Documente Academic
Documente Profesional
Documente Cultură
HelicalPile
TechnicalReferenceManual
TheinformationcontainedinthisdocumentistheintellectualpropertyofMagnumPiering,Inc.andis
disclosed solely for the purpose of providing design tools and guidance in specifying Magnum Piering
products. All material contained herein and designs based on the information herein should be
reviewed and approved by the Engineer of Record prior to construction. Copying, distributing, or
disclosingthisinformationforanypurposeotherthanprojectbiddingisexpresslyforbidden.
MagnumPiering,Inc.
6082SchumacherParkDrive
WestChester,OH45069
8008227437
www.magnumpiering.com
Table of Contents
SECTION 1000 INTRODUCTION
Introduction Letter from Dr. Howard Perko
Page
1000-1
1000-2
1000-3
1000-4
2000-1
2000-2
2000-4
2000-20
2000-25
2000-26
2000-45
2000-54
2000-86
2000-89
2000-90
2000-102
2000-103
2000-104
2000-109
3000-1
3000-2
3000-3
DESIGN CHARTS
3000-7
3000-8
3000-9
3000-12
3000-15
3000-18
3000-22
3000-26
TECHNICAL PAPERS
3000-32
3000-33
3000-44
3000-48
3000-56
3000-64
3000-84
3000-91
4000-1
SECTION 1000
INTRODUCTION
The Magnum Helical Pile Technical Reference Manual was developed specifically for architects,
geotechnical engineers, and structural engineers. It contains considerable details regarding the use and
specification of helical anchors and helical piles. The guide contains introductory information as well as
advanced concepts so that it may serve as a useful reference for the unfamiliar and the experienced.
Information regarding the pullout and bearing capacity of helical piles, corrosion rates, lateral resistance,
and connection to structures is provided herein. Sample details, plans, reports, inspections, and
specifications are included. Technical specifications for the Magnum Helical Pile product line are
supplied, as well as the test procedures and results used to obtain these specifications.
Helical piles and anchors have an established heritage of over 150 years and have been used to support
structures throughout the United States, Canada, Europe, Australia, Japan and many other countries of the
World. The frequency of their application for repairing existing foundations and for new foundations has
increased dramatically in the last 25 years. Their present popularity is due to a number of factors
including capacity determination through torque correlations, economics of rapid installation,
applicability to a wide range of soil and subsurface conditions, and the quality assurance of a factory
manufactured product.
There are presently over 50 different helical pile and anchor manufacturers throughout the world. Product
quality varies significantly between manufacturers. Depending on the requirements of a particular
project, an engineer or architect may specify minimum product quality standards such as hot-dip
galvanizing, minimum structural section modulus, and/or minimum number and size of helical bearing
plates. However, to ensure you are getting the best products available, it is imperative to specify a
Magnum Helical Piles.
Page 1000-1
Rev. 12-09
Page 1000-2
Rev. 12-09
800.822.7437 x 250
Copyright 2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 1000-3
Rev. 12-09
Page 1000-4
Rev. 12-09
QUALITY CONTROL
Along with ICC-ES evaluation and quality standards, Magnums manufacturing
quality control system is in substantial compliance with ISO 9001: 2008 certified.
Due to the high level of quality control, our customers frequently comment that
Magnums products meet or exceed manufacturer ratings more often than other
manufacturers products.
Page 1000-5
Rev. 12-09
SECTION 2000
SPECIFYING HELICAL PILES
Guide Specifications
Page 2000-1
Rev. 12-09
Magnum Piering
Model Specifications Helical Piles and Helical Anchors
Minimum Depth
For axial compression, the minimum depth is the frost depth, depth to planned bearing
stratum, depth of unknown fill, depth of the active zone in expansive soils, or depth of soft
soils, whichever is greater, as applicable. For axial tension, the minimum depth is 5 times the
maximum helical bearing plate diameter in clay soils, 10 times the maximum helical bearing
plate diameter in sand soils, or the depth of the bearing stratum, whichever is greater.
Page 2000-2
Rev. 12-09
Magnum Piering
Model Specifications Helical Piles and Helical Anchors
The planned length is specified when the Contract payment is based on unit length so that
all Contractors bid the same length. A planned length specification is not necessary when
payment terms will be based upon a per unit basis where one unit is a Helical Pile or Helical
Anchor. In order to ensure similar bids, planned length might be used with a planned helical
bearing plate configuration specification.
Special Considerations
Helical Piles and Helical Anchors can penetrate most soil and sedimentary bedrock
stratum provided the Standard Penetration Test blow count is less than 50 blows/6 inch
increment. Installation of Helical Piles and Helical Anchors is difficult in soils with blow count
greater than 50/6 inches or soils with excessive cobble, boulders, and or large debris.
Dual cutting edge helical bearing plates are recommended on sites with occasional
cobble, debris, or thin layers of cemented material. Dual cutting edge (DCE) helical bearing
plates are also recommended for projects using hand installation equipment because they tend
to track better and require less crowd for proper installation.
A corrosion engineer should be consulted and special corrosion protection should be used
in soils with resistivity below 2,000 ohm-cm, with pH below 5, with organic content above 100
ppm, in mine or industrial waste, or other severely corrosive soils.
Page 2000-3
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
SECTION 31 66 13
HELICAL PILES AND HELICAL ANCHORS
PART 1 GENERAL
1.01
Description
This work pertains to furnishing and installing Helical Piles, Helical Anchors, and Bracket
Assemblies shown in the Contract in accordance with the Drawings and this
specification. Each Helical Pile and Helical Anchor shall be installed at the location and
to the elevation, minimum length, installation torque, and allowable capacities shown on
the Plans or as established. This work also pertains to load testing and pre-loading
Helical Piles and Helical Anchors (if required on the Drawings).
1.02
Related Work
This specification is based on nationally recognized codes and standards including the
references listed below. In case of a conflict between the reference and this
specification, this specification shall govern.
A.
B.
C.
Page 2000-4
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
D.
E.
1.04
Definitions
A.
Helical Pile: Manufactured steel foundation with one or more helical bearing
plates that is rotated into the ground to support structures.
B.
Helical Anchor: Same as a Helical Pile. Term generally used when axial tension
is the primary service load.
C.
D.
E.
Lead Section: The first section of a Helical Pile or Helical Anchor to enter the
ground. Lead Sections consist of a central shaft with a tapered end and one or
more helical bearing plates affixed to the shaft.
F.
Extension Section: Helical Pile or Helical Anchor sections that follow the Lead
Section into the ground and extend the Helical Lead to the appropriate depth.
Extension Sections consist of a central shaft and may have helical bearing plates
affixed to the shaft.
G.
Brackets: Cap plate, angle, thread bar, or other termination device that is bolted
or welded to the end of a Helical Pile or Helical Anchor after completion of
installation to facilitate attachment to structures or embedment in cast-in-place
concrete.
H.
Augering: Rotation of the shaft with little or no advancement. It can occur when
the helical bearing plates pass from a relatively soft material into a comparatively
hard material. Augering can also result from insufficient crowd or downward
pressure during installation. In some cases, augering may be (temporarily)
necessary in order to grind through an obstruction.
I.
Pile Design Professional: Individual or firm responsible for the design of Helical
Piles, Helical Anchors, and Brackets.
31 66 15-2
Revised 11/10/09
Page 2000-5
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
1.05
Qualifications
A.
Due to the special requirements for manufacture and quality control of Helical
Piles, Helical Anchors, and Brackets, all Helical Piles, Helical Anchors, and
Brackets shall be obtained from Magnum Piering, Inc.
A request to substitute any other manufactured Helical Pile and Helical Anchor
products for use on this project must be submitted to the Engineer for review not
less that seven (7) calendar days prior to the bid date. The request must
include:
1.
2.
3.
4.
B.
A product catalog and all necessary technical data sufficient to qualify the
proposed product substitution.
Evidence showing manufacturer has at least ten (10) years experience in
the design and manufacture of Helical Piles and Helical Anchors.
Current ICC-ES product evaluation report or complete description of
product testing and engineering calculations used to assess product
capacity.
Current ISO9001 certificate or manufacturing quality assurance program
documentation showing methods used to asses and maintain product
quality.
Due to the special requirements for installation of Helical Piles, Helical Anchors,
and Brackets, all Helical Piles, Helical Anchors, and Brackets shall be installed
by an organization specializing in the installation of those products. Contractor
shall be an authorized Magnum Piering Installer and shall have completed
training from Magnum Piering, Inc. in the proper methods of installation of Helical
Piles and Helical Anchors and the mounting of Brackets.
Any Contractor desiring to bid as the Helical Pile and Helical Anchor installer for
this project that is not trained and authorized by Magnum Piering, Inc. shall
submit a request to the Engineer for review not less than seven (7) calendar
days prior to the bid date. The request must include:
1.
2.
3.
4.
5.
Page 2000-6
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
C.
Due to the special requirements for design of Helical Piles, Helical Anchors, and
Brackets, all Helical Piles, Helical Anchors, and Brackets shall be designed by
Magnum Geo-Solutions, LLC.
Contractors desiring to use other Pile Design Professionals shall submit a
request to the Engineer for review not less than seven (7) calendar days prior to
the bid date. The request must include:
1.
2.
3.
4.
D.
Prior to bidding by any installer that is not trained and authorized by Magnum
Piering, Inc., using a manufactured Helical Pile and Helical Anchor system that is
not produced by Magnum Piering, Inc., or using a Pile Design Professional that
is not Magnum Geo-Solutions, LLC, written approval to bid must be received
from the Engineer. Engineer shall grant approval based on compliance with
specific criteria herein. The Engineers decision is final.
1.06
Submittals
Contractor shall prepare and submit to the Engineer for review and approval,
Shop Drawings and specifications for the Helical Piles and Helical Anchors
intended for use on the project at least 14 calendar days prior to planned start of
installation. The Shop Drawings shall include the following:
1.
2.
3.
4.
5.
6.
7.
8.
Page 2000-7
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
9.
B.
C.
D.
If load tests or proof load tests are required on the Drawings, the Contractor shall
submit for review and acceptance the proposed load testing procedure. The
proposal shall provide the minimum following information:
1.
2.
3.
4.
5.
E.
F.
Work shall not begin until all the submittals have been received and approved by
the Engineer. The Contractor shall allow the Engineer a reasonable number of
days to review, comment, and return the submittal package after a complete set
has been received. All costs associated with incomplete or unacceptable
submittals shall be the responsibility of the Contractor.
31 66 15-5
Revised 11/10/09
Page 2000-8
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
1.07
A.
All Helical Pile, Helical Anchor, and Bracket Assemblies shall be free of structural
defects and protected from damage. Store Helical Piles, Helical Anchors, and
Bracket Assemblies on wood pallets or supports to keep from contacting the
ground. Damage to materials shall be cause for rejection.
PART 2 PRODUCTS
2.01
A.
All Helical Pile, Helical Anchor, and Bracket Assemblies shall be manufactured
by Magnum Piering, Inc. Unless noted otherwise, it is the Contractors Pile
Design Professionals responsibility to select the appropriate size and type of
Helical Piles, Helical Anchors, and Brackets to support the design loads shown
on the Drawings. These specifications and the Drawings provide minimum
requirements to aid the Contractor in making appropriate materials selections.
The size and number of helical bearing plates must be such that the Helical Piles
and Helical Anchors achieve the appropriate torque and capacity in the soils at
the site within the minimum and maximum length requirements. Failure to
achieve proper torque and capacity shall result in Contractor replacing Helical
Piles and Helical Anchors as appropriate to support the required loads. All
material replacements shall be acceptable to Engineer.
B.
The design strength of the helical bearing plates, shaft connections, Brackets,
and the pile shaft itself shall be sufficient to support the design loads specified on
the Drawings times appropriate service load factors. In addition, all Helical Piles
and Helical Anchors shall be manufactured to the following criteria.
1.
2.
Page 2000-9
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
3.
4.
5.
6.
7.
8.
C.
Helical Piles and Helical Anchors shall be fitted with a manufactured Bracket that
facilitates connection to the structure. Brackets shall be rated for the design
loads shown on the Drawings. Brackets shall be affixed to the end of Helical
Piles and Helical Anchors via bolts, plug welds, or continuous penetration welds
meeting the requirements for shaft connections given previously in these
specifications.
31 66 15-7
Revised 11/10/09
Page 2000-10
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
PART 3 EXECUTION
3.01
Examination
A.
Contractor shall take reasonable effort to locate all utilities and structures above
and underground in the area of the Work. Contractor shall pot hole to determine
the exact location of underground utilities and buried structures within a distance
from a Helical Pile or Helical Anchor equal to three times the maximum helix
diameter. Contractor is responsible for protection of utilities and structures
shown on the Drawings. Costs of avoiding, relocating, or repair of utilities not
shown on Drawings shall be paid by Owner as extra work.
B.
Contractor shall review Drawings and soil borings in the Contract Documents to
determine subsurface conditions for sizing and installation of Helical Piles and
Helical Anchors. In addition, Contractor shall make a site visit to observe
conditions prior to the start of Work.
C.
Contractor shall notify Engineer of any condition that would affect proper
installation of Helical Piles and Helical Anchors immediately after the condition is
revealed. Contractor shall halt installation work until the matter can be resolved
upon mutual satisfaction of Contractor, Owner, and Engineer. Costs associated
with construction delays, product substitutions, pile or anchor relocations, or
other related costs shall be the responsibility of the Owner if the result of an
unforeseen condition that could not be inferred by a reasonable Contractor from
the Drawings and Construction Documents.
D.
If the number and size of helical bearing plates required for the project is not
shown on the working drawings, the contractor shall have the option of
performing subsurface tests using methods subject to the review and acceptance
of the Owner. The data collected along with other information pertinent to the
project site shall be used to determine the required helical bearing plate
configuration.
E.
F.
3.02
Installation Equipment
31 66 15-8
Revised 11/10/09
Page 2000-11
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
A.
Torque Motor: Helical Piles and Helical Anchors should be installed with high
torque, low RPM torque motors, which allow the helical plates to advance with
minimal soil disturbance. The torque motor shall be hydraulic power driven with
clockwise and counter-clockwise rotation capability. The torque motor shall be
adjustable with respect to revolutions per minute during installation. Percussion
drilling equipment shall not be permitted. The torque motor shall have torque
capacity equal to or greater than the minimum final installation torque required
for the project. The connection between the torque motor and the installation rig
shall have no more than two pivot hinges oriented 90 degrees from each other.
Additional hinges promote wobbling and affect lateral capacity.
B.
C.
Drive Tool:
The connection between the torque motor and Helical Pile and
Helical Anchor shall be in-line, straight, and rigid, and shall consist of a
hexagonal, square, or round kelly bar adapter and helical shaft socket. To
ensure proper fit, the drive tool shall be manufactured by the Helical Pile
manufacturer and used in accordance with the manufacturers installation
instructions.
D.
Connection Pins: The central shaft of the Helical Pile or Helical Anchor shall be
attached to the drive tool by ASME SAE Grade 8 smooth tapered pins matching
the number and diameter of the specified shaft connection bolts. The connection
pins should be maintained in good condition and safe to operate at all times.
The pins should be regularly inspected for wear and deformation. Pins should
be replaced with identical pins when worn or damaged.
E.
3.03
Installation Procedures
A.
Unless shown on the Drawings, the number and size of helical blades shall be
determined by the Contractors Pile Design Professional in order to achieve the
31 66 15-9
Revised 11/10/09
Page 2000-12
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
required torque and tensile/bearing capacity for the soil conditions at the site.
The ratio of design load to the total area of the helical bearing plates shall not
exceed the Allowable Bearing Capacity.
B.
Connect the lead section to the Torque Motor using the Drive Tool and
Connection Pins. Position and align the Lead Section at the location and to the
inclination shown on the Drawings and crowd the pilot point into the soil.
Advance the Lead Section and continue to add Extension Sections to achieve
the Termination Criteria. All sections shall be advanced into the soil in a smooth,
continuous manner at a rate of rotation between 10 and 40 revolutions per
minute. Snug tight all coupling bolts.
C.
Constant axial force (crowd) shall be applied while rotating Helical Piles and
Helical Anchors into the ground. The crowd applied shall be sufficient to ensure
that the Helical Pile and Helical Anchor advances into the ground a distance
equal to at least 80% of the blade pitch per revolution during normal
advancement.
D.
The torsional strength rating of the Helical Pile or Helical Anchor shall not be
exceeded during installation. For Magnum Piering products, the torsional
strength ratings are listed below.
1.
2.
3.
4.
5.
6.
7.
E.
Bolt hole elongation due to torsion of the shaft of a Helical Anchor at the drive
tool shall be limited to inch. Helical Anchors with bolt hole damage exceeding
this criterion shall be uninstalled, removed, and discarded.
F.
When the Termination Criteria of a Helical Pile or Helical Anchor is obtained, the
Contractor shall adjust the elevation of the top end of the shaft to the elevation
shown on the Drawings or as required. This adjustment may consist of cutting
off the top of the shaft and drilling new holes to facilitate installation of Brackets
to the orientation shown on the Drawings. Alternatively, installation may
continue until the final elevation and orientation of the pre-drilled bolt holes are in
alignment. Contractor shall not reverse the direction of torque and back-out the
Helical Pile or Helical Anchor to obtain the final elevation.
G.
H.
