August 6, 2010

Soriano Construction Company


1103 Miguel Street, Piles, Makati
Philippines
851-43-44

Mr. Gabby D. Untalan


Chief Executive Officer
San Agustin Supermarket
1001 Dona Soledad, Don Bosco, Paranaque

Dear Mr. Untalan:

I write a letter to inform you of the ongoing development in the construction of


the San Agustin Supermarket.

Included with this letter is the progress report of the project from the past four
months of the construction up to the present. We also estimated the project
accomplishment for the next two months. In line with this, we included the tables,
graphs and pictures of the project to support the details for the progress report.

We are confident in our ability to finish this project efficiently. Should you have
any questions, feel free to call the number above at any time.

Thank you.

Very truly yours,

Engr. Joseph M. Pasag


Construction of San Agustin Supermarket

Progress Report: June – July 2010

In our letter dated July 6, 2010 we reported that the Ground Floor of the San
Agustin Supermarket is already finished. Parts of the ground floor which are constructed include
the following:

• Supermarket
• Food Court
• Appliance Center
• Bowling Center

Construction of the Business Center, Surplus and Fitness First was also in line to be
accomplished.

We would like to inform you that unfinished parts of the ground floor which are
the Business Center, Surplus and Fitness First as of now are finished already. On the other hand,
construction of the Upper Ground Floor had already started. As of now, five stall capacities are
done since last month or approximately thirty days. Therefore, we can say that our company can
finish five stalls per month. If you will allow us, we could fasten this process by adding more
workers. As you already know, this will cause a drastic increase in the cost of the project. You
could refer to Appendix – A of this report for further details. As a reply to your request last
month, we included an additional space in the Upper Ground Floor for the Department Store.
Instead of four by four stall measurement, we made it to six by six stall measurement as you
have instructed us to do. So far, no problems or other things that will slow the speed of
construction had been encountered.

In one month time, we can assure you that another five stalls will be finished. The
stall for National Bookstore will be our next target to be accomplished. We will assure you that
this project will run smoothly. You could refer to Appendix – B to check for the floor plan of this
project. I have also included several pictures for your convenience. We will inform you of any
progress in the near future.
Appendix A

Figures on the Worker Cost of the Project

Number of Workers Work Assignment Amount of Days Cost


Completed
Twelve Department Store Six 120, 000 Pesos
Thirteen Supermarket Seven 130, 000 Pesos
Ten Food Court Five 100, 000 Pesos
Eight Appliance Center Four 80, 000 Pesos
Ten Bowling Center Five 100, 000 Pesos
Seven Surplus Four 70, 000 Pesos
Six Business Center Three 60, 000 Pesos

Area Distribution for Ground Floor of San Agustin Supermarket

9% Supermarket
4% Department Store
18%
FoodCourt
21%
Appliance Center
26%
BowlingCenter
18%
4% Surplus
BusinessCenter
Appendix B

Floor Plan of San Agustin Supermarket