Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
1
Spectrum Carving
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
3
WCDMA/HSPA
2.2 MHz
2.4 MHz
2.6 MHz
= WCDMA/HSPA
= Non-BCCH GSM, coordinated deployment
= BCCH GSM, coordinated deployment
= GSM, uncoordinated deployment
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
4
G900 TCH
U900
GSM
UMTS 900
GSM
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
GSM spectrum allocation strategy :
Ad-Hoc ( non group BCCH-TCH)
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
5
2.2 MHz
2.4 Mhz
2.6 Mhz
Zone Setup
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
6
Zone setup
GSM900 (with U2100 zone), Buffer zone, GSM900 with U900 zone
Core Zone - Limited GSM900 band area (re-farming area) - The limited GSM900 band is used
together with 3G on U900 band.
Buffer zone - Buffer zone is having limited band for GSM900 (after re-farming) with UMTS on
2100 band. It is required to provide enough separation between the same frequencies of
GSM900 (full band) and UMTS900 (co-channel IF)
Common Zone - Full GSM900 band area - The whole available 900 band is used for GSM,
UMTS and U2100 band.
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
7
UMTS900 Area
Buffer Area
GSM900 Network Area
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
8
Network Analysis
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
9
Re-farming strategy (site coordination, UMTS 900 site list, planning area etc..)
Configuration analysis (Capacity)
Performance analysis
Parameter/feature analysis
Traffic analysis and Traffic forecast (traffic increase/decrease due to UMTS 900)
Outputs :
10
No
GSM cell >
3 TRXs
End
yes
Any
collocated
DCS
Downgrade to 3 TRXs
No
yes
Is 3 TRXs enough to
handle existing
traffic
yes
End
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
11
No
End
UMTS2100_COLOCATED
2 TRXs/cell on GSM
25542
6232
15979
1 TRX/cell on GSM
52740
9495
32654
BH traffic (Erl.)
# of DCS TRXs
48516
# of GSM TRXs
BT200321
BT200461
BT200462
BT200463
BT200561
BT200562
# of TRXs
4533
Cell name
Sum:
10%
40%
2
6
7
1
2
2
2
3
3
1
2
2
2
2
2
0
0
0
0
1
1
0.64
9.98
10.59
1.86
10.37
5.52
0.71
10.98
11.65
2.05
11.40
6.07
3
15
16
5
16
10
5
17
18
7
18
12
-1
11
12
1
12
6
0
2
2
1
2
1
0.00
6.51
7.05
0.00
6.85
2.58
-7
5
6
-5
6
0
0
1
1
0
1
0
0.00
1.38
1.92
0.00
1.72
0.00
0
0
0
0
1
1
Aim to ensure that excessive GSM 900 traffic (due to max configuration after refarming) will be planned to move either
1800 band or UMTS
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
12
Network re-planning
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
13
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
14
Re-design activities
Massive site evaluation is takes time to evaluate the
design manually.
Using Automatic Cell Planning tool to evaluate the
network
NSN uses ACORN as ACP tool.
ACP tools mainly supports for Network configuration &
optimization services - outcome:
Heights
Tilts (mechanical, electrical)
Antenna Types
Azimuth
Power
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
15
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
16
Recommended Time
frame A - B
-Minimum 14 days
-Maximum 20 days
Define Frequency
Allocation
Measurement > 14
days ?
Any co-BCCH and
co BSIC problem ?
yes
No
No
yes
yes
Retune co-BCCH and coBSIC
Neighbor optimization
OSS measurement
B
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
17
No
yes
Upload main KPI
Time frame B - C
- Minimum 7 days
GFP implementation
Neighbor Optimization
KPI Evaluation
No
C
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
18
END
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
19
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
20
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
21
URA_PCH
3G System
Re-direction
Transition to
CELL_DCH
Handover
Within CELL_DCH
UMTS 900
UMTS 900
22
GSM
DCS
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
23
Generic parameter
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
24
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
25
2.
