TABLE OF CONTENTS:


SCOPE OF WORKS

AS RECEIVED INSPECTION REPORT

LP ROTOR INCOMING VISUAL INSPECTION REPORT

LP ROTOR RUN OUT INSPECTION REPORT

LP ROTOR BEARING JOURNAL INSPECTION REPORT

LP ROTOR GLAND SEAL DIAMETER INSPECTION REPORT

LP ROTOR HARDNESS INSPECTION REPORT

LP ROTOR SURFACE ROUGHNESS INSPECTION REPORT

LP ROTOR MAGNETIC PARTICLE TESTING REPORT

FINAL INSPECTION REPORT




LP ROTOR BEARING JOURNAL INSPECTION REPORT

LP ROTOR HARDNESS INSPECTION REPORT

LP ROTOR SURFACE ROUGHNESS INSPECTION REPORT

LP ROTOR RUN OUT INSPECTION REPORT

LP ROTOR PROBE AREAS ELECTRICAL RUN OUT INSPECTION REPORT

LP ROTOR BALANCE REPORT TWO PLANES

LP ROTOR RESIDUAL UNBALANCE INSPECTION REPORT

LP ROTOR MAGNETIC PARTICLE TESTING REPORT

LP ROTOR DEMAGNETIZATION REPORT

PHOTOGRAPHS

PRO-01FR-36Rev.00

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia.

PT. Sulzer Turbo Services Indonesia

SCOPE OF WORKS:
1.

RECEIVE & INVENTORY.

2.

PERFORM INCOMING INSPECTION.

3.

CLEANING BY BLASTING THE ROTOR.

4.

PERFORM INCOMING NDT INSPECTION.

5.

WELD REPAIR BOTH JOURNAL ROTOR (GEN. SIDE & GOV. SIDE)

6.

STRAIGHTENING LP ROTOR.

7.

FINAL INSPECTION & NDT.

8.

PERFORM LOW SPEED BALANCING ROTOR AS PER STANDAR SPECIFICATION.

9.

FINAL QC INSPECTION INCLUDE DEMAGNETIZATION

10. PRESERVE & PACKAGING ROTOR.


11. SHIPMENT.
12. PROVIDE REPORT.

PRO-01FR-100 Rev.01

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

AS RECEIVED
INSPECTION REPORT
CUSTOMER
MFG./MODEL
EQUIP./NO.
P.O. NO.
TSID PROJECT

:
:
:
:
:

PJB UP MUARA KARANG


MITSUBISHI / 200 MW
LP ROTOR / UNIT #5
LOI NO. 160.LOI/612/UPHB/2014
P-01267

Rotating Equipment Services


Purwakarta Service Center
PT. Sulzer Turbo Services Indonesia

PRO-01FR-44 REV.04

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

INCOMING
VISUAL INSPECTION REPORT

MFG/MODEL

S/N & EQUIP. NO.

MITSUBISHI / 200 MW
TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-01

DATE : MAY 21, 2014

INSPECTED BY: UMR


INSTRUCTIONS:
1.
2.
3.
4.
5.

PHOTOGRAPH COMPONENT CONDITION AS RECEIVED. TAKE INDIVIDUAL PHOTOGRAPHS OF ANY AREA WHICH EXHIBITS
ABNORMAL WEAR OR DAMAGE.
RECORD ALL F.O.D., EROSION, HANDLING DAMAGE, RUST BUILD UP OR ANY OTHER OBVIOUS DEFECTS.
VISUALLY INSPECT AND RECORD GENERAL CONDITION.
MARK EACH COMPONENT WITH THE JOB NUMBER USING METAL TAGS OR AN APPROVED MARKED.
TAKE SAMPLES OF ANY DEPOSITS.

