Documente Academic
Documente Profesional
Documente Cultură
MB101105-Nazib Faizal
Clauses that related to the payment obligation are in Table 1. PAM 2006 governs the payment in
clause 30. PWD 203A governs the payment in clause 28, and PWD DB governs payment in
clause 31, 36, 53, 55, and 57.
Table 1 Clauses that related to the payment obligation
N
o
1
Standard
Form
PAM 2006
PWD 203A
PWD DB
Clause
25
26
30
37
28
31
54
60
31
36
53
55
57
63
Description
Determination of contractors employment by employer
Determination of own employment by contractor
Certificates and payment
Performance bond
Payment to contractor and interim certificates
Final account and payment certificate
Payments upon termination
Payment to nominated sub-contractor or supplier
Default in payment of wages
Direct payments to contractors consultants
Interim payments
Effect of PDs certificates and payment by government
Advance payment
Payments upon termination
MB101105-Nazib Faizal
Comparison
N
o
1
Item
PAM 2006
PWD 203A
PWD DB
parties involves
1. Contractor
2. Superintending Officer(SO),
or SOs representatives
3. Employer
Stages
Stated in appendix
parties inv
1. Contra
2. Project
3. Employ
2
3
parties involves:
1. Contractor
2. Architect
3. Quantity Surveyor
4. Employer
Stages
Stated in appendix
No advance payment
No advance payment
Procedure:
1. Contractor submit a payment
application at the interim
claim interval as stated in the
Appendix
2. Architect and Quantity
consider and ascertain the
amount in 21 days
3. Architect issues the interim
certificates base on
consideration and certain
amount
4. Employer pay the contractor
base on interim certificates
issued by architect
21 days
Procedure:
1. Contractor shall complete the
work as in Appendix
2. Regarding to the complete
work, SO shall make
valuation of the complete
work in 14 days
3. SO issuing interim certificates
4. Government pays the
contractor base on interim
certificates
25% of the
sum
Procedure
1. Contra
interim
2. PD con
the am
3. PD iss
payme
4. Govern
contrac
certific
14 days
28 days
Stated in a
stated = 30
1. The va
proper
2. The am
of varia
instruc
(clause
3. The am
expend
sums e
(clause
4. The va
unfixed
to or ad
4
5
Procedure of interim
payment
Schedule of issuing
interim certificates
Schedule of interim
certificates payment
Contractors
obligation in applying
payment
7
8
Advance p
Stated in a
N
o
Item
PAM 2006
PWD 203A
PWD DB
5.
10
Procedure of
payment upon
completion
Wages of workmen
affects the final
intende
incorpo
The up
require
clause
Within
issuan
comple
defects
comple
(if any)
submit
the fina
detail t
PD pro
accoun
docum
contrac
If final
shall is
which c
sum
Final p
govern
contrac
not be
contrac
his obl
workm
1.
Wages of
be paid an
2.
3.
4.
N
o
Item
PAM 2006
PWD 203A
PWD DB
payment
11
Retention fund
under the
The Emplo
act 1969, T
provident F
any other
employme
been paid.
No retentio
governme
12
Payment for
liquidated damages
13
Payment upon
termination
If the contr
the works
completion
extended t
to clause 4
a certificat
the contra
intention o
impose liq
ascertaine
in appendi
Base on re
contract is
clause 50
be paid (in
amounts o
already be
payments
the contra
following:
a. The va
out up
termin
b. The am
respec
items
service
has be
perform
propor
N
o
Item
14
Performance bond
15
PAM 2006
PWD 203A
PWD DB
which
carried
c. The co
goods
for the
been d
contra
contra
accept
d. A sum
any ex
incurre
the exp
comple
works
expend
recove
payme
e. The re
protec
remov
site fac
termin
under
If the contr
any of his
contract an
remedied
this contra
shall be en
performan
partially.
The perfor
released o
contractor
of works.
Applied in
N
o
16
Item
PAM 2006
PWD 203A
PWD DB
third party
to the subcontractor/consultants
nominated sub
contractor/suppliers according to
interim certificates/final
certificates
Late payment by
employer/governmen
t
No provision
contractor
purpose o
consultant
the consul
irrevocable
for the ass
due to the
directly by
No provisi