All Helical Pile and Helical Anchor components including the shaft and Bracket
shall be isolated from making a direct electrical contact with any concrete
31 66 15-10
Revised 11/10/09
Page 2000-13
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
reinforcing bars or other non-galvanized metal objects since these contacts may
alter corrosion rates.
I.
3.04
Termination Criteria
A.
Helical Piles and Helical Anchors shall be advanced until all of the following
criteria are satisfied.
B.
1.
2.
If the torsional strength rating of the Helical Pile or Helical Anchor and/or the
maximum torque of the installation equipment has been reached or Augering
occurs prior to achieving the minimum depth required, the Contractor shall have
the following options:
1.
Terminate the installation at the depth obtained subject to the review and
acceptance of the Engineer and Owner.
2.
Remove the Helical Pile or Helical Anchor and install a new one with
fewer and/or smaller diameter helical bearing plates or with dual cutting
edge helical bearing plates. The new helical configuration shall be
subject to review and acceptance of the Engineer and Owner.
3.
Remove the Helical Pile or Helical Anchor and pre-drill a 4-inch diameter
pilot hole in the same location and reinstall the anchor/pile.
31 66 15-11
Revised 11/10/09
Page 2000-14
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
C.
4.
If the obstruction is shallow, remove the Helical Pile or Helical Anchor and
remove the obstruction by surface excavation. Backfill and compact the
resulting excavation and reinstall the anchor/pile.
5.
Remove the Helical Pile or Helical Anchor and relocate 1-foot to either
side of the installation location subject to the review and acceptance of
Engineer and Owner.
6.
7.
Remove the Helical Pile or Helical Anchor and sever the uppermost
helical bearing plate from the Lead Section if more than one helical
bearing plate is in use, or reshape the helical bearing plates to create the
patented Magnum dual cutting edge shape by cutting with a band saw.
Reinstall the anchor or pile with revised helical bearing plate
configuration.
If the final installation torque is not achieved at the contract length, the
Contractor shall have the following options:
1.
Until the maximum depth is achieved (if any), install the Helical Pile or
Helical Anchor deeper using additional Extension Sections.
2.
Remove the Helical Pile or Helical Anchor and install a new one with
additional and/or larger diameter helical bearing plates.
3.
Decrease the rated load capacity of the Helical Pile or Helical Anchor and
install additional Helical Piles or Helical Anchors. The rated capacity and
additional unit location shall be subject to the review and acceptance of
the Engineer and Owner.
3.05
Allowable Tolerances
A.
Helical Piles and Helical Anchors shall be installed as close to the specified
installation and orientation angles as possible. Tolerance for departure from
installation and orientation angles shall be +/- 5 degrees.
B.
Helical Piles, Helical Anchors, and Bracket Assemblies shall be installed at the
locations and to the elevations shown on the Plans. Tolerances for Bracket
Assembly placement shall be +/- 1 inch in both directions perpendicular to the
shaft and +/- 1/4 inch in a direction parallel with the shaft unless otherwise
specified.
3.06
Quality Assurance
31 66 15-12
Revised 11/10/09
Page 2000-15
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
A.
The Contractor shall provide the Engineer and Owner copies of installation
records within 48 hours after each installation is completed. These installation
records shall include, but are not limited to, the following information:
1.
2.
3.
4.
5.
6.
7.
Type and configuration of Lead Section with length of shaft and number
and size of helical bearing plates
8.
Type and configuration of Extension Sections with length and number and
size of helical bearing plates, if any
9.
10.
11.
12.
13.
14.
15.
16.
B.
Unless specified otherwise on the Drawings or by local codes, the Engineer, the
Pile Design Professional, or an inspection agency accepted by the Engineer
shall observe and document at least 10 percent of Helical Pile and Helical
Anchor installations.
3.07
Load Testing
A.
Page 2000-16
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
1.
2.
3.
4.
5.
6.
7.
B.
7.
C.
Contractor shall perform the number of proof load tests shown on the
Drawings, if any
Proof load tests shall be performed following the procedure described in
ASTM D3689 specifications
Proof load tests shall be observed and documented by the Engineer
Unless otherwise shown on the Drawings, the maximum test load shall be
150% of the allowable load shown on the Drawings
The locations of Helical Anchors to be tested shall be determined by the
Contractor, unless shown on the Drawings
Installation methods, procedures, equipment, products, and final
installation torque shall be identical to the production anchors to the
extent practical except where otherwise approved by the Owner or
Engineer
A proof load test shall be deemed acceptable provided the maximum test
load is applied without helical anchor failure. Failure is when continuous
jacking is required to maintain the load.
Contractor shall perform the number of lateral load tests shown on the
Drawings, if any
Lateral load tests shall be performed following the free head procedure
described in ASTM D3966 specifications
Lateral load tests shall be observed and documented by the Engineer
Unless otherwise shown on the Drawings, the maximum test load shall be
200% of the allowable lateral load shown on the Drawings
31 66 15-14
Revised 11/10/09
Page 2000-17
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
5.
6.
7.
D.
If a load test fails the forgoing acceptance criteria, the Contractor shall modify the
Helical Pile or Helical Anchor design and/or installation methods and retest the
modified pile or anchor, as directed by the Owner or Engineer. These
modifications include, but are not limited to, de-rating the load capacity,
modifying the installation methods and equipment, increasing the minimum final
installation torque, changing the helical configuration, or changing the product
(i.e., duty). Modifications that require changes to the structure shall have prior
review and acceptance of the Owner.
Any modifications of design or
construction procedures, and any retesting required shall be at the Contractors
expense.
E.
The Contractor shall provide the Owner and Engineer copies of load test reports
confirming configuration and construction details within 1 week after completion
of the load tests. This written documentation will either confirm the load capacity
as required on the working drawings or propose changes based upon the results
of the tests. At a minimum, the documentation shall include:
1.
2.
3.
4.
5.
6.
7.
8.
9.
31 66 15-15
Revised 11/10/09
Page 2000-18
Rev. 12-09
Magnum Piering
CSI Format Model Specifications for Magnum Helical Piles and Helical Anchors
10.
A.
Per Unit: Payment will be at a per unit price with one unit consisting of the labor,
equipment, and materials required to furnish and install a Helical Pile or Helical
Anchor and associated Bracket at the location and to the elevation, orientation,
inclination, length, and capacity shown in the Drawings. Unless established in
the Contract, there shall be no payment for additional Helical Pile or Helical
Anchor length.
B.
Per Load Test: Payment will be at a per unit price with one unit consisting of the
labor, equipment, and materials required to perform each required load test.
END OF SPECIFICATION
NOTE: Because Magnum has a policy of continuous product improvement, we reserve
the right to change design and specifications without notice.
Printed in U.S.A. Copyright 2009 Magnum Piering, Inc., West Chester, OH
31 66 15-16
Revised 11/10/09
Page 2000-19
Rev. 12-09
Magnum Piering
DOT Format Model Specifications for helical Piles and helical Anchors
SECTION 552
HELICAL ANCHORS AND HELICAL PILES
DESCRIPTION
552.01 This work pertains to furnishing and installing helical anchors and helical piles shown in the Contract in
accordance with the Drawings and these specifications. Each helical anchor and helical pile shall be installed at the
location and to the elevation, minimum length, and installation torque indicative of the design allowable capacities
shown on the Plans or as established. In addition, helical piles and helical anchors shall be load tested and posttensioned as specified. These specifications are to be used in conjunction with Federal Highway or State
Department of Transportation Standard Specifications for Road and Bridge Construction.
MATERIALS
552.02 Guarantees and Insurance
Helical anchor and helical pile manufacturer shall furnish a guarantee for a period of ten (10) years from date of
delivery against defects due to manufacturing of helical anchors, helical piles, and bracket assemblies. Helical
anchor and helical pile manufacturer must carry product liability insurance. Refer to General Conditions for
additional insurance requirements.
552.03 Prequalification Requirements
Due to the special requirements for design and manufacture of helical anchors and helical piles, and the
requirements for proper performance of the structural system, as a whole, helical anchors and helical piles shall be
obtained from an organization specializing in the design and manufacture of helical anchors and helical piles. The
following manufacturers products are prequalified for use on this project:
Magnum Piering, Inc.
A request for using any other manufactured helical anchor and helical pile products desired for use on this project
must be submitted to the Project Manager and Foundation Engineer for review not less that seven (7) calendar days
prior to the bid date. The request must include:
1.
2.
3.
Prior to bidding by any installer using a manufactured helical anchor and helical pile system that is not prequalified,
written approval to bid must be received from the Project Manager upon consultation with the Foundation Engineer.
Project Manager shall grant approval based on compliance with specific criteria herein. The Project Managers
decision is final.
552.04 Minimum Material Requirements
Helical anchor and helical piles shall have a tubular round shaft and shall have the required number of helical blades
so as to provide for adequate load carrying capacity. The strength of the helical blades, shaft connections, bracket
assembly, and the shaft itself shall be sufficient to support the design loads specified on the Plans. Helical anchors,
helical piles, and bracket assemblies shall be designed in accordance with modern standards for steel construction.
Design capacity shall take into account corrosion over a 75 year design lifespan. Helical piles and helical anchors
shall be protected from corrosion by hot-dip galvanizing per ASTM A123 or A153, as applicable.
The helical anchor and helical pile shaft connections shall be in-line, straight and rigid and shall have a maximum
tolerable slack of 1/16-inch or as acceptable to Foundation Engineer. Bolts used to join helical anchor and helical
pile sections at the shaft connections shall be zinc coated or galvanized and shall be the grade and size specified by
the helical anchor and helical pile manufacturer. All helical anchor and helical pile bolts shall be securely snug
552-1
Revised 11/10/09
Page 2000-20
Rev. 12-09
Magnum Piering
DOT Format Model Specifications for helical Piles and helical Anchors
tightened.
Helical anchors shall be fitted with an adjustable bracket assembly that facilitates both post-tensioning and proof
load testing. Helical piles shall be fitted with a manufactured bracket assembly rated for the design loads shown on
the Plans and the strength of the concrete or other structure they support.
MATERIAL SELECTION
552.05 Design and Application
A list of all helical anchor, helical pile, and bracket materials to be used on this project shall be submitted with the
bid package. The list shall clearly state the allowable mechanical capacity of all materials. The list shall be certified
by the manufacturers engineer. It is the helical anchor and helical pile installation contractors responsibility to
select the appropriate size and type of helical anchors, helical piles, and bracket assemblies. These specifications
and the Plans provide minimum requirements to aid the contractor in making appropriate materials selections. The
size and number of helical blades must be such that the helical anchors and helical piles achieve the appropriate
torque and capacity in the soils at this site within the minimum and maximum length requirements. Failure to
achieve proper torque and capacity shall result in contractor replacing helical anchors and helical piles as
appropriate to support the required loads. All installation procedures, materials, and replacements shall be
acceptable to Foundation Engineer.
CONSTRUCTION REQUIREMENTS
552.06 Warranty and Insurance
Helical anchor and helical pile installation contractor shall furnish a warranty for a period of ten (10) years from date
of installation against defects due to workmanship on installation of helical anchor, helical pile, and bracket
assemblies. Helical anchor and helical pile installer must carry general liability insurance. Refer to General
Conditions for additional insurance requirements.
552.07 Prequalification Requirements
Due to the special requirements for installation of helical anchors and helical piles, and the requirements for proper
performance of the structural system, as a whole, helical anchors, helical piles, and bracket assemblies shall be
installed by an organization specializing in the installation of helical anchors and helical piles. The following
installation contractors are prequalified for work on this project:
< Insert Name of Authorized Magnum Installer Here >
Any other contractor desiring to bid as the helical anchor and helical pile installer for this project shall submit a
request to the Project Manager and Foundation Engineer for review not less than seven (7) calendar days prior to the
bid date. The request must include:
1.
2.
3.
4.
Prior to bidding by any installer that is not prequalified, written approval to bid must be received from the Project
Manager upon consultation with the Foundation Engineer. Project Manager shall grant approval based on
compliance with specific criteria herein. The Project Managers decision is final.
552.08 Installation Equipment
Each helical anchor and helical pile shall be advanced into the ground by application of rotational force using a
hydraulic torque converter. Installation equipment shall include a direct means of determining the installation
torque being applied to the helical anchor and helical pile. Where post-tensioning and capacity testing are required,
552-2
Revised 11/10/09
Page 2000-21
Rev. 12-09
Magnum Piering
DOT Format Model Specifications for helical Piles and helical Anchors
installation equipment also shall include a means for applying and measuring loads and deflections of helical piles
and helical anchors. Acceptable methods of post-tensioning and load testing include a calibrated hydraulic jack or
other means acceptable to the Foundation Engineer. Current evidence of calibration of Contractors load testing,
post-tensioning, and torque monitoring equipment shall be provided upon request of Foundation Engineer.
552.09 Equipment and Material Acceptance
All helical anchor and helical pile installation equipment and materials shall be acceptable to the Foundation
Engineer prior to delivery to the site. Acceptance will be based upon submission of records and data, as discussed in
Sections 552.02 through 552.08. Once accepted, changes in installation equipment and materials will not be
permitted without additional acceptance, and will be considered only after Contractor has submitted any and all
information requested by Foundation Engineer.
552.10 Installing helical Anchors and helical Piles
Loads shown on the Plans are unfactored design loads. A minimum factor of safety of 2.0 shall be used to
determine the required ultimate tensile capacity of the helical anchors and compressive capacity of helical piles with
regard to their interaction with soil and bedrock. Helical anchor and helical pile capacity in soil and on bedrock
depends on the geometric configuration of the helical blades about the lead section and the subsurface conditions.
The torque applied during installation provides an indirect verification of axial capacity. Manufacturers
recommendations should be followed regarding the torque and the tensile/bearing capacity relationship for the
particular helical anchor and helical piles selected. The number and size of blades shall be determined by the
Contractor so as to achieve the required torque and tensile/bearing capacity for the soil conditions at the site.
However, the ratio of design allowable capacity to the total area of the helical blades shall not exceed the allowable
subsurface material bearing capacity.
Helical anchors and helical piles shall be advanced into the ground until the required torque is achieved to
accommodate the ultimate tensile and bearing capacity plus an additional distance to ensure proper embedment. For
the helical anchors, the embedment length shall be achieved by continuing advancement while maintaining or
exceeding the required torque for a distance of at least three (3) feet. For the helical piles on bedrock, the
embedment length shall be that required to achieve practical refusal.
Constant normal pressure shall be applied while screwing helical anchors and helical piles into the ground. The
pressure applied shall be sufficient to ensure that, during each revolution, the helical anchor and helical pile progress
into the ground a distance equal to at least 80% of the blade pitch. Rate of helical anchor and helical pile rotation
shall not exceed 30 revolutions per minute.
The minimum and maximum length of the helical anchors shall be as shown on the Plans. The minimum length of
the helical piles shall be such that the lowest helical bearing plate is at or below the elevation of the bearing stratum
shown in the soil borings contained in the Geotechnical Report. The minimum depth of helical anchors below
ground surface shall be 5 times the largest helix diameter. The minimum length of helical anchors behind a shoring
or earth retention structure shall be this distance plus the distance behind the wall facing to the soil plane depicting
the active earth pressure.
Helical anchors and helical piles shall be installed as close to the specified installation angle as possible. Tolerance
for departure from installation angle shall be 5 degrees unless noted otherwise on the Plans.
Helical anchors, helical piles, and bracket assemblies shall be installed at the locations shown on the Plans.
Tolerances for bracket assembly placement shall be 1 in both directions perpendicular to the anchor shaft and in
a direction parallel with the anchor shaft unless otherwise specified.
All helical anchor and helical pile components including the shaft and bracket assembly shall be isolated from
making a direct electrical contact with any concrete reinforcing bars or other non-galvanized metal objects since
these contacts may alter corrosion rates.
552-3
Revised 11/10/09
Page 2000-22
Rev. 12-09
Magnum Piering
DOT Format Model Specifications for helical Piles and helical Anchors
552-4
Revised 11/10/09
Page 2000-23
Rev. 12-09
Magnum Piering
DOT Format Model Specifications for helical Piles and helical Anchors
Pay Unit
per foot
per foot
per test
Compensation will not be made for installation of helical anchors and helical piles where static load capacity tests
failed to meet the required criteria. It is the Contractors responsibility to select, furnish, and install the helical
anchors and helical piles with the appropriate number and size of helical blades so as to achieve successful static
load tests, to anticipate the required length of the helical anchor and helical piles, and include these costs in the bid
price.
