Sunteți pe pagina 1din 22

STEEL PLANT

Indonesia Integrated Steel Mill


Project

Start

Completion

Location

Client

Capacity

The Installation of new coke oven plant at PT.KRAKATAU POSCO Steel works in Cilegon, Indonesia,
comprising 2 batteries with 42 coke oven per each battery.

PT.KRAKATAU POSCO
Coke Plant No.1 Project

PT.KRAKATAU POSCO
Blast furnace No.1 Project

Jul. 2011

Jul. 2011

Nov.2013

Cilegon in
Indonesia

PT.KRAKATA
U POSCO

1,321,000 T/Y

Dec.2013

Cilegon in
Indonesia

PT.KRAKATA
U POSCO

3,000,000 T/Y
(8,650 T/D)

- Coke Oven Battery (84 Ovens)


- Gas Treatment Plant : P.G.C: 22,000N/Hr 5sets(0ne stand-by)
COG Blower: 100,000 N/Hr 2sets(0ne stand-by)
- Moving machine : Charging car(2EA), Coke transfer car(2EA)
Pusher car(2EA), Locomotive(2EA)
- Coal preparation & Coke trasportation : Coal capacity(450T/Hr)
: Coke capacity(350T/Hr, 300T/Hr)

The capacity of plant is 3 million tons of hot metal in annual. This project has been performed
to increase the steel making production capacity of PT.KRAKATAU POSCO Company in
Cilegon, Indonesia.
- Inner Volume : 3,800
- Method of Furnace Proper Cooling : Cooling Plate + Cast Iron Stave Cooler
- Application of Automatic System for Casthouse & EIC Intergrated Control System
The capacity of plant is 4.7 million tons of Sintered Ore in annual. This project was ordered by
PT.Krakatau POSCO and POSCO E&C made consortium with PT.KE (PT.Krakatau Engineering)
which is the POSCO E&C's first project in Indonesia.

PT.KRAKATAU POSCO Sinter


Plant No.1 Project

Jul. 2011

Nov.2013

Cilegon in
Indonesia

PT.KRAKATA
U POSCO

12,870 T/D

- Effective Suction Area : 450


- Material handling, Sinter Machine & Cooler, Screening & Crushing,
Utility & Auxiliary facilities
- Application of Automatic System & EIC Integrated Control System
- Environmentally friend equipment and energy saving equipment
Capacity: 3,156,000 T-S/year (Converter : 300 T/Heat)
Summary: A project to newly construct KR(2sets), converter(1set), LF(1set), RH(1set) facilities
for the purpose of integrated steel mill at Cilegon in Indonesia.

PT.KRAKATAU POSCO
Steel making No.1 Project

Jul. 2011

3,156,000 TS/year
(Converter :
300 T/Heat)

Dec. 2013

Cilegon in
Indonesia

PT.KRAKATA
U POSCO

PT.KRAKATA
U POSCO

8,750 T/D

PT.KRAKATA
U POSCO

1,500,000T/Y

Main facility
1. KR Facility (De-S) : 300 T/ch x 2 set
- KR Facility, Transfer car, etc.
2. Converter : 300 T/ch x 1 set
- Converter, Gas cooler, Waste gas treatment facility,
O2 Lance Facility
3. LF facility : 300 T/ch x 1 set
- Heating Facilities, Bubbling Facilities, Alloy Facilities
4. RH facility: 300 T/ch x 1 set (Duplex Type)
- Ladle Lifting System, Vacuum Vessel, TOB(Multi-Fuction Burner),
Vacuum Pump
3. Auxiliary facility
- Ladle, Relining facility, Compressor,
Power Receiving&Sending station, Transformer,etc.

A project for continous caster plant of integrated steel mill at Cilegon which production
capactiy is 3,000,000 tons/year.

PT.KRAKATAU POSCO Continous


caster facility No.1 Project

Jul. 2011

Dec. 2013

Cilegon in
Indonesia

PT.KRAKATAU POSCO
Plate mill Plant No.1 Project

Jul. 2011

Dec. 2013

Cilegon in
Indonesia

- Thickness : 230mm cold


- Width : 1100 mm to 2300 mm cold
- Speed : max. 2.1 m/min (LC)

Consortium with Mitsubishi Corporation, PT.KE and PT.PEI.


EP Project for Plate Mill Plant in Indonesia PT.KRAKATAU POSCO Steel works.

STEEL PLANT

Brazil CSP Steel Plant


Project

CSP
Raw material handing facility
No.1 Project

CSP
Sinter Plant No.1 Project

Start

Jan. 2012

Sep. 2012

Completion

Location

Client

May. 2015

BRAZIL CEARA
STATE
Pecem AREA

CSP
(Companhia
Siderurica do
Pecem)

Jul. 2015

In Pecem in the
State of
Ceara,Brazil

CSP

Capacity

CSP RMHF (Companhia Siderurica do Pecem) PJT is to provide coke, iron ore and submaterials into newly installed CSP Steelworks. It includes material yard, stacker/reclaimer, belt
conveyor, environmental facilties, EIC equipments and etc.
- Yard: 800M * 6 Sets
3,000,000 T/Y
- Belt conveyor: 51 Lines
- Stacker & Reclaimer: 9 Sets
- C.F.W & Vibrating feeder: 1 Lot
- Dust collector : 1 Lot

12,920T/D

The capacity of plant is 4.7 million tons of Sintered Ore in annual. This project was ordered by
CSP and POSCO E&C made contract solely which is the POSCO E&C's first project in Brazil
- Effective Suction Area : 400
- Material handling, Sinter Machine & Cooler, Screening & Crushing,
Utility & Auxiliary facilities
- Application of Automatic System & EIC Integrated Control System
- Environmentally friend equipment and energy saving equipment
The Installation of new coke oven plant in Pecem in the state of Ceara, Brazil, comprising 2 batteries with 50
coke oven per each battery.

CSP
Coke Plant No.1 Project

CSP
Blast furnace No.1 Project

Jan. 2012

Jul. 2012

Aug. 2015

Aug. 2015

In Pecem in the
State of Ceara,
Brazil

, Brazile

- Coke Oven Battery (100 Ovens)


- Gas Treatment Plant : P.G.C: 44,000N/Hr 3sets(0ne stand-by)
COG Blower: 100,000 N/Hr 2sets(0ne stand-by)
- Moving machine : Charging car(2EA), Coke transfer car(2EA)
Pusher car(2EA), Locomotive(2EA)
- Coal preparation & Coke trasportation : Coal capacity(450T/Hr)
: Coke capacity(350T/Hr, 300T/Hr)

CSP

1,319,475 T/Y

CSP

The capacity of plant is 3 million tons of hot metal in annual. This project has been performed
to increase the steel making production capacity of CSP in Brazile.
3,000,000 T/Y
(8,650 T/D)
- Inner Volume : 3,800
- Method of Furnace Proper Cooling : Cooling Plate + Cast Iron Stave Cooler
- Application of Automatic System for Casthouse & EIC Intergrated Control System
A project to newly construct KR(2sets), Converter(2sets), Ladle furnace(1set) and RH(1set)
facilities in CSP Steel Plant to meet the productivity of annual capacity of 3.0 million tons Slab.

CSP
Steel making No.1 Project

CSP
2-Strand Slab Caster No.1 Project

Sep. 2012

Jul. 2012

Aug. 2015

Aug. 2015

Pecem
Ceara, Brazil

Brazil CSP
Steelworks

CSP

CSP

3.0 million
T/Y

3.0 million
T/Y

Main facility
KR 2sets, Converter 2sets, Ladle furnace 1set, Duplex RH 1set
Heat Size: 300ton/heat
Dry type Electrostatic Precipitator
Hot metal charing crane(450/80ton) etc,.

A project to construct a new Slab caster for high quality and productivity of plates and hot
coils.
- Caster : 1Machine x 2 Strand
- Slab Specification
. Thickness x Width : 220/250/300 mmx (1,100~2,300mm)
. Length : 4,800mm~12,500mm
. Weight : Max.40Tontion
- Casting Speed : Max.1.8m/min

STEEL PLANT
Iron making > Blast Furnace

Project

India IISCO Project

Iran TAVAZON Project

Start

Oct. 2007

Jun. 2002

Completion

Location

Mar. 2010

IISCO at
Burnpur,
West Bengal,
India

Dec. 2008

ESCo. at
Shahrekord,
Esfahan, Iran

Client

IISCO
Steel Company
(India)

Esfahan
Steel Company
(Iran)

Capacity

The capacity of plant is 2.50 million tons of hot metal in annual. This project is odered by
IISCO Steel Co. (SAIL Co.) and won by POSCO E&C consortium with NCC(Nafarjuna
Construction Company) which is the POSCO E&C's first project in India.
8,000 T/D

3,836 T/D

Inner Volume : 4,150


Construction Periods : 30 Months
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
Application of Automatic System for Casthouse & EIC Intergrated Control System

The capacity of plant is 1.40 million tons of hot metal in annual. This project has been
performed to increase the steel making production capacity of Esfahan Steel Company in Iran
from 2.60 million tons to 4.00 million tons. And this is the POSCO E&C's first overseas project
through competitive bid.
- Inner Volume : 2,020
- Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
- Application of Automatic System for Casthouse & EIC Intergrated Control System

POSCO Pohang Steelworks

The capacity of plant is 3.51 million tons of hot metal in annual. And to shorten the shut down
periods, POSCO E&C applied the Method of Construction, "Large Block Ring Construction
Method", as 3 Layers 3 Blocks of furnace proper shell. The shut down periods is 58 days.

The 2nd Relining Project of No.3


Blast Furnace

Dec. 2004

May 2006

POSCO

10,100 T/D

Pohang
Steelworks

Inner Volume : 3,795 4,350


Shut Down Periods : 58 Days
Method of Construction : Large Block Ring Method
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
Application of Bischoff Scrubber (Gas Cleaning Plant)
Application of Automatic System for Casthouse & EIC Intergrated Control System

This Project was successfully executed by POSCO E&C's own technology which is including
the Field Service, Panning, Design, Procurement, Erection Work and Performance Guarantee.

