Sunteți pe pagina 1din 10

MANPOWER AND EQUIPMENT PRODUCTIVITY OUTPUT

ITEM 100

CLEARING AND GRUBBING

1. Bush Clearance (LIGHT)


250 sq.m./man-day
2. Bush Clearance (MEDIUM)
125 sq.m./man-day
3. Bush Clearance (DENSE) a) 65.50 sq.m/man-day
b) With chainsaw 200 sq.m/2 man gang/day
4. Individual removal of trees (up to maximum of0.25m. diam.)
a) 1 tree per man day
b) With chainsaw 10 trees/2 man gang/day
5. Grubbing/top soil removal (sparce vegetation)
6. Grubbing/top soil removal (dense vegetation)
7. Boulder removal (loose)

150.00 sq.m/man-day
80.00 sq.m/man-day
150.00 sq.m/man-day

NOTE: The outputs are up to a maximum disposal site distance of 10.00 meters.
ITEM 101

REMOVAL OF STRUCTURES AND OBSTRUCTIONS


Reinforced Concrete Conc. Pvmt

A. LABOR/man-day
B. EQUIPMENT
B.1 Air Compressor w/ jackleg
B.2 Road Grader

0.50 cu.m

2.50 sq.m.

2.00 cu.m

50.00 sq.m

Aspalt pvmt
8.0 sq.m.

Open-2,400 sq.m
Limited-1,200 sq.m

C. REMOVAL OF SLIDES/LOADING OF WASTE MATERIALS


USING PAYLOADER
Disposal Distance (Meters)
7.5
10
20
25
30
40
45
50
55
60

Capacity per Day (Cu.m)


Rock
Common Earth
300
430
270
390
230
330
200
280
180
260
160
230
150
220
140
210
130
190
120
170

Page 1 of 10

NOTE:
1. Open refers to trafficless working and condition otherwise would be referred to as limited.
2. For A and B, consider waste disposal.
3. For C
If necessary include bulldozer equipment.
Beyond 60.0 meter use dump truck for disposal of waste and include time spotting calculation for
hauling in the detailed estimate.
For heavy traffic areas, include the effect of traffic in the productivity output.
(Computation to be included in the detailed estimate)
ITEM 102:

EXCAVATION
Daily output in cu.m.
Common Earth
Loose Rock

A. LABOR

3.00

0.50-0.75

B. EQUIPMENT (Bulldozer) based on a maximum disposal distance of 30 meters, if


Payloader is used refer to item 101 C.

D4
D6
D8

Common Earth
210
250
410

C. SOLID ROCK
C.1. Particulars
Cap. Of 1 unit Air Compressor w/ jackhammers/day based
Based on perpindicular boring at a maximum height of
150 meters
100 boreholes
Holes required for 1 cu.m. solid rock = 2 holes (1 m. deep)
Average no. of dynamite sticks per case = 330 (Mayon Brand)
= 316 (Power Jet Brand)
C.2. Blasting Requirements per Cu.m. of solid rock
3 4 sticks of dynamite per borehole
2 pcs. Blasting caps per cu.m. of solid rock
4 m. safety fuse per cu.m. of solid rock

C.3. Clearing provisions


Deduct 0.60 m. Free Haul Distance
Refer to item 101 C Removal of Slides
Page 2 of 10

C.4. Boring Crew Composition


(Capacity of Crew 100 holes / day
1 Construction Foreman
2 Skilled Laborers
2 Laborers
C. 5. Blasting Crew composition
(Capacity of crew 100 holes / day)
1 licensed Blaster
2 Skilled Laborers
2 Laborers
NOTES:
1. Consider reduction of manpower and equipment output for heights of more than
1.50 meters and effect of heavy traffic.
2. Provide provisions of scaffolds and incidental expenses for height of more than
1.50 meters.
3. All equipments except Dumptrucks and Road Rollers are to be assisted by by a
helper or laborer.
4. Beyond 30.0 meters include Payloader and Pumptruck for disposal of waste,
attached the timespotting calculation for hauling in the detailed estimates and
the dumping area. B406
5. For Rock excavation, using Bulldozer special equipment such as D155A-3,
D20P-7 etc., indicate the equipment output in the detailed estimate to justify the
costing; and provide equipment data/specification on output to support the
justification.
ITEM 103:

STRUCTURE EXCAVATION

Daily Output in Cu.m.


Common Excavation
Loose Rock
A. Labor
1.50
0.50
B. 0.225 cu.m Backhoe
120.00
C. Jackhammer
20 ft/hour

Hard Rock
0.30
8 ft/Hr

NOTES:
1. For instances where the excavated materials is to be disposed off to a specified
place (Dumping area) computations for such waste disposal shall be considered.
2. Above labor outputs are based on maximum depth excavation of 2.00 meters
for depths of excavation exceeding 2.00 meters, add provisions for hoisting of
double/ multiple handling.