552-5
Revised 11/10/09
Page 2000-24
Rev. 12-09
Page 2000-25
Rev. 12-09
LIST OF DRAWINGS
Page
2000-26
2000-28
2000-31
2000-34
2000-37
2000-39
2000-43
Page 2000-26
Rev. 12-09
Page 2000-27
Rev. 12-09
Page 2000-28
Rev. 12-09
Page 2000-29
Rev. 12-09
Page 2000-30
Rev. 12-09
Page 2000-31
Rev. 12-09
Page 2000-32
Rev. 12-09
Page 2000-33
Rev. 12-09
Page 2000-34
Rev. 12-09
Page 2000-35
Rev. 12-09
Page 2000-36
Rev. 12-09
Page 2000-37
Rev. 12-09
Page 2000-38
Rev. 12-09
Page 2000-39
Rev. 12-09
Page 2000-40
Rev. 12-09
Page 2000-41
Rev. 12-09
Page 2000-42
Rev. 12-09
Page 2000-43
Rev. 12-09
Page 2000-44
Rev. 12-09
LIST OF DRAWINGS
Page
2000-45
2000-49
Page 2000-45
Rev. 12-09
Page 2000-46
Rev. 12-09
Page 2000-47
Rev. 12-09
Page 2000-48
Rev. 12-09
Page 2000-49
Rev. 12-09
Page 2000-50
Rev. 12-09
Page 2000-51
Rev. 12-09
Page 2000-52
Rev. 12-09
Page 2000-53
Rev. 12-09
LIST OF DRAWINGS
Page
2000-54
2000-57
2000-59
2000-61
2000-63
2000-68
2000-70
2000-71
2000-72
2000-73
2000-74
CIP Walls with Structural Floor in Expansive Soil Area for Residence
2000-76
2000-78
2000-80
2000-82
Page 2000-54
2000-84
Rev. 12-09
Page 2000-55
Rev. 12-09
Page 2000-56
Rev. 12-09
Page 2000-57
Rev. 12-09
Page 2000-58
Rev. 12-09
Page 2000-59
Rev. 12-09
Page 2000-60
Rev. 12-09
Page 2000-61
Rev. 12-09
Page 2000-62
Rev. 12-09
Page 2000-63
Rev. 12-09
Page 2000-64
Rev. 12-09
Page 2000-65
Rev. 12-09
Page 2000-66
Rev. 12-09
Page 2000-67
Rev. 12-09
Page 2000-68
Rev. 12-09
Page 2000-69
Rev. 12-09
Page 2000-70
Rev. 12-09
Page 2000-71
Rev. 12-09
Page 2000-72
Rev. 12-09
Page 2000-73
Rev. 12-09
Page 2000-74
Rev. 12-09
Page 2000-75
Rev. 12-09
Page 2000-76
Rev. 12-09
Page 2000-77
Rev. 12-09
Page 2000-78
Rev. 12-09
Page 2000-79
Rev. 12-09
Page 2000-80
Rev. 12-09
Page 2000-81
Rev. 12-09
Page 2000-82
Rev. 12-09
Page 2000-83
Rev. 12-09
Page 2000-84
Rev. 12-09
Page 2000-85
Rev. 12-09
LIST OF DRAWINGS
Page
2000-86
2000-87
Page 2000-86
Rev. 12-09
Page 2000-87
Rev. 12-09
Page 2000-88
Rev. 12-09
Page 2000-89
Rev. 12-09
This letter presents the results of our Soils and Foundation Investigation for the
proposed four-story, stair tower addition and the masonry portal addition to Saint Joseph
Seminary, in Denver, Colorado. The purpose of this investigation was to evaluate
subsurface conditions at the site, assist the Structural Engineer in foundation design and
provide foundation, slab-on-grade and subsurface drainage recommendations for the
proposed construction. Our recommendations were developed based on data from our
field and laboratory investigations, experience with similar projects, and our
understanding of the proposed construction.
Site Conditions
Saint Joseph Seminary is located between East Tennessee Avenue and East Texas
Avenue and between South Main Street and South Rose Street in Denver, Colorado
(Fig.1). The Seminary consists of several buildings. The additions will be constructed to
the Catholic Pastoral Center building which is located in the south portion of the site and
was built around 1956. We understand the existing building is founded on footings
reportedly penetrating 6 inches into the underlying bedrock. Interior building columns
are founded on shallow piers. The building has a full basement with slab-on-grade
construction. Areas surrounding the building are irrigated grass with some concrete
sidewalks and asphalt pavement. The site slopes gradually away from the building on all
sides. An approximately 7 feet deep areaway runs along the south side, outside of the
existing building, and has an underground service tunnel beneath it. The existing
building is a concrete block structure with brick veneer. We observed no cracks in the
walls of the existing building and basement floor slabs and slab bearing partition walls
showed no signs of distress. Representatives from the Archdiocese of Colorado reported
no history of water problems in the basement area. There is no knowledge of a soil report
for the existing building.
Page 2000-90
Rev. 12-09
Proposed Construction
The existing entryway and stairway at the north side of the existing building will
be demolished and a new four-story stair tower constructed in its place. Information
provided by the Structural Engineer indicates the stair tower addition will be supported
by the existing footing foundations and four new helix piers underpinning the existing
grade beams. We were informed that the existing entryway and stairway are founded on
footing pads with 26 x 6 dimensions. The Structural Engineer estimated there is
currently about 15,000 psf footing pressure on each footing pad and the footing pressure
would be increased to about 17,000 psf after construction of the new stair tower. The
Structural Engineer plans to use helix piers to carry the additional loads and control the
new loads on the existing footings lower than the existing loads.
A masonry portal addition will be built on the south side of the existing building.
The portal will be separate from the existing building and connected only with horizontal
cross members. The Structural Engineer plans to integrate the portal with the existing
areaway below-grade wall to increase lateral resistance of the wall. It is planned that the
portal be founded on drilled piers penetrating the bedrock.
We anticipate that the new additions will be constructed using concrete masonry
units with brick veneer. Some site grading and extensive repaving will be performed
surrounding the additions. A representative from the Archdiocese of Colorado has
informed us that they do not require recommendations regarding the repaving work.
Subsurface Conditions
Subsurface conditions were investigated by drilling one exploratory boring in the
area of each proposed addition to depths of 25 and 30 feet. Locations of the exploratory
borings are shown on Fig. 1. Graphic logs of the soils and bedrock found in our borings
and results of field penetration resistance tests are shown in Figs. 2 and 3. Soil and
bedrock samples were returned to our laboratory where they were visually classified and
tested. Tests included natural moisture content and dry density, swell consolidation and
unconfined compression tests. Results of the laboratory testing are presented on Figs. 4
through 5 and summarized on Table I.
Soils encountered in our borings included 5 feet of fill near the masonry portal
addition and no fill in the area of the stair tower addition. Native soils in both borings
consisted of stiff, sandy clays overlying sandstone, claystone and interbedded sandstone
and claystone bedrock. Clay samples tested showed low swell to slight compression.
Claystone samples tested in laboratory showed low and moderate swell. Ground water
was encountered at depths of 14 feet and 17 feet during drilling. Bedrock depth is likely
to vary between borings.
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-91
Rev. 12-09
Additions Foundations
We understand the proposed stair tower addition is planned to be supported on the
existing footings and new helix piers and the portal addition to be supported on new drill
piers bottomed in bedrock. Our investigations indicate the clays and claystone bedrock
under the site are low to moderately expansive. Drilled piers and helix piers can be used
to support the additions. Piers should penetrate below the zone of probable moisture
variation and be designed and constructed to resist the swelling pressure. Footings
founded on the expansive soils and bedrock need to maintain high deadload pressure to
resist the swelling pressures. Normally, footings have higher risk of heave than the piers.
Considering the existing building footing foundations have performed reasonably well,
we believe the new addition can also be supported on these footings provided similar
footing deadload and total load pressures are maintained after construction. Differential
movements between the additions and existing building will occur due to either
settlements of new foundations or rebound and reloading of the existing footings under
the addition. A slip joint should be provided where possible at the connection to reduce
the potential damages associated with the differential movements. Foundation design and
construction criteria are as follows:
Helix Piers
1. The end bearing pressure is dependent on the properties of the helix size
selected and the torque applied to install the piers. The bedrock under the site
can provide an ultimate end bearing pressure of 90,000 psf. This value does
not include a factor of safety. Helix piers should penetrate a minimum of 4
feet into relatively unweathered bedrock. Piers should be advanced to a
torque required to accommodate the end bearing pressure specified by the
structural engineer. Manufacturers recommendations regarding the torque and
bearing relationship should be followed. A minimum factor of safety of 2.0 is
required. The pier should be placed as close to vertical as possible.
2. The connection between the pier and grade beam should be designed to resist
lateral earth pressure (if any) against the grade beams. The connection should
be designed by a structural engineer. The helix piers should be attached to the
existing grade beam using brackets that allow the pier to be pre-loaded during
construction. The helix piers should be loaded so that the deadload on the
existing footing foundation remains approximately the same before and after
construction.
3. Twisting of the shaft can occur during the installation process. We
recommend the structural engineer evaluate the effect twisting of the shaft has
on the capacity of the helix pier.
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-92
Rev. 12-09
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-93
Rev. 12-09
Lateral Loads
We anticipate that no new basement construction will be part of this renovation.
It may be necessary to re-analyze the below-grade, retaining wall at the areaway on the
south side of the existing building for lateral earth pressures. We anticipate that the
retaining wall will be restrained so that deflections are minimal. An at rest equivalent
fluid pressure of 50 pcf may be used in design calculations providing wall backfill
consists of on-site soils. Loads due to surcharges and hydrostatic pressure should be
added to the above distribution. Hydrostatic pressure may be alleviated by providing
weep holes at the base of the retaining wall. If the entire retaining wall is reconstructed
or a portion of it, we recommend a gravel drain behind the wall to reduce the hydrostatic
pressure. The drain should consist of at least 12 inches of reasonably well graded clean
sand and gravel backfill to within 2 feet of the ground surface. The top 2 feet should be
compacted on-site soils. A manufactured drain such a Mira Drain may be substituted for
the drain gravel. Manufactured drains should be installed following the manufacturers
recommendations. Weep holes should be at least 4 inches in diameter and spaced 10 feet
on center with no less than 3 weep holes provided for each wall. The back of the weep
holes should be protected from clogging. Wall backfill should be placed in 8-inch
maximum loose lifts, moisture conditioned to within 2 percent of optimum and
compacted to at least 95 percent of standard Proctor maximum dry density.
We anticipate foundation piers will be designed to resist lateral loads applied to
the structure through wind, seismic, and lateral earth pressures. Several methods are
available to analyze laterally loaded piers. For helix piers and drilled piers with a length
to diameter ratio of 7 or greater, we believe the method of analysis developed by Matlock
and Reese is most appropriate. The method is an iterative procedure using applied lateral
load movement, vertical load, and pier diameter to develop deflection and movement
versus depth curves. Software developed by Reese can be used to calculate deflection for
various pier diameters and loading conditions anticipated by the structural engineer.
Movement versus depth curves developed from these analyses to aid the structural
engineer and optimizing the location of reinforcement. Other procedures require input of
horizontal modules subgrade reaction Kh. For purposes of design, we recommend the
following horizontal modulus of subgrade reaction:
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-94
Rev. 12-09
(For Bedrock)
Kh = 400/D (tons/ft3),
(For Soils)
Kh = 50/D (tons/ft3 where D = shaft diameter in feet)
These designs values do not include a factor of safety.
Exterior Slabs
We do not anticipate any new slab-on-grade floor construction. Any new exterior
flatwork and sidewalks should be separated from the structures. Movement of slabs-ongrade should not be transmitted to the foundations of the structures. Frequent control
joints should be provided according to ACI or PCA criteria to relieve problems
associated with shrinkage or cracking.
Concrete
A soluble sulfate concentrate of 0.003 percent was measured in a sample of the
on-site soils. Our experience with other sites in this area indicated a low risk of sulfate
attack as does this measurement. We believe a Type I of Type II cement can be used for
concrete in contact with the soils.
Surface Drainage
Performance of foundation is influenced by subgrade moisture conditions. The
risk of wetting the subsoils can be reduced by carefully planned and maintained surface
drainage. We recommend the following precautions be observed during construction and
maintained at all times after the construction is completed.
1. Wetting or drying of the open foundation excavation should be avoided.
2. The ground surface surrounding the exterior of the building should be sloped
to drain away from the buildings in all directions. We recommend a minimum
slope of at least 6 inches in the first 10 feet if possible.
3. Roof downspouts and drains should discharge well beyond the limits of all
wall backfill. Splash blocks and downspout extenders should be provided.
Roof drainage should not be directed below the building.
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-95
Rev. 12-09
Limitations
Our borings were used to obtain a reasonably accurate picture of the subsurface
conditions. The borings are representative of conditions only at the exact boring
locations. Our analysis and recommendations apply to the proposed construction and soil
conditions outlined in this letter. Should construction details change or differing soil
conditions be encountered, we should be contacted to evaluate our recommendations.
We believe this report was prepared using methods and procedures consistent with other
professional practicing geotechnical engineering in this area at this time. No other
warranty, express or implied, is made.
If we can be of further service in discussing the contents of this report or in our
analysis of the influence of the subsoil conditions on the design of the structures, please
call.
Sincerely,
Howard A. Perko
Geotechnical Project Engineer
ARCHDIOCESE OF COLORADO
EXAMPLE SOIL REPORT, 96-274
Page 2000-96
Rev. 12-09
Texas Avenue
Rose Street
Main Street
TH-1
TH-2
Tennessee Avenue
Boring Locations
No Scale
Fig. 1
Page 2000-97
Rev. 12-09
SITE
Fig. 2
ARCHITECT/ENGINEER
H. Perko
PROJECT
Proposed Additions
SPT - N
BLOWS / FT.
MOISTURE, %
DRY DENSITY
PCF
TYPE
NUMBER
DESCRIPTION
TESTS
USCS SYMBOL
DEPTH (FT)
GRAPHIC LOG
SAMPLES
FILL
SPT
13
17.8
105
FILL
SPT
20.9
103
CL
SPT
10
11.6
110
3550
BRCS
SPT
58
14.5
112
10,500
BRSS
SPT
65
9.8
118
BRSS
SPT
85
10.1
117
BRCS
SPT
67
13.2
109
UNCONFINED
STRENGTH
PSF
CLIENT
CLAY, SANDY
Stiff, slightly moist to moist, brown
10
15
25
BOTTOM OF BORING
30
14'
W.D.
BORING COMPLETED
RIG
WL
WL
APPROVED
Page 2000-98
CME-55
HP
10/5/1996
10/5/1996
FOREMAN
JOB NO.
DS
96-274
Rev. 12-09
SITE
Fig. 3
ARCHITECT/ENGINEER
H. Perko
PROJECT
Proposed Additions
DRY DENSITY
PCF
15
MOISTURE, %
10
SPT - N
BLOWS / FT.
TYPE
CLAY, SANDY
Stiff, slightly moist to moist, brown
NUMBER
DESCRIPTION
TESTS
USCS SYMBOL
DEPTH (FT)
GRAPHIC LOG
SAMPLES
CL
SPT
11
12.5
106
CL
SPT
10.8
104
BRCS
SPT
55
12.2
110
BRSS
SPT
58
11.1
114
BRCS
SPT
65
12.6
107
BRSS
SPT
85
9.8
112
BRCS
SPT
67
11.5
109
UNCONFINED
STRENGTH
PSF
CLIENT
8,900
BOTTOM OF BORING
25
30
17'
W.D.
BORING COMPLETED
RIG
WL
WL
APPROVED
Page 2000-99
CME-55
HP
10/5/1996
10/5/1996
FOREMAN
JOB NO.
DS
96-274
Rev. 12-09
COMPRESSION % EXPANSION
-1
-2
-3
-4
1.0
0.1
100
10
Sample of
From
110
11.6
PCF
%
COMPRESSION % EXPANSION
-1
-2
-3
-4
10
1.0
0.1
100
Sample of
From
CLAYSTONE
TH- 1 AT 14 FEET
Page 2000-100
112
14.5
PCF
%
Swell Consolidation
Test Results Rev. 12-09
FIG. 4
COMPRESSION % EXPANSION
-1
-2
-3
-4
1.0
0.1
100
10
Sample of
From
CLAYSTONE
TH- 2 AT 9 FEET
110
12.2
PCF
%
COMPRESSION % EXPANSION
-1
-2
-3
-4
10
1.0
0.1
100
Sample of
From
CLAYSTONE
TH- 2 AT 19 FEET
Page 2000-101
107
12.6
PCF
%
Swell Consolidation
Test Results Rev. 12-09
FIG. 5
Page 2000-102
Rev. 12-09
PROJECT NUMBER
DATE OF INSTALLATION
PILE DESIGNATION
ANGLE
ELEV
GRID LOCATION
PLANNED
TOP OF PILE
MEASURED
TOP OF PILE
PLANNED
INCLINATION
MEASURED
INCLINATION
LENGTH
PLANNED
MINIMUM
INSTALLED
BEARING
STRATUM
FINAL
TORQUE
TORQUE MEASURMENTS
CONFIGURATION
ABOVE GROUND
SHAFT
DESIGNATION
ISO/ICC TAG
HELIX TYPE
HELIX
DIAMETER(S)
DEPTH (FT)
5
10
15
20
25
30
35
40
45
50
REQUIRED
MEASURED
PLANNED
OBSERVED
INSTALLATION EQUIPMENT
TORQUE MEASUREMENT DEVICE
NOTES
CALIBRATION DATE
FIELD REPRESENTATIVE
REVIEWER
Page 2000-103
Rev. 12-09
Page 2000-104
Rev. 12-09
Page 2000-105
Rev. 12-09
Page 2000-106
Rev. 12-09
Page 2000-107
Rev. 12-09
Page 2000-108
Rev. 12-09
FREE HEAD
PILE A
FIXED HEAD
PILE B
DESCRIPTION
PROJECT
DESIGNATION
TEST DATE
DESIGN LOAD=
Target
Load1
kips
Target
Hold
Time
(min)
0%
2
5%
25%
50%
75%
LOADING
100%
125%
150%
170%
180%
TEST LOAD
190%
200%
UN- LOAD
150%
100%
50%
0%
kips
Load
Actual
Time
Ram
(psi)
TECHNICIAN
Pile A
Cell
(kips)
Dial
(in)
Optical
(in)
Pile B
Dial
(in)
Optical
(in)
Notes
na
na
0
5
10
0
5
10
0
5
10
15
0
5
10
15
20
0
5
10
15
20
0
5
10
15
20
0
5
10
15
20
0
5
10
15
20
0
5
10
15
20
0
15
30
45
60
0
5
10
0
5
10
0
5
10
0
15
30
Page 2000-109
Rev. 12-09
SECTION 3000
DESIGN TOOLS
Design Basics
Page 3000-1
Rev. 12-09
Spread Footing
Concrete Caisson
Cost Effective
Cost Effective
Driven Pile
Requires Casing and Dewatering Using High Mobilization Cost, Not Practical for Supports from below Depth of Seasonal
14 to 28 Day Concrete Curing Time,
Mud Bucket, Costly and Slow
Small Structures, Subject to Corrosion,
Moisture Content Changes, High
Subject to Movement Due to Expansion
Installation Process, Drilling Equipment Pile Driving Equipment Can Not Enter Quality of a Manufactured Foundation,
and Contraction of Clays with Seasonal
Can Not Enter Foundation Excavation
Foundation Excavation during
All Weather Installation, Corrosion
Changes in Moisture Content
during Unfavorable Weather
Unfavorable Weather
Resistant Galvanization
Same as Above
Limited Access may make Installation Noise and Vibrations Adversely Affect
Difficult, Hard to Get Very Near Existing Nearby Existing Structures, Limited
Structures
Access may make Installation Difficult
Contaminated Soils
Temporary Application
on Remote Site
Limited Geotechnical
Information Available
Page 3000-2
Rev. 12-09
12
STEP 1.
