Heliport Pad Restoration on Petrobras PRA-1 Platform

Project 796

PRA-1

Project:

Resurfacing heliport floor


critical to transport of
resources
Shutdown time as
short as possible

Project enclosed entire


heliport perimeter

2008 Sponge-Jet Inc. All rights reserved.

Heliport Pad Restoration on Petrobras PRA-1 Platform


Substrate: Aluminum
Specifications:
Project Size: 358m (3853 ft)
Rusted Aluminum Deck

Profile: 40-85microns(2-3mils)
Sponge Media Used:
Silver 30 Sponge Media abrasives
Preparing Containment

2008 Sponge-Jet Inc. All rights reserved.

Heliport Pad Restoration on Petrobras PRA-1 Platform

PRA-1

Considered:
Substrate was previously
cleaned with water blasting;
paint was still present
Specifications:
Profile:
50-80 microns(2-3mils)

Cleanliness level:
SSPC SP-7/ SA1
Commercial Brush Off Blasting
2008 Sponge-Jet Inc. All rights reserved.

Equipment: (1) 400-HP


and (1) 100-HP Feed Unit
working simultaneously
Safety: Initially, management was
uncomfortable with two Feed
Units blasting side by side

Heliport Pad Restoration on Petrobras PRA-1 Platform

PRA-1

Reason for choosing


Sponge-Jet?

Ordinary blasting would require


a more complex containment
structure

2008 Sponge-Jet Inc. All rights reserved.

Heliport Pad Restoration on Petrobras PRA-1 Platform


TWO BLASTERS

PRA-1

2008 Sponge-Jet Inc. All rights reserved.

Heliport Pad Restoration on Petrobras PRA-1 Platform


Outcome:
Plant managment
recognized this as a
new, safe and efficient
solution

BEFORE

PRA-1

AFTER

Contracting two more


Petrobras platform
heliports

2008 Sponge-Jet Inc. All rights reserved.

Operators doubled
production, using two
Feed Units at the same
time - 358m (3,853 ft)
in 1 days