26-Jul-15

27-Jul-15

16-Jul-15 A

01-Aug-15

100%

80%

03-Aug-15

11-Aug-15

03-Aug-15

11-Aug-15

0%

0%

03-Aug-15

09-Aug-15

03-Aug-15

09-Aug-15

0%

0%

B1CS1A6.BS.2 MEP Works Related to Structure

AREA-7 - BEAMS
BEAM & SLAB

AREA-8 - BEAMS
BEAM & SLAB

COLUMNS, WALLS
WA
& COREWALLS
AREA-2 - COLU
COLUMNS

AREA-3 - COLUMNS
COLU
& WALLS

B1CS1A3.CO.1 Steel Reinforcement for Columns & Walls

Date: 08-Aug-15 22/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

10-Aug-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS1A3.CO.2 Shuttering for Columns & Walls

04-Aug-15

10-Aug-15

04-Aug-15

10-Aug-15

0%

0%

B1CS1A3.CO.3 Pouring of Concrete for Columns & Walls

10-Aug-15

11-Aug-15

10-Aug-15

11-Aug-15

0%

0%

09-Aug-15

18-Aug-15

09-Aug-15

18-Aug-15

0%

0%

B1CS1A4.CO.1 Steel Reinforcement for Columns & Walls

09-Aug-15

13-Aug-15

09-Aug-15

13-Aug-15

0%

0%

B1CS1A4.CO.2 Shuttering for Columns & Walls

11-Aug-15

17-Aug-15

11-Aug-15

17-Aug-15

0%

0%

B1CS1A4.CO.3 Pouring of Concrete for Columns & Walls

17-Aug-15

18-Aug-15

17-Aug-15

18-Aug-15

0%

0%

13-Aug-15

23-Aug-15

13-Aug-15

23-Aug-15

0%

0%

B1CS1A5.CO.1 Steel Reinforcement for Columns & Core Wall

13-Aug-15

18-Aug-15

13-Aug-15

18-Aug-15

0%

0%

B1CS1A5.CO.2 Shuttering for Columns & Core Wall

16-Aug-15

22-Aug-15

16-Aug-15

22-Aug-15

0%

0%

B1CS1A5.CO.3 Pouring of Concrete for Columns & Core Wall

22-Aug-15

23-Aug-15

22-Aug-15

23-Aug-15

0%

0%

18-Aug-15

26-Aug-15

18-Aug-15

26-Aug-15

0%

0%

B1CS1A6.CO.1 Steel Reinforcement for Columns & Walls

18-Aug-15

24-Aug-15

18-Aug-15

24-Aug-15

0%

0%

B1CS1A6.CO.2 Shuttering for Columns & Walls

19-Aug-15

25-Aug-15

19-Aug-15

25-Aug-15

0%

0%

B1CS1A6.CO.3 Pouring of Concrete for Columns & Walls

25-Aug-15

26-Aug-15

25-Aug-15

26-Aug-15

0%

0%

24-Aug-15

01-Sep-15

24-Aug-15

01-Sep-15

0%

0%

10

B1CS1A7.CO.1 Steel Reinforcement for Columns & Walls

24-Aug-15

30-Aug-15

24-Aug-15

30-Aug-15

0%

0%

B1CS1A7.CO.2 Shuttering for Columns & Walls

25-Aug-15

31-Aug-15

25-Aug-15

31-Aug-15

0%

0%

10

B1CS1A7.CO.3 Pouring of Concrete for Columns & Walls

31-Aug-15

01-Sep-15

31-Aug-15

01-Sep-15

0%

0%

10

30-Aug-15

07-Sep-15

30-Aug-15

07-Sep-15

0%

0%

B1CS1A8.CO.1 Steel Reinforcement for Columns & Walls

30-Aug-15

05-Sep-15

30-Aug-15

05-Sep-15

0%

0%

B1CS1A8.CO.2 Shuttering for Columns & Walls

31-Aug-15

06-Sep-15

31-Aug-15

06-Sep-15

0%

0%

B1CS1A8.CO.3 Pouring of Concrete for Columns & Walls

06-Sep-15

07-Sep-15

06-Sep-15

07-Sep-15

0%

0%

05-Sep-15

13-Sep-15

05-Sep-15

13-Sep-15

0%

0%

10

B1CS1A9.CO.1 Steel Reinforcement for Columns & Walls

05-Sep-15

10-Sep-15

05-Sep-15

10-Sep-15

0%

0%

B1CS1A9.CO.2 Shuttering for Columns & Walls

06-Sep-15

12-Sep-15

06-Sep-15

12-Sep-15

0%

0%

10

AREA-4 - COLUMNS
COLU
& WALLS

AREA-5 - COLUMNS
COLU
& CORE WALL

AREA-6 - COLUMNS
COLU
& WALLS

AREA-7 - COLUMNS
COLU
& WALLS

AREA-8 - COLUMNS
COLU
& WALLS

AREA-9 - COLUMNS
COLU
& WALLS

Date: 08-Aug-15 23/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

13-Sep-15

12-Sep-15

13-Sep-15

0%

0%

10

10-Sep-15

19-Sep-15

10-Sep-15

19-Sep-15

0%

0%

B1CS1A10.CO.1Steel Reinforcement for Columns & Core Wall

10-Sep-15

16-Sep-15

10-Sep-15

16-Sep-15

0%

0%

B1CS1A10.CO.2Shuttering for Columns & Core Wall

12-Sep-15

17-Sep-15

12-Sep-15

17-Sep-15

0%

0%

B1CS1A10.CO.3Pouring of Concrete for Columns & Core Wall

17-Sep-15

19-Sep-15

17-Sep-15

19-Sep-15

0%

0%

16-Sep-15

30-Sep-15

16-Sep-15

30-Sep-15

0%

0%

B1CS1A11.CO.1Steel Reinforcement for Columns & Walls

16-Sep-15

22-Sep-15

16-Sep-15

22-Sep-15

0%

0%

B1CS1A11.CO.2Shuttering for Columns & Walls

17-Sep-15

29-Sep-15

17-Sep-15

29-Sep-15

0%

0%

B1CS1A11.CO.3Pouring of Concrete for Columns & Walls

29-Sep-15

30-Sep-15

29-Sep-15

30-Sep-15

0%

0%

22-Sep-15

06-Oct-15

22-Sep-15

06-Oct-15

0%

0%

B1CS1A12.CO.1Steel Reinforcement for Columns & Walls

22-Sep-15

04-Oct-15

22-Sep-15

04-Oct-15

0%

0%

B1CS1A12.CO.2Shuttering for Columns & Walls

29-Sep-15

05-Oct-15

29-Sep-15

05-Oct-15

0%

0%

B1CS1A12.CO.3Pouring of Concrete for Columns & Walls

05-Oct-15

06-Oct-15

05-Oct-15

06-Oct-15

0%

0%

16-Aug-15

21-Oct-15

18-Aug-15

21-Oct-15

0%

0%

12

13-Sep-15

19-Sep-15

14-Sep-15

19-Sep-15

0%

0%

35

B1CS1A1.ST.1 Steel Reinforcement for Staircase-1

13-Sep-15

17-Sep-15

14-Sep-15

17-Sep-15

0%

0%

35

B1CS1A1.ST.2 Shuttering for Staircase-1

14-Sep-15

18-Sep-15

15-Sep-15

18-Sep-15

0%

0%

35

B1CS1A1.ST.3 Pouring of Concrete for Staircase-1

18-Sep-15

19-Sep-15

19-Sep-15

19-Sep-15

0%

0%

35

15-Oct-15

21-Oct-15

16-Oct-15

21-Oct-15

0%

0%

12

B1CS1A2.ST.1 Steel Reinforcement for Staircase-2

15-Oct-15

19-Oct-15

16-Oct-15

19-Oct-15

0%

0%

12

B1CS1A2.ST.2 Shuttering for Staircase-2

16-Oct-15

20-Oct-15

17-Oct-15

20-Oct-15

0%

0%

12

B1CS1A2.ST.3 Pouring of Concrete for Staircase-2

20-Oct-15

21-Oct-15

21-Oct-15

21-Oct-15

0%

0%

12

16-Aug-15

22-Aug-15

18-Aug-15

23-Aug-15

0%

0%

43

B1CS1A3.ST.1 Steel Reinforcement for Staircase-3

16-Aug-15

20-Aug-15

18-Aug-15

21-Aug-15

0%

0%

43

B1CS1A3.ST.2 Shuttering for Staircase-3

17-Aug-15

21-Aug-15

19-Aug-15

22-Aug-15

0%

0%

43

B1CS1A9.CO.3 Pouring of Concrete for Columns & Walls


AREA-10 - COLU
COLUMNS & CORE WALL

AREA-11 - COLUMNS
COLU
& WALLS

AREA-12 - COLUMNS
COLU
& WALLS

STAIRCASE
STAIRCASE-01

STAIRCASE-02

STAIRCASE-03

Date: 08-Aug-15 24/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

