ID Task Name Duration Start Finish

Civil Work for 33 K.V substations.


38 Civil Work for Site 32 days Fri 12-11-10 Fri 17-12-10

39 Escavation for structural Foundations 3 days Fri 12-11-10 Sun 14-11-10


40 Excavation for Transformer 5 days Fri 12-11-10 Tue 16-11-10
41 Excavation for the Soak pit 5 days Fri 12-11-10 Tue 16-11-10
42 Construction of Foundation for the Structures 3 days Mon 15-11-10 Wed 17-11-10
43 Construction of Foundation for the Transformer 4 days Wed 17-11-10 Sat 20-11-10
44 Construction of Soak pit 4 days Wed 17-11-10 Sat 20-11-10
45 Construction of Dike wall around Transformer 3 days Thu 09-12-10 Sat 11-12-10
46 Fencing of Switchyard 8 days Thu 09-12-10 Fri 17-12-10
47 Installation of Gates 2 days Thu 09-12-10 Fri 10-12-10
48 Laying of Blue metal 3 days Sat 11-12-10 Tue 14-12-10
49 Curing the foundations 15 days Thu 18-11-10 Sat 04-12-10

211 Civil Works 29 days Sat 13-11-10 Wed 15-12-10

212 Main Substation and SS # 6 23 days Sat 13-11-10 Wed 08-12-10

213 Levelling of floor and compacting 3 days Sat 13-11-10 Mon 15-11-10
214 Excavation for Trenches. 2 days Tue 16-11-10 Wed 17-11-10
215 Preperation for Flooring 3 days Thu 18-11-10 Sat 20-11-10
216 Curing of Floors & Trenches 15 days Mon 22-11-10 Wed 08-12-10
217 Installation of Side Walls 8 days Mon 22-11-10 Tue 30-11-10
218 Installation of Rolling Shutters, Doors & Windows 3 days Wed 01-12-10 Fri 03-12-10

219 SS # 1 23 days Tue 16-11-10 Sat 11-12-10

220 Levelling of floor and compacting 3 days Tue 16-11-10 Thu 18-11-10
221 Excavation for Trenches. 2 days Fri 19-11-10 Sat 20-11-10
222 Preperation for Flooring 3 days Mon 22-11-10 Wed 24-11-10
223 Curing of Floors & Trenches 15 days Thu 25-11-10 Sat 11-12-10
224 Installation of Side Walls 8 days Thu 25-11-10 Fri 03-12-10
225 Installation of Rolling Shutters, Doors & Windows 5 days Sat 04-12-10 Thu 09-12-10

226 SS # 4 & 5 23 days Fri 19-11-10 Wed 15-12-10

227 Levelling of floor and compacting 3 days Fri 19-11-10 Mon 22-11-10
228 Excavation for Trenches. 2 days Tue 23-11-10 Wed 24-11-10
229 Preperation for Flooring 3 days Thu 25-11-10 Sat 27-11-10
230 Curing of Floors & Trenches 15 days Mon 29-11-10 Wed 15-12-10
231 Installation of Side Walls 8 days Mon 29-11-10 Tue 07-12-10
232 Installation of Rolling Shutters, Doors & Windows 5 days Wed 08-12-10 Mon 13-12-10

233 Main Substation and SS # 3 & 2 26 days Tue 16-11-10 Wed 15-12-10
234 Levelling of floor and compacting 3 days Tue 23-11-10 Thu 25-11-10
235 Excavation for Trenches. 2 days Tue 16-11-10 Wed 17-11-10
236 Preperation for Flooring 3 days Thu 18-11-10 Sat 20-11-10
237 Curing of Floors & Trenches 15 days Mon 22-11-10 Wed 08-12-10
238 Installation of Side Walls 8 days Mon 22-11-10 Tue 30-11-10
239 Installation of Rolling Shutters, Doors & Windows 3 days Wed 01-12-10 Fri 03-12-10
240 Installation of Hume Pipe Across the Road 3 days Mon 13-12-10 Wed 15-12-10