Re-farming
3.
WCDMA Integration
* High Rejection for Co-site CDMA, Low Rejection Non Co-site CDMA.
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
26
2.
Re-farming
3.
WCDMA Integration
4.
Cluster optimization :
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
27
Implementation process
Site audit on refarming area
Zone setup
(Core Buffer)
NetAct
Planner
analysis
Antenna Optimization
with ACP tool
Amount of
Antenna
changes
= SMALL
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
28
Project implementation
Using mini Cluster Base
Reporting
Amount of
Antenna
changes
= BiG
Implementation Validation,
Performance Monitoring and
Optimization
Implementation process
B
Spectrum Carving by
Optimizer tool
Continue Project
Implementation for next mini
Cluster
Spectrum Clean
on refarming
area
No
Yes
U900 Integration
Spectrum
Overshooting
No
Yes
Continue Optimization and
Performance stabilization
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
29
Final Acceptance
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
30
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
31
Clustering Jogjakarta
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
32
Core Zone : The limited GSM900 band is used together with 3G on U900 band.
Buffer Zone : Having limited band of GSM900 after re-farming together with 3G on U2100 bands. It is required
to provide enough separation between the same frequencies of GSM900 (full band) and UMTS900
3. Site Audit
TSSR report
Update site database on Tools (NetAct Planner, NetAct Optimizer)
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
33
Ensure NO Live
REPEATER / MCPA
integrated at CORE &
Buffer Zone Area
Mini cluster defined is for project controlling (integration, performance monitoring and KPI benchmark)
Each cluster contain 10 15 sites (resources dependency)
Define Drive Test route, and OSS KPI baseline time frame agreed between NSN Indosat
Mini cluster Drive test and OSS performance baseline report (mini cluster base)
Drive test and KPI baseline report
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
34
10. Swap and replaced to new antenna system (triple bands with feeder less)
Ensure Aerial Setting, RET Calibrated, Filter are implemented as plan, as well as radio parameter update.
Ensure the scope activity on swap modernization (DT)
Update Network Performance and Capacity Report (main KPI, Quality statement, SSV, DT reporting).
NetAct Optimizer site Database Update
Running NetAct Optimizer for new Frequency, SC allocation, if optimization is required. The process will be
done when each cluster execution is completed.
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
35
Containment on DCS as much as possible, obtain the cell performance with no degrading the KPI
Urban area: drive the traffic into DCS band in idle and dedicated mode
Suburban and rural area where: drive to GSM band in idle mode only
DT is to ensure RX level and Quality
Main KPIs, Traffic (Voice and data), Capacity resources (Traffic and signaling)
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
36
PES for Down Grading GSM 900 Capacity with detail HW Identification
19. Drive test (idle & dedicated for GSM only) before GFP
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
37
21. Drive test (idle & dedicated for GSM only) after GFP
22. Spectrum scanning 900 MHz (allocated for U900)
Scan (GSM ARFCN) focus at CORE ZONE, by using Scanner box (SEEGULL) not Mobile Phone (UE)
Scan report GSM per ARFCN in core zone with limit Level -155 dB (U900 Isolation) Template TBD
Analysis & Reporting
Physical tuning if necessary
Submit scanning Report to Indosat
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
38
Note:
Data for analysis and performance monitoring must be use from Busy Hour Busy Day
Any performance issue due to congestion or high utilization, implementation of capacity expansion is a must
Scan UARFCN focus at BUFFER ZONE, by using Scanner box (SEEGULL) not Mobile Phone (UE)
Scan report GSM per ARFCN in core zone with limit Level -155 dB (U900 Isolation) Template TBD
Analysis & Reporting
Submit scanning Report to Indosat
Note:
Data for analysis and performance monitoring must be use from Busy Hour Busy Day
Any performance issue due to congestion or high utilization, implementation of capacity expansion is a must