12-Sep-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Schedule %
Complete

Cost %
Complete

Total
Float

23-Aug-15

0%

0%

43

03-Aug-15

27-Oct-15

1%

0%

19

24-Oct-15

03-Aug-15

24-Oct-15

1.35%

0%

27-Jul-15

25-Aug-15

03-Aug-15

31-Aug-15

10.77%

0%

25

B1CS2A1.BS.1 Shuttering for Beams & Suspended Slab

27-Jul-15

04-Aug-15

03-Aug-15

10-Aug-15

45.71%

0%

B1CS2A1.BS.2 MEP Works Related to Structure

30-Jul-15

05-Aug-15

06-Aug-15

11-Aug-15

4%

0%

B1CS2A1.BS.3 Steel Reinforcement for Beams & Suspended Slab 01-Aug-15

06-Aug-15

08-Aug-15

12-Aug-15

0%

0%

B1CS2A1.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 05-Aug-15

06-Aug-15

12-Aug-15

12-Aug-15

0%

0%

B1CS2A1.BS.5 Pouring of Concrete for Beams & Suspended Slab 06-Aug-15

08-Aug-15

13-Aug-15

13-Aug-15

0%

0%

B1CS2A1.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

08-Aug-15

25-Aug-15

15-Aug-15

31-Aug-15

0%

0%

25

04-Aug-15

02-Sep-15

06-Aug-15

03-Sep-15

0%

0%

22

B1CS2A2.BS.1 Shuttering for Beams & Suspended Slab

04-Aug-15

12-Aug-15

06-Aug-15

13-Aug-15

0%

0%

B1CS2A2.BS.2 MEP Works Related to Structure

08-Aug-15

13-Aug-15

10-Aug-15

15-Aug-15

0%

0%

B1CS2A2.BS.3 Steel Reinforcement for Beams & Suspended Slab 09-Aug-15

15-Aug-15

11-Aug-15

16-Aug-15

0%

0%

B1CS2A2.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 13-Aug-15

15-Aug-15

16-Aug-15

16-Aug-15

0%

0%

B1CS2A2.BS.5 Pouring of Concrete for Beams & Suspended Slab 15-Aug-15

16-Aug-15

17-Aug-15

17-Aug-15

0%

0%

B1CS2A2.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

16-Aug-15

02-Sep-15

18-Aug-15

03-Sep-15

0%

0%

22

12-Aug-15

12-Sep-15

15-Aug-15

13-Sep-15

0%

0%

22

B1CS2A3.BS.1 Shuttering for Beams & Suspended Slab

12-Aug-15

22-Aug-15

15-Aug-15

23-Aug-15

0%

0%

B1CS2A3.BS.2 MEP Works Related to Structure

17-Aug-15

23-Aug-15

19-Aug-15

24-Aug-15

0%

0%

B1CS2A3.BS.3 Steel Reinforcement for Beams & Suspended Slab 18-Aug-15

24-Aug-15

20-Aug-15

25-Aug-15

0%

0%

B1CS2A3.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 23-Aug-15

24-Aug-15

25-Aug-15

25-Aug-15

0%

0%

B1CS2A3.BS.5 Pouring of Concrete for Beams & Suspended Slab 24-Aug-15

25-Aug-15

26-Aug-15

26-Aug-15

0%

0%

B1CS2A3.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

25-Aug-15

12-Sep-15

27-Aug-15

13-Sep-15

0%

0%

22

23-Aug-15

21-Sep-15

24-Aug-15

21-Sep-15

0%

0%

15

B1CS1A3.ST.3 Pouring of Concrete for Staircase-3

SECOND FLOOR
FLO
LEVEL
BEAMS & SLABS
SLA
AREA-1 - BEAMS
BEAM & SLAB

AREA-2 - BEAMS
BEAM & SLAB

AREA-3 - BEAMS
BEAM & SLAB

AREA-4 - BEAMS
BEAM & SLAB

Date: 08-Aug-15 25/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

Start

Finish

21-Aug-15

22-Aug-15

23-Aug-15

27-Jul-15

26-Oct-15

27-Jul-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS2A4.BS.1 Shuttering for Beams & Suspended Slab

23-Aug-15

31-Aug-15

24-Aug-15

31-Aug-15

0%

0%

B1CS2A4.BS.2 MEP Works Related to Structure

26-Aug-15

01-Sep-15

27-Aug-15

01-Sep-15

0%

0%

B1CS2A4.BS.3 Steel Reinforcement for Beams & Suspended Slab 27-Aug-15

02-Sep-15

29-Aug-15

02-Sep-15

0%

0%

B1CS2A4.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 01-Sep-15

02-Sep-15

02-Sep-15

02-Sep-15

0%

0%

B1CS2A4.BS.5 Pouring of Concrete for Beams & Suspended Slab 02-Sep-15

03-Sep-15

03-Sep-15

03-Sep-15

0%

0%

B1CS2A4.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

03-Sep-15

21-Sep-15

05-Sep-15

21-Sep-15

0%

0%

15

31-Aug-15

06-Oct-15

01-Sep-15

06-Oct-15

0%

0%

15

B1CS2A5.BS.1 Shuttering for Beams & Suspended Slab

31-Aug-15

09-Sep-15

01-Sep-15

09-Sep-15

0%

0%

B1CS2A5.BS.2 MEP Works Related to Structure

05-Sep-15

10-Sep-15

06-Sep-15

10-Sep-15

0%

0%

B1CS2A5.BS.3 Steel Reinforcement for Beams & Suspended Slab 06-Sep-15

12-Sep-15

07-Sep-15

12-Sep-15

0%

0%

B1CS2A5.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 10-Sep-15

12-Sep-15

12-Sep-15

12-Sep-15

0%

0%

B1CS2A5.BS.5 Pouring of Concrete for Beams & Suspended Slab 12-Sep-15

13-Sep-15

13-Sep-15

13-Sep-15

0%

0%

B1CS2A5.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

13-Sep-15

06-Oct-15

14-Sep-15

06-Oct-15

0%

0%

15

09-Sep-15

15-Oct-15

10-Sep-15

15-Oct-15

0%

0%

B1CS2A6.BS.1 Shuttering for Beams & Suspended Slab

09-Sep-15

19-Sep-15

10-Sep-15

19-Sep-15

0%

0%

B1CS2A6.BS.2 MEP Works Related to Structure

14-Sep-15

20-Sep-15

15-Sep-15

20-Sep-15

0%

0%

B1CS2A6.BS.3 Steel Reinforcement for Beams & Suspended Slab 15-Sep-15

21-Sep-15

16-Sep-15

21-Sep-15

0%

0%

B1CS2A6.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 20-Sep-15

21-Sep-15

21-Sep-15

21-Sep-15

0%

0%

B1CS2A6.BS.5 Pouring of Concrete for Beams & Suspended Slab 21-Sep-15

22-Sep-15

22-Sep-15

22-Sep-15

0%

0%

B1CS2A6.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

22-Sep-15

15-Oct-15

29-Sep-15

15-Oct-15

0%

0%

19-Sep-15

24-Oct-15

20-Sep-15

24-Oct-15

0%

0%

B1CS2A7.BS.1 Shuttering for Beams & Suspended Slab

19-Sep-15

03-Oct-15

20-Sep-15

03-Oct-15

0%

0%

B1CS2A7.BS.2 MEP Works Related to Structure

22-Sep-15

04-Oct-15

29-Sep-15

04-Oct-15

0%

0%

B1CS2A7.BS.3 Steel Reinforcement for Beams & Suspended Slab 29-Sep-15

05-Oct-15

30-Sep-15

05-Oct-15

0%

0%

B1CS2A7.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 04-Oct-15

05-Oct-15

05-Oct-15

05-Oct-15

0%

0%

AREA-5 - BEAMS
BEAM & SLAB

AREA-6 - BEAMS
BEAM & SLAB

AREA-7 - BEAMS
BEAM & SLAB

Date: 08-Aug-15 26/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS2A7.BS.5 Pouring of Concrete for Beams & Suspended Slab 05-Oct-15

