Training Course 1

User Input Document Prepared By SR


Training Course 2

Primavera Project Planner


User Input Document
Defining a project:

File Æ New

First four numeric of your


Project Name employee#
Number/Version Rev-0
Methanol Plant Training
Project Title Project
DESCON Engineering
Company Name
Limited
Planning Unit Day
Workdays/week 6
Project Start 02-Jan-06
Project must finish by 30-Jun-07
Decimal Places 2
week starts on Monday

Note: All remaining information will be as default

User Input Document Prepared By SR


Training Course 3

User Input Document Prepared By SR


Training Course 4

Data Æ Activity Codes

Add following information


Codes
# Name Length Description
1 DISP 1 Discipline
2 ZONE 4 Zone
3 AREA 4 Area
4 CCTR 5 Cost Center
Now
• select “DISP”
• System will ask for “Save structure edits”
• Press “yes”

Values : DISP
Value Description Order
C Civil 1
M Mechanical 2
E Electrical & Instrumentation 3

• Select “ZONE”

Values : ZONE
Value Description Order
Z1 General Civil Works 1
Z3 Utilities & Offsite Zone 2
Z2 Process Zone 3

• Select “AREA”

Values : Area
Value Description Order
Z1A2 Pipe rack/Sleeper foundation 1
Z1A3 Equipment Foundation 2
Z1A1 Sub-Station Building 3
Z2A1 Common Equipment 4
Z2A2 Process main pipe rack 5
Z2A3 Compressor feed gas treatment 6
Z2A4 Sub Station 7
Z2A5 Common Area 8
Z3A3 Utility equipment cooling water 9
Z3A2 Utility Sleeper 10
Z3A4 Utility offsite pipe rack 11
Z3A5 Utility equipment boiler 12
Z3A1 Utility/Offsite 13

User Input Document Prepared By SR


Training Course 5

• Select “CCTR”

Values: CCTR
Value Description
21120 Excavation
21130 Backfilling/Compaction
21210 Concrete Placement
21310 Form work
21410 Rebar fixing rack/sleeper
21870 Anchor bolts and embedded items
21525 Mortar Finishing
21835 Misc. Steel
21840 Protective coating/water proofing
21885 Flooring, doors, finishing etc.
22120 Structure
22130 Pipe support fabrication
22140 Pipe support erection
22210 Equipment installation
22220 Erection of equipment
22410 Insulation
22520 Painting of equipment
23120 Pipe fabrication CS
23130 Pipe erection CS
23320 Pipe fabrication SS
23330 Pipe erection SS
23420 PWHT
23530 NDT
23610 Hydro testing, cleaning flushing
25320 Cable trays and cover installation
25410 Light installation
25510 Cable laying
25520 Cable termination
25620 Field instrument installation
25730 Fabrication & Erection of supports
25820 Loop Test

Press “Close” button

User Input Document Prepared By SR


Training Course 6

User Input Document Prepared By SR


Training Course 7

Add Activities

Activity Original
id Activity description duration
0001 PROJECT START 0
0011 EXCAVATION 76
0021 REBAR FIXING RACK/SLEEPER 70
0031 CONCRETE PLACEMENT 68
0041 BACKFILLING AND COMPACTION 84
0051 MORTAR FININSHING RACK/SLEEPER FOUNDATION 56
0061 MISC. STEEL RACK/SLEEPER FOUNDATION 70
0071 PROTECTTIVE COATING/WATER PROOFING 50
0081 ANCHOR BOLTS AND EMBEDDED ITEMS 64
0091 EXCAVATION 55
0101 REBAR FIXING EQUIP. 82
0111 CONCRETE PLACEMENT 84
0121 BACKFILLING & COMPACTION 75
0131 MORTAR FINISHING 75
0141 PROTECTIVE COATING/WATER PROOFING 70
0151 ANCHOR BOLTS/EMBEDDED ITEM 75
0161 DRAINAGE PIPE WORKS 60
0171 EXCAVATION 40
0181 FORMWORK INSTALLATION & REMOVAL 82
0191 REBAR FIXING 83
0201 CONCRETE PLACEMENT 77
0211 Backfilling and compaction 84
0221 WATER PROOFING 27
0231 ROOFING SUB STATION 26
0241 FLOORING 50
0251 DOORS WINDOWS 40
0261 PIPING FABRICATION CS 72
0271 PIPING ERECTION CS 131
0281 PIPE SUPPORT FABRICATION 111
0291 PIPE SUPPORT ERECTION 130
0301 HYDROTESTING CLEANING FLUSHING 86
0311 NDT 150
0321 PIPING FABRICATION CS 70
0331 PIPING ERECTION CS 131
0341 PIPE SUPPORT FABRICATION 102
0351 PIPE SUPPORT ERECTION 131
0361 HYDROTESTING CLEANING FLUSHING 120
0371 NDT 139
0381 PIPING FABRICATION CS 98
0391 PIPING FABRICATION SS 32
0401 PIPING ERECTION CS 115
0411 PIPING ERECTION SS 113
0421 PIPE SUPPORTS FABRICATION 104
0431 PIPE SUPPORT ERECTION 140
User Input Document Prepared By SR
Training Course 8

