Sunteți pe pagina 1din 57

NATIONAL TRANSMISSION &

DESPATCH COMPANY

NTDCs PRESENT SYSTEM, FUTURE PLANS,


BOTTLENECKS & KPIs
PRESENTATION BY

MUMMAD DAUD
GENERAL MANAGER PLANNING
NTDC

SEQUENCE OF
PRSENTATION
1. General- WAPDA/PEPCO- Structure
& Roles
2. NTDC system capacity
3. Future challenges & Target
4. NTDC expansion plan
5. Bottle necks
6. Key performance indicators
3

General- WAPDA/PEPCOStructure & Roles

Pakistan
Water and Power Development Authority
(WAPDA)
WAPDA was formed in 1958. The major
responsibilities of WAPDA were;
Meet electricity demand of the country (except area of
Karachi) by installing new power plants, transmission lines
and distribution system.
Develop hydro storage project ( dams) for meeting
irrigation and demand of the country and install hydro
plants at dams locations.
WAPDA consisted of two segments :
Power Wing: For meeting electricity demand and
responsible for
generation, transmission and distribution.
Water Wing : For developing hydro projects for irrigation
requirements.
5

PAKISTAN POWER SECTOR: BACKGROUND


1. The GoP approved Pakistan Power Sector Strategic Plan for
restructuring and reform in 1992, according to which, the power wing of
WAPDA was structured into four (4) Generation Companies (GENCOs),
one (1) National Transmission and Dispatch Company (NTDC) and nine
(9) Distribution Companies (DISCOs).
2. PEPCO was established in 1998 as an independent entity with mandate
to restructure Pakistan Power Sector, corporatise & commercialize the
restructured entities, and to bring about reforms thru introduction of
competition, enhancement of efficiencies and best financial and prudent
utility practices.
3. PEPCO initiated the restructuring and reform process in 1998 with
limited initial success. The reform process was considerably slowed
down beyond 2001 when PEPCO was reduced to a Division in WAPDA.
4. The GoP reactivated the mandate of PEPCO in October 2007 to bridge6
the increasing demand supply gap and to reduce the resulting load
6
shedding in the country.

NEW FACE OF PAKISTANS POWER SECTOR

GOP/MW&P

Chairman PEPCO

Chairman WAPDA

MD PEPCO
PEPCO Management
Team

MEMBERS: Hydel power,


Finance, Water

WATER
WING

WATER

FINANCE
POWER
WING
WING
RESIDUAL WAPDA
WINGS PART
TRANSITION TO
CORPORATE ENTITIES

HYDEL
FINANCE

HYDEL
POWER

COMMON
SERVICES

RESTRUCTURED POWER
WING
AUTONOMOUS COMPANIES WITH
INDEPENDENT COMMERCIAL
OPERATIONS THROUGH BOD

HOSPITALS
ACADEMY
ETC

SERVICES

GENCOs

(4)

NTDC

(1)

DISCOs

(9)

National Transmission and Dispatch


Company Ltd.

National Transmission & Despatch Company


(NTDC) Limited was incorporated on 6th
November, 1998 and commenced commercial
operation on 24th December, 1998. It was
organized to take over all the properties,
rights and assets, obligations and liabilities of
220 KV and 500KV Grid Stations and
Transmission Lines/Network owned by
Pakistan Water and Power Development
Authority (WAPDA). .
8

NTDC Structure
NTDC segments.
1. Transmission Network Operator (TNO)
2. System Operator (SO)
3. Central Power Purchasing Agency
(CPPA)
4. Contract Registrar and Power
Exchange Administrator (CRPEA)
9

NTDC system capacities

10

Length of Transmission
Lines
Year

500kV (circuit kM)

220kV (circuit kM)

1980

315

2101

1985

1239

2422

1990

1863

2922

1995

3315

3848

2000

4094

5498

2005

4344

6993

2010

5078

7366
11

Growth in Length of Transmission


Lines (NTDC)