06-Oct-15

06-Oct-15

06-Oct-15

0%

0%

B1CS2A7.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

06-Oct-15

24-Oct-15

07-Oct-15

24-Oct-15

0%

0%

03-Oct-15

15-Oct-15

04-Oct-15

15-Oct-15

0%

0%

B1CS2A8.BS.1 Shuttering for Beams & Suspended Slab

03-Oct-15

12-Oct-15

04-Oct-15

12-Oct-15

0%

0%

B1CS2A8.BS.2 MEP Works Related to Structure

07-Oct-15

13-Oct-15

08-Oct-15

13-Oct-15

0%

0%

B1CS2A8.BS.3 Steel Reinforcement for Beams & Suspended Slab 08-Oct-15

14-Oct-15

10-Oct-15

14-Oct-15

0%

0%

B1CS2A8.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 13-Oct-15

14-Oct-15

14-Oct-15

14-Oct-15

0%

0%

B1CS2A8.BS.5 Pouring of Concrete for Beams & Suspended Slab 14-Oct-15

15-Oct-15

15-Oct-15

15-Oct-15

0%

0%

10-Aug-15

26-Oct-15

17-Aug-15

27-Oct-15

0%

0%

10-Aug-15

18-Aug-15

17-Aug-15

24-Aug-15

0%

0%

11

B1CS2A1.CO.1 Steel Reinforcement for Columns

10-Aug-15

16-Aug-15

17-Aug-15

22-Aug-15

0%

0%

B1CS2A1.CO.2 Shuttering for Columns

11-Aug-15

17-Aug-15

18-Aug-15

23-Aug-15

0%

0%

11

B1CS2A1.CO.3 Pouring of Concrete for Columns

17-Aug-15

18-Aug-15

24-Aug-15

24-Aug-15

0%

0%

11

16-Aug-15

24-Aug-15

23-Aug-15

30-Aug-15

0%

0%

12

B1CS2A2.CO.1 Steel Reinforcement for Columns

16-Aug-15

22-Aug-15

23-Aug-15

27-Aug-15

0%

0%

B1CS2A2.CO.2 Shuttering for Columns

17-Aug-15

23-Aug-15

24-Aug-15

29-Aug-15

0%

0%

12

B1CS2A2.CO.3 Pouring of Concrete for Columns

23-Aug-15

24-Aug-15

30-Aug-15

30-Aug-15

0%

0%

12

25-Aug-15

02-Sep-15

29-Aug-15

05-Sep-15

0%

0%

13

B1CS2A3.CO.1 Steel Reinforcement for Columns & Walls

25-Aug-15

31-Aug-15

29-Aug-15

02-Sep-15

0%

0%

B1CS2A3.CO.2 Shuttering for Columns & Walls

26-Aug-15

01-Sep-15

30-Aug-15

03-Sep-15

0%

0%

13

B1CS2A3.CO.3 Pouring of Concrete for Columns & Walls

01-Sep-15

02-Sep-15

05-Sep-15

05-Sep-15

0%

0%

13

31-Aug-15

08-Sep-15

03-Sep-15

10-Sep-15

0%

0%

24

B1CS2A4.CO.1 Steel Reinforcement for Columns & Walls

31-Aug-15

06-Sep-15

03-Sep-15

08-Sep-15

0%

0%

B1CS2A4.CO.2 Shuttering for Columns & Walls

01-Sep-15

07-Sep-15

05-Sep-15

09-Sep-15

0%

0%

24

B1CS2A4.CO.3 Pouring of Concrete for Columns & Walls

07-Sep-15

08-Sep-15

10-Sep-15

10-Sep-15

0%

0%

24

AREA-8 - BEAMS
BEAM & SLAB

COLUMNS, WALLS
WA
& COREWALLS
AREA-1 - COLU
COLUMNS

AREA-2 - COLU
COLUMNS

AREA-3 - COLUMNS
COLU
& WALLS

AREA-4 - COLUMNS
COLU
& WALLS

Date: 08-Aug-15 27/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

06-Sep-15

14-Sep-15

09-Sep-15

16-Sep-15

0%

0%

B1CS2A5.CO.1 Steel Reinforcement for Columns & Core Wall

06-Sep-15

12-Sep-15

09-Sep-15

14-Sep-15

0%

0%

B1CS2A5.CO.2 Shuttering for Columns & Core Wall

07-Sep-15

13-Sep-15

10-Sep-15

15-Sep-15

0%

0%

B1CS2A5.CO.3 Pouring of Concrete for Columns & Core Wall

13-Sep-15

14-Sep-15

16-Sep-15

16-Sep-15

0%

0%

13-Sep-15

21-Sep-15

15-Sep-15

22-Sep-15

0%

0%

B1CS2A6.CO.1 Steel Reinforcement for Columns & Walls

13-Sep-15

19-Sep-15

15-Sep-15

20-Sep-15

0%

0%

B1CS2A6.CO.2 Shuttering for Columns & Walls

14-Sep-15

20-Sep-15

16-Sep-15

21-Sep-15

0%

0%

B1CS2A6.CO.3 Pouring of Concrete for Columns & Walls

20-Sep-15

21-Sep-15

22-Sep-15

22-Sep-15

0%

0%

19-Sep-15

03-Oct-15

21-Sep-15

04-Oct-15

0%

0%

22

B1CS2A7.CO.1 Steel Reinforcement for Columns & Walls

19-Sep-15

30-Sep-15

21-Sep-15

01-Oct-15

0%

0%

B1CS2A7.CO.2 Shuttering for Columns & Walls

20-Sep-15

01-Oct-15

22-Sep-15

03-Oct-15

0%

0%

22

B1CS2A7.CO.3 Pouring of Concrete for Columns & Walls

01-Oct-15

03-Oct-15

04-Oct-15

04-Oct-15

0%

0%

22

30-Sep-15

08-Oct-15

03-Oct-15

10-Oct-15

0%

0%

B1CS2A8.CO.1 Steel Reinforcement for Columns & Walls

30-Sep-15

06-Oct-15

03-Oct-15

07-Oct-15

0%

0%

B1CS2A8.CO.2 Shuttering for Columns & Walls

01-Oct-15

07-Oct-15

04-Oct-15

08-Oct-15

0%

0%

B1CS2A8.CO.3 Pouring of Concrete for Columns & Walls

07-Oct-15

08-Oct-15

10-Oct-15

10-Oct-15

0%

0%

06-Oct-15

14-Oct-15

08-Oct-15

15-Oct-15

0%

0%

12

B1CS2A9.CO.1 Steel Reinforcement for Columns & Walls

06-Oct-15

12-Oct-15

08-Oct-15

13-Oct-15

0%

0%

B1CS2A9.CO.2 Shuttering for Columns & Walls

07-Oct-15

13-Oct-15

10-Oct-15

14-Oct-15

0%

0%

12

B1CS2A9.CO.3 Pouring of Concrete for Columns & Walls

13-Oct-15

14-Oct-15

15-Oct-15

15-Oct-15

0%

0%

12

12-Oct-15

20-Oct-15

14-Oct-15

21-Oct-15

0%

0%

B1CS2A10.CO.1Steel Reinforcement for Columns & Core Wall

12-Oct-15

18-Oct-15

14-Oct-15

19-Oct-15

0%

0%

B1CS2A10.CO.2Shuttering for Columns & Core Wall

13-Oct-15

19-Oct-15

15-Oct-15

20-Oct-15

0%

0%

B1CS2A10.CO.3Pouring of Concrete for Columns & Core Wall

19-Oct-15

20-Oct-15

21-Oct-15

21-Oct-15

0%

0%

18-Oct-15

26-Oct-15

20-Oct-15

27-Oct-15

0%

0%

AREA-5 - COLUMNS
COLU
& CORE WALL

AREA-6 - COLUMNS
COLU
& WALLS

AREA-7 - COLUMNS
COLU
& WALLS

AREA-8 - COLUMNS
COLU
& WALLS

AREA-9 - COLUMNS
COLU
& WALLS

AREA-10 - COLU
COLUMNS & CORE WALL

AREA-11 - COLUMNS
COLU
& WALLS

Date: 08-Aug-15 28/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS2A11.CO.1Steel Reinforcement for Columns & Walls

18-Oct-15

25-Oct-15

0%

0%

B1CS2A11.CO.2Shuttering for Columns & Walls

21-Oct-15

26-Oct-15

0%

0%

B1CS2A11.CO.3Pouring of Concrete for Columns & Walls

26-Oct-15

27-Oct-15

27-Oct-15

0%

0%

13-Sep-15

12-Oct-15

11-Sep-15

11-Oct-15

0%

0%

35

06-Oct-15

12-Oct-15

06-Oct-15

11-Oct-15

0%

0%

35

B1CS1A1.ST.6 Steel Reinforcement for Staircase-1

06-Oct-15

10-Oct-15

06-Oct-15

09-Oct-15

0%

0%

35

B1CS1A1.ST.5 Shuttering for Staircase-1

07-Oct-15

11-Oct-15

07-Oct-15

10-Oct-15

0%

0%

35

B1CS1A1.ST.4 Pouring of Concrete for Staircase-1

11-Oct-15

12-Oct-15

11-Oct-15

11-Oct-15

0%

0%

35

13-Sep-15

19-Sep-15

11-Sep-15

16-Sep-15

0%

0%

50

B1CS1A3.ST.6 Steel Reinforcement for Staircase-3

13-Sep-15

17-Sep-15

11-Sep-15

14-Sep-15

0%

0%

50

B1CS1A3.ST.5 Shuttering for Staircase-3

14-Sep-15

18-Sep-15

12-Sep-15

15-Sep-15

0%

0%

50

B1CS1A3.ST.4 Pouring of Concrete for Staircase-3

18-Sep-15

19-Sep-15

16-Sep-15

16-Sep-15

0%

0%

50

27-Aug-15

04-Nov-15

25-Aug-15

30-Oct-15

0%

0%

34

27-Aug-15

29-Oct-15

25-Aug-15

30-Oct-15

0%

0%

16

27-Aug-15

21-Sep-15

25-Aug-15

18-Sep-15

0%

0%

39

B1CS3A1.BS.1 Shuttering for Beams & Suspended Slab

27-Aug-15

03-Sep-15

25-Aug-15

31-Aug-15

0%

0%

13

B1CS3A1.BS.2 MEP Works Related to Structure

30-Aug-15

04-Sep-15

28-Aug-15

01-Sep-15

0%

0%

32

B1CS3A1.BS.3 Steel Reinforcement for Beams & Suspended Slab 31-Aug-15

05-Sep-15

29-Aug-15

02-Sep-15

0%

0%

32

B1CS3A1.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 04-Sep-15

05-Sep-15

02-Sep-15

02-Sep-15

0%

0%

32

B1CS3A1.BS.5 Pouring of Concrete for Beams & Suspended Slab 05-Sep-15

06-Sep-15

03-Sep-15

03-Sep-15

0%

0%

32

B1CS3A1.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

06-Sep-15

21-Sep-15

04-Sep-15

18-Sep-15

0%

0%

39

03-Sep-15

28-Sep-15

01-Sep-15

25-Sep-15

0%

0%

41

B1CS3A2.BS.1 Shuttering for Beams & Suspended Slab

03-Sep-15

10-Sep-15

01-Sep-15

07-Sep-15

0%

0%

13

B1CS3A2.BS.2 MEP Works Related to Structure

06-Sep-15

11-Sep-15

04-Sep-15

08-Sep-15

0%

0%

30

B1CS3A2.BS.3 Steel Reinforcement for Beams & Suspended Slab 07-Sep-15

12-Sep-15

05-Sep-15

09-Sep-15

0%

0%

30

STAIRCASE
STAIRCASE-01

STAIRCASE-03

THIRD FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
AREA-1 - BEAMS
BEAM & SLAB

AREA-2 - BEAMS
BEAM & SLAB

Date: 08-Aug-15 29/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

24-Oct-15

20-Oct-15

19-Oct-15

25-Oct-15

25-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS3A2.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 11-Sep-15