Obtain subsurface soil information and
determine if helical piles are a suitable
and reasonable foundation alternative
for your project.
Helical pile foundations can be used in
practically any soil and subsurface
conditions provided the SPT blow count is
less than about 50/6. Their installation
is not affected by groundwater nor caving
soils. Helical pile foundation installation
equipment is usually small and
maneuverable and can reach areas having limited access. They can even
be installed using hand-operated equipment. Helical pile foundations do
not produce drill spoil. The simplicity and time savings associated with
helical pile foundation use makes them economical compared to almost
any other foundation except spread footings.
Page 3000-3
Rev. 12-09
STEP 2.
Compute building live and dead loads, layout
helical pile, and specify required design
(allowable) capacities. Use Magnums design
charts to determine the pile sizes needed.
The most economical foundation plan is
one that optimizes spacing based on the
maximum allowable capacity of manufactured
helical pile foundations.
Magnum Helical piles
are available in three
series that are rated for
maximum
allowable
loads of 51, 97, and 191 kips. Sample plans are
shown in the specifying helical piles section.
STEP 3.
Identify the proper bearing
stratum for the piles. For
prescription specifications, use
Magnums design charts to
determine required helical
bearing plate sizes.
The proper bearing stratum for
helical piles is the most competent material at an easily obtainable depth.
Bedrock is the most preferable stratum for compression applications
followed by dense sand and gravel. Many large diameter helical bearing
plates can be used in softer soils to achieve required capacity. Helical
bearing plate size and number are essentially functions of the bearing
capacity of the soil or rock.
Page 3000-4
Rev. 12-09
STEP 4.
If subsurface conditions merit or if
tension loads are required, select a
minimum depth for your helical
piles.
There are many instances in which
specification of a minimum depth is
required such as helical pile
foundations subject to tensile loads or
expansive soils. Typically a minimum
depth of ten helix diameters is
sufficient
for
tensile
load
applications.
STEP 5.
Draw a reinforcing steel detail for
connection of the helical pile to the
structure. Use Magnums product
catalog to specify a pile cap.
Magnum Piering, Inc. supplies predesigned, manufactured, bare steel
and galvanized helical pile foundation
caps for tensile and compression
applications.
Examples
of
conventional reinforcing-steel details
are provided in the Specifying Helical
Piles Section of this guide.
Page 3000-5
Rev. 12-09
STEP 6.
Compose specifications or general notes for helical pile foundation
mechanical strength, galvanization, and other preferred details. For
performance specifications, specify that the pile installers engineer is
responsible for providing
engineering calculations, sizing,
and design of the helical piles.
Example written specifications are
provided in the Specifying Helical
Piles section; Guide Specifications
sub-section.
Page 3000-6
Rev. 12-09
Design Charts
Page 3000-7
Rev. 12-09
Magnum Piering
Helical Pile Specifications
System Ratings & Capacity Specifications
Magnum
Helical Pile Products
*Shaft
*Design
Wall Min.
Shaft
Design
O.D.
Gauge
(in)
(in)
Structural Capacity
(Tension & Comp)
Approx
Weight
(plf)
Ultimate
(tons)
Bare / Galv
Allowable
(tons)
Bare / Galv
Capacity by Torque
(Tension & Comp)
Maximum
Torque
(ft-lbs)
Capacity
to
Torque
Ratio
(ft-1)
Ultimate
(tons)
Allowable
(tons)
Helix Sizes
(available in
standard & dual
cutting edge)
(in)
Helix
Gauge
(in)
Bolted (B)
or
Welded (W)
Connection
Hot Dip
Galvanized
ASTM
A153
Standard
Section
Lengths
(custom sizes
available)
(ft)
6, 12, 24
MHL313
0.13
3.00
3.8
26 / 35
13 / 17
4,000
8.0
16
8,10,12,14
0.375
B (1)
standard
MHL313R
0.13
3.00
3.8
26 / 35
13 / 17
6,000
8.0
24
12
8,10,12,14
0.375
B (1)
standard
6, 12, 24
MHL325
0.25
3.00
7.3
60 / 68
30 / 34
8,700
8.0
35
17
8,10,12,14
0.375
B (1)
standard
6, 12, 24
MHL325R
0.25
3.00
7.3
60 / 68
30 / 34
12,700
8.0
51
25
8,10,12,14
0.375
B (1)
standard
6, 12, 24
MHL425
0.25
4.50
11.6
93 / 105
47 / 53
24,000
5.7
68
34
10,12,14,16
0.625
B (2)
optional
7, 10, 24
MHL425R
0.25
4.50
11.6
93 / 105
47 / 53
28,000
5.7
80
40
10,12,14,16
0.625
B (2)
optional
7, 10, 24
7, 10, 24
MHL431
0.31
4.50
14.3
118 / 131
59 / 65
29,000
5.7
83
41
10,12,14,16
0.625
B (2)
optional
MHL431R
0.31
4.50
14.3
118 / 131
59 / 65
34,000
5.7
97
48
10,12,14,16
0.625
B (2)
optional
7, 10, 24
MHL625
0.25
5.72
15.0
120 / 136
60 / 68
40,000
4.6
92
46
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
MHL625R
0.25
5.72
15.0
120 / 136
60 / 68
45,000
4.6
104
52
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
MHL637
0.37
5.72
21.2
180 / 196
90 / 98
58,000
4.6
133
67
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
MHL637R
0.37
5.72
21.2
180 / 196
90 / 98
65,000
4.6
150
75
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
MHL646
0.46
5.72
27.2
238 / 253
119 / 127
74,000
4.6
170
85
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
MHL646R
0.46
5.72
27.2
238 / 253
119 / 127
83,000
4.6
191
95
12,16,20,24
0.875
W or B (3)
optional
6, 9, 18, 24
Improved Penetration into Dense & Cobble Soils, Cuts Through Many Fills/Trash,
Eliminates Wobble, Maintains Plumbness, Less Soil Disturbance
R = Reinforced
Magnum's patent pending reinforced helical pile to torque motor connection design increases the torsional capacity of the pinned connection to the torque motor and therefore increases the pile's
ultimate capacity by approximately 10%.
All Magnum helical pile products are manufactured using minimum 65 ksi minimum yield strength structural tubing, or better, for the shaft and ASTM A36 plate steel, or better, for the helical
bearing plates. As Magnum is committed to testing and improving products, these specifications are subject to change. Additional product specifications available at www.magnumpiering.com
and in the Magnum Helical Pile Engineering Manual available upon request. Structural capacity is for piles in firm soil with fully braced pile cap. Structural capacity takes into account corrosion
over IBC design life in moderate to high corrosive soils based on ICC-ES AC358. Consult a Magnum corrosion engineer for severe corrosive soils.
Page 3000-8
Rev. 12-09
loose
medium dense
dense
110
Mechanical Limit of MH325BR Pile
100
Helix Diameters =
5-14S
90
Legend:
Single Cutting Edge
Dual Cutting Edge
80
5-12S
12S14S14S
70
10S12S14S
60
10D12D14D
50
8D10D12D
10D12D
40
8D10D
12D
20
10
0
0
10
15
20
25
30
35
40
45
50
Page 3000-9
Rev. 12-09
very
soft
soft
medium
stiff
stiff
medium hard
very stiff
110
100
Helix Diameters =
90
Legend:
Single Cutting Edge
Dual Cutting Edge
80
5-14S
5-12S
Mechanical Limit of MH325B Pile
70
12S14S14S
60
10S12S14S
Mechanical Limit of MH313BR Pile
50
10D12D14D
40
8D10D12D
30
10D12D
8D10D
12D
20
10
0
0
10
15
20
25
30
35
40
45
50
Page 3000-10
Rev. 12-09
medium hard
very
hard
hard
110
100
90
8"&10"&12"
80
10"&12"
Mechanical Limit of MH325B
70
8"&10"
60
12"
50
Possible Refusal
of Helical Pile
beyond This Point
(SPT > 50/6)
10"
40
= Helix Diameters
30
20
Legend:
Dual Cutting Edge
10
0
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
Page 3000-11
Rev. 12-09
loose
medium dense
dense
200
180
Mechanical Limit of MH431 Pile
160
5-16S
Helix Diameters =
5-14S
140
14S16S16S
Legend:
Single Cutting Edge
Dual Cutting Edge
120
14D16D16D
100
12D14D16D
80
14D16D
12D14D
60
40
14D
20
0
0
10
15
20
25
30
35
40
45
50
Page 3000-12
Rev. 12-09
very
soft medium
soft
stiff
stiff
very stiff
medium hard
200
180
160
Helix Diameters =
5-16S
5-14S
140
Legend:
Single Cutting Edge
Dual Cutting Edge
120
14S16S16S
12S14S16S
100
12D14D16D
80
14D16D
12D14D
60
40
14D
20
0
0
10
15
20
25
30
35
40
45
50
Page 3000-13
Rev. 12-09
medium hard
very
hard
hard
200
180
160
Helix Diameters =
140
14"&16"
120
12"&14"
100
16"
Possible Refusal
of Helix Foundation
beyond This Point
(SPT > 50/6)
80
14"
60
12"
40
Legend:
Dual Cutting Edge
20
0
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
Page 3000-14
Rev. 12-09
loose
medium dense
dense
400
360
Mechanical Limit of MH646 Pile
320
Helix Diameters =
5-24S
5-20S
280
Legend:
Single Cutting Edge
Dual Cutting Edge
240
20S24S24S
16S20S24S
200
16D20D24D
20D24D
160
16D20D
120
80
20D
40
10
15
20
25
30
35
40
45
50
Page 3000-15
Rev. 12-09
medium
very
soft
stiff
soft
medium hard
very stiff
stiff
400
360
Mechanical Limit of MH646 Pile
320
Helix Diameters =
5-24S
280
Legend:
Single Cutting Edge
Dual Cutting Edge
240
5-20S
20S24S24S
Mechanical Limit of MH625R Pile
16S20S24S
200
16D20D24D
20D24D
160
16D20D
120
80
20D
40
0
0
10
15
20
25
30
35
40
45
50
Page 3000-16
Rev. 12-09
medium hard
very
hard
hard
400
360
Mechanical Limit of MH646 Pile
320
Mechanical Limit of MH637R Pile
Helix Diameters =
20D24D
280
240
16D20D
200
24D
Possible Refusal
of Helical Pile
Beyond This Point
(SPT > 50/6)
160
20D
120
16D
80
Legend:
Dual Cutting Edge
40
0
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
Page 3000-17
Rev. 12-09
Magnum MH313
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
3
0.125
1.17
1.13
Soil Type
Unit Weight
(pcf)
Very Soft
Soft
Medium
Stiff
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
Cohesion
(psf)
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-19
Rev. 12-09
Magnum MH325
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
3
0.25
1.99
2.1
Soil Type
Very Loose
Loose
Medium
Dense
Unit Weight
(pcf)
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
Cohesion
(psf)
4
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
0
0.00
0.25
0.50
Displacement , (in)
0.75
1.00
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector
rigidity and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-20
Rev. 12-09
Magnum MH325
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
3
0.25
1.99
2.1
Soil Type
Very Soft
Soft
Medium
Stiff
Unit Weight
(pcf)
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
Cohesion
(psf)
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector
rigidity and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the
average performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple
redundant structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2
for single redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners
take this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Page 3000-21
Rev. 12-09
Magnum MH425
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
4.5
0.25
7.33
3.24
Soil Type
Unit Weight
(pcf)
Very Loose
Loose
Medium
Dense
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
15
13
12
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
14
Cohesion
(psf)
11
Free Head Condition
10
9
h
8
7
6
5
4
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
3
2
1
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-22
Rev. 12-09
Magnum MH425
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
4.5
0.25
7.33
3.24
Soil Type
Very Soft
Soft
Medium
Stiff
Unit Weight
(pcf)
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
15
13
12
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
14
Cohesion
(psf)
11
10
9
h
8
7
6
5
4
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
3
2
1
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector
rigidity and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the
average performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple
redundant structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2
for single redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners
take this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-23
Rev. 12-09
Magnum MH431
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
4.5
0.31
8.85
4.02
Soil Type
Unit Weight
(pcf)
Very Loose
Loose
Medium
Dense
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
15
13
12
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
14
Cohesion
(psf)
11
10
9
8
7
6
5
4
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
3
2
1
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-24
Rev. 12-09
Magnum MH431
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
4.5
0.31
8.85
4.02
Soil Type
Very Soft
Soft
Medium
Stiff
Unit Weight
(pcf)
70
90
110
120
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
15
13
12
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
14
Cohesion
(psf)
11
10
Applied Lateral Load, P (kips)
9
8
7
6
5
4
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
3
2
1
0
0.00
0.25
0.50
0.75
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector
rigidity and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the
average performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple
redundant structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2
for single redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners
take this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-25
Rev. 12-09
Magnum MH625
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.25
13.79
3.68
Unit Weight
(pcf)
Very Loose
Loose
Medium
Dense
70
90
110
120
Cohesion
(psf)
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
0.00
0.25
0.50
0.75
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes. The
design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-26
Rev. 12-09
Magnum MH625
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.25
13.79
3.68
Unit Weight
(pcf)
Very Soft
Soft
Medium
Stiff
70
90
110
120
Cohesion
(psf)
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
0.00
0.25
0.50
0.75
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes. The
design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-27
Rev. 12-09
Magnum MH637
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.375
19.94
5.54
Unit Weight
(pcf)
Very Loose
Loose
Medium
Dense
70
90
110
120
Cohesion
(psf)
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
0.00
0.25
0.50
0.75
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes. The
design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-28
Rev. 12-09
Magnum MH637
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.375
19.94
5.54
Unit Weight
(pcf)
Very Soft
Soft
Medium
Stiff
70
90
110
120
Cohesion
(psf)
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
0.00
0.25
0.50
Displacement , (in)
0.75
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
1.00
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-29
Rev. 12-09
Magnum MH646
Lateral Performance in Sand1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.46
25.3
7.31
Very Loose
Loose
Medium
Dense
Unit Weight
(pcf)
70
90
110
120
Cohesion
(psf)
Strain 50
0
0
0
0
N/A
N/A
N/A
N/A
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
25
5
29
25
33
90
39
225
0.00
0.25
0.50
0.75
Dense.
Dense
Medium.
Medium
Loose.
Loose
Very Loose.
Very Loose
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector
rigidity and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the
average performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple
redundant structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2
for single redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners
take this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-30
Rev. 12-09
Magnum MH646
Lateral Performance in Clay1
Pile Properties
Shaft O.D., d (in)
Wall thickness (in)
Area Moment of inerta (in4)
Gross Area (in2)
5.72
0.46
25.3
7.31
Unit Weight
(pcf)
Very Soft
Soft
Medium
Stiff
70
90
110
120
Cohesion
(psf)
Strain 50
200
400
800
1500
0.06
0.02
0.01
0.005
Est. Allowable
Lateral Capacity2
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1
0
Soil Type
Soil Properties
Angle of
p-y Modulus
Friction
(pci)
(deg)
0
30
0
100
0
500
0
1000
0.00
0.25
0.50
0.75
Stiff.
Stiff
Medium.
Medium
Soft.
Soft
Very Soft.
Very Soft
1.00
Displacement , (in)
1
These charts are for Magnum helical piles only as lateral performance is highly dependant on helical pile connector rigidity
and shaft properties. It is Magnum's opinion that these graphs represent a reasonable approximation of the average
performance of helical piles in the indexed soils. Using the average performance is reasonable for multiple redundant
structures (e.g. buildings, bridges, marina piers, etc.). Magnum recommends an additional factor of safety of 2 for single
redundant (non-redundant) systems (e.g. fences, signs, poles, etc.).