12

No. & Capacity of Substations


(NTDC)
500- KV Substations

220- KV Substations

*1 No. 220 KV gird station was added &


1No. 220 KV Grid station was converted to 500 KV
13

Growth of Transmission System


capacity MVA (NTDC)

14

NTDC T&T LOSSES


Year

T&T Losses
(%)

Remarks

2005

7.63

Includes losses of 132 kV Sys

2006

7.26

Includes losses of 132 kV Sys

2007

3.80

500 & 220 kV only

2008

3.48

500 & 220 kV only

2009

3.58

500 & 220 kV only

2010

3.12

500 & 220 kV only

15

16

Future challenges & Targets

17

Future Required Generation Capacity


Year

Peak Demand
(MW)

Gen Capacity
Required (MW)

Gen Capacity
Planned (MW)

2010

20101

25126

21388

2011

21705

27131

22697

2012

23441

29301

23788

2013

25306

31633

26279

2014

27438

34298

29405

2015

29463

36829

33630

2016

31672

39950

42530

2017

33154

41443

45338

2018

35568

44460

50034

2019

38557

48196

53284

2020

41783

52229

57470
18

PEPCO System Historical Data / Forecast


Historical

PMS

Peak

Peak

Difference

( MW )

(MW)

(%)

1999-00

9289

9311

0.24

2000-01

9718

9736

0.18

2001-02

10922

10243

-6.21

2002-03

10484

10799

3.00

2003-04

11078

11398

2.80

2004-05

12035

12087

0.43

2005-06

13212

12916

-2.20

2006-07

15138

15213

0.50

2007-08

16838

16480

-2.10

2008-09

17252

17867

3.50

2009-10

17847

19451

8.90

Years

19

EXISTING GENERATING
CAPACITY (Oct, 2010)
Type of Generation

Nameplate
Derated/
/Installed Dependable
Capacity
Capacity
(MW)
(MW)

Availability (MW)

Summer

Winter

WAPDA Hydro

6444

6444

6250

2300*

GENCOs

4829

3580

2780

3222**

IPPs (incl Nuclear)

7911

7695

5750

6900**

Rental

62

60

60

60**

Total

19246

17779

14840

12482

Hydro availability based on last 5 years average


** Excludes 10% Forced Outages for GENCOs & 6.0% for IPPs &
Rental

20

21

22

FUTURE GENERATION PROJECTS


SYSTEM
(Up to Year 2020)

23

NTDC Expansion plan

NTDC ONGOING DEVELOPMENT PROJECT


SR.
NO.

NAME OF SUBSTATIONS

TRANSFORMER
CAPACITY (MVA)

ASSOCIATED TRANSMISSION
LINES

EXPECTED
COMMISSIONING

Ext. at 500 kV Sheikh


Muhammadi

1x450

Dec, 2010

Ext. at 500 kV Tarbela.

1x237

Dec, 2010

Ext. at 220 kV Bannu

1x160

Augmentation of 220
kV at N.K.L.P Lahore

3x250

Upgradation of
existing 132 kV to
new 220 kV GIS
Wapda Town Lahore.

3x160

220 kV Lahore - K.L.P D/C


In/Out at Wapda Town. (10+10
km)

New 220 kV GIS


Bandala

2x160

220 kV Gatti - K.S.K D/C In/Out


at Bandala. (5+5 km)

Dec, 2011

Installation of SVCs
at 220 kV N.K.L.P.
Lahore.

SVCs

Static Var Compensators of


appropriate capacity.

Dec, 2011

June, 2011
T2 & T3
Commissioned
T1: Dec. 2011
G/station
commissioned
T/Line by Mar.
2011

NTDC ONGOING DEVELOPMENT PROJECTS


SR.NO.