12-Sep-15

09-Sep-15

09-Sep-15

0%

0%

30

B1CS3A2.BS.5 Pouring of Concrete for Beams & Suspended Slab 12-Sep-15

13-Sep-15

10-Sep-15

10-Sep-15

0%

0%

30

B1CS3A2.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

13-Sep-15

28-Sep-15

11-Sep-15

25-Sep-15

0%

0%

41

10-Sep-15

06-Oct-15

08-Sep-15

03-Oct-15

0%

0%

33

B1CS3A3.BS.1 Shuttering for Beams & Suspended Slab

10-Sep-15

18-Sep-15

08-Sep-15

15-Sep-15

0%

0%

13

B1CS3A3.BS.2 MEP Works Related to Structure

14-Sep-15

19-Sep-15

12-Sep-15

16-Sep-15

0%

0%

27

B1CS3A3.BS.3 Steel Reinforcement for Beams & Suspended Slab 15-Sep-15

20-Sep-15

13-Sep-15

17-Sep-15

0%

0%

27

B1CS3A3.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 19-Sep-15

20-Sep-15

17-Sep-15

17-Sep-15

0%

0%

27

B1CS3A3.BS.5 Pouring of Concrete for Beams & Suspended Slab 20-Sep-15

21-Sep-15

18-Sep-15

18-Sep-15

0%

0%

27

B1CS3A3.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

21-Sep-15

06-Oct-15

19-Sep-15

03-Oct-15

0%

0%

33

18-Sep-15

13-Oct-15

17-Sep-15

11-Oct-15

0%

0%

25

B1CS3A4.BS.1 Shuttering for Beams & Suspended Slab

18-Sep-15

25-Sep-15

17-Sep-15

23-Sep-15

0%

0%

12

B1CS3A4.BS.2 MEP Works Related to Structure

21-Sep-15

26-Sep-15

20-Sep-15

24-Sep-15

0%

0%

25

B1CS3A4.BS.3 Steel Reinforcement for Beams & Suspended Slab 22-Sep-15

27-Sep-15

21-Sep-15

25-Sep-15

0%

0%

25

B1CS3A4.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 26-Sep-15

27-Sep-15

25-Sep-15

25-Sep-15

0%

0%

25

B1CS3A4.BS.5 Pouring of Concrete for Beams & Suspended Slab 27-Sep-15

28-Sep-15

26-Sep-15

26-Sep-15

0%

0%

25

B1CS3A4.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

28-Sep-15

13-Oct-15

27-Sep-15

11-Oct-15

0%

0%

25

25-Sep-15

21-Oct-15

24-Sep-15

20-Oct-15

0%

0%

26

B1CS3A5.BS.1 Shuttering for Beams & Suspended Slab

25-Sep-15

03-Oct-15

24-Sep-15

01-Oct-15

0%

0%

12

B1CS3A5.BS.2 MEP Works Related to Structure

29-Sep-15

04-Oct-15

28-Sep-15

02-Oct-15

0%

0%

26

B1CS3A5.BS.3 Steel Reinforcement for Beams & Suspended Slab 30-Sep-15

05-Oct-15

29-Sep-15

03-Oct-15

0%

0%

26

B1CS3A5.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 04-Oct-15

05-Oct-15

03-Oct-15

03-Oct-15

0%

0%

26

B1CS3A5.BS.5 Pouring of Concrete for Beams & Suspended Slab 05-Oct-15

06-Oct-15

05-Oct-15

05-Oct-15

0%

0%

25

B1CS3A5.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

06-Oct-15

21-Oct-15

06-Oct-15

20-Oct-15

0%

0%

26

08-Oct-15

19-Oct-15

11-Oct-15

21-Oct-15

0%

0%

10

AREA-3 - BEAMS
BEAM & SLAB

AREA-4 - BEAMS
BEAM & SLAB

AREA-5 - BEAMS
BEAM & SLAB

AREA-6 - BEAMS
BEAM & SLAB

Date: 08-Aug-15 30/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS3A6.BS.1 Shuttering for Beams & Suspended Slab

08-Oct-15

16-Oct-15

11-Oct-15

18-Oct-15

0%

0%

B1CS3A6.BS.2 MEP Works Related to Structure

12-Oct-15

17-Oct-15

15-Oct-15

19-Oct-15

0%

0%

10

B1CS3A6.BS.3 Steel Reinforcement for Beams & Suspended Slab 13-Oct-15

18-Oct-15

16-Oct-15

20-Oct-15

0%

0%

10

B1CS3A6.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 17-Oct-15

18-Oct-15

20-Oct-15

20-Oct-15

0%

0%

10

B1CS3A6.BS.5 Pouring of Concrete for Beams & Suspended Slab 18-Oct-15

19-Oct-15

21-Oct-15

21-Oct-15

0%

0%

10

20-Oct-15

29-Oct-15

22-Oct-15

30-Oct-15

0%

0%

B1CS3A7.BS.1 Shuttering for Beams & Suspended Slab

20-Oct-15

27-Oct-15

22-Oct-15

28-Oct-15

0%

0%

B1CS3A7.BS.2 MEP Works Related to Structure

23-Oct-15

28-Oct-15

25-Oct-15

29-Oct-15

0%

0%

B1CS3A7.BS.3 Steel Reinforcement for Beams & Suspended Slab 24-Oct-15

29-Oct-15

26-Oct-15

30-Oct-15

0%

0%

B1CS3A7.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 28-Oct-15

29-Oct-15

30-Oct-15

30-Oct-15

0%

0%

06-Sep-15

26-Oct-15

04-Sep-15

28-Oct-15

0%

0%

31

06-Sep-15

13-Sep-15

04-Sep-15

10-Sep-15

0%

0%

32

B1CS3A1.CO.1 Steel Reinforcement for Columns

06-Sep-15

11-Sep-15

04-Sep-15

08-Sep-15

0%

0%

32

B1CS3A1.CO.2 Shuttering for Columns

07-Sep-15

12-Sep-15

05-Sep-15

09-Sep-15

0%

0%

32

B1CS3A1.CO.3 Pouring of Concrete for Columns

12-Sep-15

13-Sep-15

10-Sep-15

10-Sep-15

0%

0%

32

13-Sep-15

20-Sep-15

11-Sep-15

17-Sep-15

0%

0%

32

B1CS3A2.CO.1 Steel Reinforcement for Columns

13-Sep-15

18-Sep-15

11-Sep-15

15-Sep-15

0%

0%

30

B1CS3A2.CO.2 Shuttering for Columns

14-Sep-15

19-Sep-15

12-Sep-15

16-Sep-15

0%

0%

32

B1CS3A2.CO.3 Pouring of Concrete for Columns

19-Sep-15

20-Sep-15

17-Sep-15

17-Sep-15

0%

0%

32

21-Sep-15

28-Sep-15

19-Sep-15

25-Sep-15

0%

0%

31

B1CS3A3.CO.1 Steel Reinforcement for Columns & Walls

21-Sep-15

26-Sep-15

19-Sep-15

23-Sep-15

0%

0%

27

B1CS3A3.CO.2 Shuttering for Columns & Walls

22-Sep-15

27-Sep-15

20-Sep-15

24-Sep-15

0%

0%

31

B1CS3A3.CO.3 Pouring of Concrete for Columns & Walls

27-Sep-15

28-Sep-15

25-Sep-15

25-Sep-15

0%

0%

31

26-Sep-15

03-Oct-15

24-Sep-15

30-Sep-15

0%

0%

48

26-Sep-15

01-Oct-15

24-Sep-15

28-Sep-15

0%

0%

27

AREA-7 - BEAMS
BEAM & SLAB

COLUMNS, WALLS
WA
& COREWALLS
AREA-1 - COLU
COLUMNS

AREA-2 - COLU
COLUMNS

AREA-3 - COLUMNS
COLU
& WALLS

AREA-4 - COLUMNS
COLU
& WALLS

B1CS3A4.CO.1 Steel Reinforcement for Columns & Walls

Date: 08-Aug-15 31/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CS3A4.CO.2 Shuttering for Columns & Walls

27-Sep-15

02-Oct-15

25-Sep-15

29-Sep-15

0%

0%

48

B1CS3A4.CO.3 Pouring of Concrete for Columns & Walls

02-Oct-15

03-Oct-15

30-Sep-15

30-Sep-15

0%

0%

48

01-Oct-15

08-Oct-15

29-Sep-15

05-Oct-15

0%

0%

29

B1CS3A5.CO.1 Steel Reinforcement for Columns & Core Wall

01-Oct-15

06-Oct-15

29-Sep-15

03-Oct-15

0%

0%

27

B1CS3A5.CO.2 Shuttering for Columns & Core Wall

02-Oct-15

07-Oct-15

30-Sep-15

04-Oct-15

0%

0%

29

B1CS3A5.CO.3 Pouring of Concrete for Columns & Core Wall

07-Oct-15

08-Oct-15

05-Oct-15

05-Oct-15

0%

0%

29

06-Oct-15

13-Oct-15

06-Oct-15

12-Oct-15

0%

0%

29

B1CS3A6.CO.1 Steel Reinforcement for Columns & Walls

06-Oct-15

11-Oct-15

06-Oct-15

10-Oct-15

0%

0%

25

B1CS3A6.CO.2 Shuttering for Columns & Walls

07-Oct-15

12-Oct-15

07-Oct-15

11-Oct-15

0%

0%

29

B1CS3A6.CO.3 Pouring of Concrete for Columns & Walls

12-Oct-15

13-Oct-15

12-Oct-15

12-Oct-15

0%

0%

29

11-Oct-15

18-Oct-15

11-Oct-15

17-Oct-15

0%

0%

42

B1CS3A7.CO.1 Steel Reinforcement for Columns & Walls

11-Oct-15

16-Oct-15

11-Oct-15

15-Oct-15

0%

0%

25

B1CS3A7.CO.2 Shuttering for Columns & Walls

12-Oct-15

17-Oct-15

12-Oct-15

16-Oct-15

0%

0%

42

B1CS3A7.CO.3 Pouring of Concrete for Columns & Walls

17-Oct-15

18-Oct-15

17-Oct-15

17-Oct-15

0%

0%

42

19-Oct-15

26-Oct-15

22-Oct-15

28-Oct-15

0%

0%

21

B1CS3A8.CO.1 Steel Reinforcement for Columns & Walls

19-Oct-15

24-Oct-15

22-Oct-15

26-Oct-15

0%

0%

19

B1CS3A8.CO.2 Shuttering for Columns & Walls

20-Oct-15

25-Oct-15

23-Oct-15

27-Oct-15

0%

0%

21

B1CS3A8.CO.3 Pouring of Concrete for Columns & Walls

25-Oct-15

26-Oct-15

28-Oct-15

28-Oct-15

0%

0%

21

29-Oct-15

04-Nov-15

23-Oct-15

28-Oct-15

0%

0%

36

29-Oct-15

04-Nov-15

23-Oct-15

28-Oct-15

0%

0%

36

B1CS1A3.ST.9 Steel Reinforcement for Staircase-3

29-Oct-15

02-Nov-15

23-Oct-15

26-Oct-15

0%

0%

36

B1CS1A3.ST.8 Shuttering for Staircase-3

30-Oct-15

03-Nov-15

24-Oct-15

27-Oct-15

0%

0%

36

B1CS1A3.ST.7 Pouring of Concrete for Staircase-3

03-Nov-15

04-Nov-15

28-Oct-15

28-Oct-15

0%

0%

36

12-Oct-15

06-Nov-15

06-Oct-15

30-Oct-15

0%

0%

25

12-Oct-15

06-Nov-15

06-Oct-15

30-Oct-15

0%

0%

25

AREA-5 - COLUMNS
COLU
& CORE WALL

AREA-6 - COLUMNS
COLU
& WALLS

AREA-7 - COLUMNS
COLU
& WALLS

AREA-8 - COLUMNS
COLU
& WALLS

STAIRCASE
STAIRCASE-03

ROOF FLOOR
FLOO LEVEL
BEAMS & SLABS
SLA
Date: 08-Aug-15 32/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