The 2nd Relining Project of No.2


Blast Furnace

Apr. 1995

Jul. 1997

POSCO

5,200 T/D

Inner Volume : 2,550


Shut Down Periods : 101 Days
Method of Furnace Proper Cooling : All Stave Cooler
Application of Sinter Two Fraction Charging System
Application of Casthouse Floor Flatness
Innovation of Casthouse Dust Collector

POSCO Gwangyang Steelworks

The 1st Relining Project of No.3


Blast Furnace

The capacity of plant is 3.71 million tons of hot metal in annual. To follow the world trends of
enlarge of Blast Furnace inner volume, POSCO E&C has expanded the inner volume up to 21%
as 4,600 cubic meters. And this project is the shortest relining periods which is 55 days in the
world.
Jul. 2006

Nov. 2007

POSCO

10,670 T/D

Inner Volume : 3,800 4,600


Shut Down Periods : 55 Days (New World Record)
Method of Construction : 8 Layers 8 Blocks
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
EIC Intergrated Control System

The capacity of plant is 3.51 million tons of hot metal in annual. To shorten the shut down
periods, Large Block Construction Method (8 Layers 8 Blocks) and 1000 tons Crawler Crane
had been used, as a result that, the shut down periods had been shortened up to 14 days. And
this project was successfully executed by POSCO E&C's own technology.

The 1st Relining Project of No.2


Blast Furnace

Feb. 2003

May 2005

POSCO

10,100 T/D

Inner Volume : 3,800 4,350


Shut Down Periods : 66 Days
Method of Construction : 8 Layers 8 Blocks
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
EIC Intergrated Control System
Re-building of Furnace Top & Auxiliaries

The capacity of plant is 3.07 million tons of hot metal in annual. To ensure the lifetime of
Furnace Proper, the cooler of stave type had been applied. And to reduce the production cost,
the capacity of Pulverized Coal Injection System had been increased.

The 1st Relining Project of No.1


Blast Furnace

The 2st Relining Project of No.1


Blast Furnace

May 2000

Jun. 2002

Gwangyang
Steelworks

POSCO

9,160 T/D

Inner Volume : 3,800 3,950


Shut Down Periods : 91 Days
Method of Construction : 14 Layers 29 Blocks
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
EIC Integrated Control System
PCI Indivisual Flow Control System

The capacity of plant is 5.47 million tons of hot metal in annual. this project about reline old
part and enlargement of inner volume to increase production capacity.
it's first relining project to enlarge inner volume to 6,000 that is the biggist blast furnace in
the world
May. 2011

Jun. 2013

POSCO

15,300T/D

Inner Volume : 3,800 6,000


Shut Down Periods : 119Days
Method of Construction : 8 Layers 8 Blocks
Method of Furnace Proper Cooling : Copper Stave + Cast Iron Stave Cooler
EIC Intergrated Control System

The capacity of plant is 2.91 million tons of hot metal in annual. And the cooling method of
stave type and the high efficiency refractories had been applied to ensure the lifetime of
furnace shell as 20 years and more.

The New Construction Project of


No.5 Blast Furnace

Sep. 1996

Mar. 1999

POSCO

8,400 T/D

Inner Volume : 4,020


Construction Periods : 22 Months
New Construction of Furnace Proper and Subsidiary Facilities
Method of Furnace Proper Cooling : All Stave Cooler
Application of Casthouse Floor Flatness & Slag Granulation System
Application of External Combustion Type Hot Stoves

STEEL PLANT
Iron making > Finex

Project

Start

Completion

Location

Client

Capacity

POSCO Pohang Steelworks

FINEX, Pohang Steelworks

Jan. 2004

Apr. 2007

POSCO

FINEX process is a smelting-reduction technology based on direct use of fine iron ore and
non-coking coal. In the FINEX process fine iron ore is preheated and reduced to fine DRI in a
four stage fluidized bed reator system with reduction gas produced from melter gasifier. The
fine DRI is compacted and then charged in form of HCI (Hot Compacted Iron) into the melter
gasifier to produce hot metal. The charged HCI is reduced to metallic iron and melted. The
1,500,000 T/Y heat needed for the metallurgical reduction and melting is supplied by coal gasification with
( 4,110 T/D ) oxygen.
FINEX process is an environmental friendly process that uses low-cost fine iron ore and coal.
POSCO E&C successfully supplied and constructed commercial facilities with an annual
capacity of 1.5 million tons, the first in the world, and launched normal operation successfully
of the facility in Dec., 2007.

Pohang
Steelworks

3 FINEX, Pohang Steelworks

June. 2011

Dec. 2013

POSCO

FINEX process is a smelting-reduction technology based on direct use of fine iron ore and
non-coking coal. In the FINEX process fine iron ore is preheated and reduced to fine DRI in a
three stage fluidized bed reator system with reduction gas produced from melter gasifier. The
fine DRI is compacted and then charged in form of HCI (Hot Compacted Iron) into the melter
gasifier to produce hot metal. The charged HCI is reduced to metallic iron and melted. The
2,000,000 T/Y
heat needed for the metallurgical reduction and melting is supplied by coal gasification with
( 5,480 T/D )
oxygen.
FINEX process is an environmental friendly process that uses low-cost fine iron ore and coal.
POSCO E&C successfully supplied and constructed commercial facilities with an annual
capacity of 2.0 million tons, the first in the world.

FINEX DEMO PLANT

Jan. 2001

May 2003

POSCO

600,000 T/Y
( 1,644T/D )

FINEX Demo Plant is a process which produces hot metal 0.6 million tons per year based on
direct use of fine iron ore and non-coking coal without sinter and coke plant.

STEEL PLANT
Iron making > Sintering

Project

Australia BSL Project

Start

Feb. 2007

Completion

Location

Client

Apr. 2009

BSL, Port
kembla,
Australia

BSL
(Blue Scope
Steel)

Capacity

BSL project was performed to replace worn out equipment in accordance with increasing
productivity(+1,100,000T/Y, 20%UP) and longterm operation in BSL No. 3 Sinter plant
Australia (5,500,000 T/Y).
18,000 T/D

Effective suction area: 420 480


Production: 15,000 T/D 18,000 T/D
Productivity: 40.5 T/D/
Availability: 93 %

POSCO Pohang Steelworks

Pohang No. 3 Sintering Plant Revamping project was performed to increase productivity of
sinter ore (+1,440,000T/Y, 31.1% UP) in accordance with enlargement of Pohang No. 3 Blast
Furnace and change of worn out equipments through longterm operation..

No. 3 Sintering Plant Revamping

Nov. 2004

May 2006

Pohang
Steelworks

POSCO

17,500 T/D

- Effective suction area: 400 504


. Sintering machine Pallet width extension: 4m 4.5m
. Sintering machine lenth extension: 100m 112 m
- Production: 12,700 T/D 17,500 T/D
- Bed Height: 660m 760 m
- Shutdown: 52 Days

POSCO Gwangyang Steelworks

Gwangyang No. 2 Sintering plant revamping project was performed to increase productivity for
stable supply of sinter ore after enlargement Gwangyang No. 3 Blast Furnace and replace worn
out equipments through longterm operation.

No. 2 Sintering Plant Revamping

Jun. 2006

Dec. 2007

POSCO

18,000 T/D

Effective suction area: 450


Production: 15,200 T/D 18,000 T/D
Productivity: 34T/D/ 40 T/D/
Availability: 98.4 % 99 %
Bed Height: 850 mm 1,000 mm
Shut down period: 36 Days

Gwangyang No. 2 & No.4 Sintering plant revamping project was performed to increase
effective suction area and revamp related equipments for increasing sinter ore production.

No. 2&4 Sintering Plant


Revamping
(Pallet width extesion)

Mar. 2003

May 2004

Gwangyang
Steelworks

POSCO

15,200
T/D(No.2)
16,100
T/D(No.4)

- Effective suction area:


Gwangyang No. 2 Sintering Plant 400 450
Gwangyang No. 4 Sintering Plant 424 477
- Productivity: 37T/D/ 38T/D/
- Bed Height: 880mm
- Shutdown: Gwangyang No. 2 Sintering Plant 26 Days
Gwangyang No. 4 Sintering Plant 30 Days

This project was performed to increase effective suction ares of Gwangyang No. 1 & No.3
sintering plant and revamp related equipment for increasing sinter ore production in
accordance with operation of Gwangyang No. 5 blast furnace.

No. 1&3 Sintering Plant


Revamping
(Pallet width extension)

Apr. 2001

Aug. 2002

POSCO

15,300 T/D

- Effective suction area: 400 450


. Sintering machine pallet width extension: 4 m 4.5 m
. Cooler width extension: 4 m 4.6 m
- Production: 13,180 T/D 15,300 T/D
- Bed Height: 880 mm
- Ingnition furnace revamping: Reflection side burner Multi slit burner
- Shutdown: 28 Days

STEEL PLANT
Iron making > Raw material handling

Project

Start

Completion

Location

Client

Capacity

This RMHF(Raw Material Handling Facility) is to provide coke, iron ore and sub-materials into
newly installed FINEX(1.5 millions T/Y) in Pohang Steelworks. It includes material yard,
stacker/reclaimer, belt conveyor, crushing and screening equipments and etc.

FINEX Raw Material Handling


Facility

2nd phase Reclamation work of


Incheon International Airport

Oct. 2004

Jan. 2004

Dec. 2006

Pohang
Steelworks

POSCO

Nov. 2010

Incheon
International
Airport

IIAC
(Incheon
International
Airport Corp.)

4.4 million
T/Y

YARD: 400/720M * 4 SETS


BELT CONVEYOR: 10 KM
STSCKER & RECLAIMER: 8 SETS
CRUSHING & SCREENING FACILITY: 1 LOT
WATER TREATMENT FACILITY: 1LOT

This project is a part of reclaiming work for 2nd phase construction of Incheon International
Airport such as 3rd runway and IBC(International Business Center). POSCO E&C provides and
operates carrying equipments for landfill such as belt conveyor, dump hopper and etc.
4,000 T/H
- BELT CONVEYOR: 8 KM
- DUMP HOPPER: 1 LOT
- DUST COLLECTOR: 1 LOT

This project had planned to increase the storage capacity of CTS as much as 3millions T/Y in
Gwangyang Steelworks. Also, CTS is intermediary business, it carries in materials such as coal,
steel, Mn, store them in the yard then take them local site as well as abroad.

