Documente Academic
Documente Profesional
Documente Cultură
Home
Disclaimer
Inspection Checklists
Customer Support
Air, Water & Gas Processing Non Standard Equip is Our Specialty
Tweet
Tweet
Valme concrete
pipes
valme.it
Measuring Tape.
http://www.methodstatementhq.com/chiller-installation-method-statement.html
9/7/2014
General Requirements
All the materials received at site shall be as per the approved technical material submittal for
Chillers to be inspected upon receipt & approved by the engineer prior in proceeding with the
installation. Any discrepancies, damages etc., should be reported to the supplier for rectification
Chillers are normally shipped & dispatched from factory as a hermetically assembled package,
factory piped, wired and tested. All openings except for the water box vent & drain holes are
covered or plugged to prevent contamination during shipment & handling.
Special care must be taken to ensure that units are offloaded from containers. Rough handling
CATEGORIES
BMS
As soon as the units arrived at site, raise immediate inspection to the consultant & inspect
Civil Engineering
thoroughly for damage. Hence, in case of transit damage, supplier/ manufacturer must be
informed immediately.
Concrete Testing
Ensure that the units have been inspected & accepted by the consultant as per the approved
Duct Works
Electrical
Electrical Method Statem ents
Fire Suppression System
Health & Safety
HVAC Checklists
HVAC Maintenance
HVAC Method Statem ents
ISO 9001
The entire assembly of the Water Cooled Centrifugal Chillers will be rigged from store to place of
installation i.e. roof etc. Refer to Manufacturers Instruction Manual for rigging instructions for the
Piping Works
Chiller.
Pressure Testing
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the
Pum p Installation
All operatives will be equipped with minimum personnel protective equipment; hard hat,
Quality Assurance
The persons using cleaning fluid, solvent cement& any other forms of chemicals have to wear
Risk
hand gloves.
Ensure only qualified personnel shall install, test & commissioned the equipment.
During installation, display warning sign boards to be provided and barricade the area
whenever necessary. Close monitoring by the site engineers during installation is much highly
Tem plates
recommended.
Only competent, experienced & trained personnel shall perform all the required activities stated
Welding Risk
Ensure that all operatives fully understand the method of these activities.
What Is Hazard?
What Is Risk?
http://www.methodstatementhq.com/chiller-installation-method-statement.html
2/5
9/7/2014
Working At Height
TAGS
All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved by the
consultant.
Determine whether the units occur damages during the storage & shifting of location.
Permission to start or Civil Clearances prior to installation has been given by the main
contractor.
All relevant Approved Shop drawings for the installation of the equipment shall be available &
approved by the consultant.
Installation activities shall only commence when all associated works by the Civil has been
completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the
Safety in charge at site.
method Method
Of Statement Method
Prior to moving the chillers at site, ensure that the foundation requirements have been done.
Foundation details & requirements for the chillers shall be as per approved shop drawings or as
recommended by the manufacturer as follows:
1. Rigid non-warping mounting pads or a concrete foundation is available prior to shifting chillers
at site.
statement
Format Electrical
swms
template test Testing & Commissioning
Testing & Commissioning Method
Statement water
DOWNLOAD METHOD STATEMENTS
2. Ensure that the foundation will be able to support the chiller at its full operating weight.
3. For proper unit operation, the chiller must be level within 1.6mm over its length & width when set
into place on the mounting surface.
After ensuring that the foundations for the chillers are satisfactory, shift the chillers by means of
cranes to its exact location.
Ensure that the lifting cables are capable of supporting the entire weight of the chiller. Failure to
properly lift the unit could result to serious injuries & damage of the unit.
System evacuation, dehydration and charging with refrigerant shall be carried out by skilled &
experienced personnel only.
Ensure isolator pads or spring isolators are available in the chiller feet/ legs prior to lowering the
unit to its foundation.
Ensure that all piping connected to the chiller must be properly isolated & supported so that it
does not place any stress on the unit.
It is much recommended to avoid piping from 3 feet minimum to the equipment to allow
proper fit-up upon arrival of the unit at job site.
Pipe the evaporator into the chilled water circuit.
Pipe the condenser into the cooling tower water circuit.
