6.
6.1
The working drawings of MEP works (Electrical) is still awaited approval. This will be
finalized by 1st week of April 2016. The period of 5 months i.e. upto 01/09/2016 is
required to complete this work, taking into account delivery period of materials, and
installation etc.
6.2
7.
LED Lighting System (Sr. No. (xii) of reference) :There is proposal of LED lighting system for entire depot instead of conventional
lighting system . The proposal along with financial implication is submitted on
14/01/2016. The issue of detail design has come on 22/02/2016. The decision is
likely to be given by 31/03/2016 as per minutes of interface meeting of interface held
on 21/03/2016. The period of 6 months will be required for completion taking into
account design, delivery, installation, testing & commissioning. The work will
spillover upto 30/09/2016.
8.
General
8.1
Building
b)