CTS Raw Material Handling


Facility

Nov. 2003

Oct. 2005

Gwangyang
Steelworks

POSCO/
POSCO
Terminal

3 million T/Y

Venezuela POSVEN Project

Jun. 1997

Jun. 1999

Matanzas
Industrial
Complex, Bol
var, Venezuela

POSVEN CA

1.5 million
T/Y

Tubarao,
Vitoria, Brazil

CVRD

Brazil KOBRASCO
PELLETIZING PLANT

Feb. 1996

Nov. 1998

YARD: 400M * 2 SETS


BELT CONVEYOR: 8 KM
STSCKER & RECLAIMER: 3 SETS
CRUSHING & SCREENING FACILITY: 1 LOT
WATER TREATMENT FACILITY: 1LOT

This project is DRI production facility with a method of HYL process. Produced DRI is
compressed by briquetting machine then changed into HBI.
- Supply Scope : Drawings, Equipments and Test run

This project had planned to construct palletizing plant capable of 4 millions T/Y which was
J/V businesses between POSCO and CVRD of Brazil on a fiftyfifty basis mainly to stable
4 million T/Y provide of pellet into newly installed 5th Blast Furnace in Gwangyang Steelworks. POSCO
E&C fully participated in detailed drawings and equipment supply like Pellectizing Disc and
etc.

STEEL PLANT
Iron making > Lime Calcination

Project

Start

Completion

Location

Client

Capacity

POSCO Pohang Steelworks

This project successfully built new facilities capable of annual 100,000 tons of CaO, addressing
the shortage problem and responding to the plan to build new FINEX plant and boost
production of crude steel in the mid and long term.

FINEX Lime calcination facility

Sep. 2005

Sep. 2006

POSCO

300 Ton/Day
x 1 lot

Pohang
Steelworks

Revamping of No.1&2 Lime


Calcination facility

Sep. 2001

Jul. 2004

POSCO

300 Ton/Day
x 2 lot

Type of Kiln: Rotary Kiln 300 Ton/Day x 1 Lot


Capacity: 103,500 Ton/Year
Grain Size: 10mm ~ 40mm
Operation Ratio: 94.5%

A project to replace aged calcination furnaces I & II and the auxiliary systems, and to integrate
the operation room for the purpose of achieving a good balance between the supply and
consumption of lime in accordance with medium and long term investment plans covering the
construction of No.3 stainless steel plant at Pohang Steelworks.
-

Type of Kiln: Fine Lime Shaft Kiln 300Ton/Day X 2 Lot


Capacity: 207,000 Ton/Year
Grain Size: 10mm ~ 40mm or 40mm ~ 80mm
Operation Ratio: 94.5%

POSCO Gwangyang Steelworks

Lime Calcination for crude steel


increase plan

This project had planned to construct 2sets of shaft kiln and other facilities to stable supply of
additional requirement of quicklime according to increase plan of crude steel in Gwangyang
Steelworks.
Oct. 1997

Mar. 1999

Gwangyang
Steelworks

POSCO

300 Ton/Day
x 2 lot

Type of Kiln: Fine Lime Shaft Kiln 300Ton/Day X 2 Lot


Capacity: 198,000 Ton/Year
Grain Size: 10~40mm or 40~80mm
Operation Ratio: 90.4%

STEEL PLANT
Iron making > Coke oven

Project

Start

Completion

Location

Client

Capacity

POSCO Pohang Steelworks

Extension of the Coke Plant


Stage 5

Oct. 2005

Nov. 2007

Pohang
Steelworks

A new 5A coke oven battery was planned to meet the demand for the improvement of
productivity in blast furnace.
5A battery was located next to existing 5B battery and its coke productivity is the same as 5B
battery.
POSCO

620,000 T/Y
- Coke Oven Battery 1set (75 Ovens)
- Gas Refinery Plant
. P.G.C 22,000 N/Hr 1set
. COG Blower 60,000 N/Hr 1set

POSCO Gwangyang Steelworks

Desulfurization Plant for Gas


Refinery Plant

Mar. 2005

Jan. 2007

Gwangyang
Steelworks

The desulfurization plant was planned to prevent SOx emission in the air during the scheduled
maintenance period(40 days/year). Also, the installation of desulfurization plant helps the
improvement of environmental condition and prevents the surface quality defection of rolling
mill product. POSCO E&C executed basic & detail engineering, equipment supply, supervision
and commissioning.
POSCO

6,800 N/H
-

Catalytic Oven Reactor: 6,800 N/Hr *1set


Claus Reactor: 6,800 N/Hr *1set
HP & LP Cooler: 40/3.5 bar *1set
Sulfur Con. & Seprator: 6,800 N/Hr *1set
Sufur Storage System: 135 *1set

The traditional wet coke quenching system had been used in stage 5 coke plant. CDQ(Coke
Dry Quenching) was adopted instead of existing wet quenching system. CDQ improved the
energy recovery and the quality of coke for blast furnace which has been aiming at high
productivity.

CDQ for the Coke Plant Stage 4

Dec. 2003

Aug. 2005

Gwangyang
Steelworks

POSCO

180 T/H
(Dry Coke)

Turbine Generator: 29.7 MW


Waste gas Boiler : 105 T/H
Bucket Crane: 67.5 Ton
Deminerlized water facility : 65 T/H
Cooling Water System : 1,400/H * 6sets
Dedusting unit : 1,520 N/min

STEEL PLANT
Steel making > Oxygen converter

Project

Start

Completion

Location

Client

Capacity

POSCO Pohang Steelworks

Pohang New steelmaking plant

Dec. 2007

Apr. 2010

POSCO

4.6 milion T/Y

A project to increase annual production capacity to 4.65 million tons by improving


compatibility, cost saving, and the quality of the converter furnace operation via the
introduction of facilities with the same capacity as those of No.2 steelmaking plant for the
purpose of enhancing the competitiveness of the small No.1 steelmaking plant at Pohang
Steelworks.
-

De-P Converter for No.2


Steelmaking plant

De-P converter 1 set, De-C converter 1 set


Heat Size: Max. 345 ton
Boiler system for waste heat, Hot metal charging crane
Bag filter precipitator

A project to construct a De-P converter in No.2 steelmaking plant for the purpose of
establishing a system for high quality steel (electro plated steel plates and API) and cost
saving to meet the productivity of annual capacity of 1.5 million tons FINEX Plant.
Feb. 2005

Mar. 2007

Pohang
Steelworks

POSCO

4.5 milion T/Y


- Heat Size: Max. 300 ton
- Boiler system for waste heat, Hot metal charging crane
- Bag filter precipitator

A project to improve the capacity of aged No.1 steelmaking plant by revamping the converter
shell, trunnion ring, tiliting equipment and other converter facility.

Revamping of No.1 Steelmaking


plant (2nd step)

May 1996

Dec. 1997

POSCO

2.5 milion T/Y

Converter capacity : 110ton (Inner volume : 81)


Main facility
- Converter shell and converter tilting equipment
- Cooling facility for converter shell
- Converter trunnion ring
- Combined blowing technology adopting, localization of Converter bearing
block, Material conversion of Converter shell and trunnion ring (SGV 42-CR)

POSCO Gwangyang Steelworks

Capacity: 2,430,000 T-S/year (Converter : 280 T/ch)


Summary: A project to newly construct KR(2sets) & converter(1set) facilities for the purpose
of producing high grade steel plate(TMCP,API)

Converter of SMP for Gwangyang


Plate Mill Project

De-P converter of No.2 steel


making plant

N2 Splash Slag Coating of No.2


steel making plant

Feb. 2008

Apr. 2010

POSCO

May 2000

Dec. 2007

Mar. 2001

Main facility
1. KR Facility (De-S) : 250 T/ch x 2 set
- KR Facility, Transfer car, Pouring pit, etc.
2. Converter : 280 T/ch x 1 set
- Converter, Gas cooler, Waste gas treatment facility, O2 Lance Facility
3. Auxiliary facility
- Ladle, Relining facility, Water supply equipment,
Compressor, Power Receiving&Sending station,
Transformer,etc.

A project to newly construct KR(3sets) & converter(1set) facilities for the purpose of
establishing a system for the mass production of strategic products.

Gwangyang
Steelworks
Jun. 2006

2.43 million
T-S/Y

POSCO

POSCO

4.5 million
T-S/Y

8.5 million
T/Y

Reduction of construction period : 19 months 16.5 months


Main facility
Converter vessel, KR Facility, Gas cooler
Electrostatic Precipitator, Water supply equipment, Utility facility
Flux charing equipment, Main Lance, Transfer car

After converter tapping, this facility add coating materials, such as magnesia, dolomite, to slag
in converter and uniformly attach them to refractory bricks by blowing high pressure N2 gas
through lance.
This facility allows stable maintenance of converter and long life time of refractory bricks. As
a result, it is expected to reduce expenses.
Main facility
- NCompressor / NPiping / NHolder
- Control System
Applied technology: Automatic control of N2 pressure, flow rate &
operation technique of N2 coating

STEEL PLANT
Steel making > Mini mill

Project

Asia Special Steel Project

ARCO Project

Start

Dec. 2007

Completion

Location

Client

Capacity

May. 2009

HIBIKINADA,
Industrial
complex, Japan

Asia Special
Steel
Co.,Ltd.

Ingot 120,000
T/Y

Egypt Sadat
City

Arab Company
for Special
Steel

Special Steel
1.4 million
T/Y

POSCO

600,000 T/Y

Apr. 1997

Mar. 2001

Jul. 2001

Apr. 2003

POSTEEL and KOTOBUKI made a joint venture company to meet increasing demand of Ingot
product. This project comprised Electric arc melting plant and Ingot plant.
Work scope : Engineering, Procurement and installation
Key equipment : Ingot Facility, Over head crane,
De-dusting facility, Water treatment facility etc,.

ARCO project is to build the largest stainless steel plant in middle-east area.
- SMP (Electric Arc Furnace, Refining furnace,
Vacuum Decarburirzation facility, Continuous casting)
- RMP (Heating furnace, Roughing Mill, Billet, Shearing machine,
Finishing Mill, fininshing line)
- Others (Power receiving and distribution facility, Oxygen plant,
Water treament, Dedusting faclity)

POSCO Pohang Steelworks

STS No.3 Steel melt shop

POSCOE&C supplied 600,000 ton per year stainless product facilities including Plant building,
Equipment foundation, Steel structrue manufacturing & erection, Equipment installation.
Work scope: Procurement and Construction

Pohang
Steelworks

STS Expansion

This stainless steel plant has one of the largest production capacity in the world.
Dec. 1994

Aug. 1996

POSCO

840,000 T/Y
Work Scope: Engineering, Procurement and Construction

POSCO Gwangyang Steelworks

This Project is to build facilities to produce slim sheet of hot roll mill product under 1.8mm
thickness sheet and 1,800,000ton per year.

