Sunteți pe pagina 1din 2

ANSAL BUILDWELL LTD.

DAILY LABOUR STRENGTH - JAMMU PROJECT DATE : 08.10.2010.


AUGUST,2010 SHIFT : FRIDAY(Day Shift)

Rf. Fitter Helper

generater optr

PlantOperator
Mason Helper

Welder helper

Housekeeper
Misc Helpers
Time Keeper
A

Carp Helper

Store Asstt/
Reinf. Fitter

Electrician
Office Boy
Carpenter

scaffolder

Mechanic

Foreman

Operator
Batching
Plumber

Gardner
Security
Khalasi
Welder

Painter
N

Mason
Sr.No

helper

Driver

Total
USL
SKL
S Name of Contractor
AL
B
UI
LD Fabrication & Errection Work
W B.K FABRICATOR - Jammu
EL
1 CORDIDOOR /BALCONY RAILING 1 1 0 1
L
LT Total 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 1
D.
B Ansal Buildwell ltd
Departmental Work
1 MAKING PLANTER ( laying BRICK WORK ) 1 2 1 2 3
2 ARCH PLASTER AND PREPARATION 2 3 2 3 5
3 CLEANING AND SHIFTING 0 0 0
4 FIXING OF SAMPLE FLAT DOOR AND WINDOW 1 1 1 1 2
5 ELECTRICAL WORK AT SAMPLE FLAT 2 2 0 2
6 TEMP STAFF 1 1 1 1 1 3 4
Total 3 6 1 0 0 0 0 0 0 0 0 0 1 2 1 0 0 0 0 0 0 0 0 1 0 1 7 9 16

C
Saleem Ahmed -Contractor for POP work
from Delhi
POP WORK
1 POP WORK AT BED ROOM 2 1 3 1 3 4
2 POP WORK ATMASTER BED ROOM 0 0 0
6 HECKING & CHIPPING AT CORIDOOR 0 0 0
Total 1 3 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 3 4

D
Adhunik Tech-Contractor for Stone work
-from Delhi
FIXING STONE AND MARBLE
1 MAKING AND C UTTING STONE 2 2 2 2 4
2 STONE AND MARBLE AT CORIDOOR 2 2 2 2 4
Total 4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 4 8
E M/s Choudhary Builders - Jammu
Shifting of Erath from existing plot
1 earth shifting from existing plot 0 0 0
Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Overtime (in hrs.) if any
F (Global Security)
1 Day Shift (Security Guards ) 2 2 0 2
2 Night Shift (Security Guards ) 2 2 0 2
Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 0 0 0 0 0 0 0 0 4 0 4

GRAND TOTAL 8 13 1 0 0 0 1 0 0 0 0 0 1 2 1 0 4 0 0 0 0 0 0 1 0 1 17 16 33

Contd….
Note:-
Agency deployed for Shifting of Earth from the Plot.
M/s Choudhary Builders - Equipments deployed:
1 Excavator cum loader (J.C.B.) 0 No.
2 Trucks 0 Nos. No Erath shifting work at site

Quantity of Earth stacked at existing plot = 2090 cum (approx.)


Quantity of Earth shifted upto 05.10.2010 = 1455 cum (approx.)
Balance Quantity of Earth lying at site = 635 cum (112 trucks load)

No Earth was shifted today as J.C.B. Operator is not well due to chest problem.
But the shifting of Earth will start from tomorrow i.e. 10.10.2010.

S-ar putea să vă placă și