12-Oct-15

30-Oct-15

0%

0%

25

B1CSRA1.BS.1 Shuttering for Beams & Suspended Slab

06-Oct-15

12-Oct-15

0%

0%

B1CSRA1.BS.2 MEP Works Related to Structure

20-Oct-15

09-Oct-15

13-Oct-15

0%

0%

25

B1CSRA1.BS.3 Steel Reinforcement for Beams & Suspended Slab 16-Oct-15

21-Oct-15

10-Oct-15

14-Oct-15

0%

0%

25

B1CSRA1.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 20-Oct-15

21-Oct-15

14-Oct-15

14-Oct-15

0%

0%

25

B1CSRA1.BS.5 Pouring of Concrete for Beams & Suspended Slab 21-Oct-15

22-Oct-15

15-Oct-15

15-Oct-15

0%

0%

25

B1CSRA1.BS.6 Curing & Removal of Shuttering for Beams &


Suspended Slab

22-Oct-15

06-Nov-15

16-Oct-15

30-Oct-15

0%

0%

25

19-Oct-15

29-Oct-15

13-Oct-15

22-Oct-15

0%

0%

27

B1CSRA2.BS.1 Shuttering for Beams & Suspended Slab

19-Oct-15

26-Oct-15

13-Oct-15

19-Oct-15

0%

0%

B1CSRA2.BS.2 MEP Works Related to Structure

22-Oct-15

27-Oct-15

16-Oct-15

20-Oct-15

0%

0%

27

B1CSRA2.BS.3 Steel Reinforcement for Beams & Suspended Slab 23-Oct-15

28-Oct-15

17-Oct-15

21-Oct-15

0%

0%

27

B1CSRA2.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 27-Oct-15

28-Oct-15

21-Oct-15

21-Oct-15

0%

0%

27

B1CSRA2.BS.5 Pouring of Concrete for Beams & Suspended Slab 28-Oct-15

29-Oct-15

22-Oct-15

22-Oct-15

0%

0%

27

26-Oct-15

06-Nov-15

20-Oct-15

30-Oct-15

0%

0%

19

B1CSRA3.BS.1 Shuttering for Beams & Suspended Slab

26-Oct-15

03-Nov-15

20-Oct-15

27-Oct-15

0%

0%

B1CSRA3.BS.2 MEP Works Related to Structure

30-Oct-15

04-Nov-15

24-Oct-15

28-Oct-15

0%

0%

19

B1CSRA3.BS.3 Steel Reinforcement for Beams & Suspended Slab 31-Oct-15

05-Nov-15

25-Oct-15

29-Oct-15

0%

0%

19

B1CSRA3.BS.4 Inspection of Engineer Prior to Pour Beams & Slab 04-Nov-15

05-Nov-15

29-Oct-15

29-Oct-15

0%

0%

19

B1CSRA3.BS.5 Pouring of Concrete for Beams & Suspended Slab 05-Nov-15

06-Nov-15

30-Oct-15

30-Oct-15

0%

0%

19

25-Jul-15

02-Nov-15

25-Jul-15 A

28-Oct-15

0.35%

2.56%

135

25-Jul-15

02-Nov-15

25-Jul-15 A

27-Oct-15

0.43%

3.12%

137

25-Jul-15

25-Oct-15

25-Jul-15 A

26-Oct-15

0.95%

6.86%

137

25-Jul-15

25-Oct-15

25-Jul-15 A

26-Oct-15

1.27%

9.17%

64

25-Jul-15

25-Oct-15

25-Jul-15 A

26-Oct-15

1.27%

9.17%

64

30-Jul-15

17-Aug-15

25-Jul-15 A

12-Aug-15

2.67%

30%

34

AREA-1 - BEAMS
BEAM & SLAB

AREA-2 - BEAMS
BEAM & SLAB

AREA-3 - BEAMS
BEAM & SLAB

FINISHES
GROUND FLOOR
FL
LEVEL
AREA-1
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

B1CCG1.MA.03Block Work up to Lintel Level

Date: 08-Aug-15 33/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

06-Nov-15

06-Oct-15

12-Oct-15

19-Oct-15

15-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B1CCG1.MA.01Ceiling Fairfacing & Plaster

25-Jul-15

02-Aug-15

25-Jul-15 A

08-Aug-15

75%

20%

27

B1CCG1.MA.04Lintel Beams

11-Aug-15

23-Aug-15

12-Aug-15

24-Aug-15

0%

0%

64

B1CCG1.MA.05Block Work up to Full Height

23-Aug-15

09-Sep-15

24-Aug-15

10-Sep-15

0%

0%

64

B1CCG1.MA.06Sub-Frame to Opennings

09-Sep-15

15-Sep-15

10-Sep-15

16-Sep-15

0%

0%

66

B1CCG1.MA.07MEP Clearance to allow Plastering

16-Sep-15

17-Sep-15

17-Sep-15

19-Sep-15

0%

0%

64

B1CCG1.MA.08Surface Preparation & Rush Coat Plaster

17-Sep-15

07-Oct-15

19-Sep-15

08-Oct-15

0%

0%

64

B1CCG1.MA.09Final Plastering Works

07-Oct-15

25-Oct-15

08-Oct-15

26-Oct-15

0%

0%

64

30-Aug-15

13-Oct-15

31-Aug-15

14-Oct-15

0%

0%

148

ELECTRICAL S
SYSTEM

30-Aug-15

13-Oct-15

31-Aug-15

14-Oct-15

0%

0%

86

1ST FIX ELECTRICAL


ELECT

30-Aug-15

13-Oct-15

31-Aug-15

14-Oct-15

0%

0%

86

B1CMG1.EE.1 Installation of Electrical Conduits Inside Block Wall 30-Aug-15

16-Sep-15

31-Aug-15

17-Sep-15

0%

0%

64

B1CMG1.EE.2 Installation of CB, SMDB, MDB Panel Box

03-Oct-15

13-Oct-15

03-Oct-15

14-Oct-15

0%

0%

86

PLUMBING SYSTEM
SYS

30-Aug-15

10-Oct-15

31-Aug-15

29-Sep-15

0%

0%

160

1ST FIX PLUMBING


PLUM

30-Aug-15

10-Oct-15

31-Aug-15

29-Sep-15

0%

0%

160

B1CMG1.PL.1 Installation of Drainage Piping Concealed to


Blockwall

30-Aug-15

16-Sep-15

31-Aug-15

17-Sep-15

0%

0%

117

B1CMG1.PL.2 Installation of Water Supply Piping Concealed to


Blockwall

16-Sep-15

10-Oct-15

06-Sep-15

29-Sep-15

0%

0%

160

27-Aug-15

28-Oct-15

25-Aug-15

26-Oct-15

0%

0%

94

27-Aug-15

28-Oct-15

25-Aug-15

26-Oct-15

0%

0%

41

27-Aug-15

28-Oct-15

25-Aug-15

26-Oct-15

0%

0%

41

B1CCG2.MA.01Civil Inspection for Blockwork Layout

27-Aug-15

29-Aug-15

25-Aug-15

26-Aug-15

0%

0%

20

B1CCG2.MA.02Ceiling Fairfacing & Plaster

27-Aug-15

06-Sep-15

25-Aug-15

03-Sep-15

0%

0%

13

B1CCG2.MA.03Block Work up to Lintel Level

29-Aug-15

15-Sep-15

26-Aug-15

13-Sep-15

0%

0%

20

B1CCG2.MA.04Lintel Beams

15-Sep-15

03-Oct-15

13-Sep-15

30-Sep-15

0%

0%

41

B1CCG2.MA.05Block Work up to Full Height

03-Oct-15

20-Oct-15

30-Sep-15

18-Oct-15

0%

0%

41

B1CCG2.MA.06Sub-Frame to Opennings

20-Oct-15

26-Oct-15

18-Oct-15

24-Oct-15

0%

0%

43

MEP WORKS

AREA-2
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

Date: 08-Aug-15 34/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

28-Oct-15

25-Oct-15

26-Oct-15

0%

0%

41

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

95

ELECTRICAL S
SYSTEM

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

41

1ST FIX ELECTRICAL


ELECT

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

41

B1CMG2.EE.1 Installation of Electrical Conduits Inside Block Wall 10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