NO.1 Mini-Mill

Jan. 1995

Oct. 1996

Gwangyang
Steelworks

POSCO

1.8 million
T/Y

Electric Arc Furnace : 130ton x 2


LF x 2
VTD x 2
Continuous casting: 1MC x 1 Str x 2
Heat Holding Furnace(12M) 1
Reduction Unit(4 Hi - 2 Stand) 1
- Hot Roll Mill plant : 4Hi 5Stand(27,000 KW) 1
- Total Distance of equipment : 185m

This Project is to revamp the existing steel making plant , and to replace the two(2) lines of
caster and intermediate facilities with one(1) line of high speed caster and modernized
intermediate facilities so as to be connected with the existing rolling mill directly in 2 phases.

CEM
(Compact Endless Casting & Rolling Mill)

Nov. 2007

June. 2009

Gwangyang
Steelworks

POSCO

1.8 million
T/Y

Electric Arc Furnace : 130ton x 2


LF x 2
VTD x 2
High Speed Continuous caster: 1MC x 1 Str (casting speed: 8 mpm)
Reduction Unit(4 Hi - 3 Stand) 1
Mandrel Furnace 1
Hot Roll Mill plant : 4Hi 5Stand(27,000 KW) 1
Total Distance of equipment : 185m

STEEL PLANT
Steel making > Ladle refining

Project

Start

Completion

Location

Client

Capacity

POSCO Pohang Steelworks


Duplex-RH facility (POSCO E&C patent application) is supplied for production enlargement of existing No.1
steel-making plant(110T/Ch)

New Steel-Making Plant RH

Dec. 2007

Apr. 2010

POSCO

35 CH/D
(330 T/ch)

No.3 RH for No.2 Steelmaking


plant

Aug. 2006

Jul. 2007

POSCO

RH: 35 CH/D
(330 T/ch)

Revamping of No.2 RH for No.1


Steelmaking plant

CHIS for No.2 Steelmaking plant

Revamping of No.1 RH / VTD for


No.2 Steelmaking plant

LF for No.1 Steelmaking plant

LF for No.2 Steelmaking plant

2Booster/2Ejector/2Condenser/3WRP
2 Vessel / 2 Ladle Transfer Car
Multi-function burner
Dust tank system

Duplex-RH facility (POSCO E&C patent application) improved in the capabilities of production & vacuum
treatment is supplied.

Apr. 2005

Jul. 2004

May 2002

Apr. 2000

May 1995

Feb. 2006

Dec. 2004

Dec. 2002

Dec. 2001

Dec. 1997

POSCO

Pohang
Steelworks

POSCO

25CH/Day
(110 T/ch)

2.1 million
T/Y

- 3Booster/2Ejector/2Condenser/3WRP
- 2 Vessel / 2 Ladle Transfer Car
- Multi-function burner

Revamping of obsolete facilities


Capacity enlargement in vacuum vessels / vacuum pumps
Modernization of Alloy equipment
Modernization of Relining & Preheating equipment
Modenization of Transger car & Bubbling equipment

Key facilities
2Booster/2Ejector/2Condenser/3WRP
Vessel Transfer Car Type
Introduction of Multi-function Burner

Key facilities
Snorkel Rotating & Lifting equipment
O& PI Lance equipment
Snorkel Transfer Car
Alloy equipment & Wire feeder
PLC control system
Process effects in CHIS(Chemical Heating in Snorkel)
O2 pick-up prevention in alloy charging
Increase in Alloy comsumption for Slag Free molten-steel
Operation time reduction with rapid heating speed(ave.15/min)
Electrical Arc

POSCO

RH: 25 CH/D
VTD: 3 CH/D

(330 T/ch)
-

PHD(POSCOENC Hybrid Degasser)


Revamping of the old-fashioned RH Facility
Create VTD Degassing facility (Heat size : 320ton/heat)
Diversity and state-of-the-art of Production steel grade
Main facilities
3Booster / 2Ejector / 2Condenser / 3WRP
RH/VTD + 1 Vacuum Pump System
Adopted Swiching Duct (POSCO E&C Patent)

POSCO

105 T/H x 20
CH

POSCO

The project that creation of LF (Ladle Furnace) 1 set for the production system of POSCO
Pohang No.2 Steel making plant strategy product
- Arcing Equipment
- Alloy addition equipment
330 T/H x 20
- Powder Injection facility
CH
- Transfer cars
- Utility facility
- System
- Hoists, etc

The project that creation of LF (Ladle Furnace) 1 set for the production system of POSCO
Pohang No.1 Steel making plant strategy product
- Arcing Equipment
- Alloy addition equipment
- Powder Injection facility
- Transfer cars
- Utility facility, Hoist, etc.

STEEL PLANT
Steel making > Ladle refining

Project

Start

Completion

Location

Client

Capacity

POSCO Gwangyang Steelworks

No.3 RH for NO.1 steel making


plant

Apr. 2008

Aug. 2009

POSCO

RH: 33 CH/D
(275 T/ch)

RH-VTD for Increasing


productivity of plate

Feb. 2008

Apr. 2010

POSCO

RH/VTD:
30 CH/D
(280 T/ch)

No.2 RH-TOB for No.2 steel


making plant

Aug. 1998

Jun. 2000

POSCO

2.54 million
T/Y

No.2 RH-POSB for No.2 steel


making plant

Aug. 1998

Feb. 1999

POSCO

2.3 million
T/Y

No.1 RH-TOB for No.2 steel


making plant

- Heavy vacuum: 2 Booster / 2 Ejector / 2 Condenser / 4 WRP


- 3 Hot-off take / 3 Upper-Vessel / 4 Lower-vessel
- Multi-function burner
A project to construct a RH-VTD facility as constructing a new plate mill producing luxury
plates(TMCP,ASP) 2 million ton annually.
- Heavy vacuum: 2 Booster / 2 Ejector/ 2 Condenser / 6 WRP
- 2 Vessel / 1 Ladle Transfer Car
- Multi-function burner
A revamping project of vaccum facility and EIC facility to renovate aged facility such as
vaccum vessels and pump and produce stratgic steel like a plate of car
- Heat Size (325 T/H )
- Vacuum Unit (Booster 2, Ejector 3, Water Ring Pump 3)

POSCO E&C renovated aged facilities such as vacuum vessels and pumps to increase their
exhaust capacity and decarbonization capability, and established a system for the production
of ultra-low-carbon steel for steel sheets for automobiles.
- Heat Size(275 T/H)
- Vacuum Unit(Booster 2, Ejector 3, Water Rng Pump 3)

Gwangyang
Steelworks

No.2 RH-POSB for No.1 steel


making plant

A project to consruct a Duplex-RH facility to treat the amount of De-gas as increasing amount
of hot metal for new steel making plant in Kwang-Yang and eleminate the Neck-operation for
existed NO.1 steel making plant in Kwang-Yang.

May-98

Nov. 1998

POSCO

2.3 million
T/Y

POSCO E&C renovated aged facilities such as vacuum vessels and pumps to increase their
exhaust capacity and decarbonization capability, and established a system for the production
of ultra-low-carbon steel for steel sheets for automobiles.
- Heat Size(275 T/H)
- Vacuum Unit(Booster 3, Ejector 3, Water Rng Pump 3)

Feb. 1998

Jul. 1998

POSCO

2.3 million
T/Y

POSCO E&C renovated aged facilities such as vacuum vessels and pumps to increase their
exhaust capacity and decarbonization capability, and established a system for the production
of ultra-low-carbon steel for steel sheets for automobiles.
- Heat Size(275 T/H)
- Vacuum Unit(Booster 2, Ejector 3)
A project to construct Ladle Furnace to establish a production system for main products of
Gwangwang No.1 steel making work.

LF for No.1 Steelmaking plant

No.1 RH-TOB for No.1


Steelmaking plant

Apr. 1997

Nov. 1996

Jun. 1998

Sep. 1997

POSCO

275 T/H x 20
CH

POSCO

2.3 million
T/Y

Heating system
Flux and Ferro-alloy handling system
Power Injection system
Transfer car
Utility supply system
System
Hoist

A project to establish a production system of high quality steel by the economical and
optimum vacuum facility that is considering limited flow rate of cooling water and steam of
the existing facilities.
- Heat Size(275 T/H)
- Vacuum Unit(Booster 2, Ejector 3, Water Rring Pump 3)

STEEL PLANT
Continuous casting

Project

Start

Completion

No.2 Bloom for No.1 Continuous


casting plant

May 2006

Revamping of No.4 machine for


No.3 Continuous casting plant

Mar. 2005

Location

Client

Capacity

Feb. 2008

POSCO

1.1 million
T/Y

A project to construct a new bloom caster for high grade wire rods in the existing No.1 slab
yard.
- Bloom size: 400 x 500mm

May 2006

POSCO

3.4 million
T/Y

A revamping project to replace an existing continuous caster of casting bow type with a
continuous caster of segment type for an improvement in productivity.
- Slab Size: 250t x (740 ~ 1,650)mm

POSCO Pohang Steelworks

poStrip(Strip Caster)

Jun. 2004

Jun. 2006

POSCO

Pohang
Steelworks

Revamping of No.1 machine for


No.2 Continuous casting plant

Aug. 2003

May 2005

POSCO

A project to construct a poStrip Demo Plant for technical development of strip casting process.
POSCO E&C carried out all basic design except Mill line by its own abillity.
- Casting speed : 27.8 ~133 mpm
0.6 millionT/Y
- Casting thickness : 2.0 ~4.0 mm
- Coil thickness : 1.6 ~4.0 mm
- Coil width : 1040 ~1304 mm

2.8 million
T/Y

A revamping project to rebuild an existing continuous caster into an exclusive plate


continuous caster for an improvement in productivity.
- Slab Size: 220,300t x (1,600~2,200) mm
- Casting Speed: max. 2.0m/min

A project to construct a continuous caster including design and supply of equipment with a
government task. POSCO E&C carried out all basic design including casting platform, mold and
segment by its own abillity.
0.6 millionT/Y
- Casting thickness : 100 mm ~ 140 mm
- Casting width : 600 mm ~ 1000 mm
- Casting speed : Max. 5 mpm

Pilot continuous caster

Dec. 2001

Mar. 2003

POSCO

No.1 Bloom for No.1 Continuous


casting plant

Dec. 2000

Nov. 2002

POSCO

0.8 million
T/Y

Apr. 2008

Aug. 2009

POSCO

3.2 million
T/Y

A project to construct a new bloom caster for high grade wire rods and an improvement of
productivity in the No.1 continuous casting plant.
- Bloom Size: 300 x 400mm

POSCO Gwangyang Steelworks

Revamping of No.2 machine for


No.1 Continuous casting plant

A revamping project to rebuild an existing continuous caster into a vertical bending type
caster for the demand of automotive steel
- Casting speed: 2.1m/min
A project to construct a new plate caster for an improvement in productivity.