NAME OF
SUBSTATIONS

Looping In/Out of
220 kV G/BarothaS/Bagh T/L at
Mardan

TRANSFORMER
CAPACITY (MVA)

ASSOCIATED TRANSMISSION
LINES

EXPECTED
COMMISSIONING

Looping in & out of one circuit


of Ghazi Barotha Shahi Bagh
at Mardan (30 km)

Mar, 2011

Dec, 2011

Extension/Augmenta
tion at existing
substations:
500 kV Dadu

1x450
1x160

220 kV Burhan

1x160

220 kV Mardan

1x250

500 kV Sheikh
Muhammadi

1x160

500 kV New Rewat

1x250

220 kV Shikarpur
10

1x160

220 kV Okara
3x250

11

220 kV Toba Tek


Singh/Gojra

3x250

Commissioned
220 kV Yousafwala - Sarfaraz
Nagar D/C In/Out at Okara. (5 +
5km)
220 kV Faisalabad-Multan D/C
In&Out at T.T.Singh/Gojra. (1+1

Dec, 2011

NTDC ONGOING DEVELOPMENT PROJECTS


SR.
NO.

NAME OF NEW
SUBSTATIONS

TRANSFORMER
CAPACITY (MVA)

12

Installation of
SVC at Quetta

13

Ext. at Ghazi
Brotha for
addition of 600
MVA 500/220 kV
T/F.

1x600

14

220 kV Loralai

2x250

15

Augmentation of
220 kV Ravi at
Lahore.

3x250

500kV D.G Khan


Substation.

2x600
2x250

16

SVC

ASSOCIATED TRANSMISSION
LINES
Static Var Compensators of
appropriate capacity

EXPECTED
COMMISSIONING
Jun, 2012

Jun, 2011

220 kV D.G Khan Loralai (250 km)

Dec, 2012

March, 2011
500kV Guddu-Multan 2nd cct In/Out
at D.G. Khan substation(20+20) km

Dec, 2012

NTDC ONGOING DEVELOPMENT PROJECTS


SR.
NO.

NAME OF NEW
SUBSTATIONS

17

220 kV Rohri
New for
interconnection
of IPPs at Engro
Energy PP and
Mari (Dharki)
CCPP

TRANSFORMER
CAPACITY
(MVA)
2x250

ASSOCIATED TRANSMISSION
LINES

EXPECTED
COMMISSIONING

220 kV D/C T/L Dharki CCPP


Rohri New (115 km)
132 kV D/C T/L for In/Out of
Rohri-Khairpur/Gambat D/C T/L
at Rohri New (1+1 km)
220kV D/C Rohri New-Shikarpur
T/L (50 km)

Dec, 2011

220 kV D/C T/L for In/Out of


Dharki -Rohri New at Engro
CCPP (5+5 km)
132 kV Rohri New-Gambat D/C
T/L (53 km)
18

19

220 kV
Gridstation at
Khuzdar,
220 kV Grid
Station at Ghazi
Road, Lahore

2x160
3x160

220kV D/C Dadu Khuzdar


Transmission Line (300 km)
220 kV D/C T/L for In&Out of
NKLP Sarfraz Nagar at Ghazi
Road. (30 km)
220 kV D/C T/L for In&Out of
Ravi KSK at Ghazi Rd. (30 km)

Dec, 2011

Dec, 2012

NTDC ONGOING DEVELOPMENT PROJECTS


SR.
NO.
20

NAME OF NEW
SUBSTATIONS

T/F
CAPACITY
(MVA)

ASSOCIATED TRANSMISSION
LINES

EXPECTED
COMMISSIONING

220 kV D/C Transmission Line for


In&Out of Vehari Yousafwala at
Kassowal. (45+45 km)

Jan, 2012

220 kV D/C T/L from Pak-Iran


border to Gwadar (100 km)

Jun, 2012

Jun. 2012

220 kV Grid Station at


Kassowal along with
associated 220kV D/C
T/Lines.

2x160

21

220 kV GIS substation


at Gwadar

2x160

22

500 kV R.Y.Khan

2x600

500 kV Guddu - Multan 3rd


Circuit In/Out at R.Y.K (30+30 km)

23

220 kV GIS Shalamar


(Mehmood Buti)

3x250

220 kV Ravi-KSK D/C In/Out at


Shalamar (9km long overhead
T/L) & (3+3km) cable

Jun.2012

NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP

S.#

Name of
Project

220 kV
Gujrat

220 kV
Chishtian

500 kV New
Lahore

Transformer
Capacity
(MVA)

ASSOCIATED
TRANSMISSION
LINES

3x250

220 kV ManglaGhakkar D/C In/Out at


Gujrat (2+2 km)

2805

33

22.10.2007

JICA

2x250

220 kV Vehari Chishtian D/C T/Line.