0441 HYDROTESTING, CLEANING, FLUSHING 111


0451 ERECTION OF DUMP STEAM CONDENSOR 21
0461 ERECTION OF FLASHED STEAM CONDENSOR 22
0471 NDT 201
0481 PWHT 201
0491 INSULATION OF EQUIPMENT 49
0501 PIPING FABRICATION CS 117
0511 PIPING ERECTION CS 160
0521 PIPING FABRICATION SS 83
0531 PIPING ERECTION SS 139
0541 PIPE SUPPORTS FABRICATION 108
0551 PIPE SUPPORT ERECTION 165
0561 ERECTION OF BOILER 114
0571 INSULATION OF EQUIPMENT 168
0581 HYDROTESTING, CLEANING, FLUSHING 91
0591 NDT 195
0601 PWHT 204
0611 STRUCTURE 60
0621 FIELD INSTRUMENT INSTALLATION UTILITY 35
0631 FILED INSTRUMENT INSTALLATION OFFSITE 64
0641 CABLE TRAYS & COVERS INSTALLATION 78
0651 CABLE LAYING 45
0661 CABLE TERMINATION 39
0671 FABRICATION AND ERECTION OF SUPPORTS 77
0681 LOOP TEST 28
0691 STATIONARY EQUIPMENT INSTALLATION 62
0701 PIPING FABRICATION CS 145
0711 PIPING FABRICATION SS 64
0721 PIPING ERECTION CS 170
0731 PIPING ERECTION SS 118
0741 PIPE SUPPORT FABRICATION 150
0751 PIPE SUPPORT ERECTION 170
0761 HYDROTESTING CLEANING FLUSHING 130
0771 NDT 170
0781 ERECTION OF HEAVY ENDS CONDENSOR WEST SIDE 27
0791 ERECTION OF HEAVY ENDS CONDENSOR EAST SIDE 25
0801 INSULATION OF EQUIPMENT 54
0811 ERECTION OF WATER COOLER 10
0821 PIPING FABRICATION CS 130
0831 PIPING ERECTION CS 117
0841 PIPING FABRICATION SS 99
0851 PIPING ERECTION SS 92
0861 ERECTION OF GAS COMPR/TURBINE 79
0871 PIPE SUPPORT FABRICATION 120
0881 PIPE SUPPORT ERECTION 140
0891 HYDROTESTING CLEANING FLUSHING 114
0901 NDT 153
0911 PWHT 208
User Input Document Prepared By SR
Training Course 9

0921 INSULATION OF EQUIPMENT 49


0931 CABLE TRAYS & COVERS INSTALLATION 163
0941 CABLE LAYING 141
0951 CABLE TERMINATION 66
0961 FABRICATION AND ERECTION OF SUPPORTS 152
0971 LIGHT INSTALLATION 24
0981 INSULATION OF PIPE/MISC. EQPT 190
0991 PAINTING OF EQUIPMENT AND PIPING 154
1001 PROJECT COMPLETION 0

User Input Document Prepared By SR


Training Course 10

User Input Document Prepared By SR


Training Course 11

Assign Discipline,Zone,Area & CCTR to Activities


• Press F7, it will open activity form
• Select the activity one by one
• Assign “type”
• Assign Discipline, Zone, Area & CCTR from dropdown menu given at the
bottom of form
• Press OK

ZONE = Z1
AREA = Z1A1

Activity
Activity description Type Disp Zone Area CCTR
id
0171 EXCAVATION Task C Z1 Z1A1 21120
0181 FORMWORK INSTALLATION & REMOVAL Task C Z1 Z1A1 21310
0191 REBAR FIXING Task C Z1 Z1A1 21410
0201 CONCRETE PLACEMENT Task C Z1 Z1A1 21210
0211 Backfilling and compaction Task C Z1 Z1A1 21130
0221 WATER PROOFING Task C Z1 Z1A1 21885
0231 ROOFING SUB STATION Task C Z1 Z1A1 21885
0241 FLOORING Task C Z1 Z1A1 21885
0251 DOORS WINDOWS Task C Z1 Z1A1 21885

AREA = Z1A2

Start
mile C Z1 Z1A2
0001 PROJECT START stone
0011 EXCAVATION Task C Z1 Z1A2 21120
0021 REBAR FIXING RACK/SLEEPER Task C Z1 Z1A2 21410
0031 CONCRETE PLACEMENT Task C Z1 Z1A2 21210
0041 BACKFILLING AND COMPACTION Task C Z1 Z1A2 21130
MORTAR FININSHING RACK/SLEEPER
0051 Task C Z1 Z1A2 21525
FOUNDATION
0061 MISC. STEEL RACK/SLEEPER FOUNDATION Task C Z1 Z1A2 21835
0071 PROTECTTIVE COATING/WATER PROOFING Task C Z1 Z1A2 21840
0081 ANCHOR BOLTS AND EMBEDDED ITEMS Task C Z1 Z1A2 21870