2
IBC2006 states the allowable lateral capacity of a pile is half the load causing 1" of displacement. Many practitioners take
this to be nearly the same as the lateral load predicted at 1/2" displacement. The graph presented here can be used to
evaluate capacity for either condition as well as to judge lateral performance under other displacement criteria and codes.
The design allowable displacement is the responsibility of the engineer of record.
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-31
Rev. 12-09
Technical Papers
Page 3000-32
Rev. 12-09
Revised August 10, 2001. Original published in New Technological and Design Developments in Deep
Foundations, Proceedings of GeoDenver 2000, Norman D. Dennis, Jr., Ray Castelli, and Michael W.
ONeill, Eds., Geotechnical Special Publication, ASCE Press, Reston, VA
Manager, Secure Products, LLC, 727 Laporte Ave., Ft. Collins, CO 80521
howie@engr.colostate.edu, phone: 970-472-5068, fax: 970-472-0264
1
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-33
Perko
Rev. 12-09
difficulty with limit state analysis for helix piers is that it requires prior knowledge of the
soil strength and the ability to determine the probable mode of failure.
Torque measurements taken during installation of a helix pier are indicators of
soil shear strength at the depth through which the helical blades are passing. Due to the
complex interaction of the blades with the soil, it is difficult to relate torque
measurements with angle of friction and cohesion of the soil. In order to avoid this
difficulty, a model is proposed, wherein the capacity of a helix pier is directly related to
the installation torque by energy equivalence. This method accounts for downward
pressure during installation, helical blade geometry, multiple helices, blade pitch per
revolution, and hub radius. Predictions based on the model are compared with data from
previous studies.
Model Derivation
The energy model for predicting helix pier capacity/torque relationships is based
on the following postulate.
Postulate:
Justification for this postulate is derived from the characteristic soil stress-displacement
function shown in Fig. 1. The initial portion of this function is approximately linear. A
new constitutive parameter, P, is defined as the slope of the stress-displacement function.
Penetration energy is simply
(1)
where
1 is displacement,
is final displacement, ) is stress, and A is penetrator area.
Replacing ) in Eq. (1) by P
and integrating results in
(2)
Since area times displacement is just the volume of soil displaced, A
can be replaced
by V and the penetration energy is
(3)
Thus, the penetration energy is proportional to the volume of soil displaced times the
distance displaced. The proportionality factor, P, is constant for small displacements
typical of local shear.
2
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-34
Perko
Rev. 12-09
3
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-35
Perko
Rev. 12-09
Page 3000-36
Perko
Rev. 12-09
pier is given by
(7)
where m is the total number of blades even if they follow the same path. However, )
can be replaced by P
in accordance with the penetration energy postulate. By
incorporating the appropriate values of
for the blades and the hub, Eq. (7) can be
written in the form
(8)
The constitutive parameter, P, can be found by incorporating Eqs. (5), (6), and (8) into
Eq. (4) and solving for P in terms of torque.
The next step in the derivation of the model is to formulate an equation for the
capacity of a helix foundation or anchor in terms of P. There are two predominant
methods of determining helix foundation or anchor capacity based on limit state analysis.
Limit state conditions can require considerable displacements in order to mobilize shear
strength and for general bearing capacity failure. For practical purposes, the allowable
movement of foundations and anchors is typically limited to small displacements. The
capacity for small displacements can be determined using the penetration energy
postulate and an energy balance between the energy exerted during loading and the
appropriate penetration energy of each of the supporting blades.
(9)
In Eq. (9), it is assumed that energy losses due to friction along the hub are negligible,
because only a fraction of the shear strength is mobilized for small displacements. Also,
the capacity in uplift is approximately equal to the bearing capacity, since small
movements in either the upward or downward direction should only depend on the
effective confining stress around the blades.
The energy during loading can be determined by integrating the applied force
over a specific helix pier displacement. For a linear force-displacement function, the
energy during loading is given by
(10)
where Q is the final capacity and d is the vertical movement.
Penetration energy during loading can be determined according to Eq. (3). The
volume of soil displaced by the helix pier is equal to the sum of the areas of the blades
and the end area of the hub times the displacement distance, d. This assumes that the
end of the hub is closed to prohibit soil entry. Penetration energy is given by
(11)
Substitution of Eqs. (10) and (11) and the result for P from step one into Eq. (9) yields
an expression for capacity in terms of installation torque, applied downward force, pier
5
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-37
Perko
Rev. 12-09
6
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-38
Perko
Rev. 12-09
Total
Number of
Blades
m
1
1
1
1
1
2
3
4
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2
3
4
1
1
1
1
1
1
1
1
1
1
Blade
Radius
R
(in)
Hub
Radius
r
(in)
Blade
Pitch
p
(in/rev)
6
6
6
6
6
6
6
6
4
5
6
7
6
6
6
6
6
6
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.1
1.4
1.6
1.8
2.0
3.0
4.0
5.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
3.0
Effective
Capacity
Hub
Blade
to Torque
Length Thickness
Ratio
t
K
-1
(in)
(in)
(ft )
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.375
0.5
0.75
0.375
0.375
0.375
11.8
11.8
11.8
11.8
11.8
12.4
12.6
12.7
13.7
13.0
11.8
10.6
11.8
9.1
6.2
10.2
9.1
8.0
The diamond symbol in Fig. 4 represents an field test by Rupiper and Edwards
(1989), which consisted of measuring the installation torque and bearing capacity of a
square-hub helix pier with a single 14-in diameter helical blade. According to their
paper, the pier exhibited a maximum capacity at a displacement of only 0.15 in. Both the
model and the field test indicate a low capacity to torque ratio for such a small
displacement.
The open circle symbols in the figure correspond to a laboratory investigation
that was performed by Ghaly, Hanna, and Hanna (1991) which involved uplift capacity
testing of several small helix anchors. Each anchor had a round hub with a single 2-in
diameter helical blade. Blade pitch varied from 3/8 to 3/4 inch per revolution.
Installation torque varied from 17 to 30 ft-lbs. The model indicates a weak dependance
of K on pitch and generally matches the laboratory results. Their investigation also
included unsymmetrical and parallel-blade, variable-pitch anchors. It is considerably
more difficult to apply the model to these types of anchors; consequently, they were not
analyzed.
Referring again to Fig. 4, the open triangle symbols represent full scale field tests
performed by Mitsch and Clemence (1985) on square hub piers with triple 11-in diameter
helical blades, while the open square symbols represent laboratory tests performed by the
same investigators on 1/3 scale models. Some of the models had uniform diameter triple
7
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-39
Perko
Rev. 12-09
helical blades. Others had single blades. The model predicts nearly the same value of
K for single and multiple blade helix pier geometries. Most of the variations in K
predicted by the model are the result of different values of measured helix pier
displacement. For example, the set of open square symbols on the left side of the graph
correspond to helix piers that reached peak capacity at a displacement of about 0.1 in,
while the same symbols in the middle of the graph correspond to helix pier displacements
of 0.2 in and the same symbols near the top right corner of the graph correspond to helix
pier displacements of 0.4 in.
Another set of data in Fig. 4, shown by the star symbols, are associated with field
tests performed by Hargrave and Thorsten (1992) using square hub helix piers with
single 10-in diameter helical blades. The model matched the results of their field tests
with nearly 1:1 correspondence. Field tests were also conducted on helix piers with
multiple radii, double blades, and again these data were omitted to avoid complexity.
These more complicated geometries will be the subject of a forthcoming theoretical
study not yet completed.
Rupiper and Edwards (1989): 14-in
diameter single helix, 1.5-in square hub
pier
40.0
30.0
20.0
10.0
0.0
0
10
20
30
40
Page 3000-40
Perko
Rev. 12-09
In practical applications, helical blades do not often follow the path cut by one another
due to accidental augering and slipping during installation.
In applying the model, the effective length of the hub was assumed to equal the
pitch of the helical blades. For square shaft helix piers, this assumption is based on the
square hub creating a round hole and displacing the soil away from the hub within one
revolution. For round-shaft helix piers, the value of is less evident. The magnitude of
predicted values of K has a significant dependance on the effective hub length, , that is
assumed. Larger values of correspond with smaller values of K. As consistent with
square-shaft hubs, a value of equal to the blade pitch provides the closest match to the
K value measured by Hoyt and Clemence and in other field tests. This indicates that
much of the soil separates from the hub during installation due to wobbling.
In developing the model, the friction generated along the blades and sides of the
hub during installation was assumed to be proportional to the penetration resistance, and
a proportionality factor, , was introduced. For the model predictions presented herein,
was set equal to 0.6. Justification for this value is based on the following.
As the soil moves to the side to allow for helical blade insertion, the penetration
resistance, ), is left acting in a direction approximately normal to the surface of the
blade, as shown in Fig. 5. The penetration resistance is the major principle stress in the
soil about the helical blades and leading end of the hub during installation. If the friction
angle between galvanized steel and soil is 30 degrees, then the friction generated along
the blades and hub is equal to 0.6 ). Note that this does not require the assumption that
) is uniform. Instead, ) is related to the distance of soil displacement and the volume
of soil displaced during penetration in accordance with Eq. (1). There may be some
dependence of and K on soil consistency, but this dependence is expected to be small
because the friction coefficient between steel and soil is largely independent of soil
density (Das, 1990).
Page 3000-41
Perko
Rev. 12-09
Predictions based on the model correlate well with previous field and laboratory
measurements. The model indicates that the capacity/torque ratio, K, is largely
independent of downward force during installation, final installation torque, number of
independent cutting blades, total number of helical blades, and blade pitch. The model
indicates that K is moderately affected by helical blade radius and strongly affected by
hub diameter and blade thickness. These predictions generally match measurements cited
in previous literature.
Acknowledgments
The funding for this research program was provided by Secure Products, LLC.
Appreciation is extended to Dr. Samuel P. Clemence of Syracuse University for his
review and comments.
Nomenclature
V
1
)
A
d
Epenetration
Einstallation
Elosses
Eloading
F
K
n
m
P
r
Rn
Rm
tn
tm
T
Q
References
A.B. Chance, Co. (1995). Sample Calculations for Helical Pier Application. Manufacturer Technical
Support Document, Centralia, MO.
Clemence, S.P. (1985). Uplift Behavior of Anchor Foundations in Soil. Proceedings of a Session
Sponsored by the Geotechnical Eng. Div. of ASCE, Detroit, MI.
Clemence, S.P. and Pepe, F.D. Jr. (1984). Measurement of Lateral Stress Around Multihelix Anchors
in Sand. Geotechnical Testing Journal, GTJODJ, Vol. 7, No. 3, Sept. 1984, pp. 145-152.
10
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-42
Perko
Rev. 12-09
Das, B.M. (1990) Principles of Geotechnical Engineering, 2nd Edition, PWS-Kent Publishing Company,
Boston.
Ghaly, A., Hanna, A., and Hanna, M. (1991a). Uplift Behavior of Screw Anchors in Sand. I: Dry
Sand. Journal of Geotechnical Engineering, Vol. 117, No. 5, pp. 773-793.
Ghaly, A., Hanna, A., and Hanna, M. (1991b). Installation Torque of Screw Anchors in Dry Sand
Soils and Foundations, Vol. 31, No. 2, Japanese Society of Soil Mechanics and Foundation
Engineering, pp. 77-92.
Hargrave, R.L., and Thorsten, R.E. (1992). Helical Piers in Expansive Soils of Dallas, Texas 7th
International Conference on Expansive Soils.
Hoyt, R.M. and Clemence, S.P. (1989). Uplift Capacity of Helical Anchors in Soil. Proceedings of
the 12th International Conference on Soil Mechanics and Foundation Engineering, Rio de
Janeiro, Brazil.
Mitsch, M.P., Clemence, S.P. (1985). The Uplift Capacity of Helix Anchors in Sand. Proceedings of
a Session Sponsored by the Geotechnical Engineering Division, ASCE Convention, Detroit,
MI, October 24, pp. 26-47.
Rao, S.N., Prasad, Y.V.S.N., and Shetty, M.D. (1991). Behavior of Model Screw Piles in Cohesive
Soils. Soils and Foundations, Vol. 31, No. 2, pp. 35-50.
Rao, S.N., Prasad, Y.V.S.N., and Veeresh, C. (1993). Behaviour of Emebedded Model Screw Anchors
in Soft Clays. Geotechnique, 43, No. 4, pp. 605-614.
Rupiper, S. and Edwards, W.G. (1989). Helical Bearing Plate Foundations for Underpinning.
Proceedings of Foundation Engineering Congress/SCE/CO Div., Evanston, IL, June 25-29.
11
Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-43
Perko
Rev. 12-09
Page 3000-44
Rev. 12-09
Page 3000-45
Rev. 12-09
Page 3000-46
Rev. 12-09
Page 3000-47
Rev. 12-09
Abstract
A summary of helical anchor use in retaining wall systems is presented. The summary
includes engineering analysis of helical anchor capacity and an example retaining wall design.
Previous research is discussed particularly regarding effects of inclination angle on pullout
capacity, performance in soft clays, performance in sands, and stress-strain behavior.
Introduction
Tie-back, earth retaining walls are
commonly restrained using grouted anchors.
Another technology for retaining wall restraint is
the use of helical anchors. A helical anchor
consists of one or more helically shaped,
galvanized steel blades attached to an elongate,
central, galvanized steel shaft with square,
tubular or round cross-section. A schematic
diagram of an example helical anchor is shown in
Fig. 1. The shaft is turned into the ground by
application of torsion using a truck mounted
auger or a torque head attached to a backhoe or
front-end loader. Once the blades are advanced
to the appropriate depth, they offer significant
pull-out resistance. Tensile loads as high as 100
kips are achievable for particular anchors in
certain soils. Most non-grouted manufactured
helical anchors have a maximum ultimate pullout capacity of between 35 and 80 kips.
Helical anchors offer numerous
advantages over conventional grouted anchors.
Installation of helical anchors progresses rapidly,
and post tensioning can be immediately
performed without waiting for grout to set. A
helical anchor installed in an incorrect location
can be easily removed and reinstalled. Likewise,
helical anchors can be removed and salvaged if
desired, such as in the case of a temporary
Page 3000-48
Rev. 12-09
Page 3000-49
Rev. 12-09
anchors.
A factor of safety of 3.0 is commonly
used in bearing capacity calculations. However,
when the foundation installation process includes
an indirect measurement of soil strength at the
foundation depth, a smaller factor of safety is
permissible. A traditional example of this is pile
driving where a much lower factor of safety is
often allowed. The American Society of Civil
Engineers (1996) explains that a factor of safety
of 1.5 is acceptable for pile foundations. Since
the instillation torque of helical anchors also
provides an indication of soil strength at the
depth of the helices, a lower factor of safety is
permissible for allowable pullout capacity
calculations. Typically a factor of safety of 2.0
is used in helical anchor design.
Page 3000-50
Rev. 12-09
I.
II.
III.
IV.
V.
VI.
VII.
VIII.
IX.
Design Example
The usual procedure for design of a
helical anchor retaining wall is as follows.
-4-
Page 3000-51
Rev. 12-09
(11)
The downward component of this force must be
taken into account in the design of a suitable
foundation for the retaining wall facing. Helix
piers provide a convenient foundation for helical
anchor retaining walls.
A remaining step in helical anchor design
is to verify that the anchor itself is sufficient to
withstand the calculated pullout capacity.
Helical anchors are typically manufactured of
high strength carbon steel having an ultimate
tensile strength in the range of 35,000 to 70,000
psi. In this example, the helical anchor shaft
must have a cross-sectional area of at least 0.07
to 0.14 in2. Strength of the helical anchor
section connectors should also be checked.
Most helical anchor manufacturers provide
Page 3000-52
Rev. 12-09
Embedment Length
Clay
5 ft
Loose Sand
7 ft
Medium Sand
9 ft
Dense Sand
11 ft
(13)
where the vertical stress for the shallowest
helical anchor was used to be conservative.
In helical anchor retaining wall design, it
is better practice to round-down the number of
blades and implement a minimum installation
-6-
Page 3000-53
Rev. 12-09
References
Conclusions
The use of helical anchors in earth
retaining wall restraint is a viable alternative to
grouted earth anchors that offers many
advantages including ease of installation,
immediate post tensioning, penetration through
ground water and caving soils, removal, and
reuse. There are three methods for determining
anchor pullout capacity: cylindrical shear,
individual bearing, and installation torque.
When designing a helical anchor retaining wall,
pullout capacity should be approximated using
the most conservative result obtained from
cylindrical shear and individual bearing methods.
Installation torque should be used as a final field
verification of helical anchor capacity. Effects of
-7-
Page 3000-54
Rev. 12-09
-8-
Page 3000-55
Rev. 12-09
Presented August 8, 2003 at the Foundations Technology Seminar - Helical Foundations and Tiebacks, Deep Foundation
Institute, Helical Pile Committee, University of Cincinnati, Cincinnati, OH.
Page 3000-56
Rev. 12-09
the helix pier foundations have some lateral capacity, and that capacity can be validly estimated
using nonlinear p-y type analysis. A parameter was introduced to account for disturbance of the
ground due to the installation process of helix piers. This parameter, Cu, was determined to be
approximately 3.0 through correlations with lateral load test data. The effect of incorporating this
parameter into p-y type analysis is to increase deflection under lateral loads directly through
multiplication by Cu.
