PHASE1BDELAYEDACTIVITIESASPERBASELINEEARLYDATESANDREASONSFORTHEDELAY

DataDate: 26Apr13

PlannedDataasPerDetailedBaselineofPhase1BRevision01SubmissionNo.05
Prev.Week
No.ofBuildings
Act. Var. Schd. Act. Var. Prod. Prog.

Progress
Schd.
Act.

420SanitaryWareandFittings

151

152

151

100%

99.51%

425BathroomAccessories

146

152

146

100%

98.63%

660PlumbingTestingandCommissioning

151

152

151

100%

99.43%

151

152

151

100%

152

152

152

650WiringDevices,DoorBellInstallation

151

152

151

665ElectricalandSystemTesting&Commissioning

133

19

152

141

11

Activity

ReasonForTheDelay

CorrectiveAction

PlumbingWorks
LateStartduetodoorlocks(Nomaterialsarrive)

Followthetilelayout(InProgress)

DependsonActivities310and375(DoorLeafsand
Ironmongery&PainttoInternalWallsFinalCoat,
Latestartoftheactivity,duetothelatedeliveryof
WaterHeater.

Itwasdelayeduntildoorswithlocksareinstalled(late
approvalofIronmongery)InProgress
Productivityhasincreasedanddelaysarebeingrecovered.In
Progress

99.25%

Notavailableworkingareafortheseactivities.

InProgress

100%

0.00%

AfterCompletionofChemicalTreatmentofChilledWater
Pipework

NoActionPossibleatthisStage.

100%

99.09%

Dependsonotheractivities.

FollowCivilActivitiesasInstallationofDoorsandWindows.
InProgress

11

100%

96.16%

Dependsonotheractivities.

FollowCivilActivitiesasInstallationofDoorsandWindows.

MechanicalWorks
525Grilles&DiffusersInstallation
655MechanicalCommissioning

ElectricalWorks

Page1of1