User Input Document Prepared By SR


Training Course 12

AREA = Z1A3

0091 EXCAVATION Task C Z1 Z1A3 21120


0101 REBAR FIXING EQUIP. Task C Z1 Z1A3 21410
0111 CONCRETE PLACEMENT Task C Z1 Z1A3 21210
0121 BACKFILLING & COMPACTION Task C Z1 Z1A3 21130
0131 MORTAR FINISHING Task C Z1 Z1A3 21525
0141 PROTECTIVE COATING/WATER PROOFING Task C Z1 Z1A3 21840
0151 ANCHOR BOLTS/EMBEDDED ITEM Task C Z1 Z1A3 21870
0161 DRAINAGE PIPE WORKS Task C Z1 Z1A3 21885

User Input Document Prepared By SR


Training Course 13

User Input Document Prepared By SR


Training Course 14

ZONE = Z2

AREA = Z2A1

Activity Zon
Activity description Type Disp Area CCTR
id e
0691 STATIONARY EQUIPMENT INSTALLATION Task M Z2 Z2A1 22210

AREA = Z2A2

0701 PIPING FABRICATION CS Task M Z2 Z2A2 23120


0711 PIPING FABRICATION SS Task M Z2 Z2A2 23320
0721 PIPING ERECTION CS Task M Z2 Z2A2 23130
0731 PIPING ERECTION SS Task M Z2 Z2A2 23330
0741 PIPE SUPPORT FABRICATION Task M Z2 Z2A2 22130
0751 PIPE SUPPORT ERECTION Task M Z2 Z2A2 22140
0761 HYDROTESTING CLEANING FLUSHING Task M Z2 Z2A2 23610
0771 NDT Task M Z2 Z2A2 23530
ERECTION OF HEAVY ENDS CONDENSOR
0781 Task M Z2 Z2A2 22210
WEST SIDE
ERECTION OF HEAVY ENDS CONDENSOR
M Z2 Z2A2 22210
0791 EAST SIDE Task
0801 INSULATION OF EQUIPMENT Task M Z2 Z2A2 22410
0811 ERECTION OF WATER COOLER Task M Z2 Z2A2 22210

AREA = Z2A3

0821 PIPING FABRICATION CS Task M Z2 Z2A3 23120


0831 PIPING ERECTION CS Task M Z2 Z2A3 23130
0841 PIPING FABRICATION SS Task M Z2 Z2A3 23320
0851 PIPING ERECTION SS Task M Z2 Z2A3 23330
0861 ERECTION OF GAS COMPR/TURBINE Task M Z2 Z2A3 22220
0871 PIPE SUPPORT FABRICATION Task M Z2 Z2A3 22130
0881 PIPE SUPPORT ERECTION Task M Z2 Z2A3 22140
0891 HYDROTESTING CLEANING FLUSHING Task M Z2 Z2A3 23610
0901 NDT Task M Z2 Z2A3 23530
0911 PWHT Task M Z2 Z2A3 23420
0921 INSULATION OF EQUIPMENT Task M Z2 Z2A3 22410

User Input Document Prepared By SR


Training Course 15

AREA = Z2A4

Activity Disp Zon Area


id Activity description Type e CCTR
0931 CABLE TRAYS & COVERS INSTALLATION Task E Z2 Z2A4 25320
0941 CABLE LAYING Task E Z2 Z2A4 25510
0951 CABLE TERMINATION Task E Z2 Z2A4 25520
0961 FABRICATION AND ERECTION OF SUPPORTS Task E Z2 Z2A4 25730
0971 LIGHT INSTALLATION Task E Z2 Z2A4 25410

AREA = Z2A5

0981 INSULATION OF PIPE/MISC. EQPT Task M Z2 Z2A5 22410


0991 PAINTING OF EQUIPMENT AND PIPING Task M Z2 Z2A5 22520
Finish
1001 PROJECT COMPLETION mile Z2 Z2A5
stone

User Input Document Prepared By SR


Training Course 16

User Input Document Prepared By SR


Training Course 17

ZONE = Z3
AREA = Z3A1

Activity Disp Zon Area


id Activity description Type e CCTR
0621 FIELD INSTRUMENT INSTALLATION UTILITY Task E Z3 Z3A1 25620
0631 FILED INSTRUMENT INSTALLATION OFFSITE Task E Z3 Z3A1 25620
0641 CABLE TRAYS & COVERS INSTALLATION Task E Z3 Z3A1 25320
0651 CABLE LAYING Task E Z3 Z3A1 25510
0661 CABLE TERMINATION Task E Z3 Z3A1 25520
0671 FABRICATION AND ERECTION OF SUPPORTS Task E Z3 Z3A1 25730
0681 LOOP TEST Task E Z3 Z3A1 25820

AREA = Z3A2

0321 PIPING FABRICATION CS Task M Z3 Z3A2 23120


0331 PIPING ERECTION CS Task M Z3 Z3A2 23130
0341 PIPE SUPPORT FABRICATION Task M Z3 Z3A2 22130
0351 PIPE SUPPORT ERECTION Task M Z3 Z3A2 22140
0361 HYDROTESTING CLEANING FLUSHING Task M Z3 Z3A2 23610
0371 NDT Task M Z3 Z3A2 23530