The buckling of square shaft helix piers used for underpinning was studied by Hoyt, R.,
Seider, G., Reese, L.C., Hon, M., and Wang, S. (1995). LPILE software was used to simulate
underground buckling in different soil conditions. The results were found to be in agreement with
full-scale field tests. Their results, which have been summarized below, indicated that the buckling
capacity of helix pier shafts in soft clays decreased with shaft length. This is opposite of
conventional Euler theory wherein the buckling capacity of slender columns generally decreases with
increasing unsupported shaft length. A close examination of their results shows that the helix piers
being modeled were failing due to overturning moments caused by bracket eccentricities rather than
pure buckling. The main conclusion of their study was that buckling of deeply embedded square
shaft helix piers with underpinning brackets occurs at less than 40 kips only in soft to very soft clay.
40
Stiff Clay
Med Sand
30
20
Soft Clay
V. Loose Sand
10
V. Soft Clay
0
0
10
15
20
Fig. 1 Buckling Capacity of 1-1/2" Square Shaft Helix Piers Used for Underpinning
(Modified from Hoyt, et al., 1995)
Since helix piers are being used with increased frequency for new foundations, it would be
beneficial to examine their buckling capacity without the stresses caused by bracket eccentricities.
Often in construction, deep foundations must be relied upon for lateral as well as axial support.
Hence, it is also of value to determine the lateral capacity of helix pier shafts. There are presently
5 to 6 helix pier manufacturing companies. Helix piers are available with different shaft
configurations from square to tubular. Examination of the lateral capacity and buckling resistance
of these different shaft sizes is also of interest.
-2Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-57
Rev. 12-09
Buckling Theory
Software for underground pile buckling computation is not readily available to the practicing
engineer. One of the most widely used software packages for lateral pile analysis is LPILE by Reese
and others. This software package incorporates a nonlinear discrete element p-y method of analysis
to determine lateral pile deflections under various boundary conditions. It is difficult to apply LPILE
to determine buckling capacity for pinned end conditions. However, a method using alternative
boundary conditions is suggested as a valid approximation for buckling.
Recall that Eulers formula can be written as (Beer, F.P. and Johnston, E.R., 1981)
Pcr
2 EI
=
Le 2
where Pcr is critical load, E is Modulus of Elasticity, I is area moment of inertia, and Le is effective
length. The effective length for a column with pinned end conditions is simply equal to the column
length as shown on the left side of Fig. 2. Similarly, the effective length for a column with fixed
slope and free translation top boundary conditions is shown on the right side of Fig. 2. Although
buckling for the pinned end condition can not be determined readily using LPILE, the buckling
condition with fixed slope and free translation conditions can be easily modeled. Since the elastic
curve for the buckled portion of each of these conditions has the same effective length, it is
suggested that the two configurations should yield approximately the same critical buckling load.
Hence, buckling for different helix pier shafts was computed herein using the second model with
fixed slope and free translation boundary conditions. Yet, the results are indicative of both
conditions.
Page 3000-58
Rev. 12-09
Clay
Sand
Very Loose
Loose
Medium
Dense
Very Soft
Soft
Medium
Stiff
Horiz. Mod.
of
SPT Blow
Subgrade
Count
Unit Weight Reaction
(blows/ft)
(pcf)
(pci)
0-4
70
5
4-10
96
25
10-30
110
90
30-50
130
225
0-2
82
30
2-4
86
100
4-8
92
500
8-15
104
1000
Angle of
Friction
(deg)
25
29
33
39
-
Cohesion
(psf)
200
400
800
1500
Strain at
50% Peak
Strength
(in/in)
0.06
0.02
0.01
0.005
(in )
2
(in )
0.42
2.25
1.06
1.02
2.5" Nom.
Schd. 80
Pipe
1.92
2.25
3.89
3.02
It was determined that buckling is a critical constraint on the design capacity of helix piers
only in very soft to soft clays and very loose to loose sands. Buckling capacity was in excess of
manufacturers recommended maximum allowable axial capacity of the helix piers in the other soil
conditions. The results of buckling calculations are shown in Table 3. Allowable buckling capacity
was determined from ultimate buckling capacity by application of a factor of safety of 1.5. The
results in the table represent the maximum recommended axial design capacity for these helix pier
shafts in the soil conditions shown. Buckling failure does not exclude the use of helix piers in weak
soils. Rather, it is required that the design axial capacity be lower than or equal to these allowable
limits in order to avoid buckling-type failure.
Page 3000-59
Rev. 12-09
Clay Sand
Very Loose
Loose
Very Soft
Soft
1.5"x1.5"
Square
Bar
1.75"x1.75"
Square
Bar
3.0" O.D.
0.12 Wall
HSST
2.5" Nom.
Schd. 80
Pipe
3.0" O.D.
0.25 Wall
HSST
3" Nom.
Schd. 80
Pipe
23
28
15
28
28
41
21
38
38
55
28
50
51
75
34
63
64
81
38
68
79
115
50
89
The results determined in this study for 1.5"x1.5" square shaft helix piers in very soft to soft
clay soils correspond well with those published by Hoyt, et al. (1995). As can be seen in Fig. 1, the
ultimate buckling resistance of 1.5"x1.5" square shaft helix piers used for underpinning, as
determined by Hoyt, et al. (1995), is approximately 28 kips for very soft clays and 37 kips for soft
clay. Application of a factor of safety of 1.5 yields allowable buckling capacities of 19 and 25 kips,
respectively. These values for the same shaft in similar soil conditions shown in Table 3 are 15 and
28 kips, respectively. The results determined in this study for 1.5"x1.5" square shaft helix piers in
very loose to loose sand soils are less than those determined by Hoyt, et al. (1995). One reason for
this difference is that the angle of internal friction for very loose sand used here was 25 deg instead
of 28 deg as assumed by Hoyt. The difference in values for very loose to loose sands between the
two studies could not be determined because buckling limits that occurred over 40 kips was not
published by Hoyt.
Interestingly, the length of shaft affected by buckling in these soil conditions varied generally
from 7 to 12 feet. Provided that at least this length of helix pier shaft was surrounded by weak soils,
the buckling capacity was independent of any additional length bounded by weak soils. This
contradicts traditional Euler buckling theory. The conclusion is made that underground buckling of
helix pier shafts occurs at the capacities shown if there is at least 7 to 12 feet of weak soils. The
buckling capacity of helix piers is not changed by the presence of more than 7 to 12 feet of week
soils. The length of helix pier shafts used in this study was 30 feet. The length of shaft over which
buckling occurred was determined by the depth where pier shaft deflections were insignificant.
The results show that confirm the conclusion of Puri, et al. (1984) that the lateral resistance
of helix piers is significantly affected by the mechanical rigidity of the helix pier shaft. More rigid
round helix pier shafts are able to support higher loads before buckling. Nonetheless, the practitioner
should reference Table 3 in order to check the design capacity of all helix pier shafts when
installation in weak soils is anticipated.
Lateral Capacity Analysis
In order to resist wind shear and earthquake loads, often large commercial and industrial
structures supported by helix pier foundations must be braced laterally by either supplying
foundation elements subject to passive soil resistance or by installing additional helix piers at a batter
angle. However, helix pier foundations have some lateral capacity which may be incorporated to
resist shear loads applied to lightly loaded structures so as to avoid the necessity of other measures.
The lateral capacity of 3.0" O.D., 0.25" thick wall, high strength structural tube helix pier
foundations was determined using LPILE software. Fixed slope, free translation top end boundary
-5Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-60
Rev. 12-09
conditions were incorporated in this analysis. These conditions are indicative of a pile that is rigidly
fixed to a structure so as to resist bending moments. However, the entire foundation could translate
laterally. The soil conditions used in the analysis were as shown in Table 1. Shaft mechanical
properties were as shown in Table 2. The results of the analysis are given in Figs. 3 and 4.
The results of the LPILE analysis of the lateral capacity of these helix piers indicates that
between 3,000 and 6,000 lbs of shear load can generally be applied in good soil conditions for "
of allowable lateral movement. These loads are not large, however even 3,000 lbs is sufficient to
support an example lateral wind pressure of 28 psf on an 8 ft x 8 ft section of wall or the lateral earth
pressure behind a 4 feet tall x 9 ft long crawl space wall (a factor of safety of 1.7 was incorporated
in the live loads used in these examples).
9,000
8,000
Stiff
7,000
6,000
Medium
5,000
4,000
Soft
3,000
2,000
Very Soft
1,000
0
0.0
0.2
0.4
0.6
0.8
1.0
Displacement (in)
Fig. 3 Lateral Load Resistance of 3" O.D., 0.25" Wall HSST Helix Piers in Clays
Page 3000-61
Rev. 12-09
9,000
Dense
8,000
7,000
6,000
Medium
5,000
4,000
Loose
3,000
2,000
Very
Loose
1,000
0
0.0
0.2
0.4
0.6
0.8
1.0
Displacement (in)
Fig. 4 Lateral Load Resistance of 3" O.D., 0.25" Wall HSST Helix Piers in Sands
Discussion
A parameter to account for disturbance of ground due to installation of helix blades per Puri,
et al. (1984) was not taken into account. However, the lateral loads given in Figs. 3 and 4 have been
confirmed in at least 5 separate load tests performed by Magnum Piering, Inc. in stiff clays. More
study is recommended for various pier shaft configurations and soil conditions to determine
positively if the soil disturbance parameter recommended by Puri is justified.
The free movement of forged upset couplings typically used with square shaft helix piers was
not taken into account in the buckling computations. As suggested by Hoyt, et al. (1995), additional
studies should be performed to determine the effect of these couplings on buckling capacity.
Conclusions
LPILE software was used to investigate the lateral strength and buckling resistance of helix
foundations in various soil conditions. It is suggested that the analysis performed using fixed
rotation, free translation end conditions is a valid estimation of the buckling resistance of helix pier
shafts with pinned end conditions. Buckling was found to impart limits on the allowable axial load
that can be applied to solid square shaft, standard pipe, and high strength structural tube helix pier
foundation shafts in very soft to soft clays and very loose to loose sands. Buckling was not found
to be important in more competent soil conditions. Buckling was found to occur over a 7 to 12 feet
long section of shaft regardless of the remaining length of shaft within the same weak soil stratum.
-7Copyright2000-10 Magnum Piering, Inc.
All Rights Reserved
Page 3000-62
Rev. 12-09
Results of buckling computations generally match those found previously by others using
underpinning bracket reactions.
The lateral capacity of 3" O.D. high strength structural tube helix pier shafts with rigid
connections was found to range from 3 to 6 kips for " of deflection in good soil conditions. These
results are consistent with lateral load tests conducted by Magnum Piering, Inc. of West Chester, OH.
Lateral capacity of 3 kips was shown to be of value in the design of residential and other lightly
loaded structures.
References
Beer, F.P. and Johnston, E.R., Jr. (1981) Mechanics of Materials, McGraw-Hill, Inc.
Hoyt, R., Seider, G., Reese, L.C., Hon, M., and Wang, S. (1995) Buckling of Helical Anchors Used
for Underpinning Foundation Upgrading and Repair for Infrastructure Improvement, ASCE, pp.
89-108.
Prasad, Y.V.S.N. and Rao, S.N. (1996) Lateral Capacity of Helical Piles in Clays Journal of
Geotechnical Engineering, Vol. 122, No. 11, November, ASCE, Reston, VA.
Puri, V.K., Stephenson, R.W., and Dziedzic, E., and Goen, L. (1984) Helical Anchor Piles Under
Lateral Loading Laterally Loaded Deep Foundations: Analysis and Performance, ASTM STP 835,
Langer, Mosley, and Thompson, Eds., American Society for Testing and Materials, pp. 194-213.
Page 3000-63
Rev. 12-09
Page 3000-64
Rev. 12-09
Page 3000-65
Rev. 12-09
Page 3000-66
Rev. 12-09
Page 3000-67
Rev. 12-09
Page 3000-68
Rev. 12-09
Page 3000-69
Rev. 12-09
Page 3000-70
Rev. 12-09
Page 3000-71
Rev. 12-09
Page 3000-72
Rev. 12-09
Page 3000-73
Rev. 12-09
Page 3000-74
Rev. 12-09
Page 3000-75
Rev. 12-09
Page 3000-76
Rev. 12-09
Page 3000-77
Rev. 12-09
Page 3000-78
Rev. 12-09
Page 3000-79
Rev. 12-09
Page 3000-80
Rev. 12-09
Page 3000-81
Rev. 12-09
Page 3000-82
Rev. 12-09
Page 3000-83
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
Corrosion
Corrosion is the exothermic chemical
transformation of a metal or metal alloy to a
non-reactive covalent compound such as an
oxide or silicate that is often similar or even
identical to the mineral from which the metals
were extracted. Thus, corrosion has been
called extractive metallurgy in reverse
(Payer, et al., 1980).
Rust is a general term often used for
the covalent compounds formed during the
corrosion of iron and steel. The composition
of rust depends on the abundance and species
1
Page 3000-84
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
Resistivity (S cm)
Very Low
>10,000
Low
5,000 to 10,000
Moderate
2,000 to 5,000
High
1,000 to 2,000
Very High
<1,000
Passivity
Passivity is the formation of a thin,
non-conductive, oxide surface film that
hinders the flow of electrical current and
reduces the rate of corrosion. Zinc forms such
a layer in the presence of carbon dioxide,
which is almost always found in soil pore air
and dissolved in ground water.
Long-term
soil-testing
programs
conducted by the National Bureau of
Standards between 1910 and 1955 comprise
much of the data on soil corrosivity in the
Galvanic Corrosion
The galvanizing
process
is
the
Page 3000-85
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
5.0
Severe
High
Moderate
Low
4.5
Clays
4.0
Peat
3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
50000
Page 3000-86
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
100%
3.0
90%
2.5
70%
2.0
Galvanized Pipe
Bare Pipe
60%
1.5
40%
1.0
80%
30%
20%
0.5
10%
0.0
0%
Pairs of Burried Pipe Samples in Different Soils
Life Expectancy
The helix foundation manufacturer
A.B. Chance Company (1992) used steel and
zinc loss in weight over time given by
Ramanoff (1989) to provide a sample
4
Page 3000-87
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
350
300
250
200
150
100
50
0
0
500
1000
1500
2000
2500
3000
3500
Soil Resistivity
(Ohm cm)
Fig. 3 Sample Calculation for Expected Helix Life (A.B. Chance, Co., 1992)
reduce corrosion rates by 50%, which is the
most conservative and least effect shown in
Fig. 2.
A helix foundation with 3/8 inch thick
blade and Schedule 80 pipe shaft was used as
the model in the analysis. This configuration
is representative of round-shaft helix
foundations manufactured by Magnum
Piering, Inc. (standard and heavy duty series),
Atlas Foundations, Inc., Precision Pier USA,
Inc., and the A.B. Chance Company, among
others. The computations are considered valid
approximations for square shaft helix
foundations with nominal dimensions of at
least 1.5x1.5 inches, however the computed
life expectancies should be divided by 2 for
thinner wall pipe shaft helix foundations such
as the Magnum Piering, Inc. light duty series.
Results of the analysis are shown in
Table 2. Different soil types were categorized
according to electrical resistivity.
Some
Page 3000-88
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
mode of helix
Soil Resistivity
(Ohm-cm)
0-2,000
2,000-10,000
10,000-30,000
> 30,000
Corrosivity
Category
SEVERE
HIGH
MODERATE
LOW
(Minimum)
95% Probability
(Average)
Example Soils
Galvanized
(15)
(40)
30
75
(80)
(200)
(55)
(140)
70
170
(135)
(340)
(50)
(125)
55
140
(140)
(350)
(345)
(865)
325
810
(555)
(1385)
Page 3000-89
Rev. 12-09
Presented at Helical Foundations and Tiebacks (November 2004) Specialty Seminar, Helical Foundations and
Tiebacks Committee, Deep Foundation Institute, Tampa, FL.
Page 3000-90
Rev. 12-09
Adams, J.I. and Hayes, D.C. (1967) The Uplift Capacity of Shallow Foundations Ontario Hydro
Research Quarterly, Vol. 19, No. 1, pp. 1-13.
Adams, J.I. and Klym, T.W. (1972) A Study of Anchors for Transmission Tower Foundations Canadian
Geotechnical Journal, Vol. 9, No. 1, pp. 89-104.
Bobbitt, D.W., and Clemence, S.P. (1987) Helical Anchors: Application and Design Criteria Proceedings
of the 9th Southeast Asian Geotechnical Conference, Vol. 2, pp. 6-105 - 6-120.
Carville, C.A. and Walton, R.W. (1994) Design Guidelines for Screw Anchors Proceedings of the
International Conference on Design and Construction of Deep Foundations, Vol. 2, pp. 646-655.
Carville, C.A. and Walton, R.W. (1995) Foundation Repair Using Helical Screw Anchors Foundation
Upgrading and Repair for Infrastructure Improvement, ASCE, pp. 56-75.
Clemence, S.P. and Pepe, F.D. Jr. (1984) Measurement of Lateral Stress Around Multihelix Anchors in
Sand. Geotechnical Testing Journal, GTJODJ, Vol. 7, No. 3, Sept. 1984, pp. 145-152.
Clemence, S.P. (1985) Uplift Behavior of Anchor Foundations in Soil Proceedings of a Session
Sponsored by the Geotechnical Eng. Div. of ASCE, Detroit, MI.
Clemence, S.P., Crouch, L.K., and Stephenson, R.W. (1994) Uplift Capacity of Helical Anchors in Soils
Proceedings of the 2nd Geotechnical Engineering Conference, Cairo, Vol. 1, pp. 332-343.