2 Strand slab caster for Plate mill


CCP3 / CCM1

Jan. 2008

May-10

POSCO

3.2 million
T/Y

Gwangyang
Steelworks

Revamping of No.3 machine for


No.2 Continuous casting plant

Jun. 2006

Nov. 2007

POSCO

3.5 million
T/Y

Thickness: 250mm, 300mm


Width: 1,400mm ~ 2,400mm
Length: 5,500mm ~ 12,000mm
Weight: Max. 45ton

A revamping project to rebuild an exsting bending type caster into a vertical bending type and
high speed caster for an improvement in productivity.
POSCO E&C applied a new technology which is a secondary cooling water nozzle for high
speed control, a width adjustable mold equipment and an automative robot.
- Slab Size: 250t x (820 ~ 1600)mm
- Casting Speed: Max. 2.7m/min

Revamping of No.4 machine for


No.2 Continuous casting plant

A revamping project to rebuild an exsting bending type caster into a vertical bending type
caster for an improvement in cold rolled steel quality.
Jan. 2004

Jul. 2005

POSCO

2 million T/Y
- Slab size: 250t X (820~2000)mm
- Casting Speed: Max. 2.2m/min
A project to establish a four side scarfing machine and a grinding machine for an improvement
of quality in the No.1 &No.2 continuous casting plant.

Scarfing machine for No.1 & No.2


Continuous casting plant

Mar. 2003

Revamping of No.3 machine for


No.1 Continuous casting plant

Dec. 2001

No.4 machine for No.1 Continuous


casting plant

Dec. 1995

Feb. 2006

Jul. 2003

Gwangyang
Steelworks

POSCO

1 million T/Y
x 2M/C

POSCO

1.8 million
T/Y

4 side scarfing machine


Grinding machine
Crack detecting equipment
A dust collector

A revamping project to rebuild an exsiting bending type caster into a vertical bending type
caster for an improvement in cold rolled steel quality. It is applied a new soft reduction
technology which is operated during the casting.
- Slab Size: 250t x (820~2000)mm
- casting Speed: Max. 1.8m/min

Sep. 1997

POSCO

2.25 million
T/Y

A project to construct a vertical bending type caster(1M/C x 2Strand) for an improvement in


productivity and cold rolled steel quality.
- Slab Size: 230t X (8001,600)W
- Casting Speed: Max. 2.2m/min

STEEL PLANT
Hot rolling

Project

Start

Zhangjiagang Pohang Stainless


May 2004
Steel(ZPSS) Hot strip mill in China

Completion

Location

Sep. 2006

Zhangjiagang
City
Jiangsu, China

Client

ZPSS
(ZhangjigangPohang
Stainless
Steel)

Capacity

800,000 T/Y

A project to construct new hot strip mill for stainless steel with an annual capacity of 800,000
tons in order to supply stainless steel products in China domestic market.
Main facilities
: Reheating furnace,Roughing mill,Steckel Mill, Down coiler, Utility facilities
Product Capacity : 800,000 t/y stainless steel hot rolled coil
Engineering, Equipment supply, Erection, Commissioning, Supervision

POSCO Pohang Steelworks

Modernization of Coil Conveyor


for No.2 Hot strip mill

Mar. 2006

Apr. 2006

POSCO

4,900,000 T/Y

This project is to revamp coil conveyor system o to modernize eye vertical type into eye
horizontal type.
Main facilities: Car for moving, chain conveyor, Inspection line
Engineering, Equipment supply, Erection, Commissioning, Supervision

High Density Cooling System of


No.2 Hot strip mill

Mar. 2006

Apr. 2006

POSCO

4,900,000 T/Y

This project is to install the high density cooling system for uniform rapid cooling of all strip.
Main facilities
: Runout table, High density cooling system, Water treatment facilities
Engineering, Equipment supply, Erection, Commissioning, Supervision

Jan.2001

May 2005

POSCO

760,000 T/Y

Revamping of the Billet Mill

Pohang
Steelworks

With The increasing Demand and the High Quality of the product from the POSCO
Main facilities: Reheating furnace adopted RCB
Engineering, Equipment supply, Erection, Commissioning, Supervision

Increasing the unit product


weight of No.1 hot strip mill

Jul. 2001

Apr. 2003

POSCO

This project is to supply the facilities for increasing the production capacity(2,710,000 T/Y
3,240,000 T/Y) by increasing the unit product weight, and for improving the quality of
stainless steel product.
3,240,000 T/Y
Main facilities: Slab depiling system, Coil conveyor, Hot skinpass mill,
Water treatment facility
Engineering, Equipment supply, Erection, Commissioning, Supervision

Modernization of No.1 hot strip


mill

May 1996

Jul. 1997

POSCO

2,400,000 T/Y

This project is to supply the facilities for modernization of No.1 hot strip mill in order to
improve good profile and high quality of product.
Main facilities: Crop shear, Finishing scale breaker
Engineering, Equipment supply, Erection, Commissioning, Supervision

High Density Cooling System of


No.3 Hot strip mill

Oct. 2007

Nov. 2007

POSCO

4,810,000 T/Y

This project is to install the high density cooling system for uniform rapid cooling of all strip.
Main facilities: Runout table, High density cooling system,
Laminar cooling system, Water treatment facilities
Engineering, Equipment supply, Erection, Commissioning, Supervision

Revamping of Hot dividing line of


No.2 Hot strip mill

Mar. 2007

May 2007

POSCO

5,000,000 T/Y

This project is to revamp the existing hot dividing line for transforming 2-hi mill into 4-hi
mill.
Main facilities: 4-hi skinpass mill, Roll changing system, Coil car
Engineering, Equipment supply, Erection, Commissioning, Supervision

High Density Cooling System of


No.1 Hot strip mill

Apr. 2007

Apr. 2007

POSCO

4,800,000 T/Y

This project is to install the high density cooling system for uniform rapid cooling of all strip.
Main facilities: Runout table, High density cooling system,
Laminar cooling system
Engineering, Equipment supply, Erection, Commissioning, Supervision

High Density Cooling System of


No.2 Hot strip mill

Feb. 2007

Feb. 2007

POSCO

5,000,000 T/Y

This project is to install the high density cooling system for uniform rapid cooling of all strip.
Main facilities: Runout table, High density cooling system,
Laminar cooling system
Engineering, Equipment supply, Erection, Commissioning, Supervision

POSCO Gwangyang Steelworks

Gwangyang
Steelworks

This project is to supply the preheating furnace and the entry & delivery equipment for new
installation of preheating furnace.
Main facilities: Preheating furnace, Charger&extarctor,
entry&delivery roller table
Engineering, Equipment supply, Erection, Commissioning, Supervision

New Preheating Furnace of No.3


Hot strip mill

Jun. 2005

Nov. 2007

POSCO

250 T/Hr

Modernization of Coil Conveyor


for No.3 Hot strip mill

Oct. 2004

Mar. 2005

POSCO

4,810,000 T/Y

This project is to revamp coil conveyor system in order to modernize eye vertical type into eye
horizontal type.
Main facilities: Car for moving coils, chain conveyor, Inspection line
Engineering, Equipment supply, Erection, Commissioning, Supervision

Modernization for No.2 Hot strip


mill

Sep. 2000

Jul. 2002

POSCO

3,000,000 T/Y

This project is to supply the facilities for modernization of No.2 hot strip mill.
Main Facilities : Reheating furnace, Hot skinpass line, Runout table,
Entry & delivery equipment of furnace, Coil conveyor
Engineering, Equipment supply, Erection, Commissioning, Supervision

No.4 Hot Strip Mill

Dec. 2010

Jul. 2014

POSCO

3,500,000 T/Y

This Project will be designed to produce hot strip and hot coil in high efficiency.
The annual production of Hot Strip Mill will be 3,500,000ton on slab base.
Main facilities: Reheating Furnace, Roughing Mill, Finishing Mii, Down Coiler
Finishing line Equipments
Scope: Engineering, Equipment Supply,Erection,Commissioning,Supervision

STEEL PLANT
Hot rolling > Plate

Project

Start

Completion

ACC & DQ Revamping for No.2


Plate Mill

Aug. 2007

Facilities covering Extreme Heavy


Plate for No.2 Plate Mill

Heat Treatment Furnace for No.3


Plate Mill

Location

Client

Capacity

Jan. 2008

POSCO

238 mT/Y

Revamping existing Cooling Facility into MULPIC System to improve product quality.
Scope: Design, Supply, Construction, S/V

Sep. 2006

Jan. 2008

POSCO

238 mT/Y

Revamping existing Facilities to cover Production Increase and Extreme Heavy Plates.
Scope: Design, Supply, Construction, S/V
Main Facilities: Reheating Furnace, Cooling Bed

Sep. 2006

Aug. 2007

POSCO

20 mT/Y

Installing Heat Treatment Furnace and Side Shifter on Mill Line to produce 20 mT/Y Heat
Treated Plates and to improve Productivity of Accelerated Cooling Plates.
Scope: Design, Supply, Construction, S/V
Main Facilities: Heat Treatment Furnace, Roller Table, Sider Shifter

POSCO Pohang Steelworks

Pohang
Steelworks

No.2 Plate Mill Revamping

Mar. 2004

Jul. 2005

POSCO

224 mT/Y

Revamping existing Facilities to produce High Quality Plates and to maintain Stable Operation.
Scope: Design, Supply, Construction, S/V
Main Facilities: ACC & DQ Facility, Cooling Bed, Finishing Line Facilities

No.2 Heat Treatment Furnace


Extension for No.2 Plate Mill

Oct. 2000

Feb. 2001

POSCO

43 mT/Y

Extending existing No.2 Heat Treatment Furnace to increase Productivity.