Customer
CustomerConfidential
Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
40
Optimization Strategy
Optimization Strategy
Accessibility
Improvement
Traffic &
Capacity
Management
Signaling
Analysis and
Improvement
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
41
Transport
Network
Audit
Retain-ability
Improvement
(E)GPRS/R99 /
HSDPA
Analysis and
Improvement
Frequency
Optimization
System Integrity
Improvement
Coverage
Assessment
Handover
Optimization
Optimization Strategy
NETWORK AUDIT
- Parameter & Neighbor audit
- Site Configuration
- Capacity audit
WORST PERFORMANCE
CELL
CBCCH & ANTENNA GRID
ALLIGNMENT
TRAFFIC MANAGEMENT
PARAMETER
OPTIMIZATION
TRANSPORT
OPTIMIZATION
CAPACITY OPTIMIZATION
FEATURE OPTIMIZATION
(E)GPRS, R99, HSDPA
OPTIMIZATION
AMR OPTIMIZATION
COVERAGE ASSESMENT
& OPTIMIZATION
HARDWARE FAULT
MONITORING &
ESCALATION
STRATEGIC FREQUENCY
PLANNING &
OPTIMIZATION
VIP CUSTOMER
COMPLAINT HANDLING
Objective
Main Activities
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
43
Objective
Main Activities
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
44
Objective
Main Activities
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
45
Customer
CustomerConfidential
Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
46
Network Statistics
Network statistics is one of the tool to monitoring and that is the one of indicator from network
performance. Deliverable shall be delivered to indosat representative as :
OSS Data
Nokia Siemens Networks collect and ensure the availability of OSS data which is accessible via OMC. Provision
of tools arranged in chapters Tool.
Daily Statistic Reports
Weekly Performance Reports
Monthly Executive Performance Report
KPI Achievement
At the end of each stage and project, Nokia Siemens Networks provides a complete and comprehensive
Performance report in the form of Executive Summary Report and Technical Report. The report is part of the
acceptance requirement.
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
47
KPI Acceptance
KPI Acceptance Method
The following methods are applied on acceptance process:
Acceptance will be based on KPI Achievement
Week of KPI Achievement is one week of the last optimization stage week.
KPI Achievement week shall be agreed by Indosat and Nokia Siemens Networks.
KPI Achievement is measured by accumulate used counters of 1 week data (7x24 hours) from Monday
to Sunday. The measurement data is based on hourly data. If any different data between Vendor and
Indosat, the value will be verified using hourly data.
KPI formula to be used in the calculation are based on KPI formula defined by Indosat
Acceptance will be based on Reward or Deduction Scoring Systems.
Nokia Siemens Networks shall submit a complete and comprehensive acceptance report as defined in
Reporting chapter before the acceptance.
Indosat will issue the acceptance certificate if the target score is achieved.
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
48
Customer
CustomerConfidential
Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
49
Drive Test
Drive Test is performed for the following circumstance:
Verification Drive Test due to Project implementation activities
Verification Drive Test after the global parameter change
Verification Drive Test for RF troubleshooting
The following rules apply in performing Drive Test:
The Drive Test data shall be recorded
All problems occured during drive test shall be logged for further analysis
The scope of drive test is limited for outdoor site
The drive test route shall be proposed to Indosat prior the execution
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
50
Reporting
Customer
CustomerConfidential
Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
51
Optimization:
Weekly Report (activity & KPI performance)
Monthly Report (activity & KPI performance)
Quarterly Report (KPI Achievement & ATP)
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
52
Activities
RF Planning (AOP):
Detail coverage & capacity planning
Parameter planning
Abis Mapping
Review of RNP Criteria (Swap/modernization)
RNP Translation (Swap/modernization)
Databuild creation for RF (PES, NDB)
Customer Confidential
Indosat 2012 / Version 2-0 / Re-farming Project 2012
53