41

PLUMBING SYSTEM
SYS

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

95

1ST FIX PLUMBING


PLUM

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

95

10-Oct-15

27-Oct-15

07-Oct-15

25-Oct-15

0%

0%

95

09-Sep-15

02-Nov-15

03-Sep-15

27-Oct-15

0%

0%

37

09-Sep-15

02-Nov-15

03-Sep-15

27-Oct-15

0%

0%

37

09-Sep-15

02-Nov-15

03-Sep-15

27-Oct-15

0%

0%

37

B1CCG3.MA.01Civil Inspection for Blockwork Layout

09-Sep-15

10-Sep-15

03-Sep-15

05-Sep-15

0%

0%

21

B1CCG3.MA.02Ceiling Fairfacing & Plaster

09-Sep-15

19-Sep-15

03-Sep-15

13-Sep-15

0%

0%

13

B1CCG3.MA.03Block Work up to Lintel Level

10-Sep-15

04-Oct-15

05-Sep-15

22-Sep-15

0%

0%

21

B1CCG3.MA.04Lintel Beams

04-Oct-15

15-Oct-15

22-Sep-15

10-Oct-15

0%

0%

37

B1CCG3.MA.05Block Work up to Full Height

15-Oct-15

02-Nov-15

10-Oct-15

27-Oct-15

0%

0%

37

21-Sep-15

29-Oct-15

15-Sep-15

28-Oct-15

0%

0%

39

21-Sep-15

21-Oct-15

15-Sep-15

15-Oct-15

0%

0%

51

21-Sep-15

21-Oct-15

15-Sep-15

15-Oct-15

0%

0%

51

21-Sep-15

21-Oct-15

15-Sep-15

15-Oct-15

0%

0%

51

B1CC11.MA.01 Ceiling Fairfacing & Plaster

21-Sep-15

06-Oct-15

15-Sep-15

30-Sep-15

0%

0%

13

B1CC11.MA.02 Civil Inspection for Blockwork Layout

03-Oct-15

04-Oct-15

21-Sep-15

22-Sep-15

0%

0%

13

B1CC11.MA.03 Block Work up to Lintel Level

04-Oct-15

21-Oct-15

22-Sep-15

15-Oct-15

0%

0%

13

B1CC11.MA.04 Lintel Beams

10-Oct-15

21-Oct-15

04-Oct-15

15-Oct-15

0%

0%

51

06-Oct-15

29-Oct-15

30-Sep-15

24-Oct-15

0%

0%

13

B1CCG2.MA.07MEP Clearance to allow Plastering


MEP WORKS

B1CMG2.PL.1 Installation of Drainage Piping Concealed to


Blockwall

AREA-3
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

FIRST FLOOR
FLOO LEVEL
AREA-1
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

AREA-2
Date: 08-Aug-15 35/42
Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

27-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

29-Oct-15

30-Sep-15

24-Oct-15

0%

0%

13

06-Oct-15

29-Oct-15

30-Sep-15

24-Oct-15

0%

0%

13

B1CC12.MA.02Ceiling Fairfacing & Plaster

06-Oct-15

15-Oct-15

30-Sep-15

10-Oct-15

0%

0%

13

B1CC12.MA.01Civil Inspection for Blockwork Layout

10-Oct-15

11-Oct-15

04-Oct-15

05-Oct-15

0%

0%

14

B1CC12.MA.03Block Work up to Lintel Level

12-Oct-15

29-Oct-15

06-Oct-15

24-Oct-15

0%

0%

13

27-Oct-15

28-Oct-15

28-Oct-15

28-Oct-15

0%

0%

27-Oct-15

28-Oct-15

28-Oct-15

28-Oct-15

0%

0%

27-Oct-15

28-Oct-15

28-Oct-15

28-Oct-15

0%

0%

27-Oct-15

28-Oct-15

28-Oct-15

28-Oct-15

0%

0%

F1-OFFICERS BUILDING-2

03-Jun-15

27-Oct-15

16-May-15
A

29-Oct-15

6.63%

11.57%

21

SUBSTRUCTURE WORK
SUBSTRUCTU

03-Jun-15

07-Sep-15

16-May-15
A

09-Sep-15

21.29%

37.2%

12-Jul-15

07-Sep-15

15-Jul-15 A

09-Sep-15

2.54%

2.21%

12-Jul-15

07-Sep-15

15-Jul-15 A

09-Sep-15

2.54%

2.21%

12-Jul-15

22-Aug-15

15-Jul-15 A

26-Aug-15

7.65%

6.67%

B2CCS1.GB.02 Preparation & Termite Control below Blinding for


Ground Beam

12-Jul-15

28-Jul-15

15-Jul-15 A

03-Aug-15

100%

70%

B2CCS1.GB.03 Blinding for Ground Beam

13-Jul-15

29-Jul-15

15-Jul-15 A

04-Aug-15

100%

70%

B2CCS1.GB.04 Horizontal Rubberized Waterproofing for Ground


Beam

29-Jul-15

05-Aug-15

21-Jul-15 A

05-Aug-15

28.57%

70%

B2CCS1.GB.05 Polythene Sheet for Ground Beam

30-Jul-15

06-Aug-15

03-Aug-15

11-Aug-15

14.29%

0%

B2CCS1.GB.06 Reinforcing Bars for Ground Beams

01-Aug-15

11-Aug-15

04-Aug-15

16-Aug-15

0%

0%

B2CCS1.GB.07 Shuttering for Ground Beams

02-Aug-15

12-Aug-15

05-Aug-15

17-Aug-15

0%

0%

B2CCS1.GB.08 Inspection of Engineer Prior to Pour Ground


Beams

06-Aug-15

15-Aug-15

10-Aug-15

19-Aug-15

0%

0%

B2CCS1.GB.09 Pouring for Ground Beams

08-Aug-15

16-Aug-15

11-Aug-15

20-Aug-15

0%

0%

B2CCS1.GB.010Rubberized Waterproofing & Polythene Sheet for


Ground Beam

17-Aug-15

20-Aug-15

20-Aug-15

25-Aug-15

0%

0%

B2CCS1.GB.011Hard Board Cover for Ground Beam

18-Aug-15

22-Aug-15

22-Aug-15

26-Aug-15

0%

0%

20-Aug-15

07-Sep-15

22-Aug-15

09-Sep-15

0%

0%

CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

AREA-3
CIVIL WORKS
FAIR FACE, BL
BLOCKWORK & PLASTER

B1CC13.MA.01Civil Inspection for Blockwork Layout

AREA-1 (EARTHWORK
(EAR
& CONCRETE)
CIVIL WORKS
GROUND BEAMS

SLAB ON GRADE

Date: 08-Aug-15 36/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

06-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B2CCS1.SG.01 Full Backfilling & Compaction in Layers up to


bottom of Slab on Grade

20-Aug-15

29-Aug-15

22-Aug-15

31-Aug-15

0%

0%

B2CCS1.SG.02 Termite Control below Blinding for Slab on Grade

26-Aug-15

30-Aug-15

27-Aug-15

01-Sep-15

0%

0%

B2CCS1.SG.03 Blinding below Slab on Grade

27-Aug-15

31-Aug-15

29-Aug-15

02-Sep-15

0%

0%

B2CCS1.SG.04 Horizontal Rubberized Waterproofing for Slab on


Grade

29-Aug-15

01-Sep-15

30-Aug-15

03-Sep-15

0%

0%

B2CCS1.SG.05 Polytene Sheet for Slab on Grade

30-Aug-15

02-Sep-15

31-Aug-15

05-Sep-15

0%

0%

B2CCS1.SG.06 Reinforcing Bar for Slab on Grade

30-Aug-15

05-Sep-15

31-Aug-15

07-Sep-15

0%

0%

B2CCS1.SG.07 20x20mm Sealant

03-Sep-15

05-Sep-15

05-Sep-15

07-Sep-15

0%

0%

B2CCS1.SG.08 Inspection of Engineer Prior to Pour Ground


Beams

05-Sep-15

05-Sep-15

06-Sep-15

07-Sep-15

0%

0%

B2CCS1.SG.09 Pouring of Slab on Grade

06-Sep-15

07-Sep-15

07-Sep-15

09-Sep-15

0%

0%

03-Jun-15

19-Aug-15

16-May-15
A

24-Aug-15

41.57%

75.03%

03-Jun-15

19-Aug-15

02-Jun-15 A

24-Aug-15

40.79%

74.7%

03-Jun-15

09-Jul-15

02-Jun-15 A

04-Aug-15

100%

96.13%

B2CCS2.GB.07 Shuttering for Ground Beams

03-Jun-15

20-Jun-15

02-Jun-15 A

01-Aug-15

100%

97%

B2CCS2.GB.08 Inspection of Engineer Prior to Pour Ground


Beams

06-Jun-15

17-Jun-15

20-Jun-15 A

01-Aug-15

100%

0%

B2CCS2.GB.09 Pouring for Ground Beams

17-Jun-15

29-Jun-15

20-Jun-15 A

01-Aug-15

100%

95%

B2CCS2.GB.010Rubberized Waterproofing & Polythene Sheet for


Ground Beam

29-Jun-15

07-Jul-15

25-Jun-15 A

02-Aug-15

100%

95%

B2CCS2.GB.011Hard Board Cover for Ground Beam

01-Jul-15

09-Jul-15

26-Jun-15 A

04-Aug-15

100%

95%

02-Jul-15

19-Aug-15

26-Jun-15 A

24-Aug-15

19.15%

66.88%

B2CCS2.SG.01 Full Backfilling & Compaction in Layers up to


bottom of Slab on Grade

02-Jul-15

30-Jul-15

26-Jun-15 A

09-Aug-15

100%

75%

B2CCS2.SG.03 Termite Control below Blinding for Slab on Grade

16-Jul-15

08-Aug-15

30-Jun-15 A

17-Aug-15

54.67%

70%

B2CCS2.SG.02 Blinding below Slab on Grade

16-Jul-15

09-Aug-15

30-Jun-15 A

18-Aug-15

51.25%

70%

B2CCS2.SG.04 Horizontal Rubberized Waterproofing for Slab on


Grade

02-Aug-15

10-Aug-15

01-Jul-15 A

19-Aug-15

0%

65%

B2CCS2.SG.06 Polytene Sheet for Slab on Grade

03-Aug-15

11-Aug-15

08-Jul-15 A

20-Aug-15

0%

65%

B2CCS2.SG.05 Reinforcing Bar for Slab on Grade

03-Aug-15

17-Aug-15

08-Jul-15 A

23-Aug-15

0%

65%

B2CCS2.SG.07 20x20mm Sealant

15-Aug-15

17-Aug-15

08-Jul-15 A

23-Aug-15

0%

65%

AREA-2 (EARTHWORK
(EAR
& CONCRETE)
CIVIL WORKS
GROUND BEAMS

SLAB ON GRADE

Date: 08-Aug-15 37/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B2CCS2.SG.08 Inspection of Engineer Prior to Pour Ground