Scope: Design, Supply, Construction, S/V

No.3 Plate Mill

Dec. 1995

Sep. 1997

POSCO

106 mT/Y

Plate Mill producing 106 mT/Y Plates


Scope: Design, Supply, Construction, S/V
Main Facilities: Reheating Furnace, Finishing Line Facilities

Apr. 2008

Jul. 2010

POSCO

200 mT/Y

Plate Mill producing 200 mT/Y Plates


Scope: Design, Supply, Construction, S/V
Main Facilities
: Reheating Furnace, ACC & DQ Facilities, Cooling Bed,
Roller Table, Power Supply, Water Treatment Facilities

POSCO Gwangyang Steelworks

Gwangyang Plate Mill

Gwangyang
Steelworks

STEEL PLANT
Hot rolling > Wire rod

Project

Start

Completion

Location

Client

Capacity

The Revamping of the No.3


Wire Rod Mill

Oct. 2000

Nov. 2001

Pohang
Steelworks

POSCO

820,000 T/Y

Vietnam VPS

Apr. 1994

Sep. 1995

Vietnam HaiPhong(Anhai)
City

VPS
(POSCO-VSC)

Relating to revamping project designed to improve quality of wire rod products and increase
production.
Supply Facility : water cooling system, reformed tub and lubliction
equipment of the RSM(Reducing and Sizing Mill)
Engineering, Equipment supply, Erection, Commissioning, Supervision

POSCO E&C carried out the spply of the equipment, costruction, test run and supervision of
200,000 T/Y the VPS mill totally that was found and joint ventured by POSCO and VSC for the producing
the wire rod & rebar.

STEEL PLANT
Cold rolling

Project

Start

Completion

Location

Client

Capacity

Jun. 2009

Oct. 2010

Dalian, China

Dalian POSCO
C&C

200,000 T/Y

Continuous Galvanizing Line with annually production capacity of 200,000 tons.


Scope of work: EP
Product: GI, GL for construction, home appliance & automobile
LINE SPEED(mpm): Enty / Process / Exit: 220 / 170 / 220
Raw Material
- F/H: 0.2 ~ 1.6 mm(t) x 700 ~ 1,250 mm(w)

May 2008

Shunde, Foshan,
Nov. 2009
Guangdong,
China

150,000 T/Y

Annealing Coating Line with annually production capacity of 150,000 tons.


Scope of work: EP
Product: LNO, MNO, HNO
LINE SPEED(mpm): Entry / Process / Exit: 120 / 90 / 120
Raw Material
- 0.5mm(t) x 1,000mm ~ 1,200mm(w)

120,000 T/Y

Color Coating Line with annually production capacity of 120,000 tons.


Scope of work: EP
Product: PCM coil for home appliance, building exterior & Laminated coil
LINE SPEED(mpm): Enty / Process / Exit: 140 / 100 / 140
Raw Material
- Aluminium: 0.5 1.0mm(t) x 600mm 1,350mm(w)
- GI/CR: 0.21.0mmt x 600mm 1,350mm(w)

Overseas Projects

DALIAN-PCSC CGL Revamping

POSCO-Guangdong ACL

PROSPERITY CCL

Feb. 2008

Jun. 2009

POSCOGuangdong

Kaohsiung,
Taiwan

Prosperity
Tieh
Enterprise
Co.,Ltd.

500,000 T/Y

Pickling & Galvanizing Line with annually production capacity of 500,000 tons.
Scope of work: EP
Product: GI, GL for construction industry application
LINE SPEED(mpm): Enty / Process / Exit: 100 / 70 / 100
Raw Material
- HR: 0.8 4.5mm(t) x 500mm 1,560mm(w)
- CR: 0.82.3mm(t) x 500mm 1,560mm(w)

PROSPERITY PGL

Sep. 2007

Jun. 2009

Kaohsiung,
Taiwan

Prosperity
Tieh
Enterprise
Co.,Ltd.

POSCO Mexico CGL

Oct. 2007

Jun. 2009

Altamira,
Mexico

POSCO Mexico

400,000 T/Y

Continuous Galvanizing Line (including RCL, CPL & Utility) with annually production capacity
of 400,000 tons.
Scope of work: EPC
Product: GI, GA for outer pannel of automobile
LINE SPEED(mpm) : Entry / Process / Exit: 300 / 180 / 300
Raw Material: 0.4mm ~ 2.0mm(t) x 800mm ~ 1,900mm(w)

POSCO Vietnam CAL

Aug. 2007

Sep. 2009

Phu My
Industrial Zone,
Vietnam

POSCO
Vietnam

700,000 T/Y

Continuous Annealing Line with annually production capacity of 700,000 tons.


Scope of work: EPC
Product: CR for automotive outer & inner pannel
LINE SPEED(mpm): Enty / Process / Exit: 600 / 400 / 600
Raw Material: 0.351.6mm(t) x 700mm 1,570mm(w)

Chung Hung steel (CHS) RCL

Sep. 2006

May 2008

Kaohsiung,
Taiwan

Chung Hung
Steel Co.

350,000 T/Y

Recoiling Line with a annually production capacity of 350,000 tons.


Scope of work: EP
LINE SPEED(mpm): Max. 500
Raw Material: CR 0.15 2.0mm(t) x 800mm 1,250mm(w)

Mar. 2007

Kaohsiung,
Taiwan

Kao Hsing
Chang Iron &
Steel Co.

360,000 T/Y

Recoiling Line with a annually production capacity of 360,000 tons.


Scope of work: EP
LINE SPEED(mpm) : Max. 500
Raw Material
- CR: 0.16 2.0mm(t) x 800mm 1,250mm(w)
- FH: 0.16 1.6mm(t) x 800mm 1,250mm(w)

Kao Hsing Chang (KHC) RCL

Feb. 2006

STEEL PLANT
Cold rolling

Project

Start

Completion

Location

Client

120,000 T/Y

Color Coating Line (including RCL, CPL & Utility) with annually production capacity of 120,000
tons.
Scope of work: EPC Turnkey
Product: PCM coil for home appliance, building exterior & Laminated coil
LINE SPEED(mpm): Entry / Process / Exit: 160 / 120 / 180
Raw Material
- Aluminium: 0.5 1.6mm(t) x 500mm 1,400mm(w)
- GI/CR: 0.21.6mmt x 500mm 1,400mm(w)

690,000 T/Y

Stainless HAPL with annually production capacity of 690,000 tons.


Scope of work: EP
Product: STS HR
LINE SPEED(mpm) : Entry / Process / Exit: 160 / 100 / 160
Raw Material: 2.1 ~ 6.1mm(t) x 800 ~ 1,350mm(w)

Prosperity
Tieh
Enterprise
Co.,Ltd.

200,000 T/Y

Continuous Galvanizing Line with annually production capacity of 200,000 tons.


Scope of work: EP
Product: GI
LINE SPEED(mpm) : Entry / Process / Exit: 220 / 170 / 220
Raw Material
- CR, HR: 0.2mm ~ 1.2mm(t) x 600mm ~ 1,250mm(w)

Sangsu in China

Sino Leading
Tech.

250,000 T/Y
x 2 line

Two(2) nos. of Continuous Galvanizing Line with annually production capacity of 250,000 tons
each.
Scope of work: EP without S/V
Product: GI ,GL
LINE SPEED(mpm) : Entry / Process / Exit: 235/180/235
Raw Material : 0.2 ~ 1.6mmT, 600 ~ 1,300 mmW

Jul. 2005

Thai Binh,
Vietnam

Thai Binh
General Trade
Company

50,000 T/Y

Continuous Galvanizing Line with annually production capacity of 50,000 tons.


Scope of work: EP
Product: GI
LINE SPEED(mpm) : Entry / Process / Exit: 70 / 50 / 70
Raw Material
- CR: 0.2mm ~ 1.6mm(t) x 600mm ~ 1,300mm(w)

Thai Binh
General Trade
Company

30,000 T/Y

Color Coating Line with annually production capacity of 30,000 tons.


Scope of work: EP
Product: PCM Coil
LINE SPEED(mpm) : Entry / Process / Exit: 50 / 30 / 50
Raw Material:
- GI/EGI/CR: 0.21.0mm(t) x 600mm 1,250mm(w)

Dalian
POSCO-CFM
Coated Steel
Co., Ltd.

150,000 T/Y

Continuous Galvanizing Line with annually production capacity of 150,000 tons.


Scope of work: EP
Product: GI for PCM coil, building exterior & automobile
LINE SPEED(mpm) : Entry / Process / Exit: 150/120/150
Raw Material: 0.2 ~ 1.6mm Thick, 720 ~ 1,250 mm W

150,000 T/Y

Stainless CRM (including ZRM, SPM, APL, CBL, TLL, STL) with annually production capacity of
150,000 tons.
Scope of work: EP
Product: Stainless
LINE SPEED(mpm) : Entry / Process / Exit: 150 / 150 / 150
Raw Material: 0.25 ~ 3.0mm(t) x 600 ~ 1,300mm(w) for STL

150,000 T/Y

Continuous Galvanizing Line with annually production capacity of 100,000 tons.


Scope of work: EP
Product: GI for building construction and electric appliance products
LINE SPEED(mpm) : Entry / Process / Exit: 180 / 120 / 180
Raw Material
- F.H: 0.25mm ~ 2.0mm(t) x 750mm ~ 1,550mm(w)

100,000 T/Y

Color Coating Line with annually production capacity of 100,000 tons.