As received visual inspection the LP ROTOR are as follow :


5

1
4
3
2

GOV SIDE
GEN SIDE

1. Coupling Gen Side exhibited medium scratches on bolt holes and axial faces, medium nick on flange, ligh
pitting, light scratch on male spigot
2. Exhibited light to medium scratches, medium pitting, medium rubs on seal area.
3. Bearing Journal Gen Side exhibited heavy rubs & pitting corrosion,deep rubs 0.5 0.28. medium rubs &
discrbration on oil deflector area, light scratch & medium pitting on probe area.
4. Gland seal Gen Side exhibited medium rubs.
5. - Stage #8 Gov & Gen side exhibited medium erosion on leading edge blades & tie wire, light to medium
pitting on disck, medium scaling.
- Stage #7 Gov & Gen side exhibited light erosion on leading edge blades, medium erosion on tie wire
- Stg #6,5,4,3,2 Gov & Gen side exhibited light pitting on blades, light rubs on shroud , medium pitting on
disk,light rubs on interstage spill strip exhibited , light rubs.
- Stg # 1 Gov & Gen side exhibited medium pitting corrosion on blades, interstage spill strip in fair conditions,
balance weight area in fair condition.
6. Gland seal Gove Side exhibited light to medium rubs.
7. Bearing Journal Gov Side exhibited heavy rubs with 0,8 deep, heavy rubs on seal area, light scratches &
pitting on probe area.
8. Coupling area Gov Side exhibted medium rubs on seal area , medium nick & dent on flange, , bolt holes
exhibited medium rubs, medium nick & dent bolt holes area, light scratches & pitting on axial face, light rubs
on male spigot.

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-33 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-02

INSPECTED BY: YD.


STATUS:

DATE: MAY 21, 2014

AS RECEIVED

OTHERS/.

FINAL

SURFACES:

RADIAL

10

AXIAL

UNITS:

1/100 MILLIMETERS

11

2
1

1/10,000 INCHES

18
3

12

13 14 15 16

17

19

B2

A2
GOV. SIDE

GEN. SIDE

B1
A1

NOTE:
1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM GOV. SIDE.
2. ZERO DEGREE POINTS IS: STAMNP 1 ON DISK
3. ROTOR/SHAFT/PART IS SUPPORTED BY: LATHE MACHINE
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-56 Rev.04

Page 1 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-02

INSPECTED BY: YD
STATUS:

DATE: MAY 21, 2014.

AS RECEIVED

FINAL

SURFACES:

RADIAL

AXIAL

UNITS:

1/100 MILLIMETERS

1/10,000 INCHES

POS

10

11

12

13

14

15

16

17

18

19

A1

A2

B1

B2

45

-1

-0.5

-0.5

-0.5

-0.5

-0.5

-1

-2

-0.5

-1

0.5

0.5

-1

-0.5

-1

90

-1

-0.5

-0.5

0.5

0.5

1.5

-1

0.5

-1

-3

-2

-1

0.5

-2

-0.5

-2

135

-1

-1

-0.5

-0.5

-1

1.5

-1

0.5

-1.5

-0.5

0.5

-1

0.5

-1

180

-1

-1

-0.5

-1.5

-0.5

0.5

-0.5

-1

-0.5

-1

-0.5

-0.5

-0.5

0.5

-1

-0.5

-1

225

-0.5

-1

-1.5

-0.5

-0.5

1.5

-2

-2

3.5

-2

-1

-1

-1.5

-0.5

-1.5

270

-1

-0.5

-0.5

-1.5

-0.5

-0.5

-2

-4

-1

0.5

-1

-2

0.5

-2

315

-1

-0.5

-1.5

-0.5

-2

-1

3.5

-1

0.5

1.5

-1

-1.5

1.5

-1.5

TOTAL

0.5

0.5

-1.5

0.5

0.5

1.5

4.5

1.5

3.5

3.5

0.5

1.5

NOTE:
1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM "GOV SIDE".
2. ZERO DEGREE POINTS IS: STAMP N0 "1" ON DISK.
3. ROTOR/SHAFT/PART IS SUPPORTED BY: LATHE MACHINE.
APPROVED BY: ASP
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-56 Rev.04

Page 2 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
BEARING JOURNAL DIAMETER INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-03

INSPECTED BY: EKA


STATUS:

DATE: MAY 21, 2014

AS RECEIVED

FINAL

1 2

SURFACES:

INSIDE DIAMETER

OUTSIDE DIAMETER

UNITS:

5 6 7

3 4

MILLIMETERS

INCHES

GOV. SIDE

GEN. SIDE
POS

379.20

379.08

379.17

379.19

379.19

379.18

379.16

379.19

90

379.19

379.09

379.15

379.19

379.19

379.17

379.16

379.18

NOTE:
1. ALL PHASE ANGLE RECORDED : 0 / 90
2. ZERO DEGREE POINTS IS: STAMP 1 ON DISK
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-55 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
GLAND SEAL DIAMETER INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-04

INSPECTED BY: EKA


STATUS:

DATE: MAY 21, 2014

AS RECEIVED

FINAL

SURFACES:

INSIDE DIAMETER

OUTSIDE DIAMETER

UNITS:

MILLIMETERS

INCHES

7
8

GOV. SIDE

GEN. SIDE
POS

418.00

508.03

508.06

508.05

508.12

508.12

508.12

417.69

90

418.00

508.03

508.05

508.06

508.12

508.12

508.12

417.70

NOTE:
1. ALL PHASE ANGLE RECORDED : 0 / 90
2. ZERO DEGREE POINTS IS: STAMP 1 ON DISK
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-58 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
BEARING JOURNAL HARDNESS INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-05

DATE: MAY 21, 2014

INSPECTED BY: YN.


STATUS:

AS RECEIVED

FINAL

1 2

UNITS:

5 6 7

3 4

HRC

HRB

GOV. SIDE

GEN. SIDE

NO

HARDNESS

25.9

29.9

27.5

29.1

27.5

28.8

24.5

29.2

NOTE:
1. THE PICKUP DATA SHOULD BE DIFFERENCE MAXIMUM 3 HRC BEFORE CALCULATING AVERAGE VALUE
2. TAKE ON THE SURFACE OF CLOSE RUNNING CLEARANCE
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-78 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
SURFACE ROUGHNESS INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-AR-06

INSPECTED BY: EKA.


STATUS:

AS RECEIVED

DATE: MAY 21, 2014


FINAL

UNITS:

GEN. SIDE

- INCH

-M

GOV. SIDE

NO

SURFACE
ROUGHNESS (Ra)

0.57 ~ 0.92

0.82 ~ 1.19

0.72 ~1.08

0.80 ~ 1.01

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-90 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

MAGNETIC PARTICLE TESTING


REPORT
INSPECTED BY :
MT LEVEL
:
QTY

PART NO.

1 UNIT

HR
II
ITEM DESCRIPTION

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT. 01 / 036M / IV 14
APRIL 12, 2014

TEST PERFORMED:

LP ROTOR

AS RECEIVED

REPAIR

FINAL
RESIDUAL FIELD CHECK

GAUSS

DEMAGNETIZATION
PROCEDURE NO. :
TEST AREA :

BEARING JOURNAL AREA ( GEN. SIDE & GOV. SIDE )


MAGNETIZER:

METHOD:

MOBILE UNIT
HEAD SHOT/CLAMP
COIL/CABLE WRAP
CONDUCTOR

RESIDUAL
MEDIA:

PROD
AMP.:

CONTINUOUS

AC/DC

PRO-01WI-41

WITNESS ON TEST/DEFECTIVE AREAS BY:

PARTICLE TYPE:
ARDROX 8800
KEROSENE
(SOLVENT MIX)
MAGNAGLO 14AM

RESIDUAL MAGNETISM :
GAUSS METER AT SURFACE:
COUPLING END
CENTER
HRUST END

WET BATH (FLUORESCENT)

(SPRAY CAN)

DEMAGNETIZED BELOW 2.0 GAUSS

DRY POWDER (VISIBLE)

OTHERS

PARTS WITH DISCONTINUITIES MARKED

YOKE
AC

DC

PERMANENT

SPRAY CAN (FLUORESCENT)