( 65 km)

3740

44

22.10.2007

JICA

12665

149

PC-I
cleared by
CDWP on
18.03.2010

JICA

2x750

Two 500 kV S/C


T/Lines for In/out of
500 kV Sahiwal
Lahore S/C at Lahore
New (15+15 km)
Two 500 kV S/C
T/Lines for In/out of
500 kV Lahore
Gujranwala S/C at
Lahore New (50+50
km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Ghazi
Road at Lahore New. (50
km)
220 kV D/C T/Line for In/out
of 220 kV NKLP-Wapda
Town at Lahore New.
(54km)

Estimated
Approval
Expected
Cost
Eqt. US$
by
Financing commissi(Rs. in
in Million
ECNEC
oning
Million)
2011-12

2011-12
2012-13

NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP

S.#

Name of
Project

Transformer
Capacity
(MVA)

ASSOCIATED
TRANSMISSION
LINES

Estimated
Expected
Eqt. US$
Cost
Approval
Year of
in
Financing
(Rs. in
by ECNEC
commissiMillion
Million)
oning

Two 500 kV S/C


T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:1 at
Shikarpur (20+20
km)

500 kV

4- Shikarpur

2x600

Two 500 kV S/C


T/Lines for In/out of
500 kV Dadu-Guddu
circuit No:2 at
Shikarpur. (22+22
km)
220 kV D/C for
In/Out of 500/220 kV
Guddu Sibbi S/C
at Shikarpur (50 km)

8160

96

Pc-I
Cleared
by CDWP
on
18.03.2010

JICA

2012-13

NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP


S.#

Name of
Project

TransforEstimated
Expected
ASSOCIATED
Eqt. US$
mer
Cost
Approval
Year of
TRANSMISSION
in
Financing
Capacity
(Rs. in
by ECNEC
commissiLINES
Million
(MVA)
Million)
oning

220 kV D/C T/L


for In/out of
MansheraIslamabad T/L
(40 km)

2nd Source of
supply to
6Hala Road
Grid Station

220 kV D/C T/L


from T.M Khan
Road to Hala
Road (30 km)

850

10

PC-I under
preparatio ADB Tr-iV
n

220 kV
Nowshera

2x160

850

10

06.02.2008 ADB Tr-iV

2012-13

2X250

220 kV Chakdara
Mardan (85
km)

38

PC-I under
preparatio ADB Tr-iIV
n

2013-14

2nd source of
supply to
5Islamabad
University

7-

220 kV
8Chakdara

1105

3230

13

PC-I under
preparatio ADB Tr-IV
n

2012-13

2012-13

NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP


S.#

Name of
Project

Transformer
Capacity
(MVA)

Augmentation
of 500 & 220 kV
existing
substations

Estimated
Expected
ASSOCIATED
Eqt. US$
Cost
Approval
Year of
TRANSMISSI
in
Financing
(Rs. in
by ECNEC
commissiON LINES
Million
Million)
oning

500 kV Rewat

1x750

500 kV Sh.
Muhammadi

4x250

2x250

4x250

220 kV Bund
Rd

4x250

220 kV
Bahawalpur

2x250

220 kV Quetta
Industrial

2X250

9- 220 kV Mardan
220 kV Burhan

3825

45

PC-I
submitted
to GoP in
Aug,2010

ADB Tr-I
(Ext-II)

2011-12

NTDC FUTURE PROJECTS WHERE FINANCING HAS BEEN LINED UP


Transfor
S.#
-mer
Name of Project
`
Capacity
(MVA)

10-

11-

220 kV Mirpur
Khas

220 kV Taxila.

