Sunteți pe pagina 1din 4

Pressure Tests of Piping systems -Hydrotest Vs Pneumatic Test :

A pressure test is always required for a new pressure system before use or an existing pressure system after repair or
alteration to ensure the following:

Safety

Reliability of operation

and leak tightness of pressure systems

Also The last physical quality test in the fabrication process

Normally two methods for pressure testing: hydrostatic and pneumatic, are widely used in process industry.
A hydrostatic test is performed by using water as the test medium, whereas a pneumatic test uses air, nitrogen, or any
non-flammable and nontoxic gas. Pressure tests (both hydrostatic and pneumatic) must always be performed under
controlled conditions, following an approved test plan, and documented in a test record. A single approved test plan could
be used for several similar tests, but for each test a separate test record is required.

When to perform a Pressure Test:


As per the governing code, pressure test has to be performed on piping system after all hot works have been completed on
a certain piping system. Here the term hot work means everything related to welding or the post weld heat treatment
(PWHT). PWHT also has a potential of degrading the mechanical properties of piping, in case not addressed properly. And
this is the reason why code calls for NDT after PWHT operation. In case after carrying out pressure testing, some
modification has to be made requiring hot work, it calls for a retest as per code. Here code specifies that the minor repairs
/ modifications may be waived off provided adequate measures have been taken to ensure sound construction. Now taking
this decision as to which repairs or modifications may be waived off should be taken very carefully. Normally, the maximum
extent of repairs not requiring retesting shall be the tack welding of any piping support or pad. Anything else shall be done
following a retest.
Pressure testing and conducting 100% radiography or ultrasonic inspection shall not be interchanged. In case carrying out
of hydrostatic or pneumatic test stands impractical then 100% radiography or ultrasonic testing may be performed but in
addition to this it is advisable to check that the whole piping and its components have been supplied against acceptable
ASTM standards and required test certificates are available. Conducting 100% radiography of all the weld joints assure that
your weld joints are defect free but can never provide you with the assurance of mechanical integrity of a system. This is
also to be noted that radiography / ultrasonic inspection shall also not to be waived off if the pipeline is to be
hydrostatically tested. This may pose an additional safety risk during the test. Moreover, some defects in the weld zones
may prove to be detrimental way after taken in service due to severe extended service conditions.

Comparison of Hydrostatic and Pneumatic Testing:


Hydrostatic Testing

Pneumatic Testing

Test pressure is normally 30% higher than the design pressure Test pressure is normally 10% higher than the design
pressure
Recommended for high pressure applications

Recommended only for low pressure applications

Test media (Water) used is not compressible by pressure


application

Test media (Air) used is compressible by pressure


application

Energy stored per unit volume of water under test pressure is


very negligible

Energy stored per unit volume of compressed air under


test pressure is very high

Needs thorough cleaning after test to eliminate moisture


especially for service which are reactive to moisture / fluids

Easy to clean after testing

Pressure Relief devices are recommended to control sudden


increase in pressure during testing

Pressure relief devices are must during test to ensure


no over pressurization

Chances of equipment/ Pipe / test apparatus


failures are very low

Chances of equipment/ Pipe / test apparatus


failures are high

Weight of equipment along with test medium as


water is high hence special attention should be given to floor
and supporting arrangements

Weight of equipment with test medium


as air is comparatively less

Needs verification and examination of joints and connections


before testing

Needs very careful checking of weld joints thoroughly


before testing

Test media can be reused or transferred to other place after


testing

Test media cannot be reused or transferred to other


place after testing

Skilled and semi-skilled personnel can carry out the test

Needs involvement of senior experienced staff to


monitor the test.

Recommended where large volumes are to be tested at same


time (example pipe lines )

If pipe lines are tested should be done with small


segmental lengths at a time.

Damages made by failures are less compared to failures in


pneumatic testing

Damages made by failures in testing are very huge and


extensive

Hydrotest is a regular day to day practice and safe procedure


and it can be followed in any work site

Needs special attention and safety precautions

Pressure changes finite amount by infinitesimal change in


volume

Pressure change proportional to volume change

Difficulties with Hydrostatic Testing:

Supply & disposal of water, disposal of fluid additives

Water leak can cause equipment damage

Freeze susceptibility

Structural support limitations

Contamination

Operational impacts process contaminant

Affect dry-out of internal refractory linings

Difficulties with Pneumatic Testing:


Pneumatic tests are potentially more dangerous than hydrostatic tests because of the higher level of potential energy
stored during compressing the gas. Care must be exercised to minimize the chance of brittle failure during testing by
initially assuring the system is suitable for pneumatic testing. Pneumatic tests could be performed only when at least one
of the following conditions exists:

When the systems are designed in such a way thet it cannot be filled with water.

When the systems are such that it is to be used in services where traces of the testing medium cannot be
tolerated.
Using a pneumatic test instead of hydrostatic requires approval from proper authority or body.

Test Pressure:
ASME Code B 31.3 provides the basis for test pressure. The minimum hydrostatic test pressure for metallic piping shall be
as per the following equation:
Pt=1.5*Pd*(St/Sd)
Here,
Pt=minimum test gauge pressure
Pd=internal design gauge pressure
St=allowable stress value at test temperature
Sd=allowable stress value at design temperature.
The maximum allowable value of St/Sd is 6.5
The pneumatic test pressure shall be as per the following equation: Pt=1.1*Pd
Normal Basis for Test Method Selection:
Normally the following basis is followed in process piping industry for selection of hydro or pneumatic tests.
1. If the fluid handled by piping system is liquid then the pipe must be hydro tested.
2. If the fluid handled is vapour or gas then the internal design pressure dictates the testing method. For pipe design
pressure 10 bar and above the pipe is hydrotested. For pipe design pressure below 10 bar pipe is pneumatically
tested.
3. If fluid handled is stream then hydrotesting is suggested.
4. If fluid handles is two-phase flow then hydrotesting is suggested. However for big size flare headers pneumatic
testing is performed.
Test Duration:
Normally every EPC company have their own standard for duration of tests. However the recommended practice is that a
QC inspector have to walk through the whole piping system and check for leaks. Every single length of piping, welds, bolted
connections shall be visually examined for any leakage. Duration of this activity varies with the span of piping system. For
larger piping system time taken for this activity is enough to clear the pressure test. In case of piping system having
smaller span, 1 hour time may be made as standard practice for hydrostatic testing. For Pneumatic test the test time is far
lesser.
Few important points to consider while hydrotesting:
The tower overhead lines which are normally hydro tested shall be decided by stress engineer group whether to hydro test
after erection or at grade, based on the capacity of standard clip available as per engineering specification for pipe
supports.

During hydrotest in case of big bore it should be decided first that line is to be hydrotested on rack or grade if
hydrotest is done on rack , hydrotest load should be considered in case of vapour lines while providing structure /
rack loading information.

S-ar putea să vă placă și