RUST PRESERVATION

INSPECTIONS RESULTS:
NO CRACK INDICATION ON ABOVE INSPECTED AREA, EXCEPT HEAVY RUBS. SEE THE ATTACHMENT

I CERTIFY THAT THE ABOVE LISTED ITEMS WERE INSPECTED


IN ACCORDANCE WITH APPLICABLE SULZER TSID STANDARD

HR
INSPECTOR SIGNATURE

ENGINEERING/NDT LEVEL III/QC COMMENTS:

APPROVED BY

: ES

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-08 Rev.03

Page 1 of 3

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

MAGNETIC PARTICLE TESTING


REPORT
INSPECTED BY :
MT LEVEL
:

HR
II

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT. 01 / 036M / IV 14
APRIL 12, 2014

BEARING JOURNAL ( GOV. Side )

Fig.1 Steam turbine rotor after sand blasting

Fig. 2 No crack indication on bearing journal Gov. side

Fig.3 Heavy rubs on bearing journal area

Fig. 4 Heavy rubs on bearing journal area

Fig. 5 Typical deep rubs on bearing journal

Fig. 6 Typical of dent on oil seal area

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-08 Rev.03

Page 2 of 3

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

MAGNETIC PARTICLE TESTING


REPORT
INSPECTED BY :
MT LEVEL
:

HR
II

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT. 01 / 036M / IV 14
APRIL 12, 2014

BEARING JOURNAL ( GEN. Side )

Fig. 7 No crack indication on bearing journal


Gen. Side

Fig.9 Heavy rubs on bearing journal area

Fig. 8 Typical of deep rub on bearing journal area

Fig. Heavy rubs on bearing journal area

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-08 Rev.03

Page 3 of 3

FINAL
INSPECTION REPORT
CUSTOMER
MFG./MODEL
EQUIP./NO.
P.O. NO.
TSID PROJECT

:
:
:
:
:

PJB UP MUARA KARANG


MITSUBISHI / 200 MW
LP ROTOR / UNIT #5
LOI NO. 160.LOI/612/UPHB/2014
P-01267

Rotating Equipment Services


Purwakarta Service Center
PT. Sulzer Turbo Services Indonesia

PRO-01FR-44 REV.04

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
BEARING JOURNAL DIAMETER INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-01

INSPECTED BY: DNY


STATUS:

DATE: JUNE 05, 2014

AS RECEIVED

FINAL

1 2

SURFACES:

INSIDE DIAMETER

OUTSIDE DIAMETER

UNITS:

5 6 7

3 4

MILLIMETERS

INCHES

GOV. SIDE

GEN. SIDE
POS

379.25

379.24

379.25

379.25

379.25

379.24

379.25

379.24

90

379.23

379.23

379.24

379.25

379.24

379.24

379.25

379.24

NOTE:
1. ALL PHASE ANGLE RECORDED : 0 / 90
2. ZERO DEGREE POINTS IS: STAMP 1 ON DISK
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-55 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
BEARING JOURNAL HARDNESS INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-02

DATE: MAY 30, 2014

INSPECTED BY: KARNO.


STATUS:

AS RECEIVED

FINAL

UNITS:

2 3 4 5

7 8

HRC

HRB

9 10

GOV. SIDE

GEN. SIDE

POS
HARDNESS

WELDING AREA

HAZ AREA

BASE METAL AREA

HAZ AREA

WELDING AREA

10

24.4 ~ 28.5

23.2 ~ 26.5

24.0 ~ 26.9

24.7 ~ 26.4

25.1 ~ 27.0

29.1 ~ 30.1

23.6 ~ 25.8

23.2 ~ 26.5

24.2 ~ 26.5

24.1 ~ 27.2

NOTE:
1. TAKE ON THE SURFACE OF CLOSE RUNNING CLEARANCE

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-78 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
SURFACE ROUGHNESS INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-03

INSPECTED BY: EKA.


STATUS:

AS RECEIVED

DATE: JUNE 08, 2014


FINAL

UNITS:

GEN. SIDE

- INCH

-M

GOV. SIDE

NO

SURFACE
ROUGHNESS (Ra)

0.17 ~ 0.20

0.12 ~ 0.19

0.17 ~ 0.18

0.22 ~ 0.23

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-90 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-04

INSPECTED BY: UMR.