12- 220 kV Manshera

13-

220 kV D.M
Jamali

Interconnection
of 1200 MW AES
Imported coal
14based Power
Plant near
Karachi (Part-I)

ASSOCIATED
TRANSMISSION
LINES

Estimate
Expected
d Cost
Eqt.
Approval
Year of
(Rs. US$ in
Financing
by ECNEC
commissi
in
Million
-oning
Million)

2x160

220 kV D/C T/L from


Hala Rd. to .M.Khan
Rd. (10 km)
In/Out of one
circuit of above
220 kV proposed
T/L at Mirpur Khas
New (70 km).

2975

35

PC-I under
preparation

ADB Tr-IV

2013-14

2x250

In/Out of 220 kV
Burhan - ISPR S/C
at Taxila. (6 km)

2295

27

PC-I under
preparation

ADB Tr-IV

2013-14

2x160

In/out of 220 kV Alai


Khawar-Sangjani
T/L at Manshera
(0.5+.0.5 km)

1105

13

PC-I under
preparation

Iranian
Loan

2013-14

1x160
1x100

in/out of 220 kV
Uch-Guddu S/C at
D.M. Jamali (5 km)

10

PC-I
submitted
to GoP

PMs Fund

2013-14

500 kV Jamshoro-R.Y.K (535 km)


500 kV Moro-Dadu
(55 km)

298

PC-I cleared
by CDWP
on
18.03.2010

ADB Tr-III

2015-16

850

25330

NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED

SR
#.
1-

NAME OF NEW
SUBSTATIONS

ESTIMATE
D COST*
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

2890

34

2012-13

2975

35

2012-13

2x250

220 kV Gatti - Ludewala


D/C In/Out at Chiniot
Industrial. (2+2 km)

2380

28

2012-13

2x250

220 kV D/C cable from


Shadman to Bund Road
(30 km)

4250

50

2012-13

3825

45

T/F
CAP.
(MVA)

220 kV Chakwal
2x160

2-

220 kV GIS Jhang


Rd. Faisalabad

3-

220 kV Chiniot.
Industrial

4-

5-

7-

2x250

220 kV Shadman

220 kV D.I Khan

220 kV Gharo

2x250

2x250

ASSOCIATED
TRANSMISSION LINES
In/out of 220 kV ManglaRewat S/C at Chakwal
(50 km)
220 kV Samundri Rd.
Jhang Rd. D/C T/L (40 km)

220 kV D/C T/Line for


In/out of 220 kV Chashma
Nuclear Ludewala S/C at
D.I Khan (100 km)
220 kV Gharo T.M Khan
Road ((130)

2012-13

4590

54

2012-13

NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED


SR
#.

NAME OF NEW
SUBSTATIONS

8-

220 kV Jhimpir

9-

220 kV
Mastung

10-

220 kV Jamrud`

11-

500 kV
Faisalabad New

ASSOCIATED
TRANSMISSION LINES

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRD
YEAR OF
COMMISSIONING

2x250

In/Out of 220 kV Gharo T.M


Khan Road at Jhimpir (65
km)

3230

38

2012-13

2x250

220 KV Mastung Sibbi (120


km)

4080

48

2013-14

2x250

220 kV Jamrud Sh.


Muhammadi (10 km)

1445

17

2013-14

2x750

In/out of 500 kV Muzaffargarh


Gatti 1st circuit at at
Faisalabad new (1+1 km)

6630

78

2013-14

3570

42

2013-14

T/F
CAP.
(MVA)

2x250
12-

220 kV M-3
Industrial
Estate
Faisalabad

220 kV Faisalabad New T.T


Singh D/C T/Line (70 km)
220 kV M3 Industrial Estate
Faisalabad New (70 km)

2x250

In/Out of 220 kV Faisalabad


New - M3 Industrial Estate at
220 kV Chinot Industrial New
(30 km)

NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED

SR
#.

NAME OF NEW
SUBSTATIONS

13-

500 kV
Peshawar New

T/F
CAP.
(MVA)

220 kV Kohat

REQUIRED
YEAR OF
COMMISSIONING

In/Out of 220 kV Sh.