Clemence, S.P. and Smithling, A.P. (1984) Dynamic Uplift Capacity of Helical Anchors in Sand
Proceedings of the 4th Australia-New Zealand Conference on Geomechanics, Vol. 1, pp. 88-93.
Curle, R. (1995) Screw Anchors Economically Control Pipeline Bouyancy in Muskeg Oil and Gas
Journal, Vol. 93, No. 17, pp.
Davisson, M.T. and Gill, H.L. (1963) Laterally Loaded Piles in Layered Soil System Journal of Soil
Mechanics and Foundation Division, ASCE, Vol. 89, No. SM3.
Ghaly, A., Hanna, A., and Hanna, M. (1991a) Uplift Behavior of Screw Anchors in Sand. I: Dry Sand.
Journal of Geotechnical Engineering, Vol. 117, No. 5, pp. 773-793.
Ghaly, A., Hanna, A., and Hanna, M. (1991b) Installation Torque of Screw Anchors in Dry Sand Soils
and Foundations, Vol. 31, No. 2, Japanese Society of Soil Mechanics and Foundation
Engineering, pp. 77-92.
Ghaly, A. and Hanna, A. (1992) Stresses and Strains Around Helical Screw Anchors in Sand Soils and
Foundations, Vol. 32, No. 4, pp. 27-42.
Ghaly, A.M. and Clemence, S.P. (1998) Pullout Performance of Inclined Helical Screw Anchors in Sand
Journal of Geotechnical and Geoenvironmental Engineering, Vol. 124, No. 7, ASCE, Reston,
VA, pp. 617-627.
Ghaly, A., Hanna, A., Ranjan, G. and Hanna, M. (1991) Helical Anchors in Dry and Submerged Sand
Subjected to Surcharge Journal of Geotechnical Engineering, ASCE, Vol. 117, No. 10, pp. 14631470.
Page 3000-91
Rev. 12-09
Ghaly, A.M., Hanna, A.M. and Hanna, M.S. (1991) Uplift Behavior of Screw Anchors in Sand -II:
Hydrostatic and Flow Conditions Journal of Geotechnical Engineering, ASCE, Vol. 117, No. 5,
pp. 794-808.
Ghaly, A.M. and Hanna, A.M. (1991) Experimental and Theoretical Studies on Installation Torque of
Screw Anchors Canadian Geotechnical Journal, Vol. 28, No. 3, pp. 353-364.
Ghaly, A.M. and Hanna, A.M. (1991) Stress Development in Sand Due To Installation and Uplifting of
Screw Anchors Proceedings of the 4th International Conference on Piling and Deep
Foundations, Vol. 1, pp. 565-570.
Ghaly, A.M. and Hanna, A.M. (1994) Model Investigation of the Performance of Single Anchors and
Groups of Anchors Canadian Geotechnical Journal, Vol. 31, pp. 273-284.
Ghaly, A.M. and Hanna, A. (1994) Ultimate Pullout Resistance of Single Vertical Anchors Canadian
Geotechnical Journal, Vol. 31, No. 5, pp. 661-672.
Hanna, A. and Ghaly, A. (1992) Effects of Ko and Overconsolidation on Uplift Capacity Journal of
Geotechnical Engineering, ASCE, Vol. 118, No. 9, pp. 1449-1469.
Hanna, A. and Ghaly, A. (1994) Ultimate Pullout Resistance of Groups of Vertical Anchors Canadian
Geotechnical Journal, Vol. 31, No. 5, pp. 673-682.
Hargrave, R.L., and Thorsten, R.E. (1992). Helical Piers in Expansive Soils of Dallas, Texas 7th
International Conference on Expansive Soils.
Hoyt, R.M. and Clemence, S.P. (1989). Uplift Capacity of Helical Anchors in Soil. Proceedings of the
12th International Conference on Soil Mechanics and Foundation Engineering, Rio de Janeiro,
Brazil.
Hoyt, R., Seider, G., Reese, L.C., and Wang, S.T. (1995) Buckling of Helical Anchors Used for
Underpinning Foundation Upgrading and Repair for Infrastructure Improvement, ASCE, pp. 89108.
Huang, F.C., Mohmood, I., Joolazadeh, M., and Axten, G.W. (1995) Design Considerations and Field
Load Tests of a Helical Anchoring System for Foundation Renovation Foundation Upgrading
and Repair for Infrastructure Improvement, ASCE, pp. 76-88.
Johnston, G.H. and Ladanyi, B. (1974) Field Tests of Deep Power-Installed Screw Anchors in Permafrost
Canadian Geotechnical Journal, Vol. 11, No. 3, pp. 348-359.
Lutenegger, A.J., Smith, B.L. and Kabir, M.G. (1988) Use of In Situ Tests to Predict Uplift Performance
of Multi-Helix Anchors Special Topics in Foundations, ASCE, pp. 93-110.
Mitsch, M.P. and Clemence, S.P. (1985) The Uplift Capacity of Helix Anchors and Sand Uplift Behavior
of Anchor Foundations in Soil, ASCE, pp. 26-47.
Mitsch, M.P., and Clemence, S.P. (1985) Uplift Behavior of Anchor Foundations in Soil. Journal of
Geotechnical Engineering, ASCE, pp. 26-47.
Mooney, J.S., Adamczak, S.Jr., and Clemence, S.P., (1985) Uplift Capacity of Helix Anchors in Clay and
Silt Uplift Behavior of Anchor Foundations in Soil, ASCE, pp. 48-72.
Page 3000-92
Rev. 12-09
Narasimha Rao, S., Prasad, Y.V.S.N., Shetty, M.D. and Joshi, V.V. (1989) Uplift Capacity of Screw Pile
Anchors Geotechnical Engineering, Vol. 20, No. 2, pp. 139-159.
Narasimha Rao, S., Prasad, Y.V.S.N., and Prasad, C.V. (1990) Experimental Studies on Model Screw Pile
Anchors Proceedings of the Indian Geotechnical Conference, pp. 465-468.
Narasimha Rao, S., Prasad, Y.V.S.N., and Shetty, M.D. (1991). Behavior of Model Screw Piles in
Cohesive Soils. Soils and Foundations, Vol. 31, No. 2, pp. 35-50.
Narasimha Rao, S., Prasad, Y.V.S.N., and Veeresh, C. (1993). Behavior of Embedded Model Screw
Anchors in Soft Clays. Geotechnique, Vol. 43, No. 4, pp. 605-614.
Narasimha Rao, S. and Prasad, Y.V.S.N. (1993). Estimation of Uplift Capacity of Helical Anchors in
Clays. Journal of Geotechnical Engineering, Vol. 119, No. 2, ASCE, pp. 352-357.
Pack, J.S. (2000) Design of Helical Piles for Heavily Loaded Structures New Technological and Design
Developments in Deep Foundations, ASCE, pp. 353-367.
Perko, H.A. (2001) Introduction to Corrosion and Galvanizing of Helix Foundations Magnum Piering
Technical Reference Guide, Engineering Analysis, Section 3.
Perko, H.A. (2000) Energy Method for Predicting the Installation Torque of Helical Foundations and
Anchors New Technological and Design Developments in Deep Foundations, ASCE,, p. 342.
Perko, H.A. (1999) Summary of Earth Retaining Methods Utilizing Helical Anchors Magnum Piering
Technical Reference Guide, Engineering Analysis, Section 3.
Prasad, Y.V.S.N. and Narasimha Rao, S., (1994) Pullout Behavior of Model Piles and Helical Pile
Anchors Subjected to Lateral Cyclic Loading Canadian Geotechnical Journal, Vol. 31, No. 1,
pp. 110-119.
Prasad, Y.V.S.N. and Narasimha Rao, S. (1996) Lateral Capacity of Helical Piles in Clays Journal of
Geotechnical Engineering, ASCE, Vol. 122, No. 11, pp. 938-941.
Puri, V.K., Stephenson, R.E., Dziedzic, E. and Goen, L. (1984) Helical Anchor Piles Under Lateral
Loading, Laterally Loaded Deep Foundations: Analysis and Performance, ASTM Special
Technical Publication 835, Langer, J.A., Mosley, E.T., Thompson, C.D. Eds., pp. 194-213.
Radhakrishna, H.S. (1976) Helix Anchor Tests in Sand Ontario Hydro Research Division Research
Report 76-130-K, pp. 1-33.
Robinson, K.E. and Taylor, H. (1969) Selection and Performance of Anchors for Guyed Transmission
Towers Canadian Geotechnical Journal, Vol. 6, pp. 119-135.
Rodgers, T.E. Jr. (1987) High Capacity Multi-Helix Screw Anchors for Transmission Line Foundations
Foundation for Transmission Line Towers, ASCE, pp. 81-95.
Rupiper, S. (1994) Helical Plate Bearing Members, A Practical Solution to Deep Foundations
Proceedings of the International Conference on the Design and Construction of Deep
Foundations, Vol 2, pp. 980-991.
Rupiper, S.J. and Edwards, W.G. (1989) Helical Bearing Plate Foundations for Underpinning.
Proceedings of Foundation Engineering Congress/SCE/CO Div., Evanston, IL, June 25-29.
Page 3000-93
Rev. 12-09
Seider, G. (1999) Eccentrically Loaded Helical Pier Systems A.B.Chance, Co., Bulletin 01-9303.
Seider, G. (1993) Eccentric Loading of Helical Piers for Underpinning Proceedings of the 3rd
International Conference on Case Histories in Geotechnical Engineering, Vol. 1, pp. 139-145.
Trofimenkov, J.G. and Maruipolshii, L.G. (1965) Screw Piles Used for Mast and Tower Foundations
Proceedings of the 6th International Conference on Soil Mechanics and Foundation Engineering,
Vol. 2, pp. 328-332.
Udwari, J.J, Rodgers, T.D., and Singh, H. (1979) A Rational Approach to the Design of High Capacity
Multi-Helix Screw Anchors Proceedings of the 7th Annual IEEE/PES, Transmission and
Distribution Exposition, pp. 606-610.
Vickars, R.A. and Clemence, S.P. (2000) Performance of Helical Piles with Grouted Shafts New
Technological and Design Developments in Deep Foundations, ASCE, pp. 327-341.
Weikart, A.M. and Clemence, S.P. (1987) Helix Anchor Foundations - Two Case Histories Foundations
for Transmission Line Towers, ASCE, pp. 72-80.
Yokel, F.Y., Chung, R.M., and Yancey, C.W.C. (1981) NBS Studies of Mobil Home Foundations U.S.
National Bureau of Standards Report NBSIR 81-2238.
Page 3000-94
Rev. 12-09
SECTION 4000
PRODUCT QUALITY
Page 4000-1
Rev. 12-09
ESREPORT:PROPOSEDDRAFTMAGNUMHELICALFOUNDATIONSYSTEM
June5,2009
DIVISION:02SITECONSTRUCTION
Section:02465BoredPiles
REPORTHOLDER:
MAGNUMPIERING,INC.
6082SCHUMACHERPARKDRIVE
WESTCHESTER,OH45069
8008227437
www.magnumpiering.com
hperko@magnumpiering.com
EVALUATIONSUBJECT:
MAGNUMHELICALFOUNDATIONSYSTEM
1.0 SCOPE
Compliancewiththefollowingcodes:
InternationalBuildingCode(IBC)
PropertiesEvaluated:
AllowableloadanddeformationcapacitiesofMagnumhelicalpilesandassociatedbracketstoresist
axialcompression,axialtension,andlateralloadsincluding:P1BracketCapacity,P2ShaftCapacity,P3
HelixCapacity,andP4SoilCapacity(IncludingCapacitytoTorqueRatio).
2.0 USES
TheMagnumhelicalfoundationsystemconsistofhelicalpilesandbracketsasdefinedinIBC1802.1that
cansupportaxialcompression,axialtension,andlateralloadsforalltypesofstructuresconstructedin
accordancewiththeIBC.Theuseofthisevaluationreportisapplicableforsupportofstructuresunder
thefollowingconditions:
1. StructuresinIBCSeismicDesignCategoriesA,B,orC,only.Helicalpilessupporting
structuresinotherIBCSeismicDesignCategoriesshallbedesignedbyaregistereddesign
professionalaccordingtoIBC2009Section1810.3.11through1810.3.13andevidenceof
supportcharacteristicsshallbesubmittedtobuildingofficial.
2. Exposureconditionstosoilthatarenotindicativeofapotentialpiledeteriorationor
corrosionsituationasdefinedby:(1)soilresistivitylessthan1,000ohmcm;(2)soilpHless
than5.5;(3)soilswithhighorganiccontent;(4)soilsulfateconcentrationsgreaterthan
Page 4000-2
Rev. 12-09
1,000ppm;(5)soilslocatedinlandfills,or(6)soilcontainingminewaste.Helicalpilesin
soilsindicativeofapotentialpiledeteriorationorcorrosionsituationshallbedesignedbya
registereddesignprofessionaltakingintoaccountcorrosionlossandevidenceofsupport
overtheIBCdesignlifeof50yearsshallbesubmittedtothebuildingofficial.
3.0DESCRIPTION
TheMagnumHelicalFoundationSystemconsistsofsegmental,tubular,roundshaftswithbolted
couplingsandoneormorehelicalbearingplates.TheMagnumsystemincludestwohelicalpiletypes,
theMH325BGandtheMH325BRG,thatdifferonlybythecouplingmechanismbetweenshaftsegments.
TheMagnumsystemalsoincludestwodifferentmanufacturedfoundationbracketsforattachmentto
structures.AllMagnumhelicalpilesandbracketsaremanufacturedwithzincgalvanizedsteel.
Magnumhelicalpilesarerotatedintotheground.Thesystemscansupportbothtensileand
compressiveloadsandareusedinresidential,commercial,andindustrialconstruction.Applications
include,butarenotlimitedto:a.)deepfoundationsforresidentialandcommercialbuildings,bridges,
boardwalks,anddecks,b.)anchorsforhydrostaticuplift,retainingwalls,membranestructures,
moorings,andguywires,andc.)batteredpilesforresistanceofwind,flood,seismic,andotherlateral
loads.
3.1MH325BGandMH325BRGHelicalPiles
BothMH325BGandMH325BRGhelicalpilesconsistofacentralshaftmadeof3.0O.D.by0.25
minimumgaugehighstrengthstructuralroundtubemeetingtherequirementsofASTMA513Grade
1026,65ksiminimumyieldstrengthsteelorbetter.ThedifferencebetweentheMH325BGand
MH325BRGversionshastodowiththecouplingmechanismbetweenshaftsections.TheMH325BG
versionhasanoutercollarwithsingle7/8diameterSAEGrade5bolt.TheMH325BRGversionhasan
outercollarandaninnersleevecouplingwithasingle1diameterSAEGrade8bolt.
Helicalbearingplatesare3/8"thick,madeofASTMA36steelorbetter,andcoldpressedintoanear
perfecthelixshapewith3"averagepitchusingastampingmachine.Thehelicalbearingplatesare
attachedtothecentralshaftviaa1/4"continuousfilletweldallaroundtheperimeteroftheshafton
bothsidesofthehelix.Thehelicalbearingplatesarespaced25.5"oncenterandalternatedirections
alongthecentralshaft.ThisalternatingarrangementofhelicalbearingplatesisoneofMagnumPiering,
Inc.spatentedtechnologies,anditspurposeistobalancethemomentexertedontheshaftduring
rotationalpenetrationintotheground.Despitethealternatingarrangement,thehelicalbearingplates
arespacedtofollowthesamecuttingpathintheground.Momentbalancingreduceswobbleand
binding,therebyimprovingpenetrationandplumbness.Thepiletiphasa45degpilotpoint.
Helicalbearingplatesvaryindiameterandnumberdependingongroundconditionsandrequiredaxial
capacity.Commonlyavailablehelicalbearingplatediametersare8,10,12and14".Helicalbearing
platescoveredinthisevaluationreporthavestandardcircularedgegeometries.Typically,thesmallest
Page 4000-3
Rev. 12-09
diameterhelicalbearingplateisplacednearestthebottomendoftheleadsectionandthelargest
diameterhelicalbearingplateisplacedneartheuppermostortrailingend.
3.2MHC1000GTypeBDirectLoadBracket
TheMHC1000Gdirectloadbracketconsistsofa1thickrectangularsteelplateweldedtotwo
horizontalreinforcingsteelbarsandacollarsleeve.TheMHC1000Ghasthesamecollarsleeveandbolt
holeastheMH325BGhelicalpile.Thebracketisintendedtobeembeddedincastinplaceconcretefor
supportofconcretefoundationelements.
3.3MP1001GTypeASideLoadPlateBracket
TheMP1001Gconsistsofa21inchby8inch,0.38inchthickplatewitheighteen0.56inchdiameter
holesforattachmenttoconcretestructure.Weldedtotheplateisacollartubewiththreethreaded
inchdiameterboltholesforattachmenttotheshaftfromeithertheMH325BGorMH325BRGhelical
piles.Thisbracketisintendedtoattachtothesideofanexistingstructureforfoundation
augmentation.
4.0 DESIGNANDINSTALLATION
4.1GeneralDesign
4.1.1TheallowablecapacityoftheMagnumhelicalfoundationsystemshallbetheleastallowable
capacityofthebracket(P1),shaft(P2),helicalbearingplates(P3),andsoilfoundationinteraction(P4),
asapplicable.Tablesoftheallowablecompression,tension,andlateralcapacitiesofMagnumhelical
pilesystemsaregiveninTables1through4.Section1808oftheIBCshallapplytotheseproducts.
