83%(6)83% au considerat acest document util (6 voturi)
2K vizualizări2 pagini
This document contains examples of calculating schedule variance, cost variance, cost performance index (CPI), and schedule performance index (SPI) for projects. It provides the formulas and shows the calculations for several sample projects. The variances and indexes are used to measure project performance and cost efficiency. A negative schedule variance or a CPI and SPI below 1 would indicate the project is over budget or behind schedule.
This document contains examples of calculating schedule variance, cost variance, cost performance index (CPI), and schedule performance index (SPI) for projects. It provides the formulas and shows the calculations for several sample projects. The variances and indexes are used to measure project performance and cost efficiency. A negative schedule variance or a CPI and SPI below 1 would indicate the project is over budget or behind schedule.
This document contains examples of calculating schedule variance, cost variance, cost performance index (CPI), and schedule performance index (SPI) for projects. It provides the formulas and shows the calculations for several sample projects. The variances and indexes are used to measure project performance and cost efficiency. A negative schedule variance or a CPI and SPI below 1 would indicate the project is over budget or behind schedule.
NOTE: Do this work on an MS Excel Spreadsheet - Include the
Questions. 1 (p. 466): Find the schedule and cost variances for a project that has an actual cost as month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. Show work and Answers on an Excel spreadsheet: Please find the detailed answer as follows: BCWP = Budgeted cost of work performed = (Earned Value) ACWP = actual cost of work performed BCWS = budgeted cost of work scheduled Schedule Variance = BCWP - BCWS CV = BCWP - ACWP BCWP = $535,000 ACWP = $540,000 BCWS = $523,000 Schedule variance: 535,000 - 523,000 = $12,000 Cost variance: 535,000 - 540,000 = -$5,000 2 (p. 466): A sales project at mon5 had an actual cost of $34,000, a planned cost of $42,000, and a value completed of $39,000. Find the cost and schedule variances and the CPI and SPI. Show work and Answers on an Excel spreadsheet: Given actual cost or AC = 34,000, planned cost or PV = 42,000, and value completed or earned value (EV) = 39,000 Cost Variance (CV) CV = EV AC CV = 39,000 34,000 = 5,000 Schedule Variance (SV) SV = EV PV SV = 39,000 42,000 = 3,000 Cost Performance Index (CPI) The cost efficiency ratio of earned value to actual costs (CPI = EV/AC) In PMPlan, the CPI is used to calculate Estimate at Completion (EAC) (EAC = BAC/CPI) CPI = EV/AC CPI = 39,000/34,000 = 1.15 Schedule Performance Index (SPI) The schedule efficiency ratio of earned value accomplished against planned value (SPI = EV/PV). The SPI describes what portion of the planned schedule was actually accomplished. SPI = EV/PV
SPI = 39,000/42,000 = 0.93
7 (p. 466): Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry? Explain. Schedule Variance = Earned Value - Planned Value = 12000*70% 12000 = -$3600 Cost Variance = Earned Value - Actual Cost = 12000*70% - 10000 = $1600 No, the client will not be please as the variances indicate "Overbudget" for the client. At the same time, the actual value derived is less than the valued planned,