Muhammadi-Shahibagh at
Peshawar New (5 km)

5440

64

2014-15

5950

70

2014-15

2635

31

2014-15

425

2014-15

1445

17

2015-16

220 kV Kohat Peshawar


New (50 km)
2x250

15-

Eqt.
US$ in
Million

In/out of Tarbela Sh.


Muhammadi at Peshawar
New (2+2 km)
2x750

14-

ASSOCIATED
TRANSMISSION LINES

ESTIMATE
D COST
(Rs.in
Million)

220 kV
Islamabad I-10

2x250

16-

Ext. at 220 kV
Gujrat

1x250

17-

220 kV
Kamalabad

2x250

220 kV Kohat Bannu


(150 km)
In/Out of 220 kV Rewat
Islamabad University D/C at
Islamabad I-10 (30+30 km)
In/out of Rewat Islamabad
Peshawar Rd. at Kamalabad
(5+5 km)

NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED


SR
#.

NAME OF NEW
SUBSTATIONS

T/F
CAP.
(MVA)

18-

Ext. at 500 kV
Gujranwala

1x600

19-

Ext. at 500 kV
Lahore New

1x750

20-

220 kV Kamra

21-

220 kV Iqbal
Town

22-

220 kV
Gujranwala
New

ASSOCIATED
TRANSMISSION LINES
-

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

1700

20

2015-16

2040

24

2015-16

2x250

In/out of 220 kV Tarbela


Taxila at Kamra (5 km)

1275

15

2015-16

2x250

In/Out of 220 kV Lahore


Wapda Town D/C at Iqbal
Town (20+20 km)

2125

25

2015-16

2890

34

2015-16

28

2015-16

2x250

In/Out of 220 kV Mangala


K.S.K at Gujranwala New
(20 km)
220 kV Nokhar - Gujranwala
New (50 kM)

2324-

220 kV Pindi
Bhattian
220 kV Head
Faqirian

2x250

220 kV Pindi Bhattian Ind.


Gujranwala (50 km)

2380

2x250

220 kV Head Faqirian


Ludewala (60 km)

2380

28

2015-16

NTDC FUTURE PROJECTS FOR WHICH FINANCING IS REQUIRED


SR
#.

NAME OF NEW
SUBSTATIONS

25-

220 kV
Joharabad

26-

220 kV Alizai

27-

2nd Source of
supply to 220
kV Chakwal
substation

28-

29-

2nd Source of
supply to 220
kV Bhawalpur
substation
220 kV Arif
Wala

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

2x250

In/out of 220 kV D/C


Ludewala Chashma at
Jauharabad (5+6 km)

1445

17

2015-16

2x250

220 kV Kohat Ali zai D/C


(110 km)

3825

45

2015-16

In/out of 220 kV Mangla


-Rewat 2nd circuit at Chakwal
(60 km)

1530

18

2015-16

3825

45

2015-16

1445

17

2015-16

82620

972

T/F
CAP.
(MVA)

2x250

ASSOCIATED
TRANSMISSION LINES

220 kV R.Y.K Bahalawlpur


D/C T/L (150 km)

In/Out of 220 kV Yousafwala


Kassowal D/C at Arifwala
(5+5 km)

Total:

POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS


SR
#.

NAME OF NEW
SUBSTATIONS

T/F
CAP.
(MVA)

1-

Power Dispersal
from 747 MW
CCPP at Guddu

2-

Dispersal of
Power from Uch-2

3-

UAE Combined
Cycle power plant
at GTPS
Faisalabad

4-

Interconnection of
1200 MW AES
Imported coal
based power near
Karachi (Part-II)

1x160

500 kV
switch
ing
statio
n at
Matiari

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

7735

91

2012-13

220 kV Uch-II Sibbi D/C


(125 km)

2975

35

2012-13

In/out of existing 220 kV


T/lines at Proposed power
plant

1700

20

2012-13

14450
(PC-I
cleared by
CDWP on
18.3.10)

170

2015-16

ASSOCIATED
TRANSMISSION LINES
500 kV Guddu New PP
M. Garh (256 km)
In/Out of Guddu Multan
at New Guddu (10+10 km)

500 kV S/C T/Line from


AES Power Plant to
Matiari switching station
(200 km)
In/Out of 500 kV HubJamshoro S/C T/Line at
AES (45+45 km)
In/out of 500 kV
Jamshoro-R.Y.K at Matiari
(5+5 km)

POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS


SR
#.