STATUS:

DATE: JUNE 06, 2014

AS RECEIVED

OTHERS/.

FINAL

SURFACES:

RADIAL

10

AXIAL

UNITS:

1/100 MILLIMETERS

11

2
1

1/10,000 INCHES

18
3

12

13 14 15 16

17

19

B2

A2
GOV. SIDE

GEN. SIDE

B1
A1

NOTE:
1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM GOV. SIDE.
2. ZERO DEGREE POINTS IS: STAMNP 1 ON DISK
3. ROTOR/SHAFT/PART IS SUPPORTED BY: V-BLOCKS
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-56 Rev.04

Page 1 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-04

INSPECTED BY: UMR.


STATUS:

DATE: JUNE 06, 2014

AS RECEIVED

FINAL

SURFACES:

RADIAL

AXIAL

UNITS:

1/100 MILLIMETERS

1/10,000 INCHES

POS

10

11

12

13

14

15

16

17

18

19

A1

A2

B1

B2

45

-05

-0.5

0.5

-0.5

-0.5

-1

-1

-0

0.5

-1

-1

-1

90

-0.5

0.5

-1

-1.5

-0.5

-2

-1

0.5

-1

-1

-2

-1

-1.5

135

-1

-1.5

0.5

-0.5

0.5

-0.5

0.5

-0.5

-1

-0.5

-1

0.5

-1

180

-1

1.5

-0.5

0.5

-0.5

0.5

-1

-2

-0.5

-0.5

-1

-0.5

-1

0.5

225

-1.5

-0.5

0.5

0.5

-0.5

0.5

0.5

-2

-0.5

1.5

-2

270

-1

0.5

-0.5

0.5

-2

0.5

-0.5

-1

-1

-1.5

315

0.5

0.5

-2

0.5

-0.5

-1

-1

-1.5

0.5

-1.5

TOTAL

1.5

1.5

2.5

0.5

0.5

0.5

0.5

0.5

0.5

0.5

1.5

NOTE:
1. ALL PHASE ANGLE RECORDED : CCW AS VIEWED FROM "GOV SIDE".
2. ZERO DEGREE POINTS IS: STAMP N0 "1" ON DISK.
3. ROTOR/SHAFT/PART IS SUPPORTED BY: V-BLOCKS
APPROVED BY: ASP
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-56 Rev.04

Page 2 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
PROBE AREAS ELECTRICAL RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-05

INSPECTED BY: SGH


STATUS:

AS RECEIVED

ERO LOCATION

DATE: JUNE 05, 2014


FINAL

SURFACES:

RADIAL

AXIAL

UNITS:

MILLIMETERS

INCHES

: RADIAL GS

RESULT: ELC. R/O = 22 m

MAX. ALLOWABLE ELECTRICAL


RUNOT:
RADIAL = 25 m

COMMENTS:
-

ACCEPTABLE

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-41 Rev.04

Page 1 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
PROBE AREAS ELECTRICAL RUNOUT INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-05

INSPECTED BY: SGH.


STATUS:

AS RECEIVED

ERO LOCATION

DATE: JUNE 05, 2014


FINAL

SURFACES:

RADIAL

AXIAL

UNITS:

MILLIMETERS

INCHES

: RADIAL TS

RESULT: ELC. R/O = 24 m

MAX. ALLOWABLE ELECTRICAL


RUNOT:
RADIAL = 25 m

COMMENTS:
-

ACCEPTABLE

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-41 Rev.04

Page 2 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
BALANCE REPORT
(TWO PLANES)

MFG/MODEL

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BIFNL-06

INSPECTED BY: YD

DATE : JUNE 07, 2014

 BALANCE PROCEDURE:
FULL ASSEMBLY BAL.
 TYPE OF ROTOR:
STEAM TURBINE.

CHECK BAL.

 TYPE MACHINE USED:


 BALANCE SPEED:

INDIVIDUAL BAL.