Beams

16-Aug-15

23-Aug-15

0%

0%

B2CCS2.SG.09 Pouring of Slab on Grade

08-Jul-15 A

24-Aug-15

0%

65%

22-Jun-15

16-May-15
A

01-Aug-15

100%

99%

20

04-Jun-15

22-Jun-15

16-May-15
A

01-Aug-15

100%

99%

20

20-Aug-15

27-Oct-15

24-Aug-15

29-Oct-15

0%

0%

21

08-Sep-15

27-Oct-15

09-Sep-15

29-Oct-15

0%

0%

21

08-Sep-15

20-Oct-15

09-Sep-15

22-Oct-15

0%

0%

10

08-Sep-15

17-Sep-15

09-Sep-15

20-Sep-15

0%

0%

B2CCSG1.BS.0 Steel Reinforcement for Columns & Walls

08-Sep-15

15-Sep-15

09-Sep-15

17-Sep-15

0%

0%

B2CCSG1.BS.02Shuttering for Columns & Walls

09-Sep-15

16-Sep-15

10-Sep-15

19-Sep-15

0%

0%

B2CCSG1.BS.03Pouring of Concrete for Columns & Walls

16-Sep-15

17-Sep-15

19-Sep-15

20-Sep-15

0%

0%

16-Sep-15

01-Oct-15

17-Sep-15

04-Oct-15

0%

0%

10

B2CCSG1.BS.04Steel Reinforcement for Columns & Walls

16-Sep-15

29-Sep-15

17-Sep-15

01-Oct-15

0%

0%

10

B2CCSG1.BS.05Shuttering for Columns & Walls

17-Sep-15

30-Sep-15

19-Sep-15

03-Oct-15

0%

0%

10

B2CCSG1.BS.06Pouring of Concrete for Columns & Walls

30-Sep-15

01-Oct-15

03-Oct-15

04-Oct-15

0%

0%

10

11-Oct-15

20-Oct-15

13-Oct-15

22-Oct-15

0%

0%

10

11-Oct-15

20-Oct-15

13-Oct-15

22-Oct-15

0%

0%

10

B2CCSG1.SC.0Shuttering for Staircase-1,2&3

11-Oct-15

18-Oct-15

13-Oct-15

20-Oct-15

0%

0%

10

B2CCSG1.SC.0Steel Reinforcement for Staircase-1,2&3

13-Oct-15

19-Oct-15

15-Oct-15

21-Oct-15

0%

0%

10

B2CCSG1.SC.0Pouring of Concrete forStaircase-1,2&3

19-Oct-15

20-Oct-15

21-Oct-15

22-Oct-15

0%

0%

10

17-Sep-15

27-Oct-15

20-Sep-15

29-Oct-15

0%

0%

21

17-Sep-15

22-Oct-15

20-Sep-15

25-Oct-15

0%

0%

17-Sep-15

22-Oct-15

20-Sep-15

25-Oct-15

0%

0%

B2CCSR6.BS.0Shuttering of Big Beams

17-Sep-15

29-Sep-15

20-Sep-15

01-Oct-15

0%

0%

B2CCSR6.BS.0MEP Works Related to Structure for Big Beams

21-Sep-15

30-Sep-15

29-Sep-15

03-Oct-15

0%

0%

MEP WORKS
B2CMS2.PL.01 Under Ground Utilities to Officer's Building-2

SUPERSTRUCTURE WORKS
SUPERSTRUC
PHASE-1 CONCRETE
CO
WORKS
GROUND FLOOR
FLOO LEVEL
AREA-6 (COLUMNS
(COLUM
& WALLS)

AREA-7 (COLUMNS
(COLUM
& WALLS)

STAIRCASE
STAIRCASE-1,2&3
STAIRCASE-1,2

ROOF FLOOR LEVEL


AREA-6: (BEAMS
(BEAM & SLAB)
AREA-6a: (BEAMS)
(BEA

Date: 08-Aug-15 38/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

17-Aug-15

08-Jul-15 A

17-Aug-15

19-Aug-15

04-Jun-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B2CCSR6.BS.0Steel Reinforcement for Big Beams

21-Sep-15

03-Oct-15

29-Sep-15

05-Oct-15

0%

0%

B2CCSR6.BS.0Inspection of Engineer Prior to Pour Big Beams

01-Oct-15

03-Oct-15

04-Oct-15

05-Oct-15

0%

0%

B2CCSR6.BS.0Pouring of Concrete for Big Beams

03-Oct-15

04-Oct-15

05-Oct-15

06-Oct-15

0%

0%

B2CCSR6.BS.0Curing & Removal of Shuttering for Big Beams

05-Oct-15

22-Oct-15

07-Oct-15

25-Oct-15

0%

0%

29-Sep-15

14-Oct-15

01-Oct-15

17-Oct-15

0%

0%

B2CCSR6.BS.0Shuttering of Beams & Roof Slab

29-Sep-15

11-Oct-15

01-Oct-15

13-Oct-15

0%

0%

B2CCSR6.BS.0MEP Works Related to Structure

03-Oct-15

12-Oct-15

05-Oct-15

14-Oct-15

0%

0%

B2CCSR6.BS.0Steel Reinforcement for Beams & Roof Slab

04-Oct-15

13-Oct-15

06-Oct-15

15-Oct-15

0%

0%

B2CCSR6.BS.1Inspection of Engineer Prior to Pour Beams & Slab 12-Oct-15

13-Oct-15

14-Oct-15

15-Oct-15

0%

0%

B2CCSR6.BS.1Pouring of Concrete for Beams & Roof Slab

13-Oct-15

14-Oct-15

15-Oct-15

17-Oct-15

0%

0%

11-Oct-15

27-Oct-15

13-Oct-15

29-Oct-15

0%

0%

B2CCSR7.BS.0 Shuttering of Beams

11-Oct-15

22-Oct-15

13-Oct-15

25-Oct-15

0%

0%

B2CCSR7.BS.02MEP Works Related to Structure

15-Oct-15

25-Oct-15

18-Oct-15

27-Oct-15

0%

0%

B2CCSR7.BS.03Steel Reinforcement for Beams

15-Oct-15

27-Oct-15

18-Oct-15

29-Oct-15

0%

0%

B2CCSR7.BS.04Inspection of Engineer Prior to Pour Beams

22-Oct-15

27-Oct-15

25-Oct-15

29-Oct-15

0%

0%

07-Oct-15

17-Oct-15

10-Oct-15

19-Oct-15

0%

0%

B2CCSR6.CW.0 Steel Reinforcement for Columns

07-Oct-15

14-Oct-15

10-Oct-15

17-Oct-15

0%

0%

B2CCSR6.CW.0 Shuttering for Columns

08-Oct-15

15-Oct-15

11-Oct-15

18-Oct-15

0%

0%

B2CCSR6.CW.0 Pouring of Concrete for Columns

15-Oct-15

17-Oct-15

18-Oct-15

19-Oct-15

0%

0%

17-Oct-15

26-Oct-15

19-Oct-15

28-Oct-15

0%

0%

B2CCSR6.RB.0 Shuttering of Roof Beams

17-Oct-15

24-Oct-15

19-Oct-15

26-Oct-15

0%

0%

B2CCSR6.RB.0 Steel Reinforcement for Roof Beams

18-Oct-15

25-Oct-15

20-Oct-15

27-Oct-15

0%

0%

B2CCSR6.RB.0 Pouring of Concrete for Roof Beams

25-Oct-15

26-Oct-15

27-Oct-15

28-Oct-15

0%

0%

25-Oct-15

27-Oct-15

27-Oct-15

29-Oct-15

0%

0%

21

25-Oct-15

27-Oct-15

27-Oct-15

29-Oct-15

0%

0%

21

AREA-6b: (BEAMS
(BEA
& SLABS)