Scope of work: EP
Product: PCM Coil for Building exterior
LINE SPEED(mpm) : Entry / Process / Exit: 120 / 80 / 120
Raw Material
- GI, GL, CR: 0.25 ~ 1.6mm(t) x 750 ~ 1,550mm(w)

Saudi Iron &


Al-Jubail, Saudi
Steel Company
Arabia
(HADEED)

HADEED CCL

Apr. 2005

Aug. 2007

ZPSS HAPL

Dec. 2004

Oct. 2006

Zhangjiagang,
China

ZPSS

Sep. 2005

Kaohsiung,
Taiwan

Jun. 2005

PROSPERITY CGL

SINO LEADING TECH CGL

GENERAL TRADE CGL

Feb. 2004

Oct. 2003

Jul. 2003

GENERAL TRADE CCL

Jul. 2003

Jul. 2005

Thai Binh,
Vietnam

PCCS CGL Revamping

Jul. 2003

Mar. 2004

Dalian, China

QPSS Stainless CRM

KISCO CGL

KISCO CCL

Jan. 2003

Jan. 2003

Jan. 2003

Capacity

Dec. 2004

Jun. 2004

Apr. 2004

Qingdao, China

QPSS

Unnan, China

KUNMING
IRON & STEEL

Unnan, China

KUNMING
IRON & STEEL

STEEL PLANT
Cold rolling

Project

Start

Completion

Location

NAKISCO

20,000 T/Y

Color Coating Line with annually production capacity of 20,000 tons.


Scope of work: EP
Product: PCM Coil
LINE SPEED(mpm) : Entry / Process / Exit: 50 / 30 / 50
Raw Material:
- GI/EGI/CR: 0.21.0mm(t) x 600mm 1,250mm(w)

NAKISCO

30,000 T/Y

Continuous Galvanizing Line with annually production capacity of 30,000 tons.


Scope of work: EP
Product: GI
LINE SPEED(mpm) : Entry / Process / Exit: 50 / 30 / 50
Raw Material
- CR: 0.2mm ~ 1.6mm(t) x 600mm ~ 1,300mm(w)

100,000 T/Y
x 2 line

Two(2) nos. of Color Coating Line with annually production capacity of 100,000 tons each.
Scope of work: EP
Product: PCM Coil for Building exterior, home appliance & Printed coils
LINE SPEED(mpm) : Entry / Process / Exit: 140 / 100 / 140
Raw Material
- GI, EGI, GF, GL: 0.25 ~ 1.5mm(t) x 900 ~ 1,350mm(w)

NAKISCO CCL

Jan. 2003

Feb. 2004

BinhDuong,
Vietnam

NAKISCO CGL

Jan. 2003

Feb. 2004

BinhDuong,
Vietnam

Client

Capacity

HANDAN NO.1, 2 CCL

Dec. 2002

Jul. 2005

HANDAN
Handan, China IRON & STEEL
Group

PCCS No.2 CCL

Feb. 2002

Mar. 2003

Dalian, China

Dalian
POSCO-CFM
Coated Steel
Co., Ltd.

100,000 T/Y

Color Coating Line with annually production capacity of 100,000 tons.


Scope of work: EP
Product: CCI For architecture and home appliance,Polyester,Si-polyester,PVDF
LINE SPEED(mpm) : Entry / Process / Exit: 120/80/120
Raw Material: 0.2 ~ 1.4 mmThick, 600 ~ 1,250 mm Width

ZPSS NO.2 STS

Dec. 2001

Dec. 2003

Zhangjiagang,
China

ZPSS

150,000 T/Y

Stainless CRM with annually production capacity of 150,000 tons.


Scope of work: EP
Product: Cold Stainless Steel 300 & 400 series
LINE SPEED(mpm) : Entry / Process / Exit: 90 / 160 / 90
Raw Material: 0.3 ~ 3.0mm(t) x 1,000 ~ 1,300mm(w)

SHUNPO MCL

Oct. 2001

Feb. 2003

Shunde, China

POSVINA CCL

Apr. 2001

Jun. 2002

Hochiminh,
Vietnam

POSVINA

22,000 T/Y

Color Coating Line with annually production capacity of 22,000 tons.


Scope of work: E+P
Product: PCM coil
LINE SPEED(mpm) : Entry / Process / Exit: 50/30/50
Raw Material: CR, GI, EGI coil

HAIER CCL

Oct. 2000

Sep. 2001

Hefei, China

HAIER Co.,
LTD.

70,000 T/Y

Color Coating Line with annually production capacity of 70,000 tons.


Scope of work: EP
Product: PCM Coil for Building exterior, home appliance
LINE SPEED(mpm) : Entry / Process / Exit: 80/60/80
Raw Material: 0.25 ~ 1.2 mmT, 600 ~ 1,320mm W

PCCS No.1 CCL

Aug. 1997

Nov. 1998

Dalian, China

Dalian
POSCO-CFM
Coated Steel
Co., Ltd.

50,000 T/Y

Color Coating Line with annually production capacity of 50,000 tons.


Scope of work: EP
Product: PCM Coil for Building exterior, home appliance
LINE SPEED(mpm) : Entry / Process / Exit: 80/60/80
Raw Material: 0.2 ~ 1.2 mmT , 600 ~ 1,250 mmW

ZPSS

150,000 T/Y

Stainless CRM with annually production capacity of 150,000 tons.


Scope of work: EP
Product: Cold Stainless Steel 300 & 400 series
LINE SPEED(mpm) : Entry / Process / Exit: 90 / 160 / 90
Raw Material: 0.3 ~ 3.0mm(t) x 1,000 ~ 1,300mm(w)

ZPSS

100,000 T/Y

Continuous Galvanizing Line with annually production capacity of 100,000 tons.


Scope of work: EP
Product: GI
LINE SPEED(mpm) : Entry / Process / Exit: 150 / 120 / 150
Raw Material: 0.2 ~ 1.6mm(t) x 720 ~ 1,250mm(w)

ZPSS No.1 STS

Apr. 1997

Jan. 1999

Zhangjiagang,
China

ZPSS CGL

Sep. 1996

May 1998

Zhangjiagang,
China

Multi Coating Line with annually production capacity of 100,000 tons.


Shunde
NO: 100,000
Scope of work: EP
POSCO Coated
T/Y
Product: NO
Steel Co. Ltd. Color : 50,000
LINE SPEED(mpm) : Entry / Process / Exit: 160 / 120 / 160
(ShunPo)
T/Y
Raw Material: F.H NO Coil 0.35 ~ 0.65mm(t) x 600 ~ 1,270mm(w)

STEEL PLANT
Cold rolling

Project

Start

Completion

Dec. 2007

Aug. 2009

Location

Client

Capacity

POSCO

85,000 T/Y

HCL with annually production capacity of 85,000 tons.


Scope of work: EPC
Product: GO(silicon steel)
LINE SPEED(mpm) : Entry / Process / Exit: 170 / 110 / 170
Raw Material: 0.15mm ~ 0.5mm(t) x 960mm ~ 1,270mm(w)

POSCO Pohang Steelworks

No.3 HCL For Silicon Steel Plant

No.3 COF For Silicon Steel Plant

Dec. 2007

Aug. 2009

POSCO

100,000 T/Y

COF with annually production capacity of 100,000 tons.


Scope of work: EP+C
Product: Grain oriented electromagentic steel
LINE SPEED(mpm) : Entry / Process / Exit:
Raw Material
- Annealed steel:0.15mm~0.35mm(t)x800mm~1,270mm(w)

No.3 DCNL For Silicon Steel Plant

Dec. 2007

Aug. 2009

POSCO

100,000 T/Y

DCNL with annually production capacity of 100,000 tons.


Scope of work: EP+C
Product: GO
LINE SPEED(mpm) : Entry / Process / Exit: 180 / 120 / 180
Raw Material: 0.15 ~ 0.65mm(t) ~ 960 ~ 1,270mm(w)

No.3 APL For Silicon Steel Plant

Sep. 2007

Aug. 2009

POSCO

352,000 T/Y

No.3APL with a annually production capacity of about 352,000tons.


Scope of work: EP+C
Product: Non Grain Oriented Hyper NO,HN0,HGO,CGO
LINE SPEED(mpm): Entry / Process / Exit: 120 / 75 / 120
Raw Material
- FH 1.5 ~ 3.0mm(t) x 950mm ~ 1320mm(W)

STS APF

Aug. 2007

May 2009

POSCO

400,000 T/Y

APF with annually production capacity of 400,000 tons.


Scope of work: EP+C
Product: Cold Stainless Steel 300 & 400 series
LINE SPEED(mpm) : Entry / Process / Exit: 210 / 150 / 210
Raw Material: 0.3 ~ 3.0mm(t) x 1,000 ~ 1,350mm(w)

No.2 HCL For Silicon Steel Plant

Oct. 2005

Jun. 2006

POSCO

160,000 T/Y

HCL with annually production capacity of 160,000 tons.


Scope of work: EPC
Product: GO(silicon steel)
LINE SPEED(mpm) : Entry / Process / Exit: 230/170/230
Raw Material: 0.15mm ~ 0.5mm(t) x 550mm ~ 1,270mm(w)

No.2 COF For Silicon Steel Plant

Oct. 2005

Jun. 2006

POSCO

80,000 T/Y

COF with annually production capacity of 80,000 tons.


Scope of work: EP+C
Product: Grain oriented electromagentic steel
LINE SPEED(mpm) : Entry / Process / Exit:
Raw Material: Annealed steel:0.2mm~0.35mm(t)x800mm~1,270mm(w)

Modernization of No.2 DCNL For


Silicon Steel Plant

Oct. 2005

Jun. 2006

POSCO

80,000 T/Y

DCNL with annually production capacity of 80,000 tons.


Scope of work: EP+C
Product: Annealed steel
LINE SPEED(mpm) : Entry:180mpm / Process:120mpm / Exit:180mpm
Raw Material: cold rolled steel

No.3 ACL For Silicon Steel Plant

May 2005

Jul. 2006

POSCO

362,000 T/Y

Annealing and Coating Line with a annually production capacity of about 361,732tons.
Scope of work: EP+C
Product: Non Grain Oriented MNO & HNO
LINE SPEED(mpm): Entry / Process / Exit: 320 / 250 / 320
Raw Material: FH 0.15mm ~ 0.7mm(t) x 914mm ~ 1,270mm(w)

No.2 APL For Silicon Steel Plant

Nov. 2003

Jun. 2005

POSCO

250,000 T/Y

No.2APL with a annually production capacity of about 250,000tons.


Scope of work: EP+C
Product: HGO,CGO,NO
LINE SPEED(mpm): Entry / Process / Exit: 60 / 45 / 60
Raw Material: 1.5 ~ 3.0mm(t) x 550mm ~ 1300mm(W)

No.1 COF For Silicon Steel Plant

Sep. 2003

Dec. 2004

POSCO

75,000 T/Y

COF with annually production capacity of 75,000 tons.