Page 3 of 10

ITEM 104:

EMBANKMENT

A. SHRINKAGE FACTOR

20% ( For common borrow only)

B. PLACING
B.1. Labor
Common Earth
Daily output in cu.m./man-day
B.2. Equipment
Output of one unit Road grader

4 cu.m

Hard rock
2.50 cu.m

500.00 cu.m./day

C. COMPACTION
C.1. Labor (Tamping)
2 cu.m./Man-day (applicable to backfill for cross drains and retaining walls.
C.2. Equipment
Portable plate compactor
1 Tonner Road Roller
9 11 Tonner Road Roller
Water Truck

50 cu.m./Day
100 cu.m./day
300 cu.m /day
8,000 sq.m./day

NOTE: For Hauling of embankment materials, attached timespotting calculation in the


detailed estimates.
ITEM 105:

SUB-GRADE PREPARATION

A. EQUIPMENT (Using motorized road grader)


A.1. Reshaping and Grading
Preparation of dirt/earth road for application of gravel
Item 200 or item 201 or 300
12, 500.00 sq.m/day
Preparation of gravel road for the construction of Asphalt Concrete pavement
9,000.00 sq. m. /day
NOTE: 1. Compaction refer to Item 104
2. For heavy traffic, include the effect of traffic in the productivity output
computation to be included in the detailed estimate.

Page 4 of 10

SPL:

AGGREGATE HAULING/TIMESPOTTING
A. QUARRYING
Output of one (1) D4 Bulldozer

210 cu.m./day of unprocessed matl.

B. SCREENING AND STOCKPILING


GENERAL FORMULA
For Wheel Loader:
Q = q x (60/CM) x E
Where:Q Hourly production in cu.m./Hour
q Production per cycle
CM cycle time in minutes
E Job efficiency
q = q1 x k
Where: q1 Heaped capacity of loader
k Bucket factor
CYCLE TIME (Cm) FOR LOADER
1. In a cross loading
Cm = D/F + D/R + Z
2. For V Shaped loading
Cm = D/F + 2 + D/R + 2 + Z
3. In Load and carry
Cm = D/F x Z
Where: Cm cycle time in minutes
D Hauling Distance
F Forward speed in meters/minute
R Reverse speed in meters/minut
Z Fixed Time (minutes) sum of gear shifting, loading, turning,
dumping and waiting time

Page 5 of 10

Computation of screening and stockpiling output for wheel loaders (articulated), use job
efficiency (E) of 0.83 (83%) Cm = 1.00 Minute (Cycle time for screening 1 bucket of
unprocessed material)
GENERAL FORMULA:
Q = q x ( 60 / Cm) x E; use q = use struck bucket capacity
= q x (60/1) x (0.83)
= 49.8 cm./hr
where: q is the struck bucket capacity. However, for screening fine and course
aggregates, introduce (f) quarry factors to the general formula, therefore,
1. For screening fine aggregates
Q = 49.8 qFf (cu.m./hour)
2. For screening course aggregates
Q = 49.8 qFc (cu.m./hr)
Where:

Ff = quarry factor for fine aggregates


Fc = quarry factor for course aggregates

Moreover, in the screening process of fine and course aggregates, there is extra time
required for stockpiling screened waste. Materials which needs to be determined as factor of
cycle time to be multiplied to the above formulas to arrive at the output.
C. LOADING AND UNLOADING
C.1. Loading and Unloading Time
a. Using payloader and dumptrucks
1. Aggregates: a.1. Loading Time
5 min.
a.2. Unloading Time 1 min.
a.3 Slack time
2 6 min.
Depending on the availability and location of maneuvering area:
2. Boulders 6 minnutes
b. Manual Loading (Crew of 6 laborers to fill one unit)
C2. Capacity of 1 unit Dumptruck

5 cu.m. 1 Hr.

D. SPEED 0F DUMPTRUCK

Loaded Trip
W/o Load

Below 7% Grade
Dirt Road
Paved
15
25
20
30

Speed in KPH
7 12
Above 20%
Dirt Rd
Paved
Paved
10
15
5
15
20
10

Page 6 of 10

E. STOCKPILING OF BOULDERS
E.1 From sideslope: (Barring down and stockpiling)
Labor Capacity
2.00 cu.m/man day
E.2. Picking and stockpiling from riverbed
Labor capacity
2.00 cu.m/MD

ITEM 200 AND 201:

AGGREGATE SUB-BASE COURSE AND AGGREGATE BASE


COURSE RESPECTIVELY

A. SHRINKAGE FACTOR

15%

B. SPREADING CAPACITY OF 1 UNIT RD GRADER

500 cu.m./Day

NOTE:

1. Compaction, refer to item 104


2. For Pakyaw projects, include Civil Engineer and Lab Tech.
In the labor/supervision.
C. LABOR/SUPERVISION
1 Foreman
2 Flagmen (Optional)
1 Helper/Laborer for every equipment except for dumptrucks and rollers.