4.1.2Bracketcapacities(P1)aregiveninTable1.ConcretecovershownfortheMHC1000Gbracketin
thetabletakesintoaccountbearingandtwowaypunchingshear.InstallationofMP1001Gbrackets
shallbelimitedtouncrackedconcrete.Ifconcreteiscracked,itshallberepairedbeforeapplicationofa
helicalpilebracket.AregistereddesignprofessionalshallcheckconcretebreakoutperACI318for
expansionboltgroupandtheparticulargeometryoftheconcretestructuretowhichtheMP1001G
bracketisattached.
4.1.3Shaftcapacities(P2)aregiveninTable2forfullybracedconditionsandvariousunbraced
conditions.Allowablecapacitiesfortheunbracedconditionsaretabulatedbasedoneffectiveunbraced
length(kL)inordertoallowthedesignengineertoselecttheapplicablesoilconditionsandpilebracket
fixity.BracedandunbracedconditionsaredefinedinChapter18oftheIBC.Fluidsoilsaredefinedas
standardpenetrationtest(SPT)blowcountofweightofhammerorweightofrod,andsoftsoilsare
definedashavingaSPTblowcountof5orless.Shaftcapacity(P2)influidsoilsshallbedeterminedbya
registereddesignprofessional.
Page 4000-4
Rev. 12-09
4.1.4Helixbearingplatecompressionandtensioncapacities(P3)aregiveninTable3foreachdiameter.
Allhelicalbearingplateshavethesamethickness,pitch,andmaterialstrength.Thestrengthofthe
helicalbearingplatesandtheirconnectiontothepileshaftisthesameforbothMH325BGand
MH325BRG.
4.1.5Soilcapacityincompressionandtension(P4)shallbeverifiedinthefieldbasedoncorrelations
withinstallationtorqueasgivenby
Q=KtT
Qa=0.5Q
whereQisultimatecapacityinsoil,Ktisthecapacitytotorqueratio,Tisfinalinstallation
torque,andQaisallowablecapacity.
Therecommendedultimatecapacitytotorqueratio,Kt,forbothMagnumMH325BGandMH325BRG
helicalpilesis8.0ft1intensionandcompression.Theminimumembedmentdepthofahelicalpilein
tensionshallbe12timesthelargesthelicalbearingplatediameterorasestablishedbythelicensed
designprofessionalforloadingconditionsandsoilpropertiesatthesite.
4.1.6Soilcapacityforlateralresistance(P4)ofMagnumhelicalpilesinstiffclaysoilsisshowninTable4.
Soilcapacity(P4)inthelateraldirectionneedstobedeterminedbyaregistereddesignprofessionalper
IBC1810.2.4unlessthesoilconditionsforthesiteinquestionaregenerallyconsistentwithsoiltypes
describedinTable4.Foranyhelicalpilesubjecttocombinedlateralandaxialloading,themaximum
allowablestrengthisgovernedbytheinteractionequationgiveninAISCManualofSteelConstruction.
4.1.7Baresteelandzinccoatedcomponentsshallnotbecombinedinthesamefoundationsystem.
TabulatedvaluesofallowablecapacityinthisreportarebasedonthecorrodedsectionperAC358.
Helicalfoundationsystemsshallbeisolatedfromdirectelectricalcontactwithstructuralsteel,
reinforcingsteel,andothermetalcomponentsofbuildings.
4.1.8Asitespecificfoundationandsoilinvestigationreportisrequiredforalldeepfoundationsper
IBC1810.1.1.Thefoundationandsoilinvestigationreportshalladdresstheseissues:corrosive
propertiesofthesoil,supportconditionsforthepileshaft,effectsofgroundwater,andother
questionablecharacteristicsofthesubsurface.Thefoundationandsoilinvestigationreportshall
addressaxialcompression,axialtension,andlateralloadsoilcapacitiesifvaluescannotbedetermined
fromtheevaluationreport.
4.1.9Thelicenseddesignprofessionalshallperformthenecessarystructuralanalysisforproper
applicationofthesystemincludingconsiderationofinternalshearsandmomentsduetostructure
eccentricity,ifany,andthemaximumspanbetweenhelicalpiles.Lateralbracingandpilestabilityis
providedinaccordancewithIBCSection1810.2.1and1810.2.2.
Page 4000-5
Rev. 12-09
4.1.10Theminimumhelicalpileshaftspacingshallbe4timestheaveragehelicalbearingplatediameter
toavoidgroupeffects.Thelicenseddesignprofessionalshallperformagroupanalysisonpilesatcloser
spacings.
4.2Installation
TheMagnumhelicalfoundationsystemisinstalledbyMagnumcertifiedinstallerstrainedbythereport
holderintheproperinstallationoftheproductscoveredinthisevaluationreport.
4.2.1MH325BGANDMH325BRGHelicalPiles
Installationbeginsbyattachingthehelicalpileleadsectiontothetorquemotorusingadrivetooland
drivepin.Next,crowdshouldbeappliedtoforcethepilotpointintothegroundattheproperlocation,
inclination,andorientation.Thenthepileshouldberotatedintothegroundinasmooth,continuous
mannerwhilemaintainingsufficientcrowdtopromotenormaladvancement.Installationcontinuesby
addingextensionsectionsasnecessary.Inclinationandalignmentshouldbecheckedandadjusted
periodicallyduringinstallation.Connectionboltsbetweensectionsofshaftshallbesnugtightenedas
definedintheAISCManualofSteelConstruction.Careshouldbetakennottoexceedthetorsional
strengthratingofthehelicalpilesduringinstallation.Helicalpilesshallbeadvanceduntilaxialcapacity
isverifiedbyachievingtherequiredfinalinstallationtorqueandtheminimumdepth,ifany.
4.2.2MHC1000GTypeBDirectLoadBracket
Afterhelicalpileinstallationiscomplete,thepileshaftiscutofftotheplannedelevation.Tolerances
forfinalpileheadelevationaretypically+1to1/2inchunlessotherwisespecified.Ifcompressionloads
onlyarerequired,thebracketisplacedoverthecutoffpileshaftanddoesnotrequireabolt.Iftension
loadsarerequired,newholesaredrilledthroughthehelicalpileshaftinthefieldtomatchthebracket
collartubeandtoensuredirectbearingoftheplateonthepileshaftforcompression.Theholesshall
matchthediameterandminimumedgedistancesofthebracketcollartube.Torchcutholesarenot
permitted.Afterholedrilling,MHC1000Gbracketsfortensionapplicationsareinstalledoverthehelical
pileshaftandboltedinplacewithasingle7/8diameterSAEGrade5(ASTMA325)thruboltandhex
nut.
4.2.3MP1001GTypeASideLoadPlateBracket
Afterhelicalpileinstallationiscomplete,thebracketisslidoverthehelicalpileshaftandattachedtothe
concretestructureusingeitherdiameterITWRedHeadTruboltCarbonSteelWedgeAnchors(ESR
2251)orSimpsonStrongBoltWedgeAnchors(ESR1771).AhydraulicramorMagnumremoveable
liftingassemblymaybeusedtopreloadthepileortoliftthestructure,ifrequired.Then,11/16inch
diameterholesaredrilledthroughthehelicalpileshaftatthethreadedholelocationsinthebracket
collartubeandfromonetothreeSAEGrade8(ASTMA490)boltsareimpactedthroughthebracket
intothepileshaftinsingleshear.Thelengthofshaftextendingthroughthetopofthebracketcanbe
cutoffabovethebracket.
Page 4000-6
Rev. 12-09
4.2.4SpecialInspection
SpecialinspectionisrequiredinaccordancewithSection1704.10oftheIBC.Theitemstobeobserved
bythespecialinspectorshallinclude:verificationofmanufacturerandproductidentification,helical
pileandbracketconfiguration,installationtorqueanddepth,andcomplianceoftheinstallationwith
approvedconstructiondocumentsandthisevaluationreport.Inlieuofcontinuousspecialinspection,
periodicspecialinspectioninaccordancewithIBCSection1701.6.2maybepermittedwhenthe
followinginformationisprovidedtothebuildingofficial:a.)structuralobservationsinaccordancewith
IBCSection1702,b.)aperiodicinspectionschedule(preparedbytheregistereddesignprofessional),
andc.)evidenceofinstallertrainingbythereportholder.
5.0 CONDITIONS
MagnumMH325BGandMH325BRGhelicalpilesandbracketsdescribedinthisreportcomplywiththe
2009InternationalBuildingCodeandspecificallyIBCSection1810.3subjecttothefollowingconditions:
5.1HelicalpilesandbracketsaremanufacturedattheMagnumPiering,Inc.facilitylocatedat6082
SchumacherParkDrive,WestChester,Ohio45069.
5.2Helicalpilesandbracketsaremanufactured,identified,andinstalledinaccordancewiththisreport.
5.3TheappliedworkingloadsmustnotexceedtheallowableloadsinSection4.0ofthisreport.
6.0 EVIDENCESUBMITTED
Evidencesubmittedforevaluationincludeproductdescription,drawingsandspecifications,installation
instructions,engineeringcalculations,IASaccreditedlaboratoryandfieldloadtests,andqualitycontrol
documentation.
7.0 IDENTIFICATION
HelicalpilesandbracketsareidentifiedbyalabelbearingthenameofMagnumPiering,Inc.,the
productseriesormodelnumber,theevaluationreportnumber(ICCESESRT.B.D.),AC358acceptance
criteria,andajobnumberthatprovidesameanstotracethefinishedproductbacktotheproduction
andqualitycontrolrecordsatthemanufacturingfacility.
Page 4000-7
Rev. 12-09
Table1.BracketCapacity(P1)
BRACKET
SHAFTTYPE
TYPE
MP1001G MH325BGor
MH325BRG
(P1)ALLOWABLECOMP.&TENS.(KIPS)
CONNECTIONTO
CONNECTIONTOSTRUCTURE
PILE
QTY.OF3/4"
QTY.OFEXPANSIONANCHORS2
BOLTS
10
12
14
16
18
1
2
3
29
35
41
47
52
Appliedtofoundationasaresultofbracketeccentricity.
LessorofSimpsonStrongBolt(ESR1771)orITWRedhead(ESR2251).
18
35
OVERTURNING
MOMENT1
(KIPIN)
53
designload2"
BRACKET
TYPE
CONC.
SHAFTTYPE
STRGTH.
(PSI)
MHC1000G
2,500
MH325BGor
MH325BRG
4,500
(P1)ALLOWABLECAPACITY
CONCRETE
COVER
CONCRETE
COVER
"c"3
(IN)
11
15
9
COMPRESSION
(KIPS)
33
50
33
12
50
RequiredconcretecoverperFigure1.Minimum3inchesofcoverrequiredperIBCChapter18.
Maximumallowablecapacityintensionlimitedbyboltedconnectiontoshaft.
"t"3
(IN)
TENSION4
(KIPS)
11
33
33
Page 4000-8
Rev. 12-09
Table2.ShaftCapacity(P2)
SHAFT
TYPE
NUMBER
OF
UNBRACEDCONDITIONS
1
KL=0"
COUPLINGS8
0
MH325BG
1
2
0
MH325BRG
1
2
KL=40
KL=48"3
KL=80"4
KL=96"5
KL=126"6
KL=252"7
81
33
30
81
50
ALLOWABLEBUCKLINGCAPACITY9(P2)(KIPS)
70
65
43
33
19
33
33
33
28
18
29
28
22
19
14
70
65
43
33
19
50
50
38
30
18
5
5
5
5
5
50
50
47
34
27
17
Fullybracedcondition.Pileheadisbracedlaterallyandrotationally.Noportionofshaftisinair,water,orfluidsoils.
Fixedcondition.Pileheadisbracedlaterallyandrotationally.Shaftsupportedinfirmsoils(N5).
Pinnedcondition.Pileheadisbracedlaterallyonly.Shaftsupportedinfirmsoils(SPTN5).
Fixedcondition.Pileheadisbracedlaterallyandrotationally.Shaftsupportedinsoftsoils(SPT0<N<5).
Pinnedcondition.Pileheadisbracedlaterallyonly.Shaftsupportedinsoftsoils(SPT0<N<5).
Freecondition.Pileheadisunbraced.Shaftsupportedinfirmsoils(SPTN5).
Freecondition.Pileheadisunbraced.Shaftsupportedinsoftsoils(SPT0<N<5).
Numberofcouplingsinunbracedlength;takesintoaccountcouplingstrengthrigiditythroughsecondaryeffects.
ConsiderscorrosionperAC358,maximumcouplingstrength,andeccentricityinducedbycouplingrigidity.
SHAFT
TYPE
MH325BG
MH325BRG
OUTSIDE
CONDITION DIAM.
MIN.10
WALL
THICK.
MOMT.
GROSS
OF
AREA INERTIA
2
SECT.
MOD.
3
ALLOWABLECAPACITY(P2)
TENSION
FLEXURE
SHEAR
NEW
(IN)
3.01
2.99
3.01
(IN)
0.26
0.24
0.26
(IN )
2.22
2.11
2.22
(IN )
2.12
2.01
2.12
(IN )
1.41
1.34
1.41
(KIPS)
35
33
53
(INKIPS)
80
76
80
(KIPS)
27
26
27
CORRODED11
2.99
0.24
2.11
2.01
1.34
50
76
26
NEW
CORRODED11
10
Valuesgivenareminimumthickness.Nominal(average)thicknessaregenerally0.02"greater.
11
BasedoncorrosionofburriedgalvanizedsteelperAC358overIBCdesignlife.
Page 4000-9
Rev. 12-09
Table3.HelicalBearingPlateCapacity(P3)
HELIX
SHAFT
HELIX
DIAM.
(IN)
8
10
12
14
TYPE
MH325BG/MH325BRG
MH325BG/MH325BRG
MH325BG/MH325BRG
MH325BG/MH325BRG
GAUGE
(IN)
0.375
0.375
0.375
0.375
HELIX
PITCH
(IN)
3.0
3.0
3.0
3.0
ALLOWABLE
CAPACITY1(P3)
(KIPS)
50
54
56
56
Forhelicalpileswithmorethanonehelix,theallowablecapacityofthehelicalbearingplatesmaybe
summedtodeterminethetotalallowablecapacity(P3)ofthesystem.
Table4.LateralSoilCapacity(P4)
SHAFT
SOIL
AVERAGE
TYPE
TYPE
MH325BG SANDYCLAY4
MH325BRG SANDYCLAY4
SPTN
(BLOWS/FT)
21
21
MIN
DEPTH
(FT)
11.5
11.5
ALLOWABLE
ALLOWABLE
2
LATERALCAPACITY
(LBS)
2,200
1,425
LATERALCAPACITY3
(LBS)
3,400
2,200
Allowablecapacityishalftheloadcausing3/4"ofdeflectionperAC358Section4.4.2.2.
Allowablecapacityishalftheloadcausing1"ofdeflectionperIBC2009Section18.10.3.3.2.
Allowablelateralcapacity(P4)forothersoiltypesshallbedeterminedbyregistereddesignprofessionalperIBC1810.2.4.
Page 4000-10
Rev. 12-09
Figure1MagnumHelicalPileMH325BG
Page 4000-11
Rev. 12-09
Figure2MagnumHelicalPileMH325BRG
Page 4000-12
Rev. 12-09
Figure3MagnumMHC1000GDirectLoadBracket
Page 4000-13
Rev. 12-09
Figure4MagnumMP1001GSideLoadPlateBracket
Page 4000-14
Rev. 12-09
Page 4000-15
Rev. 12-09
APPENDIX B
QUALITY SYSTEM DOCUMENTATION CROSS-REFERENCE MATRIX
Identify in the matrix below where, in the quality system documentation, the information required in Section 2.0 of the
ICC-ES Acceptance Criteria for Quality Documentation (AC10) can be found.
Company Name:
Product/Material:
Todd Paddock
AC10 SECTION
2.1.1
(Signature)
2.1.2
(Manufacturing location
and contact info)
2.1.3
(Manual revisions)
2.1.4
(Product identification)
2.1.5
(Traceability)
2.1.6
(Work flow)
2.1.7
(Product changes)
2.1.8
(Organizational
information)
2.1.9
(Packaging)
2.1.10
(Complaints procedure)
2.2.
(Incoming materials)
2.3
(In-process quality
control)
2.4
(Final inspection)
2.5
(Nonconforming
materials)
2.6.1
(Test equipment)
2.6.1
(Calibrations)
Date:
DOCUMENT IDENTIFICATION
AND DATE OF DOCUMENT
Title page of Quality Control
Manual for Magnum Piering, Inc.
dated May 1, 2009 (hereafter QC
Manual)
Section 2.1.2 of QC Manual
May 1, 2009
Page 4000-16
Rev. 12-09
AC10 SECTION
2.7.1
(QC forms)
DOCUMENT IDENTIFICATION
AND DATE OF DOCUMENT
Section 2.7.1 of QC Manual
APPENDIX B
QUALITY SYSTEM DOCUMENTATION CROSS-REFERENCE MATRIX (Continued)
AC10 SECTION
2.7.2
(Document approval)
2.7.3
(Records retention)
DOCUMENT IDENTIFICATION
AND DATE OF DOCUMENT
Section 2.7.2 of QC Manual
Signature:
Name of signer (type or print):
Todd Paddock
TBD
Date:
May 1, 2009
Page 4000-17
Rev. 12-09
Page 4000-18
Rev. 12-09