AREA = Z3A3

0261 PIPING FABRICATION CS Task M Z3 Z3A3 23120


0271 PIPING ERECTION CS Task M Z3 Z3A3 23130
0281 PIPE SUPPORT FABRICATION Task M Z3 Z3A3 22130
0291 PIPE SUPPORT ERECTION Task M Z3 Z3A3 22140
0301 HYDROTESTING CLEANING FLUSHING Task M Z3 Z3A3 23610
0311 NDT Task M Z3 Z3A3 23530

User Input Document Prepared By SR


Training Course 18

AREA = Z3A4

Activity Disp Zon Area


id Activity description Type e CCTR
0381 PIPING FABRICATION CS Task M Z3 Z3A4 23120
0391 PIPING FABRICATION SS Task M Z3 Z3A4 23320
0401 PIPING ERECTION CS Task M Z3 Z3A4 23130
0411 PIPING ERECTION SS Task M Z3 Z3A4 23330
0421 PIPE SUPPORTS FABRICATION Task M Z3 Z3A4 22130
0431 PIPE SUPPORT ERECTION Task M Z3 Z3A4 22140
0441 HYDROTESTING, CLEANING, FLUSHING Task M Z3 Z3A4 23610
0451 ERECTION OF DUMP STEAM CONDENSOR Task M Z3 Z3A4 22210
ERECTION OF FLASHED STEAM M Z3 Z3A4
0461 CONDENSOR Task 22210
0471 NDT Task M Z3 Z3A4 23530
0481 PWHT Task M Z3 Z3A4 23420
0491 INSULATION OF EQUIPMENT Task M Z3 Z3A4 22410

AREA = Z3A5

0501 PIPING FABRICATION CS Task M Z3 Z3A5 23120


0511 PIPING ERECTION CS Task M Z3 Z3A5 23130
0521 PIPING FABRICATION SS Task M Z3 Z3A5 23320
0531 PIPING ERECTION SS Task M Z3 Z3A5 23330
0541 PIPE SUPPORTS FABRICATION Task M Z3 Z3A5 22130
0551 PIPE SUPPORT ERECTION Task M Z3 Z3A5 22140
0561 ERECTION OF BOILER Task M Z3 Z3A5 22210
0571 INSULATION OF EQUIPMENT Task M Z3 Z3A5 22410
0581 HYDROTESTING, CLEANING, FLUSHING Task M Z3 Z3A5 23610
0591 NDT Task M Z3 Z3A5 23530
0601 PWHT Task M Z3 Z3A5 23420
0611 STRUCTURE Task M Z3 Z3A5 22120

User Input Document Prepared By SR


Training Course 19

User Input Document Prepared By SR


Training Course 20

Organize the Schedule

FormatÆ Organize

Group By
Project
Zone
Area

• Also Select the Background and text colour


• Press the button “Organize now”

User Input Document Prepared By SR


Training Course 21

User Input Document Prepared By SR


Training Course 22

Assign Relationship and Schedule

• Select the activity


• Press “SUCC” Tab
• Select the successor activity
• Assign the Relationship
• Press “OK”
• Press F9
• Press “Schedule now”
Repeat above steps to assign each of the following relationship:

Successor
Activity
Activity Description Activity
id
id Activity description REL Lag
0011 EXCAVATION SS 0
PROJECT START
0001 0261 PIPING FABRICATION CS SS 0
0021 REBAR FIXING RACK/SLEEPER SS 10
EXCAVATION
0011 0091 EXCAVATION SS 30
CONCRETE PLACEMENT
MISC. STEEL RACK/SLEEPER
REBAR FIXING RACK/SLEEPER 0031 FOUNDATION SS 12
0061 ANCHOR BOLTS AND EMBEDDED SS 0
0021 0081 ITEMS SS 10
BACKFILLING AND COMPACTION
CONCRETE PLACEMENT 0041 MORTAR FININSHING FF 6
0031 0051 RACK/SLEEPER FOUNDATION FF 4
0041 BACKFILLING AND COMPACTION 1001 PROJECT COMPLETION FS 0
MORTAR FININSHING RACK/SLEEPER PROTECTTIVE COATING/WATER
0051 FOUNDATION 0071 PROOFING SS 0
MISC. STEEL RACK/SLEEPER
0061 FOUNDATION 0401 PIPING ERECTION CS SS 20
0071 PROTECTTIVE COATING/WATER 1001 PROJECT COMPLETION FS 0

