TO OPEN EYES AND MINDS OF PEOPLE ABOUT LEAN AND ONE-PIECE FLOW PRODUCTION,
BENEFITS AND EFFECTIVENESS THAT CAN BE OBTAINED FOR COMPANY AND EMPLOYEES
MATERIALS
- LEGO BLOCKS
- STOPWATCH = 3 PCS
1 PERSON AS OPERATOR SUB ASSY PROCESS TOP PARTS (SHORT & LONG)
AFTER GENERAL RULES EXPLAINED AND ROLES WERE ASSIGNED “START” STAGE 1
STOP PERFORMED ON LUNCH BREAK OR WHEN QUALITY ISSUES OCCURRED
LAYOUT
CUSTOMER
QC
OPERATOR 1
SUB ASSY BOTTOM
OPERATOR 2
SUB ASSY TOP
SUPERVISOR
OPERATOR 3
FULL ASSEMBLY
QC
1S
TAKT TIME
50 SETS / DAY
1 DAY = 8MINUTES = 480 SEC
480 / 50 = 9,6 SEC → TAKT 8 SEC (SAFETY)
WITH TIME COUNTER TAP THE QC EVERY 8 SEC OPERATOR 1
PRODUCE SHORT PRODUCT
WITH 8 SEC TAKT TIME
KANBAN
OPT 1 & 2 ONLY FILL WHEN KANBAN EMPTY
BATCH SIZE 1 L & 1 S
ONE PIECE FLOW RULE
AFTER ONE PIECE FLOW RULES EXPLAINED AND ROLES WERE ASSIGNED “START” STAGE 4
CHANGE THE OPERATOR IN THE MIDDLE OF THE GAME
RESULT OF STAGE 4
- EVALUATION AFTER THE END OF STAGE FOUR
FROM THE GAME HELD ON SEPTEMBER 28TH, 2010 WE HAVE :
KFI LEAN DEVELOPMENT DAY 1 DAY 2 DAY 3 DAY 4
BATCH SIZE 10 3 5 1
PEOPLE 8 8 8 4
AREA 20 m2 20 m2 20 m2 8 m2
SOLD 50S / 50L 50S / 50L 50S / 50L 50S / 50L
DELIVERED NUMBER 30S / 20L 36S / 24L 50S / 50L 50S / 50L
TURN OVER (@ 50 000) 2500000 3000000 5000000 4950000
(after 6 min) (-50000 truck)