1. PleaseexplaintheFIVERIGHTandthebuyersroleinestablishingtheseFIVERIGHT(10
Point)
2. Explain the ways in which the purchaser can obtain, analyze and interpret the necessary
priceandcostinformationbeforeanegotiation(5Point)
3. Identify issues which may be discussed between a buyer and a seller in reaching an
agreementonpaymentterms.(5Point)
4. Identifyfactorsthatshouldbecontainedinatechnicalspecification.(10Point)
5. TotalCostofOwnership(TCO)ismadeupofvariouscostandimportancevariabletotake
decision in procurement. The cost equation is consist of four costs of which is purchase
price.Pleaseexplainthreeoftheothercosts.(15Point)
6. Toobtainthepossibilitytoreducecostsandmaintainhighstandards,ithasbeenexamining
the advantages and possible pitfalls of sourcing many of its supplies from some of the
emerging economies of the world. After a time it becomes apparent that you are able to
negotiatesuchissuesasthepriceanddeliverytimeofthesupplies,butdonotknowhowto
go about agreeing contracts/purchase order with international suppliers with regard to
packagingandtransport,aswellascustomsandotherdutiespayable.Youareawareofthe
natureandpurposesofIncotermsduringdealwiththoseinternationalsuppliers.Youalso
haveinmindsomespecificIncotermsthatyoubelievewouldbeusefulfortheorganisation.
TASKS:
ExplainthepurposeofIncotermsandthewaysinwhichtheirusebenefitsboth
buyerandseller.(5Point)
OutlinetheprovisionsofExworks(EXW)(5Point)
OutlinetheprovisionsofCostandFreight(CFR)(5Point)
Suggest which Incoterms you would use for the company and provide reasons
foryourchoice.(5Point)
SupplierAinCanada:
TheunitpriceisUSD125,000EXWorkCanada
Recommended for commissioning and 2 year operating spares parts USD
10,000
Term of payment nett 30 days after received invoice against equipment
delivered
On site technical assistance to supervise during installation and
commissioningisUSD15,000lumpsump
1/20/2012Page1of2
SupplierBinAustralia:
TheunitpriceisUSD130,000CFRSurabayaPort
Recommended for commissioning and 2 year operating spares parts USD
10,000
Term of payment nett 30 days after received invoice against equipment
delivered
On site technical assistance to supervise during installation and
commissioningisUSD10,000lumpsump
SupplierCinJakarta:
TheunitpriceisUSD145,000FCASurabayaWarehouse
Recommended for commissioning and 2 year operating spares parts USD
12,500
Term of payment nett 30 days after received invoice against equipment
delivered
On site technical assistance to supervise during installation and
commissioningisUSD5,000lumpsump
Otherinformation:
Base on technical information from suppliers, shipping & traffic section advise the
followingcost:
EstimateshippingandhandlingcostfromCanadatoSurabayaPortisUSD
10,000andfreightinsurancecostapproximatelyUSD1,900
EstimateshippingandhandlingcostfromAustraliatoSurabayaPortisUSD
5,000andfreightinsurancecostapproximatelyUSD1,000
EstimateShippingandhandlingcostfromJakartatoSurabayaisUSD1,500
andfreightinsurancecostisUSD400
Estimate charge internally to handling the equipment from Surabaya to
SoroakoisapproxUSD1,500
Applicable Import Duty for this equipment is 5 % from CIF basis and VAT Import/
VATis10%
All Air Vent (s) proposed by suppliers have same delivery time and technically
complywithuserrequirements
TASK:Pleaseprovideyourcommercialrecommendationandexplainthereason.(20Point)
8. Youhavebeenaskedtomakeapresentationtoyourmanagementabouttheimportanceof
ethicalstandardsinprocurementarea.Youhavebeengiventwoheadingswhichyoumust
address.
TASKS:
Foreachheadinglistthemainpointsthatyouwouldincludeinyourpresentation
a) Personalethicsanddealingwithsuppliers(10point)
b) Ethicalsourcing(5Point)
1/20/2012Page2of2