COMPRESSOR

 WHEEL/DISK NUMBER:

 CORR. METHOD:

MITSUBISHI / 200 MW

PUMP.

.
H 20 BU

ADDITIONAL

PROGRESSIVE BAL.
OTHER / GENERATOR

SHAFT ONLY
H 40 BU
REMOVAL

H6B
PERMANENT

ABRO
TEMPORARY

OTHERS

200 RPM

INITIAL BALANCE MACHINE READING:


1329

GRAMS, AT RADIUS

420

MM, AT

96

DEGREES, ON

GEN/S

SIDE.

1385

GRAMS, AT RADIUS

420

MM, AT

100

DEGREES, ON

GOV/S

SIDE.

FINAL BALANCE MACHINE READING:


51

GRAMS, AT RADIUS

420

MM, AT

45

DEGREES, ON

GEN/S

SIDE.

114

GRAMS, AT RADIUS

420

MM, AT

245

DEGREES, ON

GOV/S

SIDE.

ALLOWABLE RESIDUAL UNBALANCE TOLERANCE (ACC. TO ANSI/API STANDARD):


177

GRAMS, AT RADIUS

420

MM, ON

GEN/S

SIDE.

177

GRAMS, AT RADIUS

420

MM, ON

GOV/S

SIDE.

 BALANCE MACHINE SETUP:


a: 830 . mm

b: 3120 . mm

c: 770 .mm

r1: 420 .mm

r2: 420 . mm

 ZERO DEGREE POINT IS:

MARKING 1 HOLE BALANCE WEIGHT


(BALANCING ROTATION = OPERATION ROTATION)

 KEY WEIGHTS USE (IN GRAMS):


 OTHER REMARKS:

N/A

FINAL BALANCING ROTOR ASSY

COMMENTS:

ACCEPTABLE
APPROVED BY: ASP.
This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-30 Rev.04

Page 1 of 1

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RESIDUAL UNBALANCE INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-07

INSPECTED BY: YD
STATUS:

DATE: JUNE 7,2014

INITIAL

FINAL

PLANE:1

COUPLING

EXCITER

GEN/S

ROTOR/PART DESCRIPTION: STEAM TURBINE ROTOR


MAXIMUM CONTINUOUS SPEED ( N ): 3000 RPM.
JOURNAL STATIC WEIGHT LOAD ( W ): 19250 Kg.
UNBALANCE RADIUS: 420 mm.

TRIAL WEIGHT:650 Gr

 ALLOWABLE RESIDUAL UNBALANCE TOLERANCE: 74 340 gr-mm.


Note: If not specified, Residual Unbalance Tolerance Allowable is:
6350 W/N (gr-mm.). Acc. To ANSI / API Standard.
No.

AMP

PHASE

629

Gr.

Degree

689

Gr.

97

Degree

475

Gr.

183

Degree

470

Gr.

265

Degree

Gr.

Degree

Gr.

Degree

TRIAL UNBALANCE :
Y=
X=

420 x 650

200

400

600

800

100
00

= 273 000 Gr-mm.

MAX. READING - MIN. READING


 = 109
2
MAX. READING + MIN. READING
 = 659
2

 RESIDUAL UNBALANCE :
 273000x  109
 659

= 45 155 gr-mm. (PASS)

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-23 Rev.04

Page 1 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

LP ROTOR
RESIDUAL UNBALANCE INSPECTION REPORT

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.

BI-FNL-07

INSPECTED BY: YD

STATUS:

DATE: JUNE 7,2014

INITIAL

FINAL

PLANE:2

COUPLING

EXCITER

GOV/S

ROTOR/PART DESCRIPTION: STEAM TURBINE ROTOR


MAXIMUM CONTINUOUS SPEED ( N ): 3000 RPM.
JOURNAL STATIC WEIGHT LOAD ( W ): 19250 Kg.
UNBALANCE RADIUS: 420 mm.

TRIAL WEIGHT: 650 Gr

 ALLOWABLE RESIDUAL UNBALANCE TOLERANCE: 74 340 gr-mm.