ITEM 311

PORTLAND CEMENT CONCRETE PAVEMENT

A. MATERIALS
A.1. 9.10 bags of cement per cu. M. of concrete
A.2 Aggregates: Loose Volume
Quantity per cu. M. of concrete
Fine Aggrregates
0.50 cu.m.
Coarse Aggregates
0.80 cu.m.
Include other miscellaneous accessories, e.g. dowel bars, joint fillers, curing compound, etc.
B. BATCHING AND CASTING IN PLACE
B.1. Using 2 units 1 - bagger concrete mixer (minimum)
a. Capacity
150 bags / day (i.e. 75 bags per 1 bagger concrete mixer
b. Crew members
4 - Masons
2 - Carpenters
24 - Laborers
1 - Foreman
b.1. Consider water provision
b.2. For Pakyaw projects, include Civil Engineer and Lab tech.
c. Equipment support for 2 units 1 bagger
c.1. Consider water provision
Page 7 of 10

c.2.
c.3.
c.4.
c.5.
c.6.

2 Portable concrete vibrator


1 Bar cutter
1 Concrete cutter
2 Template depth min = 3
steel forms gauge No. 18

B.2. Using Transit Mixer


1. For No. of trips/day, apply time spotting
(Maximum distance of batching plant 10 km.)
2. Crew at Batching Plant
3 - Laborers
3. Crew at Project Site
1 Foreman
2 - Masons
2 - Carpenters
6 - Laborers
4. Equipment Requirement
Transit Mixer - quantity depends on the location of batching plant
1 Payloader / backhoe
1 - Portable Concrete Vibrator
1 Water Truck
1 Concrete Batching Plant (include labor for assembly batching and
lease of batching area)
1 Bar cutter
1 Portable Concrete Cutter
4 templates
1 Motorized Screeder
C. CURING PROVISION
C.1. Curing Compound, specify, liter additive/bag
C.2. Ponding
C.3. Combination of the above or any method specified under the 1995 DPWH Std.
Specs.
D. OTHERS
D.1.
D.2.
D.3.
D.4.
concrete.
D.5.

Estimate for continuous 2 days operation.


Use steel forms gauge No. 18.
Consider provisions for used oil.
Consider additional support materials for heavy downpour during pouring off

Consider traffic/warning signs as safety measures.

Page 8 of 10

ITEM 400

PILING
CONDITIONS
1. Hammer THD 22
2. Piles are spotted
Capacity 6 8 meter/hr. depending on type of foundation

ITEM 404

REINFORCEING STEEL BARS

A. MATERIALS
A.1. Tie wires

15 kg wires per ton of steel bars

B. LABOR: (Cutting, bending, fabrication, installation and other miscellaneous works)


B.1. Crew Composition: (Minimum Composition)
1 Construction Foreman
2 Skilled Laborers
2 - Steelman
6 - Laborers
For Pakyaw projects, include one Civil Engineer and Lab. Tech. In
C. EQUIPMENT REQUIREMENT PER GANG
1- unit Bar Cutter
2- Bar Bender
ITEM 405

STRUCTURAL CONCRETE

A. MATERIALS
CLASS
CEMENT FACTOR
(bags/cu.m.)
A
9.10
B
8.00
C
9.50
D
11.00

SAND FACTOR
(Loose vol./cu.m.)
0.50
0.45
0.55
0.44

GRAVEL FACTOR
(Loose vol./cu.m.)
0.80
0.85
0.75
0.73

B. BATCHING AND CASTING IN PLACE


B.1. Crew for 1 bagger or 2 bagger concrete mixer and transit mixer is the same as
Item except for steelman which is included under Item 404 and Carpenters
which is revised per section D of this Item.
B.2. Supporting equipments for Batching Plant same as Item 311.

C. CURING (Depends on the type of structure)


C.1. Either thru ponding use of curing compound or combination of both or as
specified in the 1995 Standard DPWH Specification.
Page 9 of 10

D. FORMWORKS
D.1. Formworks
Minimum Crew Composition. Dependent on the type of structure
1 Construction Foreman
2 Carpenters
4 Laborers
Capacity: (DEPENDING ON THE TYPE OF STRUCTURE)
1. Fabrication and Installation
35 sq.m./day
2. Stripping
60 sq.m./day
E. Include miscellaneous hardware materials in the estimates.
ITEM IV

ITEM V

MASONRY WORKS
6 x 8 x 16 CHB
Capacity of Crew of 2 Masons and 3 Laborers
(Up to 2.0 m. height of structure

230 pcs./day

Capacity of crew of 2 Masons and 5 Laborers


(Above 2.0 height of structure)

230 pcs./day

FORMWORKS
TIMBER FORMS AND SCAFFOLDING
1. Fabrication and Installation
2. Removal

35 sq.m./day
60 sq.m./day

Crew Composition
1 Foreman
3 Laborers
ITEM 1003

CARPENTRY
1. Roof Framing (one storey building)
2. Ceiling
3. Partition
a. Movable
b. Fixed
4. Exterior Walls
Crew Composition
1 Foreman
2 - Carpenters
1 Helper

Page 10 of 10

10 sq.m./day
15 sq.m./day
3.5 sq.m/day
7.0 sq.m/day
58.0 sq.m./day

S-ar putea să vă placă și