Chassis

Engine Block (5)-5

Transmission
Engine Frame Ass’y
Radiator

Battery (5)-3

Shocks
Suspension
Body (10)-6
Brakes (8)-4
Midsize Car
Windshield (5)-4

Wheels (20)-1 Seats (34)-2

Rims (38)-4 Tire Ass’y

Tires (30)-5

Days
1 2 3 4 5 6 7

-Build -EB (5) -Wind -Battery (5) Seats (34) Wheels (20) Assembly
Body shield (5)
(10) -Tires (30)
-Brakes(8)

-Rims (38)

Untuk 10 mobil dalam 7 hari


Projected Body Stamping

Qrtr Panel = 2 + (10 x 4 x 0.5) = 22 hari

Hood = 1 + (10 x 1 x 0.3) = 4 hari

Fender = 2 + (10 x 2 x 0.3) = 3 hari


Roof = 2 + (10 x 1 x 0.2) = 4 hari

Doors = 2 + (10 x 4 x 0.2) = 10 hari

Total = 48 jam/8 jam = 6 hari

2. Projected Body Stamping (15 Mobil)

Qrtr Panel = 2 + (15 x 4 x 0.5) = 32 hari

Hood = 1 + (15 x 1 x 0.3) = 5.5 hari

Fender = 2 + (15 x 2 x 0.3) = 11 hari

Roof = 2 + (15 x 1 x 0.2) = 5 hari

Doors = 2 + (15 x 4 x 0.2) = 14 hari

Total = 675 jam/ 4 hari = 16.875 hari

Hence, Workhour should be added from 8 hours to be 16.875 hours/Days and 15 cars should be
assembled in 2 batch.

For 15 Cars in 5 Days

Assumption:

-Tires should be 15 on Hand (adding 5)

-Transmission should be 15 on hand (adding 5)

-Engine Block should be 15 on hand (adding 10)

-Assembling 10
1 2 3 4 5
cars in batch 1

-Assembling 5 cars
in Batch 2
-Brakes (13) -Battery -seats -Wheels
(10) (54) (40)
-Rims (58)
-Chassis -Radiator
-Windshield
(5) (5)
(10)

-Buld Body
(15)