DATE: 29-Aug-2015
Contract Title : EPIC for Security Buildings and Boundary & Landscaping Works
Contract No. GC - 13 111100
CIVIL / STRUCTURAL
Sr. Staf
Sr. Supervisor
Foreman
13
CIVIL / STRUCTURAL
Sr. Staf
Sr. Supervisor
Foreman
10
Unskilled Labour
Subcontractor
11
Boundary Fence
Activity
Survey / Setting Out
Surface Preparation
FDT Test
Shuttering
Blinding Concrete
Concrete Protection
Screed
Fence Post / Shutter Installation
Progress
Total Qty.
946
946
946
946
946
946
946
Unit
nos
nos
nos
nos
nos
nos
nos
946
nos
Subcontractor
Operators /
Drivers
Work Completed
Unskilled Labour
31
15
28
0
MANPOWER DETAILS OF SECOND SHIFT ( FROM 1500 HRS TO 0100
Operators /
Drivers
Todate Remarks
565
400
400
400
365
285
248
76
946
946
nos
nos
Ground Improvement
Site grading in progress (1650 meters out of 2910 meters)
Canopy Area
127
0
On Going activity
A
Gate Security Building (Milestone 2)
Backfilling of Substructure with selected fill materail is going on.
Shuttering preparation for grade beam blinding
B
Boundary Fence
Setting-out of line posts
Fill material laying & compaction of line post footing
Shuttering and line post of fence foundations
Casting of fence post foundations
C
Ground Improvement
Site grading in progress
D
Canopy Area
Excavation in Canopy area
Remarks
97
OM 1500 HRS TO 0100 HRS)
TOTAL
30