User Input Document Prepared By SR


Training Course 23

PROOFING
0081 ANCHOR BOLTS AND EMBEDDED ITEMS 0031 CONCRETE PLACEMENT SS 1

0171 EXCAVATION SS 30
0091 EXCAVATION 0101 REBAR FIXING EQUIP. SS 10
CONCRETE PLACEMENT
0101 0111 ANCHOR BOLTS/EMBEDDED SS 10
REBAR FIXING EQUIP. 0151 ITEM SS 8
STATIONARY EQUIPMENT
INSTALLATION
0691 BACKFILLING & COMPACTION FS 0
0111 CONCRETE PLACEMENT
0121 MORTAR FINISHING FF 6
0131 ERECTION OF DUMP STEAM FF 4
0451 CONDENSOR FS -6
0121 BACKFILLING & COMPACTION 0161 DRAINAGE PIPE WORKS FF -2
PROTECTIVE COATING/WATER
0131 MORTAR FINISHING 0141 PROOFING SS 0
PROTECTIVE COATING/WATER
0141
PROOFING 1001 PROJECT COMPLETION FS 0
0151 ANCHOR BOLTS/EMBEDDED ITEM 0111 CONCRETE PLACEMENT SS 1
0161 DRAINAGE PIPE WORKS 1001 PROJECT COMPLETION FS 0
FORMWORK INSTALLATION &
0171 EXCAVATION 0181 REMOVAL SS 8
0181 FORMWORK INSTALLATION & REMOVAL 0191 REBAR FIXING SS 0
0191 REBAR FIXING 0201 CONCRETE PLACEMENT SS 11
0211 Backfilling and compaction FF 10
0201 CONCRETE PLACEMENT
0221 WATER PROOFING SS 40
0211 Backfilling and compaction 1001 PROJECT COMPLETION FS 0
0221 WATER PROOFING 0231 ROOFING SUB STATION SS 0
0231 ROOFING SUB STATION 0241 FLOORING FS 0
DOORS WINDOWS
CABLE TRAYS & COVERS
0241 FLOORING 0251 INSTALLATION SS 8
0931 FABRICATION AND ERECTION OF FS 0
0961 SUPPORTS SS 0

User Input Document Prepared By SR


Training Course 24

0251 DOORS WINDOWS 1001 PROJECT COMPLETION FS 0


0321 PIPING FABRICATION CS SS 26
0271 PIPING ERECTION CS SS 12
0261 PIPING FABRICATION CS
0281 PIPE SUPPORT FABRICATION SS 0
0311 NDT SS 0
HYDROTESTING CLEANING
0271 PIPING ERECTION CS
0301 FLUSHING FS -26
0281 PIPE SUPPORT FABRICATION 0291 PIPE SUPPORT ERECTION SS 12
0291 PIPE SUPPORT ERECTION 0271 PIPING ERECTION CS SS 0
0301 HYDROTESTING CLEANING FLUSHING 1001 PROJECT COMPLETION FS 0
0311 NDT 1001 PROJECT COMPLETION FS 0
0331 PIPING ERECTION CS SS 5
0341 PIPE SUPPORT FABRICATION SS 0
PIPING FABRICATION CS
0321 0371 NDT SS 0
0381 PIPING FABRICATION CS SS 36
HYDROTESTING CLEANING
0331 PIPING ERECTION CS 0361 FLUSHING FS -20
0341 PIPE SUPPORT FABRICATION 0351 PIPE SUPPORT ERECTION SS 5
0351 PIPE SUPPORT ERECTION 0331 PIPING ERECTION CS SS 0
0361 HYDROTESTING CLEANING FLUSHING 1001 PROJECT COMPLETION FS 0
0371 NDT 1001 PROJECT COMPLETION FS 0
0391 PIPING FABRICATION SS SS 26
0401 PIPING ERECTION CS SS 16
0381 PIPING FABRICATION CS 0421 PIPE SUPPORTS FABRICATION SS 0
0471 NDT SS 10
0501 PIPING FABRICATION CS SS 50
0391 PIPING FABRICATION SS 0411 PIPING ERECTION SS SS 10
HYDROTESTING, CLEANING,
0401 PIPING ERECTION CS 0441 FLUSHING FS -26
HYDROTESTING, CLEANING,
0411 PIPING ERECTION SS 0441 FLUSHING SS 30
0421 PIPE SUPPORTS FABRICATION 0431 PIPE SUPPORT ERECTION SS 15
0431 PIPE SUPPORT ERECTION 0401 PIPING ERECTION CS SS 0
0441 HYDROTESTING, CLEANING, FLUSHING 0481 PWHT FF 0
0451 ERECTION OF DUMP STEAM 0461 ERECTION OF FLASHED STEAM SS 12