5-

NAME OF NEW
SUBSTATIONS

Interconnection of
1200 MW Engro &
1200 MW PEPCOs
Thar Coal Based
Power Plants at
Thar

Interconnection of
1200 MW Imported
coal based PPIB
and 1000 MW
Imported Coal
based PEPCOs
power Plants at
Karachi

T/F
CAP.
(MVA)

ASSOCIATED
TRANSMISSION LINES

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

88400

1040

2015-16

85000

1000

2015-16

500 kV D/C T/L form Thar


coal power plants to
Matiari (275 km)
-

500 kV HVDC Matiari


Lahore/ Faisalabad T/L
(1100 km)
Terminal Stations at both
ends
Two 500 kV circuits from
Power Plants to Matiari
(200 km each)

500 kV HVDC Matiari


Lahore/Faisalabad T/L
(1100 km)
Extension of Terminal
Stations at both ends

POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS


SR
#.

NAME OF NEW
SUBSTATIONS

7-

Import of 1000 MW
Power from Iran

8-

Import of 1000 MW
Power from
Tajikistan (CASA1000)

9-

Dispersal of
Power from 340
MW Chashma-III

T/F
CAP.
(MVA)

ASSOCIATED
TRANSMISSION LINES
Two 500 kV HVAC S/C
T/Lines from Zahidan to
Quetta with series
compensation (198 km)
Switching station at
Zahidan, Quetta and
midpoint between Zahidan
& Quetta
500 kV HVDC T/L from
Pak-Afghan Border to
Peshawar (71 km)

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

40120

472

2015-16

16065

189

2015-16

3000

35

2016-17

500 kV Converter Station


Peshawar
220 kV Chashma New
Bannu (125 km)
-

In/out of 220 kV D.I. Kahan


Jahurabad S/C at
Chashma New (1 km)

POWER DISPERSAL PROJECTS FOR THERMAL POWER PLANTS


SR
#.

NAME OF NEW
SUBSTATIONS

10-

Interconnection of
2x1000 MW
Nuclear Power
Plants at Karachi

T/F
CAP.
(MVA)

ASSOCIATED
TRANSMISSION LINES

ESTIMATE
D COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

Three 500 kV Circuits from


Nuclear Plants to Matiari
(200 km each)

25500

300

2018-19

284945

3352

Total

LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER


PLANTS
SR
#.

NAME OF NEW
SUBSTATIONS

1-

Dispersal of
Power from 969
MW Neelum
Jhelum Hydro
Power Project to
Rawat &
Gujranwala

2-

Dispersal of
Power from 720
MW Karot HPP

3-

Power Dispersal
of 740 MW
Munda HPP

T/F CAP.
(MVA)

ASSOCIATED
TRANSMISSION
LINES

ESTIMATED
COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

19125

225

2015-16

13250

156

2015-16

850

10

2016-17

500 kV Neelum
Jhelum Rawat S/C
T/Line (110 km).
500 kV Neelum
Jhelum Gujranwala
S/C T/Line (235 km)
500 kV Karot
Lahore New (270 km)
-

In/Out of 500 kV
Neelum Jhelum
Gujranwala at Karot
(10 km)
In/Out of 220 kV
Peshawar Shahi
Bagh at Munda (35
km)

LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER


PLANTS
SR
#.

NAME OF NEW
SUBSTATIONS

T/F CAP.
(MVA)

ASSOCIATED
TRANSMISSION
LINES

ESTIMATED
COST
(Rs.in
Million)

11000

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER


PLANTS
SR
#.