Scope of work: EP+C
Product: Grain oriented electromagentic steel
LINE SPEED(mpm) : Entry / Process / Exit:
Raw Material: Annealed steel 0.2mm~0.35mm(t)x800mm~1,270mm(w)

Pohang
Steelworks

STEEL PLANT
Cold rolling

Project

1CAL of No.1 Cold Rolling Mill

Start

Completion

May 2002

Mar. 2005

Location

Client

Capacity

POSCO

300,000 T/Y

Continuous Anealing Line of BP with a annually production capacity of 300,000 tons.


Scope of work: EP+C
Product: Black Plate
LINE SPEED(mpm): Entry / Process / Exit: 750 / 600 / 850
Raw Material: FH 0.15mm ~ 0.6mm(t) x 600mm ~ 1,070mm(w)

3CAL of No.2 Cold Rolling Mill

Nov. 2001

May 2003

POSCO

700,000 T/Y

Continuous Anealing Line with a annually production capacity of 700,000 tons.


Scope of work:EP + C
Product: Cold rolled anealed steel
LINE SPEED(mpm) : Entry:600mpm / Process:450mpm / Exit:640mpm
Raw Material: Cold rolled steel 0.2mm~2.0mm(t)x600mm~1,650mm(w)

STS No.3 H-APL

May 2001

May 2003

POSCO

500,000 T/Y

H-APL with annually production capacity of 500,000 tons.


Scope of work: EP + C
Product: STS HR
LINE SPEED(mpm) : Entry / Process / Exit: 130 / 80 / 130
Raw Material: 1.5 ~ 5.0mm(t) x 600 ~ 1,350mm(w)

Pohang
Steelworks

Enhancement of annually production capacity from 900,000 tons to 1,100,000 tons


Scope of work: EP + C
1,100,000 T/Y Product: Full hard
LINE SPEED(mpm) : Entry :650mpm/ Process:260mpm / Exit:350mpm
Raw Material: Hot coil 2.0mm~4.5mm(t) x600~1,300mm(w)

Modernization of No.1 Cold


Rolling Mill

Mar. 1997

Jul. 1999

POSCO

No.1 ACL Revamping For Silicon


Steel Plant

Nov. 1996

Jun. 1998

POSCO

100,000 T/Y

Annealing and Coating Line with annually production capacity of 100,000 tons.
Scope of work: EP + C
Product: Non Oriented Silicon steel LNO,MNO,HNO
LINE SPEED(mpm) : Entry 100 / Process 80 / Exit: 100
Raw Material: F/H NO Coil: 0.2 0.65mm(t) x 600mm 1,270mm(w)

No.2 ACL For Silicon Steel Plant

Aug. 1996

Sep. 1998

POSCO

220,000 T/Y

Annealing and Coating Line with annually production capacity of 220,000 tons.
Scope of work: EP+ C
Product: Non Oriented Silicon steel LNO,MNO
LINE SPEED(mpm) : Entry 250/ Process 170/ Exit: 250
Raw Material: F/H NO Coil: 0.2 0.65mm(t) x 600mm 1,270mm(w)

NO.7 CGL

Feb. 2008

Mar. 2011

POSCO

500,000 T/Y

Continuous Galvanizing Line with annually production capacity of 500,000 tons.


Scope of work: EP+C
Product: GA for automobile
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 180(220) / 350
Raw Material: 0.4 ~ 2.3mm(t) x 800 ~ 1,900mm(w)

NO.2 CGL Revamping

Nov. 2006

Dec. 2007

POSCO

430,000 T/Y

Continuous Galvanizing Line with annually production capacity of 430,000 tons.


Scope of work: EP+C
Product: GA for automobile
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 250 / 350
Raw Material: 0.4 ~ 2.3mm(t) x 720 ~ 1,900mm(w)

NO.1 CGL Revamping

Oct. 2005

Jun. 2006

POSCO

450,000 T/Y

Continuous Galvanizing Line with annually production capacity of 450,000 tons.


Scope of work: EP+C
Product: GI
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 250 / 350
Raw Material: 0.4 ~ 2.3mm(t) x 800 ~ 1,860mm(w)

POSCO Gwangyang Steelworks

NO.6 CGL

Jun. 2004

Jun. 2006

POSCO

400,000 T/Y

Continuous Galvanizing Line (including Utility) with annually production capacity of 400,000
tons.
Scope of work: EPC
Product: GI, GA for outer pannel of automobile
LINE SPEED(mpm) : Entry / Process / Exit: 300 / 180 / 300
Raw Material: 0.4mm ~ 2.0mm(t) x 800mm ~ 1,900mm(w)

MCL

Jan. 2003

Aug. 2005

POSCO

250,000 T/Y

Multi Coating Line with annually production capacity of 250,000 tons.


Scope of work: EP+C
Product: GI, GA Coating
LINE SPEED(mpm) : Entry / Process / Exit: 250 / 140 / 250
Raw Material: 0.45 ~ 3.25mm(t) x 800 ~ 1,860mm(w)

Gwangyang
Steelworks

NO.5 CGL

Jul. 2003

Oct. 2005

POSCO

450,000 T/Y

Continuous Galvanizing Line (including CPL & Utility) with annually production capacity of
450,000 tons.
Scope of work: EPC
Product: GI, GA for outer pannel of automobile
LINE SPEED(mpm) : Entry / Process / Exit: 300 / 180 / 300
Raw Material: 0.4mm ~ 3.2mm(t) x 800mm ~ 1,900mm(w)

No.4 Cold Rolling FingerprintResistant Facility

Dec. 1999

May 2000

POSCO

100,000 T/Y

Fingerprint-Resistant Facility with annually production capacity of 100,000 tons.


Scope of work: EP+C
Product: Anti Finger printed coil for Home appliance
LINE SPEED(mpm) : Entry / Process / Exit: 300/180/300
Raw Material: 0.4 ~ 2.0 mmT , 700 ~ 1,570 mmW

NO.4 CGL

May 1998

Jun. 2000

POSCO

400,000 T/Y

Continuous Galvanizing Line (CPL & Utility) with annually production capacity of 450,000 tons.
Scope of work: EPC
Product: GI, GA for outer pannel of automobile
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 250 / 350
Raw Material: 0.4mm ~ 2.3mm(t) x 800mm ~ 1,900mm(w)

No.4 Cold Rolling Mill (PL/TCM)

Sep. 1995

Aug. 1997

POSCO

1,800,000 T/Y

EGL of No.4 Cold Rolling Plant

Jul. 1995

Aug. 1997

POSCO

300,000 T/Y

Cold Roll Mill with annually production capacity of 1.8 million tons. (1.5 million tons of Cold
Rolling Coil & 300,000 tons of Electrically Zinc-Galvanized Plate)
Scope of work: EP+C
Product: HR
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 250 / 1,800
Raw Material: 2.3 ~ 5.0mm(t) x 1860mm(w)
EGL with annually production capacity of 300,000 tons.
Scope of work: EP+C
Product: EI,
LINE SPEED(mpm) : Entry / Process / Exit: 300/180/300
Raw Material: 0.4 ~ 2.0 mmT , 700 ~ 1,570 mmW

STEEL PLANT
Cold rolling

Project

Start

Completion

Location

Client

Capacity

Dec. 2007

Jun. 2009

Busan, Korea

Union Steel

370,000 T/Y

POSCO

3,000 T/Y

Other Domestic Projects

Union Steel NO.5 CGL

Continuous Galvanizing Line with annually production capacity of 370,000 tons.


Scope of work: EP
Product: GI, GA
LINE SPEED(mpm) : Entry / Process / Exit: 360 / 240 / 360
Raw Material: F.H 0.25 ~ 2.5mm(t) x 800 ~ 1,600mm(w)
The Magnesium Production Plant with nominal annual capacity of 3,000 tons per year
Magnesium Coil & Sheet.
Scope of work: EP+C
Product: Magnesium Coil & Sheet
LINE SPEED(mpm) : Entry / Process / Exit:
Raw Material: 0.4 ~ 3.0mm(t) x 630mm(w) for STL

Magnesium Production Plant

Sep. 2006

Jul. 2007

Suncheon,
Korea

POCOS NO.2 CCL Revamping

Mar. 2005

Dec. 2005

Pohang, Korea

POCOS

150,000 T/Y

Color Coating Line with annually production capacity of 150,000tons.


Scope of work: EPC turnkey
Product: CCI for architecture and Home appliance
LINE SPEED(mpm) : Entry / Process / Exit: 160/120/160
Raw Material: 0.3 ~ 1.2 mmT, 600 ~ 1,320 mmW

POCOS NO.1 CGL Revamping

Feb. 2005

Aug. 2006

Pohang, Korea

POCOS

300,000 T/Y

Continuous Galvanizing Line with annually production capacity of 300,000 tons.


Scope of work: EP+C
Product: GI, GL
LINE SPEED(mpm) : Entry / Process / Exit: 220 / 150 / 220
Raw Material: 0.3 ~ 2.3mm(t) x 600 ~ 1,270mm(w)

POCOS NO.2 CGL

Sep. 2002

Dec. 2004

Pohang, Korea

POCOS

300,000 T/Y

Continuous Galvanizing Line with annually production capacity of 300,000 tons.


Scope of work: EP+C
Product: GI, GL
LINE SPEED(mpm) : Entry / Process / Exit: 350 / 200 / 350
Raw Material: F.H 0.2 ~ 2.3mm(t) x 700 ~ 1,300mm(w)

POCOS NO.1 CCL Revamping

Jul. 1998

Jun. 1999

Pohang, Korea

POCOS

120,000 T/Y

Color Coating Line with annually production capacity of 120,000 tons.


Scope of work: EPC Turnkey
Product: CCI for architecture and Home appliance
LINE SPEED(mpm) : Entry / Process / Exit: 160/120/180
Raw Material: 0.3 ~ 1.6mmT , 600 ~ 1,320mmW

Dong-Kuk Industries HGL

Aug. 1996

Nov. 1997

Pohang, Korea

Dong-Kuk
Industries

150,000 T/Y

This production facility adopts the continuous galvanizing line (CGL) treatment after the
pickling process of hot-rolled coil, and produces construction materials.

S-ar putea să vă placă și