AREA-7: (BEAMS)
(BEAM

AREA-6: (COLUMNS)
(COLU

AREA-6: ROOF BEAM

STAIRCASE

B2CCSR1.SC.0 Shuttering for Staircase

Date: 08-Aug-15 39/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Start

Finish

Schedule %
Complete

Cost %
Complete

Total
Float

25-Oct-15

24-Aug-15

28-Oct-15

0%

0%

17

20-Aug-15

05-Oct-15

24-Aug-15

08-Oct-15

0%

0%

34

20-Aug-15

31-Aug-15

24-Aug-15

03-Sep-15

0%

0%

20

B2CCSG1.CW.1 Steel Reinforcement for Columns & Walls

20-Aug-15

29-Aug-15

24-Aug-15

01-Sep-15

0%

0%

B2CCSG1.CW.2 Shuttering for Columns & Walls

22-Aug-15

30-Aug-15

25-Aug-15

02-Sep-15

0%

0%

20

B2CCSG1.CW.3 Pouring of Concrete for Columns & Walls

30-Aug-15

31-Aug-15

02-Sep-15

03-Sep-15

0%

0%

20

29-Aug-15

06-Sep-15

01-Sep-15

09-Sep-15

0%

0%

16

B2CCSG2.CW.1 Steel Reinforcement for Columns & Walls

29-Aug-15

03-Sep-15

01-Sep-15

07-Sep-15

0%

0%

B2CCSG2.CW.2 Shuttering for Columns & Walls

30-Aug-15

05-Sep-15

02-Sep-15

08-Sep-15

0%

0%

16

B2CCSG2.CW.3 Pouring of Concrete for Columns & Walls

05-Sep-15

06-Sep-15

08-Sep-15

09-Sep-15

0%

0%

16

03-Sep-15

13-Sep-15

07-Sep-15

16-Sep-15

0%

0%

11

B2CCSG3.CW.1 Steel Reinforcement for Columns & Walls

03-Sep-15

10-Sep-15

07-Sep-15

14-Sep-15

0%

0%

B2CCSG3.CW.2 Shuttering for Columns & Walls

05-Sep-15

12-Sep-15

08-Sep-15

15-Sep-15

0%

0%

11

B2CCSG3.CW.3 Pouring of Concrete for Columns & Walls

12-Sep-15

13-Sep-15

15-Sep-15

16-Sep-15

0%

0%

11

10-Sep-15

21-Sep-15

14-Sep-15

30-Sep-15

0%

0%

B2CCSG4.CW.1 Steel Reinforcement for Columns & Walls

10-Sep-15

19-Sep-15

14-Sep-15

22-Sep-15

0%

0%

B2CCSG4.CW.2 Shuttering for Columns & Walls

12-Sep-15

20-Sep-15

15-Sep-15

29-Sep-15

0%

0%

B2CCSG4.CW.3 Pouring of Concrete for Columns & Walls

20-Sep-15

21-Sep-15

29-Sep-15

30-Sep-15

0%

0%

19-Sep-15

03-Oct-15

22-Sep-15

06-Oct-15

0%

0%

B2CCSG5.CW.1 Steel Reinforcement for Columns & Walls

19-Sep-15

30-Sep-15

22-Sep-15

04-Oct-15

0%

0%

B2CCSG5.CW.2 Shuttering for Columns & Walls

20-Sep-15

01-Oct-15

29-Sep-15

05-Oct-15

0%

0%

B2CCSG5.CW.3 Pouring of Concrete for Columns & Walls

01-Oct-15

03-Oct-15

05-Oct-15

06-Oct-15

0%

0%

20-Sep-15

05-Oct-15

29-Sep-15

08-Oct-15

0%

0%

34

20-Sep-15

05-Oct-15

29-Sep-15

08-Oct-15

0%

0%

34

20-Sep-15

03-Oct-15

29-Sep-15

06-Oct-15

0%

0%

34

PHASE-2 CONCRETE
CO
WORKS
GROUND FLOOR
FLOO LEVEL
AREA-1 (COLUMNS
(COLUM
& WALLS)

AREA-2 (COLUMNS
(COLUM
& WALLS)

AREA-3 (COLUMNS
(COLUM
& WALLS)

AREA-4 (COLUMNS
(COLUM
& WALLS)

AREA-5 (COLUMNS
(COLUM
& WALLS)

STAIRCASE
STAIRCASE-1,2&3
STAIRCASE-1,2

B2CCSG2.SC.0Shuttering for Staircase-1,2&3

Date: 08-Aug-15 40/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Baseline
Start

Baseline
Finish

20-Aug-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B2CCSG2.SC.0Steel Reinforcement for Staircase-1,2&3

22-Sep-15

07-Oct-15

0%

0%

34

B2CCSG2.SC.0Pouring of Concrete forStaircase-1,2&3

07-Oct-15

08-Oct-15

0%

0%

34

25-Oct-15

03-Sep-15

28-Oct-15

0%

0%

17

31-Aug-15

06-Oct-15

03-Sep-15

10-Oct-15

0%

0%

33

B2CCSR2.BS.0 Shuttering of Beams & Roof Slab

31-Aug-15

09-Sep-15

03-Sep-15

13-Sep-15

0%

0%

25

B2CCSR2.BS.03MEP Works Related to Structure

05-Sep-15

10-Sep-15

08-Sep-15

14-Sep-15

0%

0%

25

B2CCSR2.BS.02Steel Reinforcement for Beams & Roof Slab

06-Sep-15

12-Sep-15

09-Sep-15

15-Sep-15

0%

0%

25

B2CCSR2.BS.04Inspection of Engineer Prior to Pour Beams & Slab 10-Sep-15

12-Sep-15

14-Sep-15

15-Sep-15

0%

0%

25

B2CCSR2.BS.05Pouring of Concrete for Beams & Roof Slab

12-Sep-15

13-Sep-15

15-Sep-15

16-Sep-15

0%

0%

25

B2CCSR2.BS.06Curing & Removal of Shuttering for Beams &


Suspended Slab

13-Sep-15

06-Oct-15

16-Sep-15

10-Oct-15

0%

0%

33

06-Sep-15

11-Oct-15

09-Sep-15

14-Oct-15

0%

0%

29

B2CCSR2.BS.9 Shuttering of Beams & Roof Slab

06-Sep-15

13-Sep-15

09-Sep-15

16-Sep-15

0%

0%

22

B2CCSR2.BS.10MEP Works Related to Structure

08-Sep-15

14-Sep-15

12-Sep-15

17-Sep-15

0%

0%

22

B2CCSR2.BS.8 Steel Reinforcement for Beams & Roof Slab

09-Sep-15

15-Sep-15

13-Sep-15

19-Sep-15

0%

0%

22

B2CCSR2.BS.6 Inspection of Engineer Prior to Pour Beams & Slab 14-Sep-15

15-Sep-15

17-Sep-15

19-Sep-15

0%

0%

22

B2CCSR2.BS.7 Pouring of Concrete for Beams & Roof Slab

15-Sep-15

16-Sep-15

19-Sep-15

20-Sep-15

0%

0%

22

B2CCSR2.BS.11Curing & Removal of Shuttering for Beams &


Suspended Slab

17-Sep-15

11-Oct-15

21-Sep-15

14-Oct-15

0%

0%

29

13-Sep-15

19-Oct-15

16-Sep-15

22-Oct-15

0%

0%

22

B2CCSR2.BS.15Shuttering of Beams & Roof Slab

13-Sep-15

21-Sep-15

16-Sep-15

30-Sep-15

0%

0%

15

B2CCSR2.BS.16MEP Works Related to Structure

16-Sep-15

22-Sep-15

20-Sep-15

01-Oct-15

0%

0%

15

B2CCSR2.BS.14Steel Reinforcement for Beams & Roof Slab

17-Sep-15

29-Sep-15

21-Sep-15

03-Oct-15

0%

0%

15

B2CCSR2.BS.12Inspection of Engineer Prior to Pour Beams & Slab 22-Sep-15

29-Sep-15

01-Oct-15

03-Oct-15

0%

0%

15

B2CCSR2.BS.13Pouring of Concrete for Beams & Roof Slab

29-Sep-15

30-Sep-15

03-Oct-15

04-Oct-15

0%

0%

15

B2CCSR2.BS.17Curing & Removal of Shuttering for Beams &


Suspended Slab

01-Oct-15

19-Oct-15

05-Oct-15

22-Oct-15

0%

0%

22

21-Sep-15

12-Oct-15

30-Sep-15

15-Oct-15

0%

0%

ROOF FLOOR LEVEL


AREA-1 (BEAMS & SLABS)

AREA-2 (BEAMS & SLABS)

AREA-3 (BEAMS & SLABS)

AREA-4 (BEAMS & SLABS)

Date: 08-Aug-15 41/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

04-Oct-15

01-Oct-15

04-Oct-15

05-Oct-15

31-Aug-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

Activity ID

Activity Name

Baseline
Start

Baseline
Finish

Schedule %
Complete

Cost %
Complete

Total
Float

B2CCSR2.BS.2 Shuttering of Beams & Roof Slab

21-Sep-15

12-Oct-15

0%

0%

B2CCSR2.BS.22MEP Works Related to Structure

06-Oct-15

13-Oct-15

0%

0%

B2CCSR2.BS.20Steel Reinforcement for Beams & Roof Slab

11-Oct-15

07-Oct-15

14-Oct-15

0%

0%

B2CCSR2.BS.18Inspection of Engineer Prior to Pour Beams & Slab 10-Oct-15

11-Oct-15

13-Oct-15

14-Oct-15

0%

0%

B2CCSR2.BS.19Pouring of Concrete for Beams & Roof Slab

11-Oct-15

12-Oct-15

14-Oct-15

15-Oct-15

0%

0%

03-Oct-15

13-Oct-15

06-Oct-15

17-Oct-15

0%

0%

B2CCSR2.BS.27Shuttering of Beams & Roof Slab

03-Oct-15

10-Oct-15

06-Oct-15

13-Oct-15

0%

0%

B2CCSR2.BS.28MEP Works Related to Structure

05-Oct-15

11-Oct-15

08-Oct-15

14-Oct-15

0%

0%

B2CCSR2.BS.26Steel Reinforcement for Beams & Roof Slab

06-Oct-15

12-Oct-15

10-Oct-15

15-Oct-15

0%

0%

B2CCSR2.BS.24Inspection of Engineer Prior to Pour Beams & Slab 11-Oct-15

12-Oct-15

14-Oct-15

15-Oct-15

0%

0%

B2CCSR2.BS.25Pouring of Concrete for Beams & Roof Slab

12-Oct-15

13-Oct-15

15-Oct-15

17-Oct-15

0%

0%

13-Oct-15

25-Oct-15

17-Oct-15

28-Oct-15

0%

0%

B2CCSR2.CW.0 Steel Reinforcement for Columns

13-Oct-15

22-Oct-15

17-Oct-15

26-Oct-15

0%

0%

B2CCSR2.CW.0 Shuttering for Columns

14-Oct-15

24-Oct-15

18-Oct-15

27-Oct-15

0%

0%

B2CCSR2.CW.0 Pouring of Concrete for Columns

20-Oct-15

25-Oct-15

24-Oct-15

28-Oct-15

0%

0%

AREA-5 (BEAMS & SLABS)

COLUMNS

Date: 08-Aug-15 42/42


Start Date: 15-Oct-14
Completion Date: 13-Oct-16

Start

Finish

08-Oct-15

30-Sep-15

03-Oct-15

10-Oct-15

04-Oct-15

Remaining Level of Effort

Critical Activity

Project Baseline Bar

Baseline Bar

Actual Work

Current Bar Labels

Early Bar

Early Bar

Project Name: CONSTRUCTION, COMPLETION


MAINTENANCE OF OFFICER'S BUILDING 12 AT BARZAN
CAMP
Layout Name: 3Month Lookahead Programme (1.8.15)

2015
S O N

2016

F M A M J Jul A S O N

F M A M J Jul A S O N D

Date
Revision
Checked Approved
15-Oct-1... 1.8.15 Three Months Lookah... Richard Nabil

S-ar putea să vă placă și