Locate pressure gauge taps in a straight length of pipe. Place tap a minimum of one pipe
diameter downstream of any elbow, orifice, etc.
Install air vents & drain valves on the water boxes. Each water box is provided with 3/4 NPTF
(National Pipe Thread Female) vent & drain connection. Plastic plugs are factory installed in
both openings. Remove & discard the same before installing the water box vents & drain valves.
Hom e
Install pressure relief valves in the condenser & evaporator water circuits to avoid water box
Privacy Policy
Disclaim er
Whenever are applicable, install pressure relief valves at the drain connections on the
evaporator and condenser water boxes.
Install a strainer in the entering side of each piping circuit to avoid possible tube plugging in the
http://www.methodstatementhq.com/chiller-installation-method-statement.html
Hom e
3/5
9/7/2014
Privacy Policy
Install flow sensing device. Use either flow switches or differential pressure switches in conjunction
Disclaim er
with the pump interlocks to verify evaporator and condenser water flows.
Install by pass valve system to avoid circulating water through the auxiliary shell when the unit is
shut down.
Pipe the evaporator & condenser as per the approved shop drawings. Ensure that the correct
pipe sizes are to be connected to the evaporator & condenser circuit.
Ensure that the evaporator water piping is clear; check if the chilled water pump is operated
but before initial chiller start-up. If any partial blockages exists removed the same to prevent for
possible tube damage resulting from evaporator freeze-up or erosion.
For condenser & large evaporator connections, arrange the water piping so that the water
supply enters the shell at the lower connection, and exists from the top connection.
Units shall use grooved- pipe connections and flanged connections for 300 psi water boxes, use
welded flanges.
Piping joined using grooved type couplings, like all types of piping systems; require proper
support system to carry out the weight of the pipes & equipment.
Ensure that system refrigerant differential pressure must be maintained above 21 kpa at all times.
Failure to do so could result in operating problems.
Ensure that the discharge piping that allows pressure relief devices to safely vent refrigerant to
the atmosphere if over pressure occurs.
Make sure that the minimum pipe size for the vent must be equals the size of the discharge
connections on the pressure relief device.
When connecting the vent line to the chiller do not apply threading torque to the outside pipe.
If the unit is not factory insulated, install insulation around the evaporator bulb wells and ensure
that the bulb wells and connections for the water box drains and vents are still accessible after
insulation is applied. Ensure that the sensor modules and interconnecting four wire cables must
be raised up above the field installed insulation. Do not insulate over the wiring or sensor
device. Insulation shall be as per approved material submittal.
Install the controller hardware/ equipment which are used to interface with the internal chiller
data & functions provide by the controls. Note that there are four connections on the controller
that support the communication interface.
Install the control panel & ensure low voltage & high voltage areas are in proper route & field
wiring.
Install the display. The display is boxed and shrink-wrapped behind the control panel during the
shipment. Follow the procedure for installation of display as follows
Unwrap control panel & display arm.
Plug the power cable and the Ethernet cable into the bottom of the display.
Adjust the display support arm so the base plate that attaches to the display is horizontal.
Position the display with the LCD screen facing up, on top of the display support arm base plate.
Align the four holes in the display support arm base plate.
Attach the display to the display support arm base plate.
Ensure all Electrical requirements have been wired & connected as follows:
Power supply wiring to the starter
Starter to motor wiring
Starter to control panel wiring
System Control Circuit wiring
Water pump interlock circuits & flow switches & other devices.
Temperature Sensor circuits
Other unit control options present
Any field supplied control devices
Ensure that all wires & cables are of the correct sizes as voltage/ampere requirements of the
units.
After installation of the chillers, raise inspection to the consultant for acceptance prior to
http://www.methodstatementhq.com/chiller-installation-method-statement.html
4/5
9/7/2014
Portable Air
Conditioner
alibaba.com
LIKE US ON FACEBOOK
Jaim e
Filed under HVAC Met hod St at ement s, Met hod St at ement s | Tags: Chiller, Chiller inst allat ion met hod st at ement ,
HVAC Met hod St at ement s
http://www.methodstatementhq.com/chiller-installation-method-statement.html
5/5