User Input Document Prepared By SR


Training Course 25

CONDENSOR CONDENSOR
ERECTION OF FLASHED STEAM
0461 CONDENSOR 0491 INSULATION OF EQUIPMENT FS 0
0471 NDT 1001 PROJECT COMPLETION FS 0
0481 PWHT 1001 PROJECT COMPLETION FS 0
0491 INSULATION OF EQUIPMENT 1001 PROJECT COMPLETION FS 0
0701 PIPING FABRICATION CS SS 0
0511 PIPING ERECTION CS SS 10
0521 PIPING FABRICATION SS SS 0
0501 PIPING FABRICATION CS
0541 PIPE SUPPORTS FABRICATION SS 0
0591 NDT SS 0
0611 STRUCTURE SS 0
CABLE TRAYS & COVERS
INSTALLATION
FABRICATION AND ERECTION OF
0511 PIPING ERECTION CS
0641 SUPPORTS FS -26
0671 HYDROTESTING, CLEANING, FS -26
0581 FLUSHING FS -30
0521 PIPING FABRICATION SS 0531 PIPING ERECTION SS SS 15
HYDROTESTING, CLEANING,
0531 PIPING ERECTION SS 0581 FLUSHING SS 30
0541 PIPE SUPPORTS FABRICATION 0551 PIPE SUPPORT ERECTION SS 10
0551 PIPE SUPPORT ERECTION 0511 PIPING ERECTION CS SS 0
0561 ERECTION OF BOILER 0571 INSULATION OF EQUIPMENT FS -52
0571 INSULATION OF EQUIPMENT 1001 PROJECT COMPLETION FS 0
0581 HYDROTESTING, CLEANING, FLUSHING 0601 PWHT FF 0
0591 NDT 1001 PROJECT COMPLETION FS 0
0601 PWHT 1001 PROJECT COMPLETION FS 0
0611 STRUCTURE 0561 ERECTION OF BOILER FS -6
FIELD INSTRUMENT INSTALLATION
0621
UTILITY 0681 LOOP TEST FS 0
FIELD INSTRUMENT
0631 FILED INSTRUMENT INSTALLATION 0621 INSTALLATION UTILITY SS 7
OFFSITE 0681 LOOP TEST FS -6
0641 CABLE TRAYS & COVERS INSTALLATION 0651 CABLE LAYING SS 26

User Input Document Prepared By SR


Training Course 26

FILED INSTRUMENT
0651 CABLE LAYING 0631 INSTALLATION OFFSITE SS 7
0661 CABLE TERMINATION FF 6
0661 CABLE TERMINATION 0681 LOOP TEST FS 0
FABRICATION AND ERECTION OF CABLE TRAYS & COVERS
0671
SUPPORTS 0641 INSTALLATION SS 0
0681 LOOP TEST 1001 PROJECT COMPLETION FS 0
0691 STATIONARY EQUIPMENT INSTALLATION 1001 PROJECT COMPLETION FS 0
0821 PIPING FABRICATION CS SS 70
0711 PIPING FABRICATION SS SS 26
0701 PIPING FABRICATION CS 0721 PIPING ERECTION CS SS 13
0741 PIPE SUPPORT FABRICATION SS 0
0771 NDT SS 0
0711 PIPING FABRICATION SS 0731 PIPING ERECTION SS SS 38
HYDROTESTING CLEANING
0721 PIPING ERECTION CS 0761 FLUSHING FS -40
HYDROTESTING CLEANING
0731 PIPING ERECTION SS 0761 FLUSHING SS 40
0741 PIPE SUPPORT FABRICATION 0751 PIPE SUPPORT ERECTION SS 12
0751 PIPE SUPPORT ERECTION 0721 PIPING ERECTION CS SS 0
0761 HYDROTESTING CLEANING FLUSHING 1001 PROJECT COMPLETION FS 0
0771 NDT 1001 PROJECT COMPLETION FS 0
ERECTION OF HEAVY ENDS ERECTION OF HEAVY ENDS
0781
CONDENSOR WEST SIDE 0791 CONDENSOR EAST SIDE FS 0
ERECTION OF HEAVY ENDS 0801 INSULATION OF EQUIPMENT FS 0
0791
CONDENSOR EAST SIDE 0811 ERECTION OF WATER COOLER FS 0
0801 INSULATION OF EQUIPMENT 1001 PROJECT COMPLETION FS 0
0811 ERECTION OF WATER COOLER 1001 PROJECT COMPLETION FS 0
0831 PIPING ERECTION CS SS 16
0841 PIPING FABRICATION SS SS 26
0821 PIPING FABRICATION CS
0871 PIPE SUPPORT FABRICATION SS 0
0901 NDT SS 0
HYDROTESTING CLEANING
0831 PIPING ERECTION CS 0891 FLUSHING FS -26
0841 PIPING FABRICATION SS 0851 PIPING ERECTION SS SS 38

User Input Document Prepared By SR


Training Course 27

HYDROTESTING CLEANING
0851 PIPING ERECTION SS 0891 FLUSHING SS 40
0861 ERECTION OF GAS COMPR/TURBINE 0921 INSULATION OF EQUIPMENT FS 0
0871 PIPE SUPPORT FABRICATION 0881 PIPE SUPPORT ERECTION SS 15
0881 PIPE SUPPORT ERECTION 0831 PIPING ERECTION CS SS 0
PWHT
0891 HYDROTESTING CLEANING FLUSHING 0911 INSULATION OF PIPE/MISC. FF -7
0981 EQPT FF 20
0901 NDT 1001 PROJECT COMPLETION FS 0
0911 PWHT 1001 PROJECT COMPLETION FS 0
0921 INSULATION OF EQUIPMENT 1001 PROJECT COMPLETION FS 0
0931 CABLE TRAYS & COVERS INSTALLATION 0941 CABLE LAYING SS 0
0941 CABLE LAYING 0951 CABLE TERMINATION FF 4
0951 CABLE TERMINATION 0971 LIGHT INSTALLATION FF 0
FABRICATION AND ERECTION OF CABLE TRAYS & COVERS
0961
SUPPORTS 0931 INSTALLATION SS 0
0971 LIGHT INSTALLATION 1001 PROJECT COMPLETION FS 0
PAINTING OF EQUIPMENT AND
0981 INSULATION OF PIPE/MISC. EQPT 0991 PIPING FF 0
0991 PAINTING OF EQUIPMENT AND PIPING 1001 PROJECT COMPLETION FS 0
1001 PROJECT COMPLETION