6-

NAME OF NEW
SUBSTATIONS

Dispersal of
Power from 4500
MW Diamer
Basha HPP to
Lahore with
interconnection
at Dasu and
Gujar Khan

T/F CAP.
(MVA)
765 kV
HVAC
substations
at Gujar
Khan &
Lahore with
765/500 kV
3x500 MVA
T/Fs
500 MVAR
SVC at
Gujar Khan

ASSOCIATED
TRANSMISSION
LINES

ESTIMATED
COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIRED
YEAR OF
COMMISSIONING

113900

1340

2018-19

Three 765 kV HVAC


T/Ls from Basha to
Gujar Khan (407 km
long each)
Two 765 kV HVAC
T/Ls from Gujar
Khan to Lahore (260
km long each)

LIST OF POWER DISPERSAL PROJECTS FOR LARGE HYDRO POWER


PLANTS
SR
#.

7-

NAME OF NEW
SUBSTATIONS

Dispersal of
Power from 5400
-7000 MW Bunji
Hydro Power
Project to
Lahore with
interconnection
at Gujar Khan

T/F CAP.
(MVA)
765 kV
HVAC
substatin
extn at:
Basha,
Dasu,
Thakot,
Gujar khan
Lahore
765 kV new
substation
at Bunji.

ASSOCIATED
TRANSMISSION
LINES

ESTIMATED
COST
(Rs.in
Million)

Eqt.
US$ in
Million

REQUIREDD
YEAR OF
COMMISSIONING

126225

1485

2019-20

296170

3484

2 x 765 kV HVAC 110


km long Bunji Basha S/C T/Lines
1x765 kV HVAC 759
km long Bunji
Dasu-Thakot-Gujar
Khan-Lahore S/C
T/Lines

Total

PC-I for dispersal of Power from Neelum Jhelum HPP has been approved by ECNEC
Studies are being carried out to ascertain the interconnection schemes for the
projects at Sr. No: 2 to 7

BOTTLE NECKS

48

Bottle Necks
At present no major system
constraints
Intermittent over-loading of
transformers at some places being
addressed by addition of following
transformation capacities up to
2014-15
500/220 KV
220/132 KV

11400 MVA
19330 MVA
49

For huge future development the


bottle necks would be
1. Availability of finance
2. Responsibility of dispersal from power plants
& uncertainty of generation project.

Capacity of
1. Planning department
2. Local Consultant
3. Local contractors

Inconducive Law & order situation for


foreign consultants and contractors.
50

KEY PERFORMANCE
INDICATORS

51

Reference documents
NTDC GRID CODE (JUNE 2005)
NEPRA PERFORMANCE STANDARDS
(TRANSMISSION) RULES (NOV. 2005)

52

KEY PERFORMANCE
INDICATORS

1. System Reliability
Transmission System incl. Tie Lines
a) System Duration of Interruption
=

A/N

where

sum of the total outage hours recorded at all the


interconnection points (other than 132 kV line tripping) in a
period
N = Number of monitoring points (Interconnection Point)
A=

Tie lines means interconnection facility for the transfer of electric


power between the licensee and other utilities not governed by the
Act.
53

KEY PERFORMANCE
INDICATORS

1. System Reliability

b)System Frequency Interruption


=

A/N

Where

sum of the total outage hours recorded at all the


interconnection points (other than 132 kV line tripping)
in a period

A=

N=

Number of circuits

54

KEY PERFORMANCE
INDICATORS
2.

System Security
(Energy not served)
=
Pi x T

Where
Pi = Power interrupted in MW in a circuit
T = Time Duration in Hours

55

KEY PERFORMANCE
INDICATORS
3. Quality of Supply
A)

System Voltage Variation


Code Standard
-500 kV
Under Normal Conditions
Under N-1
Conditions

Grid Performance

-5 +8%
-+10%

-+ 5%
-+ 10%

-5 +8%
-+10%

-+ 5%
-+ 10%

-220 kV
Under Normal Conditions
Under N-1
Conditions

-132 kV
Under Normal Conditions
+ 5%
Under N-1
Conditions
+ 10%

-5 +8%

-+10%

56

THANKS

57

S-ar putea să vă placă și