Note: If not specified, Residual Unbalance Tolerance Allowable is:
6350 W/N (gr-mm.). Acc. To ANSI / API Standard.
No.

AMP

PHASE

655

Gr.

Degree

695

Gr.

93

Degree

645

Gr.

181

Degree

605

Gr.

274

Degree

Gr.

Degree

Gr.

Degree

200

400

600

800

100
0

TRIAL UNBALANCE : 420 x 650 = 273 000 Gr-mm.


Y=
X=

MAX. READING - MIN. READING


 = 45
2
MAX. READING + MIN. READING
 = 650
2

 RESIDUAL UNBALANCE :
 273000 x  45
 650

= 18900 gr-mm. (PASS)

APPROVED BY: ASP.


This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-23 Rev.04

Page 2 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

MAGNETIC PARTICLE TESTING


REPORT
INSPECTED BY :
MT LEVEL
:
QTY

PART NO.

1 UNIT

CH/ MN/ AM
II
ITEM DESCRIPTION

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT. 01 / 015M / VI 14
JUNE 03, 2014

TEST PERFORMED:

LP ROTOR

AS RECEIVED

REPAIR

FINAL
RESIDUAL FIELD CHECK

GAUSS

DEMAGNETIZATION
PROCEDURE NO. :
TEST AREA :

BEARING JOURNAL AREA ( GOV SIDE GEN SIDE )


MAGNETIZER:

METHOD:

MOBILE UNIT
HEAD SHOT/CLAMP
COIL/CABLE WRAP
CONDUCTOR

RESIDUAL
MEDIA:

PROD
AMP.:

CONTINUOUS

AC/DC

PRO-01WI-41

WITNESS ON TEST/DEFECTIVE AREAS BY:

PARTICLE TYPE:
ARDROX 8800
KEROSENE
(SOLVENT MIX)
MAGNAGLO 14AM

RESIDUAL MAGNETISM :
GAUSS METER AT SURFACE:
COUPLING END
CENTER
HRUST END

WET BATH (FLUORESCENT)

(SPRAY CAN)

DEMAGNETIZED BELOW 2.0 GAUSS

DRY POWDER (VISIBLE)

OTHERS

PARTS WITH DISCONTINUITIES MARKED

YOKE
AC

DC

PERMANENT

SPRAY CAN (FLUORESCENT)

RUST PRESERVATION

INSPECTIONS RESULTS:
NO CRACK INDICATION ON ABOVE INSPECTED AREA, SEE THE ATTACHMENT :

I CERTIFY THAT THE ABOVE LISTED ITEMS WERE INSPECTED


IN ACCORDANCE WITH APPLICABLE SULZER TSID STANDARD

CH
INSPECTOR SIGNATURE

ENGINEERING/NDT LEVEL III/QC COMMENTS:

ACCEPTABLE

APPROVED BY

: ES

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-08 Rev.03

Page 1 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

MAGNETIC PARTICLE TESTING


REPORT
INSPECTED BY :
MT LEVEL
:

CH/ MN/ AM
II

Fig.1 Position MT inspection on the Rotor

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT. 01 / 015M / VI 14
JUNE 03, 2014

Fig. 2

MT inspection on the Rotor

Fig.3 No Crack indication on bearing


journal Gen Side

Fig. 4

No Crack indication on bearing


journal Gen Side

Fig. 5

Fig. 6

No Crack indication on bearing


journal Gov Side

No Crack indication on bearing


journal Gov Side

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-08 Rev.03

Page 2 of 2

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

DEMAGNETIZATION
REPORT
INSPECTED BY
UT LEVEL

QTY

:
:

ES
III

PART NO.

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT.01 / 026D/ VI-14


JUNE 06, 2014

ITEM DESCRIPTION

TEST PERFORMED:
AS RECEIVED

1 UNIT

LP ROTOR

REPAIR
FINAL

TEST AREA :

PROCEDURE NO. : PRO-01WI-41

ALL VISIBLE SURFACE


DEMAGNETIZER:
MOBILE UNIT / CABLE WRAP
MAGNAFLUX

AMPERE
1000 1500 AMP

AC

YOKE 6

RESIDUAL MAGNETISM READING WITH


GAUSS METER AT SURFACE:
0

COUPLING END / DE

CENTER

THRUST END/ NDE

INSPECTION RESULT :

DEMAGNETIZATION BELOW 2 GAUSS, SEE PHOTOGRAPHS IN THE ATTACHMENT:

I CERTIFY THAT THE ABOVE LISTED ITEMS WERE INSPECTED


IN ACCORDANCE WITH APPLICABLE SULZER TSID STANDARD

HR
OPERATOR SIGNATURE

ENGINEERING/NDT LEVEL III/QC COMMENTS:

ACCEPTABLE

APPROVED BY

: ES

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-102 Rev.03

Page 1 of 3

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

DEMAGNETIZATION
REPORT
INSPECTED BY
UT LEVEL

:
:

ES
III

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT.01 / 026D/ VI-14


JUNE 06, 2014

Fig.2 Residual magnetism on Gov. Side


Coupling : 1 gauss

Fig.1 Demagnetization on Gov. Side LP rotor

Fig.3 Residual magnetism on Journal Gov.


Side :1.5 gauss

Fig.4 Residual magnetism on gland seal Gov.


Side :1 gauss

Fig.5 Demagnetization on Gen. Side LP rotor

Fig.6 Residual magnetism on gland seal Gen.


Side :1 gauss

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-102 Rev.03

Page 2 of 3

PRODUCTION Form

PT. Sulzer Turbo Services Indonesia

DEMAGNETIZATION
REPORT
INSPECTED BY
UT LEVEL

:
:

ES
III

Fig.7 Residual magnetism on Journal Gen.


Side:1 gauss

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

REPORT NO.
DATE

NDT.01 / 026D/ VI-14


JUNE 06, 2014

Fig.8 Residual magnetism on shaft Gen. Side:


1 gauss

Fig.9 Residual magnetism on shaft Gen. Side:


1 gauss

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-102 Rev.03

Page 3 of 3

PHOTOGRAPHS
CUSTOMER
MFG./MODEL
EQUIP./NO.
P.O. NO.
TSID PROJECT

:
:
:
:
:

PJB UP MUARA KARANG


MITSUBISHI / 200 MW
LP ROTOR / UNIT #5
LOI NO. 160.LOI/612/UPHB/2014
P-01267

Rotating Equipment Services


Purwakarta Service Center
PT. Sulzer Turbo Services Indonesia

PRO-01FR-44 REV.04

PRODUCTION Forms

PHOTOGRAPHS

PT. Sulzer Turbo Services Indonesia

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

Fig 01. Incoming condition of rotor

Fig 02. Incoming condition bearing journal rotor

Fig 03. Check depth of rubs journal rotor

Fig 04. Blasting rotor preparation

Fig 05. Incoming visual inspection

Fig 06. Incoming magnetic paticle test inspection

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-32 Rev.04

Page 1 of 3

PRODUCTION Forms

PHOTOGRAPHS

PT. Sulzer Turbo Services Indonesia

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

Fig 07. Under cutting both journals for weld prep

Fig 08. Welding repair both journals

Fig 09. Rough cutting both journals after welding


repair

Fig 10. Ultrasonic test after rought cutting

Fig 11. Stress relieve process

Fig 12. Final machining both journals to target size

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-32 Rev.04

Page 2 of 3

PRODUCTION Forms

PHOTOGRAPHS

PT. Sulzer Turbo Services Indonesia

MFG/MODEL

MITSUBISHI / 200 MW

S/N & EQUIP. NO.

TBA / UNIT #5

CUSTOMER

PJB UP MUARA KARANG

TSID PROJECT

P-01267

Fig 13. Final magnetic particle test

Fig 14. Final low speed balancing

Fig 15. Preserve the rotor before shipment

Fig 16. Packaging the rotor before shipment

This material is the exclusive property of PT. Sulzer Turbo Services Indonesia

PRO-01FR-32 Rev.04