User Input Document Prepared By SR


Training Course 28

User Input Document Prepared By SR


Training Course 29

User Input Document Prepared By SR


Training Course 30

Apply Constraint

• Select the activity


• Press “Constr” Tab
• Click at “Early Constraint” and give ”Start Date”
Repeat above steps for each of following constraint:

Activity id Activity Description Start Date


0861 ERECTION OF GAS COMPR/TURBINE 11-Aug-06
ERECTION OF HEAVY ENDS CONDENSOR
0781
WEST SIDE 15-Jul-06
0321 PIPING FABRICATION CS 01-Feb-06
0261 PIPING FABRICATION CS 01-Feb-06
0451 ERECTION OF DUMP STEAM CONDENSOR 06-Jun-06

User Input Document Prepared By SR


Training Course 31

User Input Document Prepared By SR


Training Course 32

Defining Resources in Resource Dictionary

Data Æ Resources

Add following two resources:

Resources
0QTY
MH

Press the “close” button

Assigning Resources to Activities

• Select Activity
• Press “RES” Tab
• Add both resources i.e. MH & 0QTY
• Against the row of “Budgeted quantity”:
o Add the values of MH & 0QTY as given below
• Add the value of curve
• Press “OK”

Activity MH 0QTY Curve


0001 PROJECT START 0
0011 EXCAVATION 685 1712.50 6
0021 REBAR FIXING RACK/SLEEPER 954 15.90 6
0031 CONCRETE PLACEMENT 1,243.00 194.83 6
0041 BACKFILLING AND COMPACTION 80 88.89 6
MORTAR FININSHING RACK/SLEEPER 6
0051 FOUNDATION 942 471.00
MISC. STEEL RACK/SLEEPER 0
0061 FOUNDATION 4,760.00 9520.00
PROTECTTIVE COATING/WATER 0
0071 PROOFING 655 1637.50
0081 ANCHOR BOLTS AND EMBEDDED ITEMS 2,288.00 1830.40 0
0091 EXCAVATION 5,713.00 14282.50 0
0101 REBAR FIXING EQUIP. 19,069.00 317.82 6
0111 CONCRETE PLACEMENT 23,966.00 3756.43 0
0121 BACKFILLING & COMPACTION 8,716.00 9684.44 6
0131 MORTAR FINISHING 2,504.00 1252.00 6
PROTECTIVE COATING/WATER 6
0141 PROOFING 3,308.00 8270.00
0151 ANCHOR BOLTS/EMBEDDED ITEM 4,552.00 3641.60 6
0161 DRAINAGE PIPE WORKS 2,500.00 12500.00 6
0171 EXCAVATION 975 2437.50 6
0181 FORMWORK INSTALLATION & REMOVAL 4,429.00 805.27 6

User Input Document Prepared By SR


Training Course 33

0191 REBAR FIXING 1,951.00 32.52 6


0201 CONCRETE PLACEMENT 1,561.00 244.67 6
0211 Backfilling and compaction 8,716.00 9684.44 6
0221 WATER PROOFING 390 1950.00 6
0231 ROOFING SUB STATION 1,171.00 5855.00 6
0241 FLOORING 3,902.00 19510.00 6
0251 DOORS WINDOWS 780 3900.00 6
0261 PIPING FABRICATION CS 14,645.00 7040.87 6
0271 PIPING ERECTION CS 16,981.00 7753.88 6
0281 PIPE SUPPORT FABRICATION 2,147.00 7.02 6
0291 PIPE SUPPORT ERECTION 379 7.02 6
0301 HYDROTESTING CLEANING FLUSHING 3,251.10 706.76 6
0311 NDT 1,115.00 1858.33 6
0321 PIPING FABRICATION CS 5,763.00 2770.67 0
0331 PIPING ERECTION CS 26,736.00 12208.22 6
0341 PIPE SUPPORT FABRICATION 6,596.00 21.56 6
0351 PIPE SUPPORT ERECTION 1,963.00 36.35 6
0361 HYDROTESTING CLEANING FLUSHING 20,109.00 4371.52 6
0371 NDT 1,115.00 1858.33 6
0381 PIPING FABRICATION CS 8,201.00 3942.79 6
0391 PIPING FABRICATION SS 1,146.00 350.46 6
0401 PIPING ERECTION CS 14,266.00 6514.16 6
0411 PIPING ERECTION SS 4,003.00 792.67 6
0421 PIPE SUPPORTS FABRICATION 1,963.00 6.42 6
0431 PIPE SUPPORT ERECTION 346 6.41 6
0441 HYDROTESTING, CLEANING, FLUSHING 6,325.00 1375.00 6
ERECTION OF DUMP STEAM 6
0451 CONDENSOR 5,220.00 168.39
ERECTION OF FLASHED STEAM 6
0461 CONDENSOR 1,107.00 35.71
0471 NDT 937 1561.67 6
0481 PWHT 714 1190.00 6
0491 INSULATION OF EQUIPMENT 7,028.00 1464.17 6
0501 PIPING FABRICATION CS 16,138.00 7758.65 6
0511 PIPING ERECTION CS 13,851.00 6324.66 6
0521 PIPING FABRICATION SS 5,216.00 1595.11 6
0531 PIPING ERECTION SS 8,336.00 1650.69 6
0541 PIPE SUPPORTS FABRICATION 2,699.00 8.82 6
0551 PIPE SUPPORT ERECTION 476 8.81 6
0561 ERECTION OF BOILER 13,394.00 432.06 6
0571 INSULATION OF EQUIPMENT 7,028.00 1464.17 6
0581 HYDROTESTING, CLEANING, FLUSHING 7,185.00 1561.96 6
0591 NDT 910 1516.67 6
0601 PWHT 797 1328.33 6
0611 STRUCTURE 3,532.00 54.34 6
FIELD INSTRUMENT INSTALLATION 6
0621 UTILITY 1,565.00 558.93
FILED INSTRUMENT INSTALLATION 6
0631 OFFSITE 3,186.00 1137.86
User Input Document Prepared By SR
Training Course 34

0641 CABLE TRAYS & COVERS INSTALLATION 7,805.00 6504.17 6


0651 CABLE LAYING 4,465.00 9500.00 6
0661 CABLE TERMINATION 274 830.30 6
FABRICATION AND ERECTION OF 6
0671 SUPPORTS 1,291.00 2151.67
0681 LOOP TEST 517 172.33 6
0691 STATIONARY EQUIPMENT INSTALLATION 17,659.00 569.65 6
0701 PIPING FABRICATION CS 23,800.00 11442.31 6
0711 PIPING FABRICATION SS 4,321.00 1321.41 6
0721 PIPING ERECTION CS 64,290.00 29356.16 6
0731 PIPING ERECTION SS 23,505.00 4654.46 6
0741 PIPE SUPPORT FABRICATION 12,271.00 40.10 6
0751 PIPE SUPPORT ERECTION 2,165.00 40.09 6
0761 HYDROTESTING CLEANING FLUSHING 25,229.00 5484.57 6
0771 NDT 1,115.00 1858.33 6
ERECTION OF HEAVY ENDS CONDENSOR 6
0781 WEST SIDE 26,116.00 842.45
ERECTION OF HEAVY ENDS CONDENSOR 6
0791 EAST SIDE 26,116.00 842.45
0801 INSULATION OF EQUIPMENT 2,289.00 476.88 6
0811 ERECTION OF WATER COOLER 7,592.00 244.90 6
0821 PIPING FABRICATION CS 32,748.00 15744.23 6
0831 PIPING ERECTION CS 25,319.00 11561.19 6
0841 PIPING FABRICATION SS 14,816.00 4530.89 6
0851 PIPING ERECTION SS 23,039.00 4562.18 6
0861 ERECTION OF GAS COMPR/TURBINE 10,811.00 245.70 6
0871 PIPE SUPPORT FABRICATION 9,510.00 31.08 6
0881 PIPE SUPPORT ERECTION 1,678.00 31.07 6
0891 HYDROTESTING CLEANING FLUSHING 2,786.00 605.65 6
0901 NDT 1,115.00 1858.33 6
0911 PWHT 14,813.00 24688.33 6
0921 INSULATION OF EQUIPMENT 6,017.00 1253.54 6
0931 CABLE TRAYS & COVERS INSTALLATION 8,395.00 6995.83 6
0941 CABLE LAYING 37,766.00 80353.19 6
0951 CABLE TERMINATION 667 2021.21 6
FABRICATION AND ERECTION OF 6
0961 SUPPORTS 1,365.00 2275.00
0971 LIGHT INSTALLATION 3,417.00 2278.00 6
0981 INSULATION OF PIPE/MISC. EQPT 98,928.00 20610.00 6
0991 PAINTING OF EQUIPMENT AND PIPING 8,491.00 9434.44 6
1001 PROJECT COMPLETION 0

User Input Document Prepared By SR


Training Course 35

User Input Document Prepared By SR


Training Course 36

Tools Æ Graphic ReportÆ Resource and Cost


• Press “ADD”
• Press “ADD” to automatic number given to report
• In “Resource Selection” tab:
Profile If Low Value Resource
EQ MH

• In “Content” tab, Select Divided By=260


• In “Date” tab:
o End Date: 30-Jun-2007
o Title Each: Month
o Time Scale: Month
• Press “OK”
• Press “Run”
• View on screen – OK
• Continue---YES
Histogram will be